Pipeline construction drainage structure

The pipeline construction drainage structure addresses the issue of sewage pump damage by incorporating a waterproof and cushion layer with a pumping mechanism and fixing system, ensuring protection and ease of maintenance, thereby enhancing construction efficiency.

CN222206434UActive Publication Date: 2024-12-20HUIZHOU DAYA BAY MUNICIPAL INFRASTRUCTURE CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202323614501.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-12-20
Estimated Expiration
2033-12-28

AI Technical Summary

Technical Problem

Existing pipeline construction drainage structures fail to effectively protect sewage pumps from mud and sand ingress, leading to frequent damage and delays in construction projects.

Method used

A pipeline construction drainage structure featuring a waterproof protective layer, cushion layer, and a pumping mechanism with a waterproof box, filter screens, and a fixing mechanism that includes a fixing rod, slider, and spring system to secure the pumping mechanism, allowing easy disassembly for maintenance.

Benefits of technology

The structure prevents mud and sand from entering the sewage pump, extends its service life, reduces maintenance frequency, and enhances construction efficiency by facilitating easy installation and disassembly of components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222206434U_ABST
    Figure CN222206434U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipeline construction drainage, in particular to a pipeline construction drainage structure. Comprising a foundation bottom plate, a waterproof protection layer fixed to the bottom end of the foundation bottom plate, a waterproof layer fixed to the bottom end of the waterproof protection layer, a cushion layer fixed to the bottom end of the waterproof layer, a water pumping pipe fixed in the foundation bottom plate, a mounting box fixed to the outer surface of the water pumping pipe and a water pumping mechanism mounted on the mounting box. According to the pipeline construction drainage structure, the water pumping mechanism is arranged on the mounting box, silt and gravel can be resisted outside the mounting box, and therefore the situation that the sewage pump is blocked by the silt and damaged is avoided, the service time of the sewage pump can be prolonged, the overhaul frequency of the sewage pump is reduced, and the water pumping efficiency is improved; the water pumping pipe and the water pumping mechanism can be conveniently mounted and dismounted, so that the water pumping mechanism can be conveniently taken out for dismounting, and components such as a foundation slab can be continuously used.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of pipeline construction drainage, and specifically to a pipeline construction drainage structure. Background Art

[0002] To bury the drainage pipe, the first thing is to check the site and arrange the power supply, drainage, earth transportation route, earth storage site and other work. Then, determine the center position of the inspection well and mark the earth excavation line on the ground according to the design drawing. At the same time, set leveling points and control piles along the pipeline. Their positions should not be affected by the construction. When preparations are ready, the pipe can be buried. There are two methods of burying pipes: open excavation, jacking method and shield method without breaking the ground. Open excavation is also called grooving and pipe laying method, which is suitable for small and medium diameter water pipes. During construction, trenches are excavated according to the determined lines.

[0003] For example, a Chinese patent (CN205205842U) discloses a local dewatering structure for a deep foundation pit, comprising: a cushion layer arranged at the bottom of the deep foundation pit; a waterproof layer arranged on the cushion layer; a foundation bottom plate arranged on the waterproof layer; a sump arranged under the cushion layer; a waterproof component arranged in the deep foundation pit, the dewatering component comprising: a pre-buried pipe, one end of the pre-buried pipe is inserted in the sump to form an insertion end, the insertion end is provided with a water permeable hole, and the other end of the pre-buried pipe is exposed from the foundation bottom plate; an upper water stop ring and a lower water stop ring are arranged on the pre-buried pipe, the upper water stop ring is fixed in the foundation bottom plate, and the lower water stop ring is fixed in the cushion layer; and a sewage pump is arranged in the sump.

[0004] The above scheme also has the following technical defects: the above scheme is not convenient for protecting the sewage pump. Since the sewage pump is in the sump, a large amount of mud and sand will enter the sewage pump when pumping water, which may easily cause blockage and damage to the sewage pump. After the sewage pump is damaged, the device needs to be removed to repair the sewage pump, which delays the progress of the project. Based on this, a pipeline construction drainage structure is proposed. Utility Model Content

[0005] In view of the deficiencies in the prior art, the present application provides a pipeline construction drainage structure, which has the advantages of convenient protection of the sewage pump and solves the problem that the sewage pump is easily damaged.

[0006] To achieve the above-mentioned purpose, the present application provides the following technical solutions: a pipeline construction drainage structure, comprising a foundation bottom plate, a waterproof protective layer fixed to the bottom end of the foundation bottom plate, a waterproof layer fixed to the bottom end of the waterproof protective layer, a cushion layer fixed to the bottom end of the waterproof layer, a water pumping pipe fixed to the inside of the foundation bottom plate, a mounting box fixed to the outer surface of the water pumping pipe, a water pumping mechanism mounted on the mounting box, a fixing mechanism mounted on the foundation bottom plate, and a drainage pipe fixed to the top end of the water pumping pipe;

[0007] The pumping mechanism includes a waterproof box fixed inside the installation box, a cleaning component installed on the installation box, two sets of filter screens fixed at the left and right ends of the installation box, and a sewage pump fixed at the top of the inner wall of the installation box.

[0008] By adopting the above technical solution, the mud and sand can be discharged outside the installation box, thereby protecting the sewage pump.

[0009] Furthermore, the fixing mechanism includes a fixing rod fixed inside the base plate, a sliding block slidably connected to the outer surface of the fixing rod, a spring sleeved on the outer surface of the fixing rod and a fixing component installed on the sliding block.

[0010] The adoption of the above technical solution can facilitate the disassembly of the pumping mechanism, thereby facilitating separate maintenance of the pumping mechanism.

[0011] Furthermore, the cleaning assembly includes a dual-axis motor fixed to the bottom end of the inner wall of the waterproof box, a rotating shaft fixed to the output shaft of the dual-axis motor, and a group of blades fixed to the outer surface of the rotating shaft.

[0012] The above technical solution makes it easy to clean the mud, sand and gravel on the surface of the installation box.

[0013] Furthermore, the fixing assembly includes a connecting rod fixed to the top of the slider, a limiting plate fixed to one end of the connecting rod, a bolt slidably connected to the inside of the fixing rod, and a nut threadedly connected to the outer surface of the bolt.

[0014] By adopting the above technical solution, the water pumping pipe can be fixed on the foundation bottom plate.

[0015] Furthermore, two first through holes are provided at both left and right ends of the installation box and the waterproof box, a first sealing ring is fixed inside the first through hole, and the rotating shaft is rotatably connected to the sealing ring.

[0016] The above technical solution can prevent mud and sand from entering the installation box and water from entering the waterproof box.

[0017] Furthermore, a second through hole is opened inside the base bottom plate, the waterproof protective layer, the waterproof layer and the cushion layer, a second sealing gasket is fixed in the second through hole, and the water pumping pipe is fixed in the second sealing gasket.

[0018] The above technical solution can prevent water from rising from the gap into the foundation slab.

[0019] Furthermore, a slide groove is provided inside the basic bottom plate, and the left and right ends of the fixing rod are fixed to the left and right sides of the slide groove.

[0020] The adoption of the technical solution makes it easy to install the fixing mechanism.

[0021] Furthermore, ear plates are fixed to both the front and rear ends of the limiting plate, and circular holes are formed on the ear plates, and the bolts slide in the circular holes.

[0022] By adopting the above technical solution, the limit plate is clamped by bolts and nuts.

[0023] Compared with the prior art, the technical solution of this application has the following beneficial effects:

[0024] 1. The pipeline construction drainage structure can block mud and gravel outside the installation box by providing a pumping mechanism on the installation box, thereby avoiding mud and sand blocking the sewage pump and causing damage to it, which can extend the service life of the sewage pump, reduce the maintenance frequency of the sewage pump, and thus improve the efficiency of pumping.

[0025] 2. The pipeline construction drainage structure can facilitate the installation and disassembly of the pumping pipe and the pumping mechanism by providing a fixing mechanism on the foundation bottom plate, thereby facilitating the removal and disassembly of the pumping mechanism, and the foundation bottom plate and other components can continue to be used. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 This is a schematic diagram of the structure of this application;

[0027] Figure 2 This is a schematic diagram of the structure of the pumping pipe, installation box and pumping mechanism for this application;

[0028] Figure 3 This is a schematic diagram of the structure of the fixing mechanism of this application;

[0029] Figure 4 It is a three-dimensional structural schematic diagram of the fixing mechanism part of the present application.

[0030] In the figure: 1. base plate; 2. waterproof protective layer; 3. waterproof layer; 4. cushion layer; 5. pumping pipe; 6. installation box; 7. pumping mechanism; 701. waterproof box; 702. dual-axis motor; 703. rotating shaft; 704. blades; 705. filter screen; 706. sewage pump; 8. fixing mechanism; 801. fixing rod; 802. slider; 803. spring; 804. connecting rod; 805. limit plate; 806. bolt; 807. nut; 9. drain pipe. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0032] See also Figure 1 A pipeline construction drainage structure in this embodiment includes a foundation slab 1, a waterproof protective layer 2 fixed to the bottom end of the foundation slab 1, a waterproof layer 3 fixed to the bottom end of the waterproof protective layer 2, a cushion layer 4 fixed to the bottom end of the waterproof layer 3, a pumping pipe 5 fixed inside the foundation slab 1, an installation box 6 fixed to the outer surface of the pumping pipe 5, a pumping mechanism 7 installed on the installation box 6, a fixing mechanism 8 installed on the foundation slab 1 and a drainage pipe 9 fixed to the top of the pumping pipe 5, a second through hole is opened inside the foundation slab 1, the waterproof protective layer 2, the waterproof layer 3 and the cushion layer 4, a second sealing gasket is fixed in the second through hole, and the pumping pipe 5 is fixed in the second sealing gasket.

[0033] In this embodiment, the base bottom plate 1 is used to facilitate the installation of the fixing mechanism 8, the waterproof protective layer 2 is used to protect the waterproof layer 3, the waterproof layer 3 is used for waterproofing, the cushion layer 4 is used to support the waterproof layer 3, the pumping pipe 5 and the drain pipe 9 are used to pump out water, the installation box 6 is used to keep the mud and gravel outside, the pumping mechanism 7 is used to pump water and clean the gravel and mud on the surface of the installation box 6, and the fixing mechanism 8 is used to facilitate the disassembly of the pumping pipe 5 and the pumping mechanism 7.

[0034] It should be noted that the waterproof layer 3 is made of polyurethane, the cushion layer 4 and the base slab 1 are both made of concrete, and the second sealing ring is used to prevent water from entering above the base slab 1.

[0035] See also Figure 1 and Figure 2 In order to facilitate the protection of the sewage pump 706, the pumping mechanism 7 in this embodiment includes a waterproof box 701 fixed inside the installation box 6, a cleaning component installed on the installation box 6, two groups of filter screens 705 fixed at the left and right ends of the installation box 6, and a sewage pump 706 fixed at the top of the inner wall of the installation box 6. The cleaning component includes a dual-axis motor 702 fixed at the bottom end of the inner wall of the waterproof box 701, a rotating shaft 703 fixed on the output shaft of the dual-axis motor 702, and a group of blades 704 fixed on the outer surface of the rotating shaft 703. Two first through holes are provided at the left and right ends of the installation box 6 and the waterproof box 701. A first sealing ring is fixed inside the first through hole, and the rotating shaft 703 is rotatably connected to the sealing ring.

[0036] The pumping mechanism 7 in this embodiment pumps water into the pumping pipe 5 through the sewage pump 706, the dual-axis motor 702 is used to drive the rotating shaft 703 to rotate, the rotating shaft 703 is used to drive the blades 704 to rotate, and the blades 704 are used to clean the mud and gravel on the surface of the installation box 6.

[0037] It should be noted that the filter screen 705 is used to filter sewage, and the first sealing ring is used to prevent mud and sand from entering the installation box 6 through the gap and to prevent sewage from entering the waterproof box 701.

[0038] See also Figure 1 , Figure 3 and Figure 4 In order to facilitate the disassembly and maintenance of the pumping mechanism 7, the fixing mechanism 8 in this embodiment includes a fixing rod 801 fixed to the inside of the basic bottom plate 1, a slider 802 slidably connected to the outer surface of the fixing rod 801, a spring 803 sleeved on the outer surface of the fixing rod 801 and a fixing component installed on the slider 802, the fixing component includes a connecting rod 804 fixed to the top of the slider 802, a limit plate 805 fixed to one end of the connecting rod 804, a bolt 806 slidably connected to the inside of the limit plate 805 and a nut 807 threadedly connected to the outer surface of the bolt 806, a slide groove is opened inside the basic bottom plate 1, the left and right ends of the fixing rod 801 are fixed to the left and right sides of the slide groove, and the front and rear ends of the limit plate 805 are fixed with ear plates, and the ear plates are opened with round holes, and the bolt 806 slides in the round holes.

[0039] The fixing mechanism 8 in this embodiment fixes the water pumping pipe 5 by abutting the limit plate 805 against the water pumping pipe 5. The bolts 806 and nuts 807 are used together to fix the limit plate 805. The connecting rod 804 is used to facilitate the sliding of the limit plate 805 and prevent the limit plate 805 from being lost.

[0040] It should be noted that the slider 802 is used to squeeze the spring 803 to deform it, and the spring 803 is used to drive the limit plate 805 to reset. The left end of the nut 807 abuts against the right end of the ear plate on the right limit plate 805.

[0041] The working principle of the above embodiment is:

[0042] (1) When the device is pumping water, the sewage pump 706 and the dual-axis motor 702 are started. The sewage pump 706 sucks the sewage in the installation box 6 into the suction pipe 5. The sewage then flows into the drain pipe 9 through the suction pipe 5 and is finally discharged through the drain pipe 9. The dual-axis motor 702 drives the rotating shaft 703 to rotate. The rotating shaft 703 drives the blades 704 to rotate. The blades 704 discharge the mud and gravel adsorbed on the installation box 6. When the pumping mechanism 7 needs to be repaired, the nut 807 is unscrewed, the bolt 806 is taken out, and then the connecting rod 804 is pulled to move. The connecting rod 804 drives the slider 802 and the limit plate 805 to move together. The slider 802 squeezes the spring 803 to deform it, and the limit plate 805 is separated from the pumping pipe 5. Then the pumping pipe 5 and the drain pipe 9 are disassembled and the pumping pipe 5 is taken out from the bottom, so that the pumping mechanism 7 can be removed for maintenance.

Claims

1. A pipeline construction drainage structure, Features: It comprises a base plate (1), a waterproof protective layer (2) fixed at the bottom end of the base plate (1), a waterproof layer (3) fixed at the bottom end of the waterproof protective layer (2), a cushion layer (4) fixed at the bottom end of the waterproof layer (3), a water pumping pipe (5) fixed inside the base plate (1), a mounting box (6) fixed to the outer surface of the water pumping pipe (5), a water pumping mechanism (7) mounted on the mounting box (6), a fixing mechanism (8) mounted on the base plate (1), and a drainage pipe (9) fixed to the top end of the water pumping pipe (5); The pumping mechanism (7) comprises a waterproof box (701) fixed inside the installation box (6), a cleaning component installed on the installation box (6), two sets of filter screens (705) fixed at the left and right ends of the installation box (6), and a sewage pump (706) fixed at the top of the inner wall of the installation box (6).

2. A pipeline construction drainage structure according to claim 1, Features: The fixing mechanism (8) comprises a fixing rod (801) fixed inside the base plate (1), a sliding block (802) slidably connected to the outer surface of the fixing rod (801), a spring (803) sleeved on the outer surface of the fixing rod (801), and a fixing component mounted on the sliding block (802).

3. A pipeline construction drainage structure according to claim 2, Features: The cleaning assembly comprises a dual-axis motor (702) fixed to the bottom end of the inner wall of the waterproof box (701), a rotating shaft (703) fixed to the output shaft of the dual-axis motor (702), and a group of blades (704) fixed to the outer surface of the rotating shaft (703).

4. A pipeline construction drainage structure according to claim 3, Features: The fixing assembly comprises a connecting rod (804) fixed to the top end of the sliding block (802), a limiting plate (805) fixed to one end of the connecting rod (804), a bolt (806) slidably connected to the inside of the limiting plate (805), and a nut (807) threadedly connected to the outer surface of the bolt (806).

5. A pipeline construction drainage structure according to claim 4, Features: Two first through holes are provided at both left and right ends of the installation box (6) and the waterproof box (701), a first sealing ring is fixed inside the first through hole, and the rotating shaft (703) is rotatably connected to the sealing ring.

6. A pipeline construction drainage structure according to claim 5, Features: The base bottom plate (1), the waterproof protective layer (2), the waterproof layer (3) and the cushion layer (4) are all provided with a second through hole, a second sealing gasket is fixed in the second through hole, and the water extraction pipe (5) is fixed in the second sealing gasket.

7. A pipeline construction drainage structure according to claim 6, Features: A slide groove is provided inside the base bottom plate (1), and the left and right ends of the fixing rod (801) are fixed to the left and right sides of the slide groove.

8. A pipeline construction drainage structure according to claim 7, Features: Ear plates are fixed to both the front and rear ends of the limiting plate (805), and a circular hole is formed on the ear plate, and the bolt (806) slides in the circular hole.

Citation Information

Patent Citations

  • Local precipitation structure of deep basal pit

    CN205205842U