Flood-fighting dam bank protection structure
Through the combination of steel sheet piles and soil fill in the dam unit structure, the problems of seepage and impact resistance of emergency temporary dams are solved, and more efficient flood control effects and flexible construction plans are achieved, adapting to different strata and flood conditions.
Patent Information
- Application Number
- CN202420277465.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-05
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-02-05
AI Technical Summary
When faced with heavy rain and floods, the prefabricated structure has low strength and poor permeability, which is easy to damage and difficult to repair. The conventional sand accumulation angle is small and the amount is large, resulting in seepage defects and overwater restrictions.
The dam unit structure is composed of steel sheet piles and soil fill. The steel sheet piles are used as anti-seepage body and protective layer, combined with flexible mesh and reinforced steel to form a dam unit structure, supporting flexible laying and reinforcement, and adapting to the distribution of different strata and flood conditions. .
It has achieved improvements in permeability and impact resistance, saved materials, provided larger water-through sections and flexible construction plans, supported rapid construction and strengthening in emergency situations, and was reusable.
Smart Images

Figure CN222120093U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of foundation treatment engineering, in particular to a flood-resistant dam bank protection structure. Background Art
[0002] Water conservancy projects are built to respond to water disasters and utilize water resources. When there is heavy rainfall, upstream dams burst, or new emergency flood channels are built to protect key areas from floods, emergency temporary dams that can be built quickly are important water conservancy facilities.
[0003] The existing emergency temporary dams, when using the earth-rock dam solution, achieve flood control by increasing the deadweight of the filled sand and soil. However, the conventional sand and soil stacking angle is small, the amount of sand and soil used is large, and the temporary soil impermeability is poor, which is prone to seepage defects. When using prefabricated structures to assemble temporary dams, the strength of the prefabricated structures is often low. When the impact of the water flow is large, or when large pieces of gravel and garbage are carried in the flood, they are easily damaged and difficult to repair. After the construction of the existing emergency temporary dams is completed, it is difficult to continue to maintain high-quality expansion and reinforcement. Summary of the invention
[0004] The purpose of the utility model is to provide a flood-resistant dam bank protection structure based on the above-mentioned deficiencies of the prior art, which adopts dam unit structures to assemble an emergency temporary dam, and ensures the flood control effect through the combined use of steel sheet piles and fill. At the same time, the dam laying plan can be flexible according to needs, and reinforcement space is left to facilitate rapid construction in emergency situations.
[0005] The purpose of this utility model is achieved by the following technical solutions:
[0006] A flood-resistant dam bank protection structure is used to establish a stress temporary dam on one side of a waterway, and is characterized in that it includes a plurality of temporary retaining wall units, the interiors of the plurality of temporary retaining wall units are filled with blocking bodies, the plurality of temporary retaining wall units can be stacked in the horizontal direction and in the height direction within the establishment range of the stress temporary dam, the interiors of the plurality of temporary retaining wall units are respectively provided with steel sheet piles extending in the direction of the waterway to form a dam unit structure, each of the steel sheet piles is inserted into an impermeable stratum and the steel sheet piles are connected to form an overall structure.
[0007] The temporary retaining wall unit body includes a plurality of soil anchor rods, and a flexible mesh is arranged between the soil anchor rods to form a whole and enclose the filling space of the blocking body; the flexible mesh has a steel sheet pile connecting section adapted to the steel sheet piles, and the steel sheet piles in adjacent temporary retaining wall unit bodies are connected and fixed by the steel sheet pile connecting section to form an integral structure.
[0008] The lower end of the soil anchor rod of the temporary retaining wall unit has a conical tip and is sleeved with a tubular support. The flexible mesh is connected to the tubular support. The conical tip matches the tubular support, so that the soil anchor rod can be inserted into the tubular support in the height direction, thereby realizing the superposition of the temporary retaining wall unit in the height direction.
[0009] The temporary retaining wall units adjacent to each other in the horizontal direction share the soil anchor rods and the tubular supports.
[0010] The flexible mesh is provided with mesh reinforcing ribs arranged in a crisscross pattern on its surface.
[0011] At least two rows of the steel sheet piles are arranged in the temporary retaining wall unit, and the steel sheet piles in each row are arranged at intervals.
[0012] A plurality of reinforcing steels are inserted into the temporary retaining wall unit body, and the plurality of reinforcing steels are evenly spaced and arranged along the extension direction of the waterway.
[0013] The advantages of the utility model are:
[0014] 1) The embankment unit structure is assembled into an emergency temporary embankment. The embankment laying plan can be flexible according to needs and leave room for reinforcement.
[0015] 2) Most of the components of the dam unit structure are standard parts; the combination of factory prefabrication and on-site assembly is adopted to suit the use scenarios of emergency temporary dams.
[0016] 3) Use steel sheet piles as the anti-seepage body of the dam to solve the anti-seepage problem, and use steel sheet piles of different lengths according to different stratum distributions.
[0017] 4) The backfill soil within the dam unit structure can serve as both the main body of flood control and the protective layer of the steel sheet pile anti-seepage body, reducing the impact damage of water flow.
[0018] 5) The emergency temporary dam composed of dam unit structure saves more space and filling materials than the general earth-rock dam, and the reserved water-passing section is larger than that of the general earth-rock dam.
[0019] 6) The unit structures of the dam are all made of recyclable materials and can be reused, which meets the requirements of emergency temporary dams.
[0020] 7) When using the emergency temporary embankment, it is convenient to add unit structures to meet the needs of thickening and raising the embankment; impact-resistant I-beams or H-beams can be added to enhance the impact resistance of the embankment. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is a schematic diagram of the dam unit structure of the utility model;
[0022] Figure 2 This is a schematic diagram of the cross-section structure of a conventional rock dam;
[0023] Figure 3 It is a schematic diagram of the cross-sectional structure of the emergency temporary dam of the utility model;
[0024] Figure 4 for Figure 3 Floor plan of
[0025] Figure 5 It is a structural schematic diagram of the temporary retaining wall unit in the utility model. DETAILED DESCRIPTION
[0026] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:
[0027] like Figure 1-5 As shown in the figure, marks 1-14 respectively represent: embankment unit structure 1, fill 2, first row of steel sheet piles 3, second row of steel sheet piles 4, steel sheet pile connecting section 5, soil layer anchor rods 6, tubular supports 7, reinforced steel 8, earth-rock dam 9, water body 10, steel sheet piles 11, temporary retaining wall unit 12, flexible mesh 13, mesh reinforcement ribs 14.
[0028] Example: Figure 2 As shown, when the conventional stress temporary dam adopts the earth-rock dam 9 as the dam solution, it mainly realizes the flood control function by increasing the deadweight of the filled sand, but the conventional sand accumulation angle is small, so it has to form a slope in the structure, resulting in a large area, a large amount of sand, and poor impermeability of the temporary pile, which is prone to seepage defects. In severe cases, the earth-rock dam 9 itself may also have the risk of breaking. At the same time, due to the slope formed by the accumulation angle, its water-passing section is also greatly limited.
[0029] The flood-resistant dam bank protection structure in this embodiment adopts an upright dam unit structure 1 to assemble an emergency temporary dam. Its laying plan can be flexibly expanded according to needs and has a large reinforcement space. At the same time, it adopts a combination of factory prefabrication and on-site assembly to achieve rapid construction of temporary dams in emergency scenarios.
[0030] Combination Figure 1 , Figure 3 and Figure 5As shown, the flood-resistant dam bank protection structure in this embodiment includes a dam unit structure 1, which is mainly composed of a temporary retaining wall unit 12 and the backfill 2 and steel sheet piles 11 inside it, wherein the temporary retaining wall unit 12 is filled with backfill 2 as a sealing body, and the backfill 2 is used as the main body of flood control to resist the impact of water flow. The steel sheet piles 11 are arranged in the backfill 2 as a dam anti-seepage body to solve the anti-seepage problem. The backfill 2 and the steel sheet piles 11 are combined to form an anti-seepage sandwich wall; at this time, the backfill 2 can also serve as a protective layer for the steel sheet piles 11 to reduce the damage caused by water flow impact.
[0031] Combination Figure 1 and Figure 5 As shown, the temporary retaining wall unit 12 in this embodiment mainly includes four soil anchor rods 6, a flexible mesh 13, four tubular supports 7 and mesh reinforcement ribs 14. Among them, the four soil anchor rods 6 are respectively inserted into the four tubular supports 7, and the bottom of the soil anchor rod 6 is provided with a cone tip to facilitate its insertion into the soil and ensure its uprightness. A flexible mesh 13 is provided between two adjacent tubular supports 7 to connect the four tubular supports 7 and the four soil anchor rods 14 into an integral structure and enclose a filling space for forming the fill 2. When in use, the flexible mesh 13 constrains the internal fill 2 to prevent the fill 2 from leaking out, and the four soil anchor rods 6 are used to fix the dam unit structure 1 as a whole in the soil. In order to further improve the structural strength and constraint performance of the flexible mesh 13, mesh reinforcement ribs 14 arranged in a criss-cross pattern are provided within the width of the flexible mesh 13.
[0032] Combination Figure 1 and Figure 4 As shown, a steel sheet pile 11 is arranged in each temporary retaining wall unit 12, and the steel sheet pile 11 is arranged along the waterway direction of the water body 10, and its bottom is inserted into the impermeable stratum; the length of the steel sheet pile 11 is selected according to different stratum distributions. A steel sheet pile connecting section 5 is arranged on the flexible mesh 13, and the steel sheet pile connecting section 5 is used to connect the steel sheet piles 11 arranged in two adjacent temporary retaining wall units 12 to form an integral structure, thereby improving the anti-seepage performance. In some cases, both sides of the steel sheet pile connecting section 5 have connectors that match the joints of the steel sheet pile 11, so that a quick connection between the steel sheet pile 11 and the steel sheet pile connecting section 5 can be achieved. For example, a nested structure is adopted, and the end joint of the steel sheet pile 11 is provided with a convex part, and the end of the steel sheet pile connecting section 5 is provided with a concave part, and the nesting is formed by the concave-convex adaptation. In addition, in order to ensure the assembly accuracy of the steel sheet piles 11 , a detachable connection structure such as a nested one is also provided between the steel sheet pile connecting section 5 and the flexible mesh 13 , so that the steel sheet piles 11 can be constructed before the temporary retaining wall unit 12 .
[0033] contrast Figure 1 and Figure 4As shown, one or more rows of steel sheet piles 11 can be arranged in the temporary retaining wall unit 12 according to different anti-seepage requirements. Figure 4 In the embodiment, only one row of steel sheet piles 11 is provided in the temporary retaining wall unit 12 to meet the needs. Figure 1 In the embodiment, a first row of steel sheet piles 3 and a second row of steel sheet piles 4 are arranged in the temporary retaining wall unit 12, for a total of two rows of steel sheet piles, to meet the anti-seepage requirements. However, in order to facilitate the adjustment of the number and position of the steel sheet piles, a plurality of steel sheet pile connection sections 5 are reserved on the flexible mesh 13 for construction selection, for example Figure 1 As shown, steel sheet pile connecting sections 5 are reserved on both sides of the first row of steel sheet piles 3 .
[0034] like Figure 1 and Figure 3 As shown, in order to improve the impact resistance of the dam unit structure 1, a reinforcing steel 8 is inserted inside the water side of the dam unit structure 1. The reinforcing steel 8 can be an impact-resistant reinforcing structure such as an I-beam or an H-beam. A plurality of reinforcing steels 8 are arranged at intervals along the waterway direction of the water body 10 to improve the overall impact resistance of the dam unit structure 1.
[0035] In this embodiment, the coordination between the dam unit structures 1 can be mainly achieved in the following forms:
[0036] 1) Horizontal extension: Figure 1 or Figure 4 As shown, each dam unit structure 1 adjacent to each other in the longitudinal direction of the water flow can share the soil anchor rod 6 and the tubular support 7. In this case, a flexible mesh 13 is provided between adjacent tubular supports 7 to improve the integrity of each dam unit structure 1, further ensure the continuity of the steel sheet piles 11, and effectively reduce the construction cost. Similarly, each dam unit structure 1 adjacent to each other in the transverse direction of the water flow can also be constructed by sharing the soil anchor rod 6 and the tubular support 7.
[0037] 2) Accumulation stacking in height direction: such as Figure 3 As shown, the positions of the tubular supports 7 of the upper and lower adjacent dam unit structures 1 match each other, and by inserting soil anchor rods 6 of the required length into the through-through tubular supports 7, the tubular supports 7 can be connected into an integral structure, thereby connecting several dam unit structures 1 into an integral structure in the height direction. In some cases, the dam unit structures 1 can also be stacked in pairs, for example: a certain gap is left at the top of the tubular supports 7 of the dam unit structure 1 of the lower layer, and the bottom of the soil anchor rod 6 of the upper dam unit structure 1 is inserted into the tubular support 7 of the lower dam unit structure 1, and the soil anchor rod 6 of the lower dam unit structure 1 is directly inserted into the soil, so that the dam unit structures 1 can also be stacked in the height direction.
[0038] contrast Figure 2 and Figure 3 As shown, the emergency temporary dam composed of the dam unit structure 1 in this embodiment is a vertical water retaining structure system, which has a larger water-passing section compared to the conventional earth-rock dam 9, and can thus hold more water.
[0039] When applied, this embodiment mainly includes the following functions:
[0040] 1) An emergency temporary dam is built through the dam unit structure 1, and the interior is filled with fill 2 to resist the impact of water flow. Steel sheet piles 11 are used as the dam anti-seepage body to solve the seepage problem, and reinforced steel 8 is used to improve the impact resistance of the emergency temporary dam.
[0041] 2) When the emergency temporary embankment needs to be strengthened according to the flood situation, it is possible to choose to add reinforcing steel 8 to the embankment unit structure 1 to improve its own impact resistance, or to build one or more rows of embankment unit structures 1 behind the existing emergency temporary embankment to resist the lateral impact force of the water body to one side of the emergency temporary embankment.
[0042] 3) When the height of the emergency temporary embankment needs to be increased according to the flood situation, a temporary embankment unit 1 is directly constructed above the existing stress temporary embankment to meet the heightening requirement.
[0043] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.
Claims
1. A flood-resistant dam bank protection structure, used to establish a stress temporary dam on one side of a waterway, characterized by: It comprises a plurality of temporary retaining wall units, each of which is filled with a blocking body. The plurality of temporary retaining wall units can be stacked in the horizontal direction and the height direction within the establishment range of the stress temporary dam. The plurality of temporary retaining wall units are respectively provided with steel sheet piles extending in the direction of the waterway to form a dam unit structure. Each of the steel sheet piles is inserted into an impermeable stratum and the steel sheet piles are connected to form an overall structure.
2. The flood-resistant dam bank protection structure according to claim 1, characterized in that: The temporary retaining wall unit body includes a plurality of soil anchor rods, and a flexible mesh is arranged between the soil anchor rods to form a whole and enclose the filling space of the blocking body; the flexible mesh has a steel sheet pile connecting section adapted to the steel sheet piles, and the steel sheet piles in adjacent temporary retaining wall unit bodies are connected and fixed by the steel sheet pile connecting section to form an integral structure.
3. The flood-resistant dam bank protection structure according to claim 2 is characterized by: The lower end of the soil anchor rod of the temporary retaining wall unit has a conical tip and is sleeved with a tubular support. The flexible mesh is connected to the tubular support. The conical tip matches the tubular support, so that the soil anchor rod can be inserted into the tubular support in the height direction, thereby realizing the superposition of the temporary retaining wall unit in the height direction.
4. The flood-resistant dam bank protection structure according to claim 3 is characterized by: The temporary retaining wall units adjacent to each other in the horizontal direction share the soil anchor rods and the tubular supports.
5. The flood-resistant dam bank protection structure according to claim 2, characterized in that: The flexible mesh is provided with mesh reinforcing ribs arranged in a crisscross pattern on its surface.
6. The flood-resistant dam bank protection structure according to claim 1, characterized in that: At least two rows of the steel sheet piles are arranged in the temporary retaining wall unit, and the steel sheet piles in each row are arranged at intervals.
7. The flood-resistant dam bank protection structure according to claim 1, characterized in that: A plurality of reinforcing steels are inserted into the temporary retaining wall unit body, and the plurality of reinforcing steels are evenly spaced apart along the extension direction of the waterway.
Citation Information
Cited By
Flood-fighting dam bank protection construction method
CN118166705A