Argon-filled welding pipeline system for furnace tube welding

By designing an argon-filled welding pipeline system including cold wall pipe, collection pipe, outlet pigtail pipe and furnace pipe, and using sponge and tape to seal argon gas, the problem of insufficient argon gas in high-temperature welding environment is solved, and the problem of significant improvement is improved. Welding quality.

CN222113952UActive Publication Date: 2024-12-06THE SIXTH CONSTR CO LTD OF CHINA NAT CHEM ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323539771.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-12-06
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

In high-temperature working environment, the argon atmosphere is insufficient during the furnace pipe welding process due to conventional argon protection methods, resulting in poor welding quality.

Method used

A pipeline system for filling argon welding for furnace pipe welding was designed. Through the combined structure of cold wall pipe, collection pipe, outlet pigtail pipe and furnace pipe, the sealing and argon gas transmission is used to ensure that the welding is filled with argon gas. , tetrafluoro gasket and bolt structure are used to seal to ensure that argon does not leak.

Benefits of technology

It effectively improves the welding quality, ensures sufficient argon environment at the welding site, and improves the overall quality of the welding.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222113952U_ABST
    Figure CN222113952U_ABST
Patent Text Reader

Abstract

The argon-filled welding pipeline system comprises a cold wall pipe, a collecting pipe, an outlet pigtail pipe and the furnace pipe which are sequentially connected from bottom to top, the end, away from the collecting pipe, of the cold wall pipe is connected with a liquid argon storage tank, and a top flange is installed at the top of the furnace pipe. The collecting tube and the cold wall tube are connected through a connecting flange, a sponge is placed at the connecting flange, a hole is formed in the center of the sponge, the welding joint of the collecting tube and the outlet pigtail tube is sealed through an adhesive tape, and the welding joint of the outlet pigtail tube and the furnace tube is sealed through an adhesive tape. Argon transmission and inflation in the welding process of the cold wall tube, the collecting tube, the outlet pigtail tube and the furnace tube are utilized, the welding joints of the collecting tube and the outlet pigtail tube and the welding joints of the outlet pigtail tube and the furnace tube are sealed through adhesive tapes, it is guaranteed that the welding joints are filled with argon in the welding process of the furnace tube, and then the welding quality is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of argon-filled pipelines, and more specifically, to an argon-filled welding pipeline system for furnace tube welding. Background Art

[0002] The primary reformer is one of the core equipment of the synthetic ammonia unit, and the installation and welding of the furnace tube is the core work of the entire reformer. The high temperature working environment of the primary reformer determines the high quality requirements of furnace tube welding. The furnace tube is made of nickel-based alloy, and the argon filling quality of its welding work is directly related to the welding quality. However, the number of furnace tubes is large and the length is large. The conventional method of directly protecting the welding point with argon gas will result in insufficient argon atmosphere, which will lead to poor welding quality. Utility Model Content

[0003] In order to achieve these purposes and other advantages according to the utility model, an embodiment of the utility model provides an argon-filled welding pipeline system for furnace tube welding, including a cold wall tube, a collecting tube, an outlet pigtail tube and a furnace tube connected in sequence from bottom to top, and the end of the cold wall tube away from the collecting tube is connected to a liquid argon storage tank, a top flange is installed on the top of the furnace tube, and a sealing gasket is installed in the middle of the top flange through a bolt structure to seal the top flange, the collecting tube and the cold wall tube are connected by a connecting flange, a sponge is placed at the connecting flange, and a hole is opened at the center of the sponge, the collecting tube and the outlet pigtail tube are welded, the outlet pigtail tube and the furnace tube are welded, the welding connection between the collecting tube and the outlet pigtail tube is sealed with tape, and the welding connection between the outlet pigtail tube and the furnace tube is sealed with tape.

[0004] According to another preferred embodiment of the present invention, the diameter of the cold wall tube is larger than the diameters of the collecting tube, the outlet pigtail tube and the furnace tube.

[0005] According to another preferred embodiment of the utility model, an openable and closable opening is provided on the tape at the welding connection between the outlet pigtail pipe and the furnace tube.

[0006] According to another preferred embodiment of the present invention, the cold wall tube is parallel to the manifold, and the plurality of outlet pigtail tubes 3 are vertically connected to the manifold, and one end of each outlet pigtail tube away from the manifold is upwardly connected to the furnace tube.

[0007] According to another preferred embodiment of the utility model, the outlet pigtail pipe includes a transverse pipe and two vertical pipes vertically connected to the two ends of the transverse pipe, the middle part of the transverse pipe is connected to the collecting pipe, and the two are interconnected, and one end of the vertical pipe away from the transverse pipe is vertically connected to the furnace pipe upward.

[0008] According to another preferred embodiment of the present invention, the sealing gasket is a polytetrafluoroethylene gasket.

[0009] The utility model at least has the following beneficial effects:

[0010] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a side view of an argon-filled welding pipeline system for furnace tube welding in one embodiment of the utility model.

[0012] Figure 2 It is a front view of an argon-filled welding pipeline system for furnace tube welding in one embodiment of the utility model. DETAILED DESCRIPTION

[0013] The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.

[0014] The following description is used to disclose the utility model so that those skilled in the art can implement the utility model. The preferred embodiments described below are only examples, and those skilled in the art can think of other obvious variations. The basic principles of the utility model defined in the following description can be applied to other embodiments, variations, improvements, equivalents, and other technical solutions that do not deviate from the spirit and scope of the utility model.

[0015] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.

[0016] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0017] like Figure 1-2As shown, an argon-filled welding pipeline system for furnace tube welding of the utility model comprises a cold wall tube 1, a manifold 2, an outlet pigtail tube 3 and a furnace tube 4 connected in sequence from bottom to top, and the end of the cold wall tube 1 away from the manifold is connected to a liquid argon storage tank 5, a top flange 5 is installed on the top of the furnace tube 4, and a sealing gasket is installed in the middle of the top flange 5 through a bolt structure to seal the top flange 5, the manifold 2 and the cold wall tube 1 are connected by a connecting flange 6, a sponge 7 is placed at the connecting flange 6, and a hole is opened at the center of the sponge 7, the manifold 2 and the outlet pigtail tube 3 are welded and connected, marked as weld B, and the outlet pigtail tube 3 and the furnace tube 4 are welded and connected, marked as weld A. The sealing gasket is a polytetrafluoroethylene gasket, the welding connection between the manifold 2 and the outlet pigtail tube 3 is sealed with a tape, and the welding connection between the outlet pigtail tube 3 and the furnace tube 4 is sealed with a tape.

[0018] In the above technical scheme, the cold wall tube 1, the manifold 2, the outlet pigtail tube 3 and the furnace tube 4 are used to transmit and inflate argon during the welding process, instead of directly performing argon protection at the welding point of the furnace tube. Moreover, the welding connection between the manifold 2 and the outlet pigtail tube 3 is sealed with tape, and the welding connection between the outlet pigtail tube 3 and the furnace tube 4 is sealed with tape. In this way, it can be ensured that the welding point of the furnace tube 4 is filled with argon during the welding process, thereby ensuring the welding quality.

[0019] In another technical solution, the diameter of the cold wall tube is larger than that of the collecting tube, the outlet pigtail tube and the furnace tube. This is because the cold wall tube, as the main pipeline, needs to provide argon to many furnace tubes at the same time, which necessarily requires a larger tube diameter.

[0020] In another technical solution, an openable and closable opening is provided on the tape at the welding connection between the outlet pigtail pipe 3 and the furnace tube 4, which can be opened and closed according to the needs during the argon filling process.

[0021] In another technical solution, the cold wall tube 1 is parallel to the manifold 2 , and the plurality of outlet pigtail tubes 3 are vertically connected to the manifold 2 , and one end of each outlet pigtail tube away from the manifold 2 is upwardly connected to the furnace tube 4 .

[0022] In another technical solution, the outlet pigtail pipe includes a transverse pipe and two vertical pipes vertically connected to the two ends of the transverse pipe. The middle of the transverse pipe is connected to the collecting pipe 2, and the two are interconnected. The end of the vertical pipe away from the transverse pipe is vertically connected to the furnace pipe upward.

[0023] The following is the argon filling process of the argon filling welding pipeline system for furnace tube welding:

[0024] Step S1: Use a bolt structure to seal the top flange 5 of the furnace 4 tube with a PTFE pad, and use tape to seal the gap between the weld A between the outlet pigtail pipe 3 and the furnace tube 4, and the gap between the weld B between the outlet pigtail pipe and the outlet manifold weld, so that the entire pipe system space is in a relatively closed state;

[0025] Step S2: placing a sponge 7 at the connection flange 6 between the manifold 2 and the cold wall tube 1, opening a hole in the center of the sponge 7, and using a hose to fill argon upward through the cold wall tube 1, so that the argon gas with higher density flows downward and upward to discharge the air;

[0026] The sponge 7 is placed here because: the argon connecting pipe extends into the interior through the cold wall tube 1, and then turns upward at the connecting flange to fill argon. The connecting flange 6 between the collecting pipe 2 and the cold wall tube 1 is very large, and the argon connecting pipe filled with argon is very small. If the sponge is not placed, the argon gas with a density greater than that of air will fall downward through the gap between the argon connecting pipe and the connecting flange, thereby leaking out. However, the sealing effect of the sponge can prevent the downward leakage of argon gas.

[0027] Step S3: Open the outlet valve of the liquid argon storage tank as much as possible to start filling with argon, open the bolts and PTFE pads on the top of each furnace tube one by one to facilitate the discharge of most of the air inside, and after most of the air is discharged, restore the PTFE pads to tighten the bolts to seal.

[0028] Step S4: After replacing most of the air inside the furnace tube, loosen the top flange bolts of the furnace tube that needs to be welded, and poke a few small holes in the center of the PTFE pad to allow the gas to be discharged from the PTFE pad. Each time, only open the top seal of the furnace tube being welded, and keep the other furnace tubes unchanged. After welding is completed, restore the seal before opening the next one.

[0029] Step S5: Start welding, first weld the lower weld (weld B), that is, the weld where the outlet pigtail pipe and the collecting pipe are connected. At this time, open a small hole in the paper tape at the upper weld of the tube (weld A), use a gas detector to check the argon content here, and then restore the paper tape seal. If the argon content here is sufficient, it means that the argon filling quality of the lower weld meets the standard and meets the welding conditions, and the lower weld (weld B) can be welded and primed.

[0030] Step S6: When the bottom welds are all primed, after a long period of argon filling, the argon filling quality at the top welds has met the welding requirements, and the top welds (welds A) can be primed one by one.

[0031] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation modes. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the illustrations shown and described herein.

Claims

1. An argon-filled welding pipeline system for furnace tube welding, characterized in that: It comprises a cold wall tube, a collecting tube, an outlet pigtail tube and a furnace tube which are connected in sequence from bottom to top, and one end of the cold wall tube away from the collecting tube is connected to a liquid argon storage tank, a top flange is installed on the top of the furnace tube, and a sealing gasket is installed in the middle of the top flange through a bolt structure to seal the top flange, the collecting tube and the cold wall tube are connected by a connecting flange, a sponge is placed at the connecting flange, and a hole is opened at the center of the sponge, the collecting tube and the outlet pigtail tube are welded, and the outlet pigtail tube and the furnace tube are welded; the welding connection between the collecting tube and the outlet pigtail tube is sealed by tape, and the welding connection between the outlet pigtail tube and the furnace tube is sealed by tape.

2. The argon-filled welding pipeline system for furnace tube welding according to claim 1, characterized in that: The diameter of the cold wall tube is larger than the diameters of the collecting tube, the outlet pigtail tube and the furnace tube.

3. The argon-filled welding pipeline system for furnace tube welding according to claim 1, characterized in that: An openable and closable opening is provided on the adhesive tape at the welding connection between the outlet pigtail pipe and the furnace pipe.

4. The argon-filled welding pipeline system for furnace tube welding according to claim 1, characterized in that: The cold wall tube is parallel to the manifold, and a plurality of the outlet pigtail tubes are vertically connected to the manifold, and one end of each outlet pigtail tube away from the manifold is upwardly connected to the furnace tube.

5. The argon-filled welding pipeline system for furnace tube welding according to claim 4, characterized in that: The outlet pigtail pipe includes a transverse pipe and two vertical pipes vertically connected to the two ends of the transverse pipe. The middle of the transverse pipe is connected to the collecting pipe, and the two are connected. The end of the vertical pipe away from the transverse pipe is vertically connected to the furnace pipe upward.

6. The argon-filled welding pipeline system for furnace tube welding according to claim 1, characterized in that: The sealing gasket is a polytetrafluoroethylene gasket.