Construction engineering pile
By designing drill bits, drainage grooves, bayonets and other components in construction engineering piles to fix the pile body, the problem of pile body deviation during concrete pouring is solved, and the project quality and stability of pile body are improved.
Patent Information
- Application Number
- CN202420553972.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2034-03-21
AI Technical Summary
During the pouring of concrete, the engineering piles may be offset, affecting the quality of the project.
A construction engineering pile is designed, including drill bits, drainage grooves, bayonets, blocks, limit rods, fixing plates, rotating plates and stabilizing components. Through the cooperation of these components, the pile body rotates by rotation after being inserted into the soil. The rod and the clamps use the cooperation of the bayonets and clamps to fix the pile body to avoid deviation.
It effectively solves the possible deviation problems of engineering piles during the pouring of concrete, improves the quality of the project, and ensures the stability and strength of the pile body.
Smart Images

Figure CN222206295U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to a construction engineering pile. Background Art
[0002] Construction engineering piles refer to a type of basic engineering material used to support buildings or other engineering structures. They can ensure the stability and safety of the buildings. However, during the piling process, the soil layer of traditional engineering piles is squeezed and becomes compacted, making it more difficult to drive the pile further downward.
[0003] To solve the above problems, the prior art patent (CN212956504U) discloses a construction engineering pile. During the continuous downward movement, soil will enter the inner tube along the guide groove, the first strip through hole and the second strip through hole, so that the pile body can move downward more smoothly.
[0004] However, in the above-mentioned prior art, after the engineering piles are inserted into the soil, the engineering piles may deviate during the process of pouring concrete, which affects the quality of the project. Utility Model Content
[0005] The utility model aims to provide a construction engineering pile, which solves the technical problem in the prior art that when the engineering pile is inserted into the soil, the engineering pile may deviate during the pouring of concrete, thereby affecting the quality of the project.
[0006] To achieve the above-mentioned purpose, the utility model adopts a construction engineering pile, including a pile body, a drill bit, a soil discharge groove and a fixing component, wherein the fixing component includes a bayonet, a block, a limit rod, a fixing plate, a rotating plate and a stabilizing component, the drill bit is fixedly connected to the pile body and is located below the pile body, the soil discharge groove is arranged on the surface of the drill bit, the bayonet is arranged at the lower end of the pile body, the fixing plate is fixedly connected to the drill bit and is located above the drill bit, the block is slidably connected to the fixing plate and is located inside the fixing plate, and the block is adapted to the bayonet, the limit rod is fixedly connected to the block and is located above the block, and the rotating plate is rotatably connected to the fixing plate and is located above the fixing plate.
[0007] Among them, the fixing assembly also includes a connecting block, a rotating rod and a handle, the connecting block is fixedly connected to the rotating plate and is located above the rotating plate, one end of the rotating rod is snap-connected to the connecting block and is located inside the connecting block, and the handle is fixedly connected to the rotating rod and is located at the other end of the rotating rod.
[0008] Among them, the stabilizing component includes a soil discharge trough, a fixed steel bar and a slot, the soil discharge trough is arranged on the outer surface of the pile body, the fixed steel bar is fixedly connected to the drill bit and is located above the drill bit, and the slot is arranged on the upper surface of the pile body.
[0009] Wherein, the stabilizing component also includes a stabilizing plate 1 and a stabilizing plate 2, wherein the stabilizing plate 1 is fixedly connected to the pile body and located on one side of the pile body, and the stabilizing plate 2 is fixedly connected to the pile body and located on one side of the pile body.
[0010] Among them, the construction engineering pile also includes handle 1 and handle 2, the handle 1 is fixedly connected to the stabilizing plate 1 and is located above the stabilizing plate 1, and the handle 2 is fixedly connected to the stabilizing plate 2 and is located above the stabilizing plate 2.
[0011] The utility model provides a construction engineering pile, the drill bit is fixedly connected to the pile body and is located below the pile body, the soil discharge groove is arranged on the surface of the drill bit, the bayonet is arranged at the lower end of the pile body, the fixing plate is fixedly connected to the drill bit and is located above the drill bit, the clamping block is slidably connected to the fixing plate and is located inside the fixing plate, and the clamping block is adapted to the bayonet, the limiting rod is fixedly connected to the clamping block and is located above the clamping block, the rotating plate is rotatably connected to the fixing plate and is located above the fixing plate, when the engineering pile is inserted into the soil as a whole, the handle is held to rotate the rotating rod to rotate the rotating plate, the clamping block is inserted into the soil through the bayonet, and the engineering pile is fixed as a whole, and this method can effectively solve the problem. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0013] Figure 1 It is a structural schematic diagram of the first embodiment of the utility model.
[0014] Figure 2 It is a side view of the first embodiment of the utility model.
[0015] Figure 3 The utility model Figure 2 AA line structural section view.
[0016] Figure 4 It is a partial structural schematic diagram of the first embodiment of the utility model.
[0017] Figure 5 It is a structural schematic diagram of the second embodiment of the utility model.
[0018] 101-pile body, 102-drill bit, 103-soil discharge trough 1, 104-bayonet, 105-block, 106-limit rod, 107-fixed plate, 108-rotating plate, 109-connecting block, 110-rotating rod, 111-handle, 112-soil discharge trough 2, 113-fixed steel bar, 114-slot, 115-stabilizing plate 1, 116-stabilizing plate 2, 201-handle 1, 202-handle 2. DETAILED DESCRIPTION
[0019] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0020] The first embodiment of the present application is:
[0021] See also Figure 1 to Figure 4 ,in Figure 1 It is a schematic structural diagram of the first embodiment of the utility model. Figure 2 is a side view of the first embodiment of the utility model, Figure 3 The utility model Figure 2 AA line structural section view, Figure 4 It is a partial structural schematic diagram of the first embodiment of the utility model.
[0022] The utility model provides a construction engineering pile, including a pile body 101, a drill bit 102, a soil discharge trough 103, a bayonet 104, a block 105, a limit rod 106, a fixed plate 107, a rotating plate 108, a connecting block 109, a rotating rod 110, a handle 111, a soil discharge trough 112, a fixed steel bar 113, a slot 114, a stabilizing plate 115 and a stabilizing plate 116. The above scheme solves the problem in the prior art that when the engineering pile is inserted into the soil and during the process of pouring concrete, the engineering pile may deviate, thereby affecting the quality of the project.
[0023] According to the present specific embodiment, the drill bit 102 is fixedly connected to the pile body 101 and is located below the pile body 101, the soil discharge groove 103 is arranged on the surface of the drill bit 102, the bayonet 104 is arranged at the lower end of the pile body 101, the fixed plate 107 is fixedly connected to the drill bit 102 and is located above the drill bit 102, the block 105 is slidably connected to the fixed plate 107 and is located inside the fixed plate 107, and the block 105 is adapted to the bayonet 104, the limit rod 106 is fixedly connected to the block 105 and is located above the block 105, the rotating plate 108 is rotatably connected to the fixed plate 107 and is located above the fixed plate 107, and the rotating plate 108 is rotated to drive the block 105 to slide out of the fixed plate 107 and insert it into the soil through the bayonet 104, so as to achieve the purpose of fixing the engineering pile.
[0024] Among them, the connecting block 109 is fixedly connected to the rotating plate 108 and is located above the rotating plate 108, one end of the rotating rod 110 is snap-connected to the connecting block 109 and is located inside the connecting block 109, the handle 111 is fixedly connected to the rotating rod 110 and is located at the other end of the rotating rod 110, the connecting block 109 connects the rotating rod 110 with the rotating plate 108, and the handle 111 facilitates workers to rotate the rotating rod 110.
[0025] Secondly, the soil discharge trough is arranged on the outer surface of the pile body 101, the fixing steel bar 113 is fixedly connected with the drill bit 102 and is located above the drill bit 102, the slot 114 is arranged on the upper surface of the pile body 101, the slot 114 is connected with the piling equipment so that the pile body 101 rotates to drill downward, and the drilled soil is discharged from the soil discharge trough 112. When the fixation is completed, cement is poured into the pile body 101. The fixing steel bar 113 can increase the strength of the pile body 101.
[0026] At the same time, the stabilizing plate 115 is fixedly connected to the pile body 101 and is located on one side of the pile body 101, and the stabilizing plate 2 116 is fixedly connected to the pile body 101 and is located on one side of the pile body 101. When the pile body 101 is fixed in the soil, the upper end of the pile body 101 that is exposed on the surface of the soil layer can be fixed by the stabilizing plate 115 and the stabilizing plate 2 116.
[0027] A construction engineering pile using the present embodiment is provided with a pile body 101, a drill bit 102, a soil discharge groove 103, a bayonet 104, a block 105, a limit rod 106, a fixed plate 107, a rotating plate 108, a connecting block 109, a rotating rod 110, a handle 111, a soil discharge groove 112, a fixed steel bar 113, a slot 114, a stabilizing plate 115 and a stabilizing plate 116. The drill bit 102 is fixedly connected to the pile body 101 and is located below the pile body 101. The soil discharge groove 103 is provided on the surface of the drill bit 102. The bayonet 104 is provided at the lower end of the pile body 101. The fixing plate 107 is fixedly connected to the drill bit 102 and is located above the drill bit 102. The block 105 is slidably connected to the fixing plate 107. It is located inside the fixed plate 107, and the block 105 is adapted to the bayonet 104, the limit rod 106 is fixedly connected to the block 105 and is located above the block 105, the rotating plate 108 is rotatably connected to the fixed plate 107 and is located above the fixed plate 107, when the pile body 101 reaches the target depth, the handle 111 is held to rotate the rotating rod 110, and the rotating plate 108 is driven to rotate through the connecting block 109, and the limit rod 106 is driven to move, and the limit rod 106 drives the block 105 to be inserted into the soil through the bayonet 104, so as to fix the engineering pile as a whole, and solves the problem that the engineering pile may be offset during the pouring of concrete after the engineering pile is inserted into the soil, which affects the technical problem of engineering quality.
[0028] The second embodiment of the present application is:
[0029] Based on the first embodiment, please refer to Figure 5 , Figure 5 It is a structural schematic diagram of the second embodiment of the utility model.
[0030] The utility model provides a construction engineering pile, which also includes a first handle 201 and a second handle 202. The above solution solves the problem that the overall construction pile is inconvenient to move in the prior art.
[0031] Among them, the handle 1 201 is fixedly connected to the stabilizing plate 1 15 and is located above the stabilizing plate 1 15, and the handle 2 202 is fixedly connected to the stabilizing plate 2 116 and is located above the stabilizing plate 2 116. The engineering pile can be easily moved as a whole by the handle 1 201 and the handle 2 202.
[0032] Using a construction engineering pile of the present embodiment, by providing a handle 1 201 and a handle 202, when the engineering pile needs to be moved, the engineering pile can be moved as a whole by holding the handle 1 201 and the handle 2 202 by hand or by fixing the handle 1 201 and the handle 2 202 with a machine, thereby solving the problem of the inconvenience of moving the engineering pile as a whole.
[0033] The above disclosure is only a preferred embodiment of the present invention, and certainly cannot be used to limit the scope of rights of the present invention. Ordinary technicians in this field can understand that all or part of the processes of the above embodiment and equivalent changes made according to the claims of the present invention still fall within the scope covered by the utility model.
Claims
1. A construction engineering pile, comprising a pile body, a drill bit and a soil discharge groove, wherein the drill bit is fixedly connected to the pile body and is located below the pile body, and the soil discharge groove is arranged on the surface of the drill bit, characterized in that: It also includes a fixing assembly, which includes a bayonet, a block, a limiting rod, a fixing plate, a rotating plate and a stabilizing component, the bayonet is arranged at the lower end of the pile body, the fixing plate is fixedly connected to the drill bit and is located above the drill bit, the block is slidably connected to the fixing plate and is located inside the fixing plate, and the block is adapted to the bayonet, the limiting rod is fixedly connected to the block and is located above the block, and the rotating plate is rotatably connected to the fixing plate and is located above the fixing plate.
2. The construction engineering pile according to claim 1, characterized in that: The fixing assembly also includes a connecting block, a rotating rod and a handle. The connecting block is fixedly connected to the rotating plate and is located above the rotating plate. One end of the rotating rod is clamped with the connecting block and is located inside the connecting block. The handle is fixedly connected to the rotating rod and is located at the other end of the rotating rod.
3. The construction engineering pile according to claim 1, characterized in that: The stabilizing component includes a soil discharge trough 2, a fixed steel bar and a slot. The soil discharge trough is arranged on the outer surface of the pile body. The fixed steel bar is fixedly connected to the drill bit and is located above the drill bit. The slot is arranged on the upper surface of the pile body.
4. The construction engineering pile according to claim 1, characterized in that: The stabilizing component also includes a stabilizing plate 1 and a stabilizing plate 2. The stabilizing plate 1 is fixedly connected to the pile body and located on one side of the pile body. The stabilizing plate 2 is fixedly connected to the pile body and located on one side of the pile body.
5. The construction engineering pile according to claim 4, characterized in that: The construction engineering pile also includes a first handle and a second handle. The first handle is fixedly connected to the first stabilizing plate and is located above the first stabilizing plate. The second handle is fixedly connected to the second stabilizing plate and is located above the second stabilizing plate.