Support for coil pipe and support module
By designing floor heating brackets for coils, using the raised structure of the base plate and stuck tubes, combined with the design of reinforcements and gaps, the problems of uneven heat dissipation and insufficient adhesion in the traditional floor heating laying method are solved, and a stronger The fixing strength and better thermal insulation and sound insulation effect.
Patent Information
- Application Number
- CN202421007431.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-05-10
AI Technical Summary
In floor heating systems, traditional floor heating laying methods lead to uneven heat dissipation, difficult to maintain indoor temperature, and dust pollution problems; and when floor heating is on the wall or on the roof, there is a lack of sufficient bonding space between the insulation body and the wall, resulting in Inadequate adhesion makes it impossible to achieve a firm fixation.
A bracket for coiled pipes is designed, including a base plate and a tube protrusion. Reinforcement parts and gaps are set on the base plate. Fasteners pass through connection holes to fix the base plate. The filler fills the gaps to increase the bonding area. The bracket is firmly fixed to the wall or roof.
It improves the fixing strength between the bracket and the wall or roof, reduces dust pollution, achieves uniform heating of the indoor temperature, and provides insulation and sound insulation functions.
Smart Images

Figure CN222378193U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of building decoration, in particular to a bracket and a bracket module for a coil. Background Art
[0002] Floor heating is usually laid by clamping pipes. For example, the utility model patent with publication number CN207035279U discloses a floor heating module and a floor heating system, wherein the floor heating module includes an insulation body and a hot water pipe. The insulation body is provided with a first groove, a second groove and a holder, the first groove and the second groove are vertically arranged, the holder is located in the first groove and the second groove, the hot water pipe is clamped in the holder and embedded in the first groove and / or the second groove. The floor heating module fixes the hot water pipe by the clamping relationship, and the hot water pipe is hardly subjected to external pressure after installation, thereby increasing the service life of the hot water pipe.
[0003] The traditional way is to lay the floor heating in the above patent below the ground surface, and the heat in the hot water pipe will be dissipated from bottom to top, so that the indoor temperature will gradually rise. However, this laying method has the following problems: 1. The heat will gradually decrease when it is dissipated from bottom to top, especially in cold weather, the indoor temperature will always be low after turning on the floor heating; 2. When the heat of the floor heating is dissipated from bottom to top, the dust on the ground surface will rise with the air flow, causing dust pollution; 3. Furniture such as beds and tables placed on the ground will hinder the dissipation of heat, resulting in uneven indoor temperature.
[0004] To this end, a new method of laying hot water pipes is currently used, in which the hot water pipes are laid inside the walls (referred to as floor heating on the wall) or on the roof (referred to as floor heating on the roof). Compared with simply laying the hot water pipes below the ground surface, this method can achieve rapid indoor heating and reduce dust pollution.
[0005] However, when floor heating is mounted on a wall or a ceiling, it needs to be fixed with plaster or cement. However, the insulation body in the above patent is an integral structure, and plaster or cement can only be attached to the surface of the insulation body. Since there is no sufficient bonding space between the insulation body and the wall, plaster (or cement) cannot provide sufficient adhesion to allow the insulation body to be firmly bonded to the wall. Utility Model Content
[0006] In order to solve the above deficiencies in the prior art, the utility model aims to provide a bracket and a bracket module for a coil, so as to achieve the purpose of firmly bonding the bracket to the wall and the bracket to the roof.
[0007] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:
[0008] A bracket for a coil comprises a base plate and a plurality of pipe clamping protrusions arranged at intervals on the base plate, wherein the height of the pipe clamping protrusions and the distance between two pipe clamping protrusions for clamping a water pipe are both adapted to the diameter of the water pipe; a reinforcing part for firmly fixing the base plate to a base body is also arranged on the base plate, and the reinforcing part comprises a plurality of connecting holes arranged on the base plate and fasteners penetrating the connecting holes to fix the base plate to the base body.
[0009] As a limitation of the present invention: the reinforcement part also includes a plurality of gaps arranged on the base plate, and the base plate is a hollow structure.
[0010] As a further limitation of the present invention: at least two reinforcement strips are arranged in each gap of the substrate, and at least two reinforcement strips are cross-connected.
[0011] As a further limitation of the present utility model: the tube-holding protrusion is cylindrical, its axial direction is arranged perpendicular to the base plate, the tube-holding protrusion is a hollow structure, and its longitudinal section is an inverted "U" shape.
[0012] As another limitation of the present invention: the top edge of the pipe clamping protrusion extends in a direction away from the center of the pipe clamping protrusion to form an extension piece, and a plurality of extension pieces are provided, which are arranged in a circumferential array along the pipe clamping protrusion; the extension pieces on the two pipe clamping protrusions for clamping the water pipe are arranged opposite to each other, and the distance between the two opposite extension pieces is adapted to the diameter of the water pipe.
[0013] As a further limitation of the present invention: reinforcing ribs for supporting the pipe clamping protrusion are arranged at the position where the base plate is connected to the pipe clamping protrusion.
[0014] As another limitation of the present invention: an inserting portion for connecting with another substrate is provided at an edge of the substrate.
[0015] The utility model also provides a bracket module, including the above-mentioned bracket for coils, and also includes a bottom plate embedded with the bracket, the size of the bottom plate is adapted to the base plate, and a groove for the base plate to be embedded is arranged on the bottom plate; the bottom plate is selected from thermal insulation and sound insulation materials.
[0016] As a further limitation of the utility model: a convex block is also arranged on the bottom plate, the shape and size of the convex block are matched with the tube clamping protrusion, and the convex block is embedded in the tube clamping protrusion.
[0017] As a further limitation of the present invention: a side of the bottom plate close to the base body is a wave-shaped structure.
[0018] Due to the adoption of the above technical solution, the utility model has the following beneficial effects compared with the prior art:
[0019] (1) The utility model includes a base plate and a plurality of pipe clamping protrusions arranged at intervals on the base plate. When the water pipe is coiled, the water pipe is clamped between two pipe clamping protrusions. Since the height of the pipe clamping protrusion is adapted to the diameter of the water pipe, and the adaptation here means that the height of the pipe clamping protrusion is greater than the diameter of the water pipe, this structure protects the water pipe and increases the service life of the water pipe. A reinforcement part is also provided on the base plate, and the reinforcement part includes a plurality of connection holes and a plurality of fasteners provided on the base plate. When in use, the fasteners are fastened to the base body after passing through the connection holes, thereby achieving a firm fixation between the base plate and the base body;
[0020] (2) The reinforcement part of the utility model also includes a plurality of gaps arranged on the base plate, so that the base plate as a whole is a hollow structure. When the bracket is mounted on a wall or a roof, the bracket is first connected to the wall or the roof using fasteners. Then, when filling materials such as gypsum or cement are applied, the filling materials will fill the plurality of gaps on the base plate, thereby increasing the bonding area between the base plate and the wall or the roof, and further ensuring the fixing strength between the bracket and the wall or the roof;
[0021] (3) The pipe clamping protrusion in the utility model is a cylindrical structure, and its bending radius is greater than four times the diameter of the water pipe, that is, it meets the minimum bending radius of the water pipe, and can realize the bending and coiling of the water pipe on the base plate. Otherwise, the bending radius of the pipe clamping protrusion is too small and the water pipe cannot be bent smoothly; the pipe clamping protrusion is also a hollow structure, which is convenient for filling with fillers, and further improves the fixing strength;
[0022] (4) The utility model also provides a bracket module, including a bracket and a bottom plate embedded in the bracket, the bottom plate is made of EPS or EPP material, which can achieve heat preservation and sound insulation functions, and the back of the bottom plate is arranged in a wavy structure, which increases the surface area, can better absorb sound waves, and improves the sound reception effect; the bottom plate is provided with a groove for the base plate to be embedded, and a protrusion adapted to the protrusion of the clamping tube, so that the bracket and the bottom plate are embedded to form a bracket module with heat preservation and sound insulation functions.
[0023] In summary, the utility model can not only improve the fixing strength between the bracket and the wall or the bracket and the roof, but also has the functions of sound insulation and heat preservation; the utility model is suitable for the interior decoration industry, especially for coils on walls and roofs. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The present invention is described in further detail below in conjunction with the accompanying drawings and specific embodiments.
[0025] Figure 1 This is a schematic diagram of the main structure of Example 1 of the utility model (screws are not shown);
[0026] Figure 2 This is a schematic diagram of the three-dimensional structure of Example 1 of the utility model;
[0027] Figure 3for Figure 2 A magnified schematic diagram of part A;
[0028] Figure 4 for Figure 2 A magnified schematic diagram of part B;
[0029] Figure 5 This is a schematic diagram of the application structure of Embodiment 1 of the present utility model;
[0030] Figure 6 This is a schematic diagram of the main structure of Embodiment 2 of the present utility model;
[0031] Figure 7 This is a schematic diagram of the three-dimensional structure of Example 3 of the utility model;
[0032] Figure 8 for Figure 7 A magnified schematic diagram of part C;
[0033] Fig. 9 This is an exploded view of Embodiment 3 of the present utility model;
[0034] Fig.10 This is a schematic diagram of the structure of the bottom plate in Example 3 of the utility model;
[0035] Fig.11 It is a partial structural schematic diagram of the pipe clamping protrusion and the protrusion in Example 4 of the utility model;
[0036] Fig.12 This is a schematic diagram of the structure of the bottom plate in Example 4 of the utility model (the groove is not shown).
[0037] In the figure: 1-base plate, 101-connecting hole, 102-gap, 103-support bar, 2-tube clamping protrusion, 3-extension piece, 4-reinforcement rib, 5-plug-in portion, 51-plug-in plate, 52-plug-in block; 6-bottom plate, 7-reinforcement bar, 8-water pipe, 9-plate, 10-groove, 11-bump. DETAILED DESCRIPTION
[0038] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the bracket and bracket module for a coil described herein are preferred embodiments, which are only used to illustrate and explain the present invention and do not constitute a limitation on the present invention.
[0039] Example 1 A bracket for a coil
[0040] like Figure 1 to Figure 5As shown, this embodiment includes a base plate 1 and a plurality of pipe clamping protrusions 2 arranged at intervals on the base plate 1. When the pipe is coiled, the water pipe 8 is clamped between two pipe clamping protrusions 2; a reinforcement part is arranged on the base plate 1, and the reinforcement part includes a plurality of connection holes 101 arranged on the base plate 1, and fasteners penetrating the connection holes 101 to fix the base plate 1 to the base body, so that the base plate 1 and the base body are firmly fixed. Here, the base body refers to a wall or a roof. In this embodiment, the fastener is a screw, which can also be replaced by a nail, an expansion screw or other fasteners.
[0041] like Figure 1 , 3 As shown, in this embodiment, the connection hole 101 is a tapered hole, and the end located on the upper surface of the substrate 1 is the end with the largest diameter. This structure enables the head of the screw to be embedded in the connection hole 101 after the screw passes through the connection hole 101, so that the surface of the substrate 1 remains flat. Otherwise, the screw protrudes from the upper surface of the substrate 1, affecting the laying of the water pipe 8.
[0042] In order to further improve the fixing strength between the bracket and the wall and the ceiling, the reinforcement part also includes a plurality of gaps 102 arranged on the base plate 1, such as Figure 1-3 As shown, the shapes of the substrate 1 and the gap 102 in this embodiment are both square, and the substrate 1 is a hollow structure as a whole, with low manufacturing cost. In other words, from the perspective of the substrate 1 as a whole, the inside of the substrate 1 is composed of a number of support bars 103 connected vertically to each other to form a number of square gaps 102, and a number of connection holes 101 are dispersedly arranged on the support bars 103. The material of this bracket is plastic. When the bracket is installed, the bracket is fixed to the wall or the top by screws through the connection holes 101 to achieve the first reinforcement; after the coil is completed, when filling materials such as gypsum or cement are applied, the filling materials can fill the gap 102, so that there is sufficient bonding area between the bracket and the wall and the top. Compared with the complete flat plate structure of the substrate 1, this structure achieves secondary reinforcement.
[0043] like Figure 2 , 3 As shown, a plurality of pipe-holding protrusions 2 are arranged at intervals on the base plate 1. In this embodiment, the pipe-holding protrusions 2 are arranged at the intersection of two mutually perpendicular struts 103. The pipe-holding protrusions 2 are cylindrical, and their axial direction is arranged perpendicular to the base plate 1. The pipe-holding protrusions 2 are also hollow structures, that is, they are hollow inside and have an open structure at the bottom. The longitudinal section is an inverted "U" shape. Cement or gypsum can also be filled between the pipe-holding protrusions 2 and the wall to improve the fixing strength.
[0044] like Figure 2 , 3 As shown, the edge of the top of the tube-holding protrusion 2 extends in a direction away from the center of the tube-holding protrusion 2 to form a plurality of extension pieces 3. In this embodiment, four extension pieces 3 are provided on each tube-holding protrusion 2 and are arranged in an array along the circumferential direction of the tube-holding protrusion 2. When the tube is coiled, as shown in FIG. Figure 5As shown, the water pipe 8 is located above the support bar 103 and between the two pipe clamping protrusions 2. Since the two extension pieces 3 for clamping the pipe are arranged oppositely, the water pipe 8 can be clamped. Here, the opposite arrangement means that the two extension pieces 3 for clamping the pipe located on different pipe clamping protrusions 2 extend toward the water pipe 8 to clamp the water pipe 8. It should be noted that if the extension piece 3 is not provided, the water pipe 8 needs to be clamped with two pipe clamping protrusions 2. At this time, the distance between the two pipe clamping protrusions 2 for clamping the water pipe 8 is adapted to the diameter of the water pipe 8. Here, the adaptation means that the closest distance between the outer walls of the two pipe clamping protrusions 2 is equal to or slightly smaller than the diameter of the water pipe 8. When coiling the pipe, press the water pipe 8 to clamp it. This method is only adapted to water pipes 8 of a single diameter. In this embodiment, the extension piece 3 is provided to adapt to the water pipe 8 with a diameter of 10mm-12mm. At this time, the closest distance between the outer walls of the two pipe-holding protrusions 2 is equal to or slightly greater than 12mm, and the distance between the two opposite extension pieces 3 is also adapted to the diameter of the water pipe 8. Adaptation here means that the distance between the two extension pieces 3 along the radial direction of the pipe-holding protrusion 2 is slightly smaller than the diameter of the water pipe 8, and in this embodiment is slightly smaller than 10mm, so as to ensure that the water pipe 8 of 10-12mm can be placed between the two pipe-holding protrusions 2, and the extension piece 3 can ensure that the water pipe 8 is always held between the two pipe-holding protrusions 2. In addition, the height of the pipe-holding protrusion 2 is adapted to the diameter of the water pipe 8. Adaptation here means that the height of the pipe-holding protrusion 2 is equal to or slightly greater than the diameter of the water pipe 8, so as to protect the water pipe 8 and increase the service life of the water pipe 8.
[0045] The cross section of the tube clamping protrusion 2 is circular. Figure 5 As shown, when the water pipe 8 is bent, the water pipe 8 fits against the arc-shaped outer periphery of the pipe clamping protrusion 2. At the same time, the minimum bending radius of the water pipe 8 is ensured to be greater than or equal to four times the diameter of the water pipe 8 to ensure that the water pipe 8 is not damaged when the pipe is bent. The minimum bending radius of the pipeline is the existing technology and will not be described in detail here.
[0046] Further, such as Figure 1-3 As shown, a reinforcing rib 4 is provided at the position where the support bar 103 is connected to the pipe-holding protrusion 2. The reinforcing rib 4 is a right triangle, and the right angle is located at the connection between the support bar 103 and the pipe-holding protrusion 2, for supporting the pipe-holding protrusion 2 and increasing the strength.
[0047] In actual installation, the wall or ceiling needs to be spliced by several brackets. Compared with the entire bracket on the wall, the assembled structure is easier to install. Figure 1 , 2 As shown, the edge of the substrate 1 is provided with a plug-in portion 5 for splicing with another substrate 1. Figure 1 , 2 The insertion parts 5 are provided on two sides of the substrate 1 for illustration only. In practice, the insertion parts 5 can be provided on all four sides of the substrate 1 as required. Figure 4As shown, the plug-in portion 5 includes a plug-in board 51 connected to the substrate 1 and a plug-in block 52 fixed on the plug-in board 51. The other substrate 1 to be spliced is provided with a plug-in board 51 and a slot adapted to the plug-in block 52, and the two are snap-fitted and snap-fitted to achieve splicing.
[0048] In order to improve this embodiment, Figure 1 As shown, a flat plate 9 is provided on the substrate 1 and can be used to stick a trademark.
[0049] When using this embodiment, taking floor heating on the wall as an example, each bracket is fixed on the wall by screws, and several brackets are spliced through the plug-in part 5 to cover the entire wall, and then the coil is installed. Figure 5 As shown, the water pipe 8 is clamped between the pipe clamping protrusions 2, and the extension piece 3 on the pipe clamping protrusion 2 limits the position of the water pipe 8 to prevent it from being detached. After the coil is completed, cement is backfilled to seal the bracket and the water pipe 8 in the wall. Since the gap 102 is provided on the base plate 1, the cement can be fully in contact with the base plate 1, thereby improving the fixing strength, and finally the wallboard or wall cloth can be attached.
[0050] Example 2 A bracket for a coil
[0051] like Figure 6 As shown, the structure of this embodiment is basically the same as that of embodiment 1, except that two reinforcing bars 7 are arranged in each gap 102 on the substrate 1, and the two reinforcing bars 7 are vertically cross-connected, so that each gap 102 and the surrounding struts 103 form a field shape, and the reinforcing bars 7 are used to increase the overall strength of the substrate 1, making it flatter, so as to prevent the substrate 1 from warping and deformation; the number of reinforcing bars 7 in each gap 102 can also be selected as three, four or other numbers as needed. The structure other than this is exactly the same as that of embodiment 1, and will not be elaborated in detail in this embodiment.
[0052] The usage process of this embodiment refers to Embodiment 1.
[0053] Example 3 Bracket Module
[0054] like Figure 7-10As shown, this embodiment includes the embodiment 1, and also includes a bottom plate 6 embedded with the embodiment 1, the size of the bottom plate 6 is adapted to the base plate 1, and the adaptation here means that the size of the bottom plate 6 is the same as that of the base plate 1. A groove 10 is provided on the bottom plate 6. After the bottom plate 6 and the bracket are assembled, the base plate 1, the support bar 103, the plug plate 51 and the tube-holding protrusion 2 are all embedded in the groove 10, and the tube-holding protrusion 2 extends out of the groove 10; at the same time, a protrusion 11 is also provided at the position corresponding to the tube-holding protrusion 2 on the bottom plate 6. The shape of the protrusion 11 is the same as that of the tube-holding protrusion 2, both of which are cylindrical, and the size of the protrusion 11 is adapted to the tube-holding protrusion 2. The adaptation here means that the outer diameter of the protrusion 11 is equal to or slightly larger than the inner diameter of the tube-holding protrusion 2, so that the two can be engaged, and the height of the protrusion 11 is less than the height of the tube-holding protrusion 2, that is, there is a gap between the protrusion 11 and the tube-holding protrusion 2 in the height direction. When the embodiment is installed on the wall, the backfilled cement will fill the gap between the protrusion 11 and the pipe clamping protrusion 2, making the connection between the two more secure. In the embodiment, the base plate 6 is made of EPS, which has heat preservation and sound insulation functions. Of course, other heat preservation and sound insulation materials, such as EPP, can also be selected.
[0055] It should be noted that the structure in Example 2 can also be assembled with the base plate 6. It is only necessary to add a groove on the base plate 6 for embedding the reinforcement strip, so that after the assembly is completed, the base plate 1, the support bar 103, the plug plate 51, the tube clamping protrusion 2 and the reinforcement strip are all embedded in the groove.
[0056] The use process of this embodiment is similar to that of embodiment 1, except that when mounting this embodiment on a wall, longer screws are selected to pass through the connection holes and the bottom plate 6 and then the embodiment is fixed to the wall.
[0057] Example 4 Bracket Module
[0058] The structure of this embodiment is basically the same as that of the embodiment 3, with two differences: First, the height of the protrusion 11 in this embodiment is nearly equal to the height of the pipe-holding protrusion 2. In practical applications, if this embodiment is pushed up, cement backfill is not required, so the height of the protrusion 11 is nearly equal to the height of the pipe-holding protrusion 2. Under this structure, the protrusion 11 can support the side wall of the pipe-holding protrusion 2, see Fig.11 . 2. To further enhance the sound insulation function, the side of the bottom plate 6 close to the base (i.e. the back side) is a wavy structure, see Fig.12 Compared with the bottom plate with a flat back in Embodiment 3, the surface area of the back of the bottom plate 6 is increased, which can better absorb sound waves, thereby improving the sound collection effect. It should be supplemented that: Fig.12 The grooves on the midsole plate 6 are not shown.
[0059] The other structures are exactly the same as those in Example 3 and will not be elaborated in detail in this example.
[0060] The usage process of this embodiment refers to Example 3.
[0061] It should be noted that the above is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A support for a coil, characterized in that: It includes a base plate and a plurality of pipe clamping protrusions arranged at intervals on the base plate. The height of the pipe clamping protrusions and the distance between two pipe clamping protrusions used for clamping water pipes are both adapted to the diameter of the water pipe. The base plate is also provided with a reinforcement part for firmly fixing the base plate and the base body. The reinforcement part includes a plurality of connection holes arranged on the base plate and fasteners penetrating the connection holes to fix the base plate to the base body.
2. A support for a coil according to claim 1, characterized in that: The reinforcement part also includes a plurality of gaps arranged on the base plate, and the base plate is a hollow structure.
3. A support for a coil according to claim 2, characterized in that: At least two reinforcement strips are arranged in each gap of the substrate, and the at least two reinforcement strips are cross-connected.
4. A support for a coil according to claim 3, characterized in that: The tube-holding protrusion is cylindrical, and its axial direction is arranged perpendicular to the base plate. The tube-holding protrusion is a hollow structure, and its longitudinal section is in an inverted "U" shape.
5. A support for a coil according to any one of claims 1 to 4, characterized in that: The top edge of the pipe clamping protrusion extends in a direction away from the center of the pipe clamping protrusion to form an extension piece, and a plurality of extension pieces are arranged in a circumferential array along the pipe clamping protrusion; the extension pieces on the two pipe clamping protrusions for clamping the water pipe are arranged opposite to each other, and the distance between the two opposite extension pieces is adapted to the diameter of the water pipe.
6. A support for a coil according to claim 5, characterized in that: A reinforcing rib for supporting the pipe clamping protrusion is arranged at a position where the base plate is connected to the pipe clamping protrusion.
7. A support for a coil according to any one of claims 1 to 4 and 6, characterized in that: The edge of the base plate is provided with an inserting portion for splicing with another base plate.
8. A bracket module, characterized in that: A bracket for a coil comprising any one of claims 1 to 7, further comprising a bottom plate embedded with the bracket, the bottom plate having a size adapted to the base plate, and a groove for embedding the base plate; Choose thermal insulation and sound insulation materials for the base plate.
9. The support module according to claim 8, characterized in that: The bottom plate is also provided with a convex block, the shape and size of which are matched with the tube clamping protrusion, and the convex block is embedded in the tube clamping protrusion.
10. The support module according to claim 8 or 9, characterized in that: The side of the bottom plate close to the base body is a wave-shaped structure.
Citation Information
Patent Citations
Warm up module and underfloor heating system
CN207035279U