Sand beach rainwater ditch structure

By setting up rainwater green belts and inspection wells in the beach storm drain structure to filter rainwater and prevent them from entering the beach, the problem of surface source pollution of coastal highways is solved, the beach environment is protected and the landscape impact of storm drains on the beach is reduced.

CN222227490UActive Publication Date: 2024-12-24ZHUHAI PLANNING&DESIGNING INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420879817.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-25
Publication Date
2024-12-24
Estimated Expiration
2034-04-25

AI Technical Summary

Technical Problem

In the prior art, the installation of exposed storm drains at the edge of the beach causes pollution of the coastal road surface source, and pollutants are directly discharged to the beach, causing pollution of the beach surface source and landscape impact.

Method used

Design a beach storm drain structure. The storm drain is set between the beach and the coastal highway, extending along the junction between the beach and the road, and multiple rainwater inspection wells are set up. The wellhead is lower than the beach surface, and the rainwater green belt is filtered between the canal and the road. Rainwater, retaining wall prevents water from entering the beach, permeable blind pipes and planting trough filters rainwater, and the plank road components facilitate sand flow.

Benefits of technology

The rainwater on the coastal highway is filtered and purified through the rainwater green belt, reducing non-point source pollution, burying inspection wells to protect the beach environment, and reducing the impact of the storm drain on the beach landscape.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222227490U_ABST
    Figure CN222227490U_ABST
Patent Text Reader

Abstract

The utility model discloses a sand beach rainwater channel structure, which belongs to the technical field of rainwater channels and comprises a rainwater channel arranged between a sand beach and a coastal highway and extending along a boundary line of the sand beach and the coastal highway. The plurality of rainwater inspection wells are arranged on the rainwater channel, the plurality of rainwater inspection wells are uniformly distributed along the extension direction of the rainwater channel, and the elevation of the well mouth of each rainwater inspection well is lower than the elevation of the sand beach surface; the rainwater green belt is arranged between the rainwater channel and the coastal road, the rainwater green belt is arranged in the extension direction of the rainwater channel, the rainwater green belt is communicated with the rainwater channel, and the rainwater green belt is used for filtering rainwater on the road surface. The non-point source pollution of the coastal road can be filtered and purified, so that the non-point source pollution of the surrounding road is treated, and meanwhile, the rainwater inspection well is buried below the sand beach surface, so that the water environment of the sand beach is maintained, and the landscape influence of the rainwater channel on the sand beach is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of stormwater channels, in particular to a beach stormwater channel structure. Background Art

[0002] When coastal cities carry out beach restoration work in nearshore waters, they will inevitably transform existing stormwater channels along the coast. Stormwater channels in the coastal zone close to the city center are mostly the main channels for urban rainwater discharge and bear the important task of drainage and flood prevention.

[0003] For coastal cities, although the restoration of coastal beaches has improved the beauty and functionality of the marine environment, in the existing technology, exposed stormwater channels are set at the edge of the beach, and a large number of inspection wells above the beach surface are set up for the convenience of maintenance, so that rainwater from the surrounding coastal highways is directly discharged into the beach area, causing non-point source pollution to the beach. Utility Model Content

[0004] The purpose of the utility model is to solve at least one of the technical problems existing in the prior art. To this end, the utility model proposes a beach rainwater channel structure, which can reduce the impact of surface source pollution of surrounding coastal highways on the beach and maintain the beach water environment.

[0005] According to the embodiment of the utility model, the beach rainwater channel structure includes a rainwater channel, which is arranged between the beach and the coastal highway, and extends along the boundary line between the beach and the coastal highway; a plurality of rainwater inspection wells, which are arranged on the rainwater channel, and are evenly distributed along the extension direction of the rainwater channel, and the wellhead elevations of the rainwater inspection wells are lower than the beach surface elevation; a rainwater green belt, which is arranged between the rainwater channel and the coastal highway, and is arranged along the extension direction of the rainwater channel, and is connected to the rainwater channel, and is used to filter rainwater on the road surface.

[0006] The beach stormwater channel structure according to the embodiment of the utility model has at least the following beneficial effects: rainwater on the coastal highway flows into the rainwater green belt, and enters the stormwater channel after being filtered by the rainwater green belt, thereby filtering and purifying the surface source pollution of the coastal highway, thereby achieving the treatment of surface source pollution of surrounding roads, and at the same time burying the rainwater inspection well below the beach surface, not only maintaining the beach water environment, but also reducing the landscape impact of the stormwater channel on the beach.

[0007] According to some embodiments of the utility model, a retaining wall is also included. The retaining wall is arranged between the stormwater channel and the stormwater green belt. The retaining wall is located at the upper end of the stormwater channel. The retaining wall is arranged along the extension direction of the stormwater channel. The retaining wall is used to prevent water in the stormwater green belt from directly entering the beach.

[0008] According to some embodiments of the utility model, indicators are provided on the retaining wall, the number of the indicators corresponds to the number of rainwater inspection wells, and multiple indicators are provided in the extension direction of the retaining wall, and the indicators are used to indicate the positions of the rainwater inspection wells.

[0009] According to some embodiments of the utility model, the indicator is a bench, and the bench is located on a side of the retaining wall close to the beach.

[0010] According to some embodiments of the utility model, the rainwater green belt includes: a planting trough, which is arranged between the rainwater channel and the coastal highway; a permeable blind pipe, which is arranged at the bottom of the planting trough, and the planting trough is connected with the rainwater channel through the permeable blind pipe.

[0011] According to some embodiments of the utility model, a filter layer and a planting layer are provided in the planting trough, the filter layer and the planting layer are arranged in sequence in a direction away from the bottom of the planting trough, and the permeable blind pipe is located in the filter layer.

[0012] According to some embodiments of the present invention, the bottom elevation of the planting trough is lower than the beach surface elevation.

[0013] According to some embodiments of the present invention, the elevation of the retaining wall is less than the elevation of the coastal highway.

[0014] According to some embodiments of the utility model, a plank road assembly is provided at the upper end of the stormwater channel, and the plank road assembly includes a plate channel gap channel, and the plate channel gap channel is located at the top of the stormwater channel, and the plate channel gap channel is used to facilitate the flow of beach sand.

[0015] According to some embodiments of the present invention, the thickness of the plate channel gap is greater than 150 mm.

[0016] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The utility model is further described below in conjunction with the accompanying drawings and embodiments;

[0018] Figure 1 A cross-sectional view of a beach stormwater channel structure according to an embodiment of the utility model;

[0019] Figure 2 for Figure 1 Floor plan in .

[0020] Reference numerals:

[0021] Storm drains 100;

[0022] Rainwater inspection well 200;

[0023] Rainwater green belt 300, planting trough 310, filter layer 311, planting layer 312, permeable blind pipe 320;

[0024] Retaining wall 400, indicator 410, bench 420;

[0025] Plank road assembly 500, imitation wood grain brick 510, precast concrete slab 520, concrete pad 530, slab channel gap channel 540;

[0026] Beach 10, coastal road 20. DETAILED DESCRIPTION

[0027] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0028] In the description of the present invention, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0029] In the description of the present utility model, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a first or second description, it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0030] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0031] refer to Figures 1 to 2 The beach stormwater channel structure according to the embodiment of the utility model is described.

[0032] like Figure 1 to Figure 2As shown, the beach stormwater channel structure includes a stormwater channel 100, which is arranged between the beach 10 and the coastal highway 20, and extends along the boundary line between the beach 10 and the coastal highway 20; a plurality of stormwater inspection wells 200, which are arranged on the stormwater channel 100, and are evenly distributed along the extension direction of the stormwater channel 100, and the wellhead elevations of the stormwater inspection wells 200 are lower than the elevation of the beach 10; a rainwater green belt 300, which is arranged between the stormwater channel 100 and the coastal highway 20, and is arranged along the extension direction of the stormwater channel 100, and is connected to the stormwater channel 100, and is used to filter rainwater on the road surface.

[0033] like Figure 1 As shown, the beach 10 and the coastal highway 20 are arranged from left to right in sequence, and both the beach 10 and the coastal highway 20 extend in the front-to-back direction. Correspondingly, the stormwater channel 100 is located between the beach 10 and the coastal highway 20, and extends along the boundary line between the beach 10 and the coastal highway 20. The stormwater channel 100 is evenly provided with a plurality of rainwater inspection wells 200 along the extension direction, and the wellhead of each rainwater inspection well 200 is lower than the elevation of the beach 10, that is, the beach 10 covers the wellhead of the rainwater inspection well 200. A rainwater green belt 300 is arranged between the rainwater channel 100 and the coastal highway 20, and the rainwater green belt 300 extends along the boundary line between the rainwater channel 100 and the coastal highway 20. Rainwater on the coastal highway 20 flows into the rainwater green belt 300, and enters the rainwater channel 100 after being filtered by the rainwater green belt 300, thereby filtering and purifying the surface source pollution of the coastal highway 20, thereby achieving the treatment of surface source pollution of surrounding roads. At the same time, the rainwater inspection well 200 is buried below the surface of the beach 10, which not only maintains the water environment of the beach 10, but also reduces the landscape impact of the rainwater channel 100 on the beach 10.

[0034] In some specific embodiments of the present invention, a retaining wall 400 is further included. The retaining wall 400 is arranged between the stormwater channel 100 and the rainwater green belt 300. The retaining wall 400 is located at the upper end of the stormwater channel 100. The retaining wall 400 is arranged along the extension direction of the stormwater channel 100. The retaining wall 400 is used to prevent the water in the rainwater green belt 300 from directly entering the beach 10.

[0035] like Figure 1 and Figure 2As shown, the retaining wall 400 is arranged between the rainwater channel 100 and the rainwater green belt 300, and is arranged at the upper end of the rainwater channel 100 in the front-to-back direction. When the rainwater on the coastal highway 20 flows toward the beach 10, the retaining wall 400 can prevent the collected rainwater from further spreading toward the beach 10 to a certain extent. It should be noted that in order to ensure the drainage safety of the coastal highway 20, the elevation of the retaining wall 400 is lower than the elevation of the coastal highway 20. Specifically, the distance between the elevation of the retaining wall 400 and the elevation of the coastal highway 20 should be no less than 200 mm. Therefore, rainwater within the standard range can enter the rainwater channel 100 after being disposed by the rainwater green belt 300, and rainwater exceeding the disposal standard of the rainwater green belt 300 can overflow the retaining wall 400 and be discharged to the beach 10.

[0036] In some specific embodiments of the utility model, an indicator 410 is provided on the retaining wall 400, the number of the indicator 410 corresponds to the number of the rainwater inspection wells 200, and multiple indicator 410 are arranged in the extension direction of the retaining wall 400, and the indicator 410 is used to indicate the position of the rainwater inspection well 200.

[0037] like Figure 1 As shown, the retaining wall 400 is provided with indicator members 410 corresponding to the number of the rainwater inspection wells 200. In this specific embodiment, each rainwater well is provided with an indicator member 410. Of course, each rainwater well may also be provided with two or three indicator members 410.

[0038] It should be noted that the wellhead elevation of the inspection well of the stormwater channel 100 should be 500mm below the elevation of the beach 10, which is convenient for cleaning the sand surface for inspection and maintenance, and does not affect the effect of the surrounding beach 10. Furthermore, the width of the inspection well of the stormwater channel 100 is not less than 1000mm, so that personnel can enter the stormwater channel 100 from the side, and at the same time, it does not affect the use of the plank road at the upper end of the stormwater channel 100.

[0039] In some specific embodiments of the utility model, the indicator 410 is a bench 420, and the bench 420 is located on the side of the retaining wall 400 close to the beach 10. Furthermore, in order to facilitate the later maintenance, the number of the inspection wells of the rainwater channel 100 corresponds to the number of the benches 420, and the positioning is performed in combination with the landscape, that is, each bench 420 is corresponding to a rainwater inspection well 200, and is aligned with the inspection well of the rainwater channel 100, thereby serving as a mark of the rainwater inspection well 200. Specifically, the distance between two adjacent inspection wells of the rainwater channel 100 is not greater than 100m.

[0040] In some specific embodiments of the utility model, the rainwater green belt 300 includes: a planting trough 310, which is arranged between the rainwater channel 100 and the coastal highway 20; a permeable blind pipe 320, which is arranged at the bottom of the planting trough 310, and the planting trough 310 is connected to the rainwater channel 100 through the permeable blind pipe 320.

[0041] In some specific embodiments of the utility model, a filter layer 311 and a planting layer 312 are provided in the planting trough 310 . The filter layer 311 and the planting layer 312 are arranged in sequence in a direction away from the bottom of the planting trough 310 , and the permeable blind pipe 320 is located in the filter layer 311 .

[0042] like Figure 1 As shown, the planting trough 310 is located between the stormwater channel 100 and the coastal highway 20. The planting trough 310 is formed by the channel wall of the stormwater channel 100, the retaining wall 400 and the coastal highway 20. Specifically, the planting trough 310 is provided with a filter layer 311 and a planting layer 312 from bottom to top. The permeable blind pipe 320 is located in the filter layer 311 and is arranged close to the bottom of the planting trough 310. In this specific embodiment, the planting layer 312 is planting soil for planting, so as to form a landscape belt arranged between the beach 10 and the coastal highway 20. The filter layer 311 is gravel. After the rainwater on the road passes through the rainwater green belt 300, it infiltrates through the planting soil, is filtered by the gravel, and is collected by the permeable blind pipe 320 and discharged into the stormwater channel 100.

[0043] Specifically, the bottom elevation of the planting trough 310 is lower than the elevation of the 10th surface of the beach, that is, the distance between the bottom elevation of the rainwater green belt 300 and the elevation of the 10th surface of the beach is not less than 100 mm, the diameter of the permeable blind pipe 320 is not less than 400 mm, and the rainwater green belt 300 should meet the characteristics of flood resistance and salt resistance. The planting soil in the planting layer 312 should have good permeability to ensure that rainwater can pass through the planting layer 312 and flow into the filter layer 311.

[0044] In some specific embodiments of the present invention, a plank road assembly 500 is provided at the upper end of the stormwater channel 100, and the plank road assembly 500 includes a plate channel gap channel 540, which is located at the top of the stormwater channel 100 and is used to facilitate the flow of sand on the beach 10.

[0045] like Figure 1 As shown, a plank road assembly 500 is arranged on the rainwater channel 100, and the plank road assembly 500 is covered and arranged on the top of the rainwater channel 100, wherein the plank road assembly 500 includes imitation wood grain bricks 510 and precast concrete panels 520, which are arranged in sequence from top to bottom, and the imitation wood grain bricks 510 are arranged on the precast concrete panels 520 by mortar bonding to form a plank road for people to walk on, and a concrete pad 530 is arranged between the concrete panel and the well body outlet end, thereby, a plate channel gap channel 540 is provided between the concrete panel and the well body, so as to facilitate the flow of beach sand 10, and also reduce the thickness of the precast concrete panel 520. Specifically, the thickness of the plate channel gap channel 540 is not less than 150 mm.

[0046] The following is a specific embodiment to specifically illustrate the structure of the beach stormwater channel. The elevation of the beach 10 is H0, the elevation of the manhole of the stormwater channel 100 is H1, the elevation of the top of the stormwater channel 100 is H2, the elevation of the bottom of the stormwater channel 100 is H3, the elevation of the bench 420 is H4, the elevation of the retaining wall 400 is H5, the elevation of the rainwater green belt 300 is H6, the thickness of the imitation wood grain brick 510 is h1, the thickness of the precast concrete slab 520 is h2, the thickness of the board channel gap channel 540 is h3, the width of the stormwater channel 100 is B2, the width of the manhole of the stormwater channel 100 is B1, the spacing of the bench 420 is L1, and the diameter of the permeable blind pipe 320 is D1.

[0047] Specifically, the height is H2-H3, and B2 and H2-H3 are determined according to the hydraulic calculation of the storm drain 100. At the same time, the elevation H0-H2 from the top of the storm drain 100 to the beach 10 should be greater than h1+h2+h3.

[0048] Specifically, the thickness h3 of the plate channel gap channel 540 is determined according to the structural function, while ensuring that the thickness h3 of the plate channel gap channel 540 is 150 mm to facilitate the flow of surface sand.

[0049] Specifically, the elevation H1 of the manhole of the storm drain 100 is 500 mm below the elevation H0 of the beach 10, and the width B1 of the manhole of the storm drain 100 is 1000 mm. The manhole of the storm drain 100 corresponds to the bench 420, and the distance L1 between them is 100 m.

[0050] Specifically, the elevation H5 of the retaining wall 400 is 200 mm lower than the elevation of the coastal highway 20.

[0051] Specifically, the bottom elevation H6 of the rainwater green belt 300 is located 100 mm below the elevation H0 of the beach 10. The diameter D1 of the permeable blind pipe 320 is 400 mm.

[0052] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A beach stormwater channel structure, characterized in that: include: A stormwater channel (100), wherein the stormwater channel (100) is arranged between the beach (10) and the coastal highway (20), and the stormwater channel (100) extends along the boundary line between the beach (10) and the coastal highway (20); A plurality of rainwater inspection wells (200), wherein the plurality of rainwater inspection wells (200) are arranged on the rainwater channel (100), the plurality of rainwater inspection wells (200) are evenly distributed along the extension direction of the rainwater channel (100), and the wellhead elevation of the rainwater inspection wells (200) is lower than the elevation of the beach (10); A rainwater green belt (300), wherein the rainwater green belt (300) is arranged between the rainwater channel (100) and the coastal highway (20), the rainwater green belt (300) is arranged along the extension direction of the rainwater channel (100), the rainwater green belt (300) is connected to the rainwater channel (100), and the rainwater green belt (300) is used to filter rainwater on the road surface.

2. The beach stormwater channel structure according to claim 1, characterized in that: The invention also comprises a retaining wall (400), wherein the retaining wall (400) is arranged between the rainwater channel (100) and the rainwater green belt (300), the retaining wall (400) is located at the upper end of the rainwater channel (100), the retaining wall (400) is arranged along the extension direction of the rainwater channel (100), and the retaining wall (400) is used to prevent water in the rainwater green belt (300) from directly entering the beach (10).

3. The beach stormwater channel structure according to claim 2, characterized in that: The retaining wall (400) is provided with an indicator (410), the number of the indicator (410) corresponds to the number of the rainwater inspection wells (200), and a plurality of the indicator (410) are arranged in the extension direction of the retaining wall (400), and the indicator (410) is used to indicate the position of the rainwater inspection well (200).

4. The beach stormwater channel structure according to claim 3, characterized in that: The indicator (410) is a bench (420), and the bench (420) is located on a side of the retaining wall (400) close to the beach (10).

5. The beach stormwater channel structure according to claim 1, characterized in that: The rainwater green belt (300) comprises: A planting trough (310), wherein the planting trough (310) is arranged between the storm drain (100) and the coastal highway (20); A water-permeable blind pipe (320), wherein the water-permeable blind pipe (320) is arranged at the bottom of the planting trough (310), and the planting trough (310) is connected to the rainwater channel (100) through the water-permeable blind pipe (320).

6. The beach stormwater channel structure according to claim 5, characterized in that: A filter layer (311) and a planting layer (312) are arranged in the planting trough (310); the filter layer (311) and the planting layer (312) are arranged in sequence in a direction away from the bottom of the planting trough (310); and the water-permeable blind pipe (320) is located in the filter layer (311).

7. The beach stormwater channel structure according to claim 5, characterized in that: The bottom elevation of the planting trough (310) is lower than the surface elevation of the beach (10).

8. The beach stormwater channel structure according to claim 3, characterized in that: The elevation of the retaining wall (400) is lower than the elevation of the coastal highway (20).

9. The beach stormwater channel structure according to claim 2, characterized in that: A plank road assembly (500) is provided at the upper end of the stormwater channel (100), and the plank road assembly (500) includes a plate channel gap channel (540). The plate channel gap channel (540) is located at the top of the stormwater channel (100), and the plate channel gap channel (540) is used to facilitate the flow of sand on the beach (10).

10. The beach stormwater channel structure according to claim 9, characterized in that: The thickness of the plate channel gap channel (540) is greater than 150 mm.