Long-distance TBM (Tunnel Boring Machine) construction tunnel vehicle staggering traffic structure platform

By designing a wrong-car traffic structure platform and using two-way four-track structures and support steel plates, the problem that single-line transportation in long-distance TBM construction tunnels cannot meet the needs, achieving two-way transportation and improving construction efficiency.

CN222141253UActive Publication Date: 2024-12-10SICHUAN ERTAN INT ENG CONSULTING
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420469813.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-12
Publication Date
2024-12-10
Estimated Expiration
2034-03-12

AI Technical Summary

Technical Problem

In long-distance TBM construction tunnels, single-line rail transportation cannot meet the construction needs, resulting in the impact of the construction progress and the inability to meet the needs of transporting materials and equipment.

Method used

A long-distance TBM construction tunnel miscarriage traffic structure platform is designed, including miscarriage section, uphill section and downhill section. The miscarriage section is a two-way four-track structure. The first and second single turnouts are used to perform the motorcycle wrong car, and the support steel plate is used. The steel plates on the contact surface support the track to ensure two-way transportation.

Benefits of technology

The single-line transportation is designed as two-way transportation, which improves the transportation efficiency of TBM tunnel construction and avoids the impact of construction progress caused by transportation pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222141253U_ABST
    Figure CN222141253U_ABST
Patent Text Reader

Abstract

The utility model discloses a long-distance tunnel boring machine (TBM) construction tunnel vehicle staggering traffic structure platform which comprises a vehicle staggering section, an uphill section and a downhill section. The uphill section and the downhill section are arranged on the two sides of the vehicle staggering section and connected. The vehicle staggering section is of a two-way running four-track structure, and the uphill section and the downhill section are of a one-way running double-track structure; a first single-open turnout is arranged at the joint of the vehicle staggering section and the uphill section, and a second single-open turnout is arranged at the joint of the vehicle staggering section and the downhill section; the vehicle staggering section comprises a first cross arm, a first supporting leg arranged below the first cross arm and connected with the first cross arm, and a supporting steel plate for connecting the first cross arm with the first supporting leg; the first transverse support is perpendicular to the track, the bottom of the first supporting leg is connected with the rock wall, and the two ends of the first transverse support are connected with the rock wall. According to the utility model, the technical problem that the single-line transportation of TBM tunnel construction cannot meet the construction requirements is solved, and the technical effect that the single-line transportation of TBM tunnel construction is designed into two-way transportation is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel excavation, in particular to a long-distance TBM construction tunnel vehicle passing traffic structure platform. Background Art

[0002] With the continuous improvement of tunnel boring machine manufacturing technology, many long and large tunnels in China use TBM (full-section tunnel boring machine) to replace the traditional drilling and blasting method. Among them, the TBM single-head excavation distance is as long as 18km, and the maximum daily footage is as high as more than 70 meters. The high footage puts forward high standards for construction traffic in the tunnel. Most of the domestic TBM construction tunnels have circular cross-sections. The use of rail transportation has the advantages of high safety performance and easy operation, and has been widely promoted and applied.

[0003] Rail transport in TBM construction tunnels usually uses a locomotive to pull a train plate for transportation. Due to the cross-section of the cavern, the conventional transportation plan mainly uses single-line transportation. During the tunnel excavation process, more materials and equipment are transported, resulting in greater transportation pressure. Therefore, simple single-line transportation can no longer meet construction needs. In serious cases, it will affect the construction progress and cause TBM shutdown. Utility Model Content

[0004] In order to solve the above problems, the utility model provides a long-distance TBM construction tunnel passing traffic structure platform, comprising: a passing section, and an uphill section and a downhill section arranged on both sides of the passing section and connected to each other;

[0005] The passing section is a four-track structure for bidirectional travel, and the uphill section and the downhill section are double-track structures for unidirectional travel;

[0006] A first single-opening turnout is provided at the connection between the passing section and the uphill section, and a second single-opening turnout is provided at the connection between the passing section and the downhill section;

[0007] The train-staggering section comprises: a first cross brace, a first leg disposed below and connected to the first cross brace, and a supporting steel plate connecting the first cross brace and the first leg;

[0008] The first cross brace is arranged perpendicular to the track, the bottom of the first leg is connected to the rock wall, and both ends of the first cross brace are connected to the rock wall.

[0009] In some embodiments, the uphill section and the downhill section have the same structure, including: a second cross brace, a second leg disposed below the second cross brace, and a second contact surface steel plate located at both ends of the second leg.

[0010] In some embodiments, the contact surface between the first cross brace and the rock wall is further provided with a first contact surface steel plate.

[0011] In some embodiments, the first cross brace, the first leg, the second cross brace and the second leg are all steel sections.

[0012] In some embodiments, a connecting piece is further connected between adjacent first legs.

[0013] By adopting the above technical solution, the utility model mainly has the following technical effects:

[0014] By setting up a four-track structure for bidirectional travel and using the passing section to pass locomotives traveling in both directions, the technical problem that single-line transportation for TBM tunnel construction can no longer meet construction needs is solved, and the technical effect of designing single-line transportation for TBM tunnel construction as bidirectional transportation is achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a schematic diagram of the structure of a long-distance TBM construction tunnel traffic structure platform of the utility model;

[0016] Figure 2 This is a structural schematic diagram of a passing section in a long-distance TBM construction tunnel passing traffic structure platform of the utility model;

[0017] Figure 3 The utility model is a schematic structural diagram of a downhill section of a long-distance TBM construction tunnel passing traffic structure platform.

[0018] The meanings of the reference numerals are as follows:

[0019] 1. Staggered section; 11. First cross brace; 12. First leg; 13. Support steel plate; 14. First contact surface steel plate; 15. Connector;

[0020] 2. Uphill section; 21. Second cross brace; 22. Second leg; 23. Second contact surface steel plate;

[0021] 3. Downhill section;

[0022] 4. The first single turnout is opened;

[0023] 5. Open the turnout for the second track. DETAILED DESCRIPTION

[0024] In order to enable those skilled in the art to better understand the solution of the utility model, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the specification of the utility model. Obviously, the described embodiment is only a part of the embodiment of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0026] See also Figure 1-Figure 3 The utility model provides a long-distance TBM construction tunnel passing traffic structure platform, which includes: a passing section 1, and an uphill section 2 and a downhill section 3 which are arranged on both sides of the passing section 1 and connected.

[0027] In some embodiments, the passing section 1 is a four-track structure for bidirectional travel, and the uphill section 2 and the downhill section 3 are double-track structures for unidirectional travel. By setting the passing section 1 as a four-track structure for bidirectional travel, the passing section 1 is used to pass the locomotives traveling in both directions, so that the rail transportation in the TBM construction tunnel can be designed from a simple single-track transportation to a two-way transportation.

[0028] Furthermore, a first single-open turnout 4 is provided at the connection between the passing section 1 and the uphill section 2, and a second single-open turnout 5 is provided at the connection between the passing section 1 and the downhill section 3, wherein the first single-open turnout 4 and the second single-open turnout 4 are both used to adjust the traveling direction of the locomotive. In some embodiments, a dedicated person is arranged to be in charge of the turnout switches of the first single-open turnout 4 and the second single-open turnout 4, and the first single-open turnout 4 and the second single-open turnout 4 are used to select a suitable track, so that the locomotives in bidirectional transportation are stopped in the passing section 1 respectively, so as to achieve the function of passing the locomotives in bidirectional transportation.

[0029] In some embodiments, the train passing section 1 includes: a first cross brace 11, a first leg 12 provided below and connected to the first cross brace 11, and a support steel plate 13 connecting the first cross brace 11 to the first leg 12. In some embodiments, the first cross brace 11 is provided perpendicular to the track and is used to support the bidirectional track provided on the first cross brace 11, the bottom of the first leg 12 is connected to the rock wall, and both ends of the first cross brace 11 are connected to the rock wall, so that the first cross brace 11 is supported by the first leg 12, and the bidirectional track is supported by the first cross brace 11.

[0030] In some embodiments, the contact surface between the first cross brace 11 and the rock wall is further provided with a first contact surface steel plate 14, and the first contact surface steel plate 14 is used to increase the contact area between the first cross brace 11 and the rock wall, thereby dispersing a portion of the load on the first cross brace 11 to the rock wall, thereby avoiding sinking of the sleeper due to excessive load acting on the first leg 12, causing an accident.

[0031] In some embodiments, the supporting steel plate 13 is a reinforcing plate connecting the first cross brace 11 and the first supporting leg 12 , and is used to enhance the stability of the connection between the first cross brace 11 and the first supporting leg 12 .

[0032] In some embodiments, connecting members 15 are further connected between adjacent first legs 12 to support the stability of the first legs 12 .

[0033] Furthermore, the uphill section 2 has the same structure as the downhill section 3, and is used to support the locomotive for transportation, and includes: a second cross brace 21, a second leg 22 disposed below the second cross brace 21, and second contact surface steel plates 23 disposed at both ends of the second leg 22, and the second cross brace 21 is connected to the rock wall via the second contact surface steel plates 23. In some embodiments, the bottom of the second leg 22 is connected to the rock wall, so that the second cross brace 21 is supported by the second leg 22, and the second cross brace 21 plays a role in supporting the one-way track. Of course, by providing the second contact surface steel plate 23, part of the load on the second cross brace 21 can also be dispersed to the rock wall, thereby avoiding the sinking of the sleeper due to excessive load acting on the second leg 22, causing an accident.

[0034] In some embodiments, the first cross brace 11, the first leg 12, the second cross brace 21 and the second leg 22 are all made of steel sections, which have the advantages of high strength and high bearing capacity, and can provide excellent support for the track.

[0035] It can be understood that the passing section 1 is bidirectional and has a higher load than the uphill section 2 and the downhill section 3 which are unidirectional. The stability of the passing section 1 can be effectively guaranteed by providing the supporting steel plate 13 and the connecting member 15 .

[0036] Finally, it should be noted that the embodiments of the present invention disclose only preferred embodiments of the present invention, which are only used to illustrate the technical solutions of the present invention, rather than to limit them. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present invention.

Claims

1. A long-distance TBM construction tunnel passing traffic structure platform, characterized in that: include: A passing section, and an uphill section and a downhill section connected to each other on both sides of the passing section; The passing section is a four-track structure for bidirectional travel, and the uphill section and the downhill section are double-track structures for unidirectional travel; A first single-opening turnout is provided at the connection between the passing section and the uphill section, and a second single-opening turnout is provided at the connection between the passing section and the downhill section; The train-staggering section comprises: a first cross brace, a first leg disposed below and connected to the first cross brace, and a supporting steel plate connecting the first cross brace and the first leg; The first cross brace is arranged perpendicular to the track, the bottom of the first leg is connected to the rock wall, and both ends of the first cross brace are connected to the rock wall.

2. A long-distance TBM construction tunnel traffic structure platform according to claim 1, characterized in that: The uphill section has the same structure as the downhill section, and includes: a second cross brace, a second leg disposed below the second cross brace, and second contact surface steel plates located at both ends of the second leg.

3. A long-distance TBM construction tunnel traffic structure platform according to claim 1, characterized in that: The contact surface between the first cross brace and the rock wall is also provided with a first contact surface steel plate.

4. A long-distance TBM construction tunnel traffic structure platform according to claim 2, characterized in that: The first cross brace, the first supporting leg, the second cross brace and the second supporting leg are all steel sections.

5. A long-distance TBM tunnel construction traffic structure platform according to claim 1, characterized in that: A connecting piece is also connected between adjacent first legs.