Hoisting tool for prefabricated T-beam boundary beam

Through the lifting work of prefabricated T-beam side beams, rectangular steel plate box, steel bar lifting ring, metal rod and other components, no reserved hole lifting is achieved, solving the problems of side beam lifting risks and inconvenience, and improving the stress strength and Construction safety.

CN222273850UActive Publication Date: 2024-12-31THE 2ND ENG CO LTD OF CHINA RAILWAY 22ND BUREAU GRP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421141158.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-23
Publication Date
2024-12-31
Estimated Expiration
2034-05-23

AI Technical Summary

Technical Problem

In the operation of T-beam lifting and moving beams, especially the hoisting of side beams, there are great risks. Traditional technology requires the reservation of lifting holes, which leads to waste of materials, safety hazards and inconvenient construction. Inadequate installation of the sealing hole formwork can easily cause the wing floor. Unevenness and water leakage.

Method used

The hoisting tooling adopts prefabricated T-beam side beams, including rectangular steel plate box, steel bar lifting ring and metal rod. There are troughs on the box, the steel bars pass through the troughs, and the lifting work ropes pass through the gaps between the metal rods to limit the deviation. , the box is moved by hand through the lifting ring to avoid reserved lifting holes.

Benefits of technology

The force strength of the edge beam flange plate is increased, which avoids uneven and water leakage of the wing plate floor caused by inadequate installation of the sealing hole formwork, and improves construction safety and material utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222273850U_ABST
    Figure CN222273850U_ABST
Patent Text Reader

Abstract

The utility model discloses a hoisting tool for a prefabricated T-beam boundary beam. The hoisting tool comprises a box body, a hoisting ring and a metal rod, the hanging ring is fixed in the middle of the top of the box; the metal rods are vertically fixed on two sides of the front surface of the box body; through grooves are formed in the box body at equal intervals; the box body is fixedly arranged at the positions of wet joints on the two sides of a beam body of the prefabricated T-beam edge beam, steel bars on the wet joints of the prefabricated T-beam edge beam penetrate through the through grooves of the box body, and a hoisting operation rope of the prefabricated T-beam edge beam penetrates through gaps between the metal rods; the metal rod is used for limiting the deviation of the hoisting operation rope; and the hanging ring is used for moving the box body in a hand-held manner. According to the utility model, the problems that the wing plate ground is uneven and water leaks easily due to the fact that the hoisting hole plugging template is not installed in place when the hoisting hole is used for hoisting and moving the beam are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of beam lifting and moving operations, in particular to a lifting tool for prefabricated T-beam side beams. Background Art

[0002] Lifting and moving T-beams is the most risky process in the beam yard, especially when lifting side beams. The side beam diaphragm is 3-5 tons heavier than the flange. Using a single wire rope to lift and move the beam can result in unsafe sideways tilting.

[0003] The current traditional process is to use reserved lifting holes to ensure that the distance from both sides of the beam to the center line of the beam is equal during the lifting operation, thereby making the beam balanced.

[0004] This process has five hidden dangers: 1. The reserved lifting holes are equipped with tooling, which is installed on the bridge wing plates. During installation, some transverse and longitudinal reinforcements need to be cut off, which affects the stress on the beam wing plates; 2. They need to be pulled out in time after pouring. After removing the formwork, the reserved holes are opened from bottom to top, which can easily cause the wing plate concrete to fall off; 3. After the beam is erected, the lifting holes need to be blocked, the formwork installed, the same grade concrete poured, and steel bars added, resulting in waste of materials and labor; 4. The stacking of hole formers on site affects the requirements of civilized construction on site. If the formwork for blocking the lifting holes is not installed in place, it can easily cause the wing plate ground to be uneven, water leakage problems, and an ugly appearance of the beam; 5. The lifting holes are blocked on the edge of the bridge deck, which requires personnel protection, especially when the formwork is installed, it is more inconvenient, and it is easy to cause safety hazards. Utility Model Content

[0005] The purpose of the present utility model is to provide a hoisting tool for prefabricated T-beam side beams in order to solve at least one of the above technical problems.

[0006] In the first aspect, an embodiment of the present invention provides a lifting tool for prefabricated T-beam side beams, which is applied to prefabricated T-beam side beams; a box, a lifting ring and a metal rod; the lifting ring is fixed to the middle position of the top of the box; the metal rod is vertically fixed to the front side of the box; the box is provided with equally spaced through grooves; the box is fixedly arranged at the wet joints on both sides of the beam body of the prefabricated T-beam side beam, and the steel bars on the wet joints of the prefabricated T-beam side beam pass through the through grooves of the box, and the lifting operation cables of the prefabricated T-beam side beam are arranged through the gaps between the metal rods; the metal rod is used to limit the deviation of the lifting operation cables; the lifting ring is used to move the box by hand.

[0007] Furthermore, the box body is a rectangular steel plate box body.

[0008] Furthermore, the lifting ring is a steel bar lifting ring.

[0009] Furthermore, the side surface of the box body is a reinforced steel rib structure.

[0010] Furthermore, reinforcing ribs are provided on the ridges where the front and top of the box intersect, and the reinforcing ribs are steel bars.

[0011] The utility model provides a lifting tool for prefabricated T-beam side beams, which can carry out the lifting and moving operation of the side beams without reserving lifting holes on the side beams, thereby increasing the stress strength of the side beam flange plates and preventing the problem of unevenness and water leakage on the wing plate surface caused by improper installation of the blocking lifting hole template when the bridge deck uses lifting holes for lifting and moving beams. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to more clearly illustrate the implementation methods of the present application or the technical solutions in the prior art, the following is a brief introduction to the drawings required for use in the specific implementation methods or the description of the prior art. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0013] Figure 1 A front perspective schematic diagram of a hoisting tool for a prefabricated T-beam side beam provided in an embodiment of the present utility model;

[0014] Figure 2 A three-dimensional schematic diagram of the back side of a prefabricated T-beam side beam lifting tool provided in an embodiment of the present invention;

[0015] Figure 3 A front view of a lifting tool for a prefabricated T-beam side beam provided in an embodiment of the utility model;

[0016] Figure 4 A top view of a lifting tool for a prefabricated T-beam side beam provided in an embodiment of the present utility model;

[0017] Figure 5 A side view of a lifting tool for a prefabricated T-beam side beam provided in an embodiment of the present utility model;

[0018] Figure 6 A front view of another prefabricated T-beam side beam lifting tool provided in an embodiment of the present utility model;

[0019] Figure 7 A schematic diagram of the application of a lifting tool for prefabricated T-beam side beams provided in an embodiment of the present utility model.

[0020] In the figure: 1. Box body, 2. Lifting ring, 3. Metal rod, 4. Through slot, 5. Reinforcement rib. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0022] Figure 1 This is a front perspective schematic diagram of a prefabricated T-beam side beam lifting tool provided according to an embodiment of the present invention, which is applied to prefabricated T-beam side beams. Figure 1 As shown, it comprises: a box body 1, a hanging ring 2 and a metal rod 3. Among them, the hanging ring 2 is fixed to the top middle position of the box body 1; the metal rod 3 is vertically fixed to the front side of the box body 1.

[0023] Optionally, in an embodiment of the present utility model, the number of the metal rods 3 is four, and two are respectively provided on both sides of the front of the box body 1 .

[0024] Preferably, the box body 1 is a rectangular steel plate box body, the lifting ring 2 is a steel bar lifting ring, and the metal rod 3 is made of steel bar material.

[0025] Preferably, the rectangular steel plate constituting the box body 1 is a 1 cm thick steel plate; the material of the hanging ring 2 and the metal rod 3 are both HPB300, with a diameter of 10 mm.

[0026] Optionally, in the embodiment of the present utility model, the lifting ring 2 and the metal rod 3 are both fixed to the box body 1 by welding.

[0027] Specifically, the lifting ring 2 is used to move the box 1 by hand.

[0028] Figure 2 This is a three-dimensional schematic diagram of the back of a lifting tool for a prefabricated T-beam side beam provided according to an embodiment of the present utility model. Figure 1 and Figure 2 As shown, the box body 1 is provided with through slots 4 at equal intervals.

[0029] Preferably, the through slots 4 of the panel of the box body 1 are provided with 1 cm thick stiffening steel ribs. The stiffening steel ribs are arranged at equal intervals, and the intervals between the stiffening steel ribs form the through slots 4.

[0030] Figure 3 This is a front view of a lifting tool for a prefabricated T-beam side beam provided according to an embodiment of the present utility model. Figure 3 As shown, the side of the box body 1 is a reinforced steel rib structure. Preferably, the thickness of the reinforced steel rib is 1 cm.

[0031] Figure 4 The utility model is provided according to an embodiment of a prefabricated T-beam side beam lifting tool provided in a top view. Figure 5 This is a side view of a lifting tool for a prefabricated T-beam side beam provided according to an embodiment of the present utility model. Figure 5 As shown, the side cross-section of the box body 1 is rectangular.

[0032] Alternatively, as Figure 3 As shown, when the prefabricated T-beam side beam with a length of 40 meters is lifted and moved, four through slots 4 are respectively provided on the front and back of the box body 1 .

[0033] Figure 6 This is a front view of another prefabricated T-beam side beam lifting tool provided according to an embodiment of the present utility model. Figure 6 As shown, when the prefabricated T-beam side beams with a length of 20 meters and 30 meters are lifted and moved, two through slots 4 are respectively provided on the front and back of the box body 1.

[0034] Preferably, if Figure 1 As shown, a reinforcing rib 5 is provided on the ridge where the front and top of the box body 1 intersect. Preferably, the reinforcing rib 5 is a steel bar.

[0035] Preferably, the reinforcing rib 5 is made of HRB400 and has a diameter of 14 mm.

[0036] Figure 7 This is a schematic diagram of the application of a lifting tool for prefabricated T-beam side beams provided according to an embodiment of the present utility model. Figure 7 As shown, when lifting and moving a precast T-beam side beam, a box 1 is fixed to the wet joints on both sides of the beam. The steel bars on the wet joints of the precast T-beam side beam pass through the box's through slots 4. The lifting cables for the precast T-beam side beam are installed through the gaps between metal rods 3. Metal rods 3 are used to limit the deviation of the lifting cables and prevent them from moving along the bridge. When lifting and moving the beam, the lifting cables pass through the middle of the metal rods 3 of the lifting fixture and are lifted when they reach the wet joints, ensuring a smooth lifting of the precast T-beam.

[0037] From the above description, it can be seen that the utility model provides a lifting tool for prefabricated T-beam side beams, which can lift and move the side beams without reserving lifting holes on the side beams, thereby increasing the force strength of the side beam flange plates and preventing the problem of unevenness and water leakage on the wing plate surface caused by improper installation of the sealing lifting hole template when the bridge deck uses lifting holes for lifting and moving beams.

[0038] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. Therefore, the embodiments should be considered in all respects as illustrative and non-restrictive, and the scope of the present invention is defined by the appended claims, not the foregoing description, and all variations within the meaning and range of equivalents of the claims are intended to be encompassed within the present invention. Any reference sign in a claim should not be construed as limiting the claim to which it relates.

[0039] In addition, it should be understood that although this specification is described in terms of implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.

Claims

1. A hoisting tool for prefabricated T-beam side beams, characterized in that: Applied to prefabricated T-beam side beams; comprising: a box, a lifting ring and a metal rod; the lifting ring is fixed at the middle position of the top of the box; the metal rod is vertically fixed at the front side of the box; the box is provided with through grooves with equal spacing; The box is fixedly arranged at the wet joints on both sides of the prefabricated T-beam side beam, and the steel bars on the wet joints of the prefabricated T-beam side beam pass through the through grooves of the box, and the hoisting operation cables of the prefabricated T-beam side beam pass through the gaps between the metal rods; The metal rod is used to limit the deviation of the lifting operation cable; The lifting ring is used to move the box by hand.

2. The hoisting tool for the prefabricated T-beam side beam according to claim 1 is characterized in that: The box body is a rectangular steel plate box body.

3. The hoisting tool for the prefabricated T-beam side beam according to claim 1 is characterized in that: The lifting ring is a steel bar lifting ring.

4. The hoisting tool for the prefabricated T-beam side beam according to claim 1 is characterized in that: The side surface of the box body is a reinforced steel rib plate structure.

5. The hoisting tool for the prefabricated T-beam side beam according to claim 1 is characterized in that: Reinforcement ribs are arranged on the ridges where the front and top of the box body intersect, and the reinforcement ribs are steel bars.