Tunnel anchor cable lengthening device

By using the clamp top retractor and cone surface to cooperate in the tunnel anchor cable attachment device, the problems of insufficient length and disassembly difficulties in anchor cable detection are solved, and the convenience of rapid disassembly and frequent detection of anchor cables is achieved, which improves the Inspection efficiency and safety.

CN222010254UActive Publication Date: 2024-11-15GANSU DALU IND CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420330794.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-22
Publication Date
2024-11-15
Estimated Expiration
2034-02-22

AI Technical Summary

Technical Problem

The existing anchor cable detection method requires the anchor cable to exceed a certain length before it can be tensile inspection, but in actual construction, the exposed part of the anchor cable is only 3-5cm, which cannot meet the detection requirements, and the existing connector is difficult to quickly disassemble. Release the clip, which leads to inconvenience in frequent replacement detection scenarios.

Method used

A tunnel anchor cable connecting device is designed, by providing a clip top retractor at the front end of the first anchor, and using the thrust force of the rotating clip top retractor, the first clip is made to be rearward in the first anchor. Move, untie the interference fit and achieve rapid disassembly; at the same time, through the tapered fit and threaded connection, ensure that the clips are closely connected during tensioning to avoid loosening.

Benefits of technology

It realizes rapid disassembly and reuse of anchor cables, simplifies the anchor cable detection process, and improves detection efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222010254U_ABST
    Figure CN222010254U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel anchor cable lengthening device which comprises a first anchorage device, a first clamping piece matched with the first anchorage device and used for clamping a tunnel anchor cable, a connector connected with the rear end of the first anchorage device, a lengthening anchor cable, a second anchorage device connected with the rear end of the connector and a second clamping piece matched with the second anchorage device and used for clamping the lengthening anchor cable. The lengthening device further comprises a clamping piece ejecting and retreating cylinder which is in threaded connection with the front end of the first anchorage device and can be arranged outside the tunnel anchor cable in a sleeving mode, the clamping piece ejecting and retreating cylinder is provided with an abutting part which stretches into the first anchorage device and can abut against the front end face of the first clamping piece, and the clamping piece ejecting and retreating cylinder is rotated to abut against the front end face of the first clamping piece under the thrust effect of the abutting part. The first clamping piece can move backwards in the first anchorage device. According to the extension device, the first clamping piece can quickly loosen the tunnel anchor cable by rotating the clamping piece jacking cylinder, so that the extension device can be quickly detached from the tunnel anchor cable, and the extension device can be used in the scene that the anchor cable is frequently replaced for detection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of tunnel anchor cable extension, and in particular relates to a tunnel anchor cable extension device. Background Art

[0002] After tunnel excavation, the original stress balance state is broken, which often leads to instability and increases safety hazards. In order to ensure the stability of tunnel components after stress redistribution, some measures such as steel support and anchor cables are introduced. Among these measures, the effective prestressing of prestressed anchor cables is crucial for the long-term stable operation of tunnel components. In order to evaluate the construction quality of anchor cables, especially their tensile bearing capacity, it is necessary to solve the detection and identification of anchor cable supported tunnels. However, in the detection and identification process of anchor cable supported tunnels, sometimes the anchor cables have been constructed and the working section has been cut, which makes it impossible to perform tension testing on the anchor cables, and thus it is impossible to evaluate the construction quality of the anchor cables.

[0003] In actual construction, the exposed part of some anchor cables is usually only 3-5cm, while the existing anchor cable detection method requires the anchor cable to extend at least 70cm beyond the anchor length. In order to solve this problem, Chinese utility model patent CN2398477Y discloses an anchor cable extender, which can extend the anchor cable. When the extended anchor cable is tensioned, the anchor cables at both ends of the extender are stretched, making the interference connection between the clip and the anchor plate tighter and tighter. After the prestress test is completed, when the extender is removed from the anchor cable, it is difficult to quickly withdraw the clip from the anchor plate to loosen the tunnel anchor cable. Therefore, it is not very convenient to use in the scenario of frequent replacement of anchor cables for detection. Utility Model Content

[0004] The utility model aims to solve the technical problems existing in the prior art and the purpose of the utility model is to provide a tunnel anchor cable extension device.

[0005] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a tunnel anchor cable extension device, comprising a first anchor, a first clip located in the first anchor and cooperating with the first anchor and capable of being sleeved and clamped outside the end of the tunnel anchor cable, a connecting head movably connected to the rear end of the first anchor, a second anchor movably connected to the rear end of the connecting head, a second clip located in the second anchor and cooperating with the second anchor, and an extended anchor cable clamped and fixed in the second clip; the extension device also includes a clip push-back cylinder threadedly connected to the front end of the first anchor and capable of being sleeved outside the tunnel anchor cable, the clip push-back cylinder has an abutting portion extending into the first anchor and capable of abutting against the front end surface of the first clip, and by rotating the clip push-back cylinder, the first clip can move backward in the first anchor under the thrust of the abutting portion.

[0006] The above technical scheme, by arranging a clip pushing and withdrawing cylinder at the front end of the first anchor, the abutting part on the clip pushing and withdrawing cylinder can push the first clip backward by rotating the clip pushing and withdrawing cylinder, thereby releasing the interference fit between the inner wall of the first anchor and the outer wall of the first clip, allowing the first clip to quickly loosen the tunnel anchor cable, thereby realizing the rapid disassembly of the extension device on the tunnel anchor cable, so that the extension device can be used in the scenario of frequent replacement and inspection of anchor cables.

[0007] In a preferred embodiment of the present invention, the outer wall of the first clip cooperates with the inner wall conical surface of the first anchor, and the large end of the first clip is located on the rear side of the small end; the outer wall of the second clip cooperates with the inner wall conical surface of the second anchor, and the large end of the second clip is located on the front side of the small end.

[0008] In the above technical solution, the first clip and the first anchor are matched with each other by a conical surface, and the second clip and the second anchor are also matched with each other by a conical surface, and the small ends of the first clip and the second clip are far away from each other. When the anchor cable is tensioned and extended, the connection between the first clip and the first anchor, and the connection between the second clip and the second anchor are tightened, so that the extension device will not loosen from the tunnel anchor cable.

[0009] In a preferred embodiment of the present invention, the connecting head has a first abutting portion that extends into the first anchor and can abut against the rear end face of the first clip, and by moving the connecting head forward relative to the first anchor, under the thrust of the first abutting portion, the outer wall of the first clip can be interference fit with the inner wall of the first anchor to clamp the tunnel anchor; the connecting head has a second abutting portion that extends into the second anchor and can abut against the front end face of the second clip, and by moving the connecting head backward relative to the second anchor, under the thrust of the second abutting portion, the outer wall of the second clip can be interference fit with the inner wall of the second anchor to clamp the connecting anchor.

[0010] In the above technical solution, the first clamp can clamp the tunnel anchor cable by moving the connecting head forward relative to the first anchor, and the second clamp can clamp the connecting anchor cable by moving the connecting head backward relative to the second anchor, which is easy to operate.

[0011] In a preferred embodiment of the utility model, the rear end of the first anchor is threadedly connected to the connecting head, and the first clamp can clamp the tunnel anchor by rotating the connecting head relative to the first anchor; the front end of the second anchor is threadedly connected to the connecting head, and the second clamp can clamp the extended anchor by rotating the connecting head relative to the second anchor.

[0012] In the above technical solution, the first anchor and the second anchor are both threadedly connected to the connecting head and can be self-locking. Moreover, by rotating the connecting head relative to the first anchor and the second anchor, the first clamp can clamp the tunnel anchor cable and the second clamp can clamp the connecting anchor cable. The rotary operation method is more convenient.

[0013] In a preferred embodiment of the present invention, the outer wall of the front end of the first anchor has an external thread, and the inner wall of the clip ejection tube has an internal thread matching the external thread.

[0014] In another preferred embodiment of the present invention, a connecting hole capable of inserting a torsion bar is provided on the outer wall of the clip ejection cylinder.

[0015] The above technical solution, by providing a connecting hole, facilitates the insertion of the torsion bar into the connecting hole, and the clip pushes the retracting tube to rotate through the torsion bar, which is more labor-saving.

[0016] In another preferred embodiment of the present invention, the outer wall of the clip ejection tube has a protrusion extending outward, and the connecting hole extends to the outer end of the protrusion.

[0017] The above technical solution prolongs the depth of the connecting hole by arranging the protrusion, so that the contact length between the torsion bar and the connecting hole is longer, thereby improving the strength.

[0018] In another preferred embodiment of the present invention, a displacement sensor is installed on the clip ejection cylinder.

[0019] The above technical solution, by setting a displacement sensor, can determine whether the first clamp is pulled when the anchor cable is tensioned and extended, so as to determine whether the tunnel anchor cable is stretched. In addition, the elongation of the tunnel anchor cable can be obtained according to the displacement sensor to obtain the prestress under the anchor, thereby improving the practicality of the extension device.

[0020] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0022] Figure 1 It is a schematic diagram of the appearance structure of a tunnel anchor cable extension device of an embodiment.

[0023] Figure 2 It is a schematic diagram of the cross-sectional internal structure of a tunnel anchor cable extension device of an embodiment.

[0024] The figure marks in the drawings of the specification include: first anchor 1, first conical hole wall 11, first clamp 2, clamp push-back tube 3, abutment 31, gap 32, connecting hole 33, protrusion 34, connecting head 4, first abutment 41, second abutment 42, second anchor 5, second conical hole wall 51, second clamp 6, tunnel anchor 7, extended anchor 8, displacement sensor 9. DETAILED DESCRIPTION

[0025] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0026] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "vertical", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0027] In the description of the present utility model, unless otherwise specified and limited, it should be noted that the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a mechanical connection or an electrical connection, or it can be the internal connection of two components. It can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to the specific circumstances.

[0028] The utility model provides a tunnel anchor cable extension device, such as Figure 1 and Figure 2 As shown, in a preferred embodiment, the extension device includes a first anchor 1, a first clamp 2 located in the first anchor 1 and cooperating therewith and capable of being sleeved and clamped outside the end of the tunnel anchor 7, a connector 4 movably connected to the rear end of the first anchor 1, a second anchor 5 movably connected to the rear end of the connector 4, a second clamp 6 located in the second anchor 5 and cooperating therewith, and an extension anchor 8 clamped and fixed in the second clamp 6. The existing method can be adopted to clamp the tunnel anchor 7 by cooperating with the first anchor 1 and the first clamp 3, and to clamp the extension anchor 8 by the second anchor 5 and the second clamp 6.

[0029] The anchor cable extension device also includes a clip push-back tube 3 which is threadedly connected to the front end of the first anchor 1 and can be sleeved on the outside of the tunnel anchor 7. For example, the outer wall of the front end of the first anchor 1 has an external thread, and the inner wall of the clip push-back tube 3 has an internal thread that matches the external thread; the clip push-back tube 3 has an abutment portion 31 that extends from the front to the back into the first anchor 1 and can abut against the front end surface of the first clip 2. By rotating the clip push-back tube 3, under the thrust of the abutment portion 31, the first clip 2 can move backward in the first anchor 1.

[0030] In the utility model, the first anchor 1 has a first tapered hole wall 11 with a small end at the front end, the outer wall of the first clip 2 matches the conical surface of the first tapered hole wall 11 of the first anchor 1, and the large end of the first clip 2 is located at the rear side of the small end. The second anchor 5 has a second tapered hole wall 51 with a large end at the front end, the outer wall of the second clip 6 matches the conical surface of the second tapered hole wall 51 of the second anchor 5, and the large end of the second clip 6 is located at the front side of the small end.

[0031] When the extension device is used for the first time, first install the first clip 2 in the first anchor 1, thread the clip push-back tube 3 and the first anchor 1, and then put the three together on the tunnel anchor 7. The first clip 2 and the first anchor 1 have an interference fit, and the tunnel anchor 7 is clamped and fixed by the first clip 2. Insert the extension anchor 8 into the second clip 6, the second clip 6 and the second anchor 5 have an interference fit, and the second clip 6 clamps and fixes the extension anchor 8, and then fix the second anchor 5 on the first anchor 1 through the connector 4 to complete the installation of the extension device. After that, the prestress detection device can perform prestress detection by tensioning the extension anchor 8. The tensioning force is transmitted to the second clip 6, the second anchor 5, the connector 4, the first anchor 1 and the first clip 2 in sequence through the extension anchor 8, and finally transmitted to the tunnel anchor 7 by the first clip 2.

[0032] After the prestress test of the tunnel anchor 7 is completed, the extension device needs to be removed from the tunnel anchor 7. Specifically, the clip top-retracting tube 3 is rotated first. Since the clip top-retracting tube 3 is threadedly connected to the first anchor 1, the rotation of the clip top-retracting tube 3 can make its abutting portion 31 move backward and contact the front end face of the first clip 2. At this time, there is a gap 32 between the front end face of the first anchor 1 and the clip top-retracting tube 3. The clip top-retracting tube 3 is continued to be rotated. Under the thrust of the abutting portion 31, the first clip 2 moves backward in the first anchor 1 to loosen the tunnel anchor 7, and then the extension device can be removed from the tunnel anchor 7.

[0033] It should be noted that, before the first clamp 2 releases the tunnel anchor 7, when the clamp push-back tube 3 is rotated, since the first anchor 1 and the first clamp 2 are fixed together on the tunnel anchor 7, they will not rotate together with the clamp push-back tube 3, so that the clamp push-back tube 3 can rotate relative to the first anchor 1; when the first anchor 1 rotates together with the clamp push-back tube 3 and the two are relatively fixed, it indicates that the clamp push-back tube 3 has pushed back the first clamp 2 and the first clamp 2 has released the tunnel anchor 7.

[0034] In the utility model, the first clamp 2 and the first anchor 1 can be interference-fitted to clamp the tunnel anchor 7 by other tools, or it can be achieved by operating the connecting head 4. Similarly, the second clamp 6 and the second anchor 5 can be interference-fitted to clamp the extended anchor 8 by other tools, or it can be achieved by operating the connecting head 4.

[0035] like Figure 2As shown, when the operation of the connector 4 is realized, the connector 4 has a first abutting portion 41 extending into the first anchor 1 and capable of abutting against the rear end face of the first clip 2, and the connector 4 has a second abutting portion 42 extending into the second anchor 5 and capable of abutting against the front end face of the second clip 6. By moving the connector 4 forward relative to the first anchor 1, under the thrust of the first abutting portion 41, the outer wall of the first clip 2 can be interference-fitted with the inner wall of the first anchor 1 to clamp the tunnel anchor 7; by moving the connector 4 backward relative to the second anchor 5, under the thrust of the second abutting portion 42, the outer wall of the second clip 6 can be interference-fitted with the inner wall of the second anchor 5 to clamp the connecting anchor 8.

[0036] Preferably, the inner wall at the rear end of the first anchor 1 is threadedly connected to the outer wall of the connector 4, and the inner wall at the front end of the second anchor 5 is threadedly connected to the outer wall of the connector 4. When installing the extension device, hold the first anchor 1 by hand to fix it, rotate the connector 4 to make its first abutting portion 41 move forward, the first abutting portion 41 pushes the first clamp 2 to move forward in the first anchor 1, and the first clamp 2 can clamp the tunnel anchor 7; then hold the connector 4 by hand to fix it, rotate the second anchor 5 to make the connector 4 rotate relative to the second anchor 5, the second anchor 5 moves forward, the second abutting portion 42 of the connector 4 makes the second clamp 6 move backward relative to the second anchor 5, and the second clamp 6 can clamp the extension anchor 8. When removing the extension device from the tunnel anchor 7, it is necessary to rotate the connector 4 first, so that the first abutting portion 41 moves backward and away from the first clamp 2, leaving space for the first clamp 2 to be pushed back. After removal, the extension device is a whole and does not need to be disassembled.

[0037] It should be noted that when the extension device is connected to another tunnel anchor cable 7, the clip push-out tube 3 and the first clip 2 of the extension device are first put on the tunnel anchor cable 7, and then the first anchor 1 is held, and the clip push-out tube 3 is rotated in the opposite direction relative to the first anchor 1 to reset it, leaving space for the forward movement of the first clip 2. After that, the connector 4 is rotated relative to the first anchor 1 (at this time, the second anchor 5, the second clip 6 and the extension anchor cable 8 rotate accordingly), and the first abutment portion 41 of the connector 4 moves the first clip 2 forward to clamp the tunnel anchor cable 7; of course, the connector 4 can also be held and the first anchor 1 can be rotated relative to the connector 4. As long as the first anchor 1 and the connector 4 rotate relative to each other, the first abutment portion 41 can press the first clip 2 tightly and make it move forward in the first anchor 1.

[0038] like Figure 1As shown, in another preferred embodiment, the outer wall of the clip ejection tube 3 has a connection hole 33 into which a torsion bar can be inserted. When the clip ejection tube 3 needs to be rotated to eject the first clip 2, the torsion bar is inserted into the connection hole 33, and the clip ejection tube 3 is rotated by the torsion bar, which is more labor-saving. Further preferably, the outer wall of the clip ejection tube 3 has a protrusion 34 extending outward, and the connection hole 33 extends to the outer end of the protrusion 34.

[0039] like Figure 1 As shown, in another preferred embodiment, a displacement sensor 9 is installed on the clamp top withdrawal tube 3, and the transmitting end of the displacement sensor 9 can be oriented toward the upper end surface of the working anchor for fixing the tunnel anchor 7, so as to measure the distance that the clamp top withdrawal tube 3 moves relative to the working anchor, so as to obtain the elongation of the tunnel anchor 7. When the anchor 8 is stretched and extended, if the displacement value detected by the displacement sensor 9 does not change, it indicates that the first clamp 2 is not pulled and the tunnel anchor 7 is not stretched; if the displacement value detected by the displacement sensor 9 increases, it indicates that the first clamp 2 is pulled, and the force value corresponding to the inflection point of the displacement value is the prestress under the anchor. The displacement value increment of the clamp top withdrawal tube 3 is the elongation of the tunnel anchor 7. According to the corresponding relationship between the elongation of the anchor and the prestress under the anchor, the prestress under the anchor can be obtained. The method of obtaining the prestress under the anchor according to the elongation of the anchor is a prior art, which is not the innovation of the present utility model and will not be described in detail here.

[0040] In the description of this specification, the description with reference to the terms "preferred embodiment", "one embodiment", "some embodiments", "example", "specific example" or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0041] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A tunnel anchor cable extension device, comprising a first anchor, a first clip located in the first anchor and cooperating with the first anchor and capable of being sleeved and clamped outside the end of the tunnel anchor cable, a connector movably connected to the rear end of the first anchor, a second anchor movably connected to the rear end of the connector, a second clip located in the second anchor and cooperating with the second anchor, and an extension anchor cable clamped and fixed in the second clip; It is characterized in that The extension device also includes a clip push-back tube that is threadedly connected to the front end of the first anchor and can be mounted outside the tunnel anchor cable. The clip push-back tube has an abutment portion that extends into the first anchor and can abut against the front end surface of the first clip. By rotating the clip push-back tube, the first clip can move backward in the first anchor under the thrust of the abutment portion.

2. The tunnel anchor cable extension device according to claim 1, It is characterized in that The outer wall of the first clip is matched with the conical surface of the inner wall of the first anchor, and the large end of the first clip is located at the rear side of the small end; The outer wall of the second clip is matched with the conical surface of the inner wall of the second anchor, and the large end of the second clip is located in front of the small end.

3. The tunnel anchor cable extension device according to claim 1, It is characterized in that The connecting head has a first abutting portion extending into the first anchor and capable of abutting against the rear end surface of the first clip. By moving the connecting head forward relative to the first anchor, under the thrust of the first abutting portion, the outer wall of the first clip can be interference-fitted with the inner wall of the first anchor to clamp the tunnel anchor cable; The connecting head has a second abutment portion that extends into the second anchor and can abut against the front end surface of the second clip. By moving the connecting head backward relative to the second anchor, under the thrust of the second abutment portion, the outer wall of the second clip can be interference fit with the inner wall of the second anchor to clamp the long anchor cable.

4. The tunnel anchor cable extension device according to claim 3, It is characterized in that The rear end of the first anchor is threadedly connected to the connector, and the first clamp can clamp the tunnel anchor cable by rotating the connector relative to the first anchor; The front end of the second anchor is threadedly connected to the connecting head, and the second clip can clamp and lengthen the anchor cable by rotating the connecting head relative to the second anchor.

5. The tunnel anchor cable extension device according to claim 1, It is characterized in that The outer wall of the front end of the first anchor has an external thread, and the inner wall of the clip ejection tube has an internal thread that matches the external thread.

6. The tunnel anchor cable extension device according to any one of claims 1 to 5, It is characterized in that The outer wall of the clip ejection cylinder is provided with a connecting hole into which a torsion bar can be inserted.

7. The tunnel anchor cable extension device according to claim 6, It is characterized in that The outer wall of the clip ejection tube has a protrusion extending outward, and the connecting hole extends to the outer end of the protrusion.

8. The tunnel anchor cable extension device according to any one of claims 1 to 5, It is characterized in that A displacement sensor is installed on the clip ejection cylinder.