High-altitude large-temperature-difference large-height-difference concrete transportation elephant trunk system

By designing a pipe slip system under high altitude and large temperature difference, using open segments and standard segment splicing, electric blanket insulation and concrete pump processing, the traditional pipe slip plugging and separation problems are solved, achieving high efficiency, Economical concrete transport.

CN222253157UActive Publication Date: 2024-12-27CCCC SECOND HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323584463.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-12-27
Estimated Expiration
2033-12-27

AI Technical Summary

Technical Problem

Under high altitude, large temperature and high difference, traditional concrete pipe transportation is prone to blocking pipes due to aggregate accumulation, which affects the construction progress, and concrete is prone to separation and difficult to effectively insulate and moisturize, resulting in harsh construction environment.

Method used

A high-altitude, large temperature difference, large height difference concrete transportation pipe slip system is designed, using alternate splicing of open segments and standard segments, and notches and transparent cover plates are set to monitor the conveying state. An electric blanket insulation layer is installed at the bottom and passed The concrete pump machine performs secondary stirring and pumping.

Benefits of technology

Real-time monitoring and prevent pipe blockage, maintain concrete transportation speed and performance, effectively deal with high temperature difference environment, eliminate separation problems, and save secondary stirring devices, improve transportation efficiency and economy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222253157U_ABST
    Figure CN222253157U_ABST
Patent Text Reader

Abstract

The utility model discloses a high-altitude large-temperature-difference large-height-difference concrete transportation elephant trunk system which is arranged on an abrupt slope mountain and comprises an elephant trunk, a feeding hopper and a concrete pump machine. A pump machine hopper is arranged at the feeding end of the concrete pump machine, the elephant trunk is obliquely arranged downwards along the slope surface of the abrupt slope mountain, the discharging end of the feeding hopper is communicated with the feeding end of the elephant trunk, and the discharging end of the elephant trunk is connected with the feeding end of the pump machine hopper; a heat preservation layer is arranged at the bottom of the elephant trunk; the articulated chute is formed by alternately splicing a plurality of open sections and a plurality of standard sections, and notches are formed in the open sections. The problems of heat preservation, segregation prevention and pipe blocking in the transportation process of the large-height-difference concrete elephant trunk in the plateau environment are solved, and the working performance of the concrete elephant trunk can be kept in the concrete transportation process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete transportation, and more specifically, to a high-altitude, large temperature difference, and large height difference concrete transportation chute system. Background Art

[0002] When concrete is transported down a steep slope with a large height difference without a temporary road, it is generally transported by a chute. A continuous steel circular chute is set from the starting point to the end point of the transportation. After the concrete is unloaded into the chute by the tank truck, it slides down along the pipe body until the end point completes the transportation. When using a traditional chute to transport concrete, due to the different flow rates of aggregates and mortar, it is easy to cause pipe blockage due to aggregate accumulation. After the pipe is blocked, the chute needs to be dismantled and replaced section by section, affecting the construction progress and causing certain economic losses; the concrete after transportation is prone to segregation, which affects the working performance of the concrete. It is necessary to use additional devices such as mixing tanks to mix it for secondary mixing to eliminate segregation. In addition, for the concrete transportation project with a large height difference and no temporary road in the deep canyon on the plateau, it is also faced with high altitude low pressure, large temperature difference, strong wind environment, and harsh construction environment, which puts forward higher requirements for heat preservation, moisture retention, anti-segregation, and anti-blocking pipe during the transportation of concrete chute. In view of the above problems, it is urgent to develop a chute system suitable for the transportation of concrete with large temperature difference and height difference in deep canyons at high altitude, which has the functions of heat preservation, moisture retention, anti-segregation, and anti-blocking pipe. Utility Model Content

[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described below.

[0004] In order to achieve these purposes and other advantages according to the utility model, a high-altitude, large temperature difference and large height difference concrete transportation chute system is provided, which is arranged on a steep slope mountain, and includes: a chute, a feed hopper and a concrete pump; the feed end of the concrete pump is provided with a pump hopper, the chute is arranged obliquely downward along the slope of the steep slope mountain, the discharge end of the feed hopper is connected with the feed end of the chute, and the discharge end of the chute is connected with the feed end of the pump hopper; an insulation layer is arranged at the bottom of the chute; the chute is formed by alternately splicing a plurality of open segments and a plurality of standard segments, and a slot is opened on the open segment.

[0005] Preferably, one opening segment is provided on the slide pipe every five standard segments.

[0006] Preferably, a transparent cover is provided on the slot, and the transparent cover is hinged to the opening segment to open or close the slot; on the vertical section of the opening segment, the central angle corresponding to the slot is not greater than 90°.

[0007] Preferably, an open discharge trough is provided between the discharge end of the feed hopper and the feed end of the chute, and between the discharge end of the chute and the feed end of the pump hopper.

[0008] Preferably, on the vertical cross section of the slide pipe, the central angle corresponding to the insulation layer is not less than 180°.

[0009] Preferably, the thermal insulation layer is an electric blanket.

[0010] Preferably, a circle of heightening plates is provided along the outer edge of the top of the pump hopper.

[0011] Preferably, a plurality of clamping rings are arranged at intervals on the slide pipe, and the clamping rings are fixed to the steep slope by steel wire ropes.

[0012] The utility model at least has the following beneficial effects:

[0013] 1. The utility model provides a high-altitude, large temperature difference, and large height difference concrete transportation chute system. The chute is formed by splicing open segments and standard segments. The concrete transportation status can be grasped in real time through the notches on the open segments. When pipe blockage occurs, concrete transportation is stopped in time, and the concrete at the blocked pipe is manually dredged through the notches, which can effectively ensure the transportation speed of concrete and is conducive to maintaining the working performance of concrete.

[0014] 2. The utility model provides a high-altitude, large temperature difference, and large height difference concrete transportation chute system, and an insulation layer is arranged at the bottom of the chute, which can cope with the large temperature difference environment in high-altitude areas and prevent the concrete temperature from being too low to affect its performance.

[0015] 3. The high-altitude, large temperature difference, and large height difference concrete transportation chute system provided by the utility model can accommodate more concrete by raising the pump hopper. When the concrete is transported to the end of the chute, it is unloaded into the pump hopper. Then, the concrete pump can be directly used to perform secondary mixing on the transported concrete and pump it for pouring, eliminating concrete segregation, saving secondary mixing equipment, and saving costs.

[0016] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a side structural schematic diagram of the high-altitude, large temperature difference and large height difference concrete transportation chute system of the utility model;

[0018] Figure 2 It is a schematic diagram of the vertical cross-section structure of the opening segment of the utility model; DETAILED DESCRIPTION

[0019] The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.

[0020] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0021] like Figure 1 and Figure 2 As shown, the utility model provides a high-altitude, large temperature difference and large height difference concrete transportation chute system, which is arranged on a steep slope mountain 6, and includes: a chute 3, a feed hopper 1 and a concrete pump 5; the feed end of the concrete pump 5 is provided with a pump hopper 4, the chute 3 is arranged obliquely downward along the slope of the steep slope mountain 6, the discharge end of the feed hopper 1 is connected with the feed end of the chute 3, and the discharge end of the chute 3 is connected with the feed end of the pump hopper 4; the bottom of the chute 3 is provided with an insulation layer 8; the chute 3 is formed by alternately splicing a plurality of open segments and a plurality of standard segments, and the open segments are provided with slots.

[0022] In this technical solution, the feed hopper 1 and the pump hopper 4 are respectively placed in the relatively flat areas at the upper and lower ends of the steep slope 6, and then the feed hopper 1 and the pump hopper 4 are connected through the chute 3. After the concrete enters through the feed hopper 1, it is transported to the pump hopper 4 through the chute 3 and enters the concrete pump 5. After being stirred by the concrete pump 5, the concrete is stirred to eliminate segregation and is pumped to the pouring site for pouring. The chute 3 is formed by splicing the open segment and the standard segment. The concrete conveying status can be grasped in real time through the notch on the open segment. When the pipe is blocked, the concrete conveying can be stopped in time, and the concrete at the blocked pipe can be manually cleared through the notch. The insulation layer 8 is provided at the bottom of the chute 3 to cope with the large temperature difference environment in high altitude areas and prevent the concrete temperature from being too low to affect its performance.

[0023] In another technical solution, one opening segment is provided on the slide pipe 3 every five standard segments. The standard segment and the opening segment can adopt the same structure. In this embodiment, the standard segment and the opening segment are processed into a standard pipe segment with an upper opening of 34 cm, a lower opening of 30 cm, and a pipe body of 2 m using 5 mm steel plates. The opening segment has a 30 cm long notch on the top surface in the middle. Buckles and latches can be used to connect two adjacent standard segments, and between the standard segment and the opening segment.

[0024] In another technical solution, a transparent cover plate 7 is provided on the slot, and the transparent cover plate 7 is hinged with the opening segment to open or close the slot; on the vertical section of the opening segment, the central angle α corresponding to the slot is not greater than 90°. The transparent cover plate 7 can be a transparent PVC cover plate, which can prevent debris from falling into the chute 3 and facilitate manual observation of the flow of concrete in the chute 3. When a pipe is blocked, the corresponding transparent cover plate 7 can be opened to clear the pipe, which is convenient and quick.

[0025] In another technical solution, a discharge trough 2 is provided between the discharge end of the feed hopper 1 and the feed end of the chute 3, and between the discharge end of the chute 3 and the feed end of the pump hopper 4. The discharge trough 2 is used to smoothly connect the feed hopper 1, the chute 3 and the pump hopper 4, so as to reduce the installation requirements of the feed hopper 1 and the pump hopper 4. The concrete is introduced from the feed hopper 1 into the chute 3, and from the chute 3 into the pump hopper 4 through the discharge trough 2.

[0026] In another technical solution, on the vertical section of the chute 3, the central angle β corresponding to the thermal insulation layer 8 is not less than 180°. The thermal insulation layer 8 covers the bottom of the chute 3 as much as possible to ensure the thermal insulation effect on the concrete in the chute 3. Specifically, the thermal insulation layer 8 is an electric blanket, which is wrapped around the bottom of the chute 3 and can provide stable thermal insulation performance.

[0027] In another technical solution, a circle of heightening plates is provided along the outer edge of the top of the pump hopper. The pump hopper 4 adopts a large-volume hopper. In actual use, the pump hopper 4 can be heightened by steel plates on the basis of the original hopper to accommodate more concrete. When the concrete is transported to the end of the chute, it is unloaded into the pump hopper 4. The concrete pump 4 is directly used to perform secondary mixing on the transported concrete and pump it for pouring, eliminating concrete segregation and saving secondary mixing devices, thus saving costs. In this embodiment, the top of the pump hopper 4 is heightened by 50 cm using steel plates.

[0028] In another technical solution, a plurality of clasps are arranged at intervals on the slide pipe 3, and the clasps are fixed to the steep slope mountain body 6 by steel wire ropes. The steel wire rope can be a longer steel wire rope, which is inserted and fixed to the steep slope mountain body 6, and then the clasp is clamped on the slide pipe 3 and connected to the steel wire rope securely.

[0029] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation modes. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the illustrations shown and described herein.

Claims

1. A high-altitude, large temperature difference, and large height difference concrete transportation chute system, which is set on a steep slope, characterized in that: include: A chute, a feed hopper and a concrete pump; a pump hopper is provided at the feed end of the concrete pump, the chute is arranged obliquely downward along the slope of the steep mountain, the discharge end of the feed hopper is connected to the feed end of the chute, and the discharge end of the chute is connected to the feed end of the pump hopper; an insulation layer is provided at the bottom of the chute; the chute is formed by alternately splicing a plurality of open segments and a plurality of standard segments, and a slot is provided on the open segment.

2. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1 is characterized in that: One opening segment is arranged on the slide pipe every five standard segments.

3. The high altitude, large temperature difference and large height difference concrete transportation chute system according to claim 1 is characterized in that: A transparent cover is provided on the slot, and the transparent cover is hinged to the opening segment to open or close the slot; on the vertical section of the opening segment, the central angle corresponding to the slot is not greater than 90°.

4. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1, characterized in that: A material discharge open trough is provided between the discharge end of the feed hopper and the feed end of the slide pipe, and between the discharge end of the slide pipe and the feed end of the pump hopper.

5. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1, characterized in that: On the vertical section of the slide pipe, the central angle corresponding to the insulation layer is not less than 180°.

6. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1, characterized in that: The thermal insulation layer is an electric blanket.

7. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1, characterized in that: A circle of heightening plates is arranged along the outer edge of the top of the pump hopper.

8. The high altitude, large temperature difference, and large height difference concrete transportation chute system according to claim 1, characterized in that: A plurality of clamping rings are arranged at intervals on the slide pipe, and the clamping rings are fixed on the steep slope by steel wire ropes.