Underground comprehensive pipe gallery pre-buried device
By designing an underground integrated pipeline corridor pre-embedded device containing embedded poles, insert blocks and ratchet plates, the problems of labor-intensive and difficult position adjustment during the installation of existing devices are solved, and fast, safe and stable Installation effect.
Patent Information
- Application Number
- CN202420954655.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-06
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2034-05-06
AI Technical Summary
The existing underground integrated pipeline pre-embedded device requires multiple workers to weld during the installation process, and the position after installation is difficult to adjust, resulting in increased construction time and cost.
An underground comprehensive pipeline corridor pre-embedding device including a base frame, a top frame, a first fixing frame, a second fixing frame and a pre-embedding mechanism is designed. The fast installation and fixation of the embedded mechanism is achieved through the plug-in connection between the embedded rod and the insertion block and the engagement of the ratchet teeth and the clamping plate.
The device can reduce installation labor and time while improving installation safety and stability, reducing the cost of subsequent adjustments and corrections.
Smart Images

Figure CN222500339U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of underground pipe gallery embedded parts, in particular to an underground comprehensive pipe gallery embedded device. Background Art
[0002] The pre-buried device of underground comprehensive pipeline corridor is a kind of equipment or component used in the construction of underground comprehensive pipeline corridor. It is usually used to be buried in concrete structure in advance to facilitate the subsequent installation of pipelines, cables and other facilities.
[0003] The anchor rods of the existing underground integrated pipe corridor pre-buried devices are mainly installed with the pipe corridor support frame by welding, and this method requires multiple workers to perform welding to effectively fix them. Moreover, the relative position between the support frame and the pre-buried device is difficult to adjust after welding. If position deviation is found or adjustment is required during subsequent construction, it may take more time and cost to correct it. Therefore, when designing the underground integrated pipe corridor pre-buried device, it is necessary to provide a novel underground integrated pipe corridor pre-buried device that can be installed more quickly and effectively, and the installation process is safer and more stable, thereby improving the overall practicality. Utility Model Content
[0004] Based on this, the purpose of the present invention is to provide an underground comprehensive pipeline corridor pre-buried device to solve the more troublesome technical problems in the installation process of the underground comprehensive pipeline corridor pre-buried device.
[0005] To achieve the above-mentioned object, the present invention provides the following technical solution: an underground integrated pipe gallery pre-embedded device, comprising a bottom frame and a top frame, a first fixing frame being provided between the bottom frame and the top frame, a second fixing frame being welded to the back of the first fixing frame, an embedded mechanism being provided on the outer surface of the first fixing frame, the embedded mechanism comprising an embedded plate, an embedded seat being provided on the back of the embedded plate, and an embedded rod being provided on the back of the embedded seat;
[0006] An insert block is provided on the back of the embedded rod, a ratchet is provided on the rear end of the embedded rod, a socket is provided inside the insert block, and a clamp is provided inside the socket.
[0007] By adopting the above technical solution, since the first fixing frame is provided between the bottom frame and the top frame, and the second fixing frame is welded to the back of the first fixing frame, the first fixing frame and the second fixing frame can be effectively installed through the bottom frame and the top frame.
[0008] Furthermore, the embedded rod is plugged into the plug block, and the ratchet is engaged with the clamping plate.
[0009] By adopting the above technical solution, since the embedded rod is plugged into the plug block, the embedded rod can be effectively inserted into the interior of the plug block.
[0010] Furthermore, the pre-embedded mechanisms are provided in plurality, and the plurality of pre-embedded mechanisms are arranged in a linear array at equal intervals.
[0011] By adopting the above technical solution, multiple embedded mechanisms are provided, and multiple embedded plates can be effectively installed through the multiple embedded mechanisms.
[0012] Furthermore, the embedded rods are provided in multiple groups, and each group includes four embedded rods, and the four embedded rods are respectively connected to the first fixing frame and the second fixing frame.
[0013] By adopting the above technical solution, since multiple groups of embedded rods are provided, and each group of embedded rods is provided with four, the four embedded rods can ensure that the embedded seat can be effectively installed on the first fixing frame and the second fixing frame.
[0014] Furthermore, the embedded seats are provided in plurality, and the plurality of embedded seats are provided in multiple groups, and each group is provided with three, and the three embedded seats are arranged equidistantly from top to bottom.
[0015] By adopting the above technical solution, since there are multiple embedded seats, the multiple embedded seats are arranged in multiple groups, and each group is provided with three, so an embedded plate can be effectively installed and fixed through three embedded seats.
[0016] Furthermore, a first buckle slot and a second buckle slot are provided at the front end of the insert block, and the first buckle slot and the second buckle slot are respectively engaged with the first fixing frame and the second fixing frame.
[0017] By adopting the above technical solution, since the front end of the insert block is provided with the first buckle groove and the second buckle groove, the first buckle groove and the second buckle groove can ensure that the insert block can be buckled with the first fixing frame and the second fixing frame.
[0018] Furthermore, the first fixing frame and the second fixing frame are made of stainless steel, and the entire embedded mechanism is made of aluminum alloy.
[0019] By adopting the above technical solution, since the material of the first fixing frame and the second fixing frame is stainless steel, which is a high-strength material with good tensile strength and compressive strength, this enables the stainless steel steel frame to withstand various loads during the construction process, including its own weight, the weight of construction equipment and materials, etc., to ensure the safety and stability of the pipeline corridor construction. At the same time, the durability of stainless steel is also excellent, and it can maintain its mechanical properties and structural stability for a long time.
[0020] Furthermore, the first fixing frame and the second fixing frame are provided in plurality, and the plurality of the first fixing frames and the second fixing frames are arranged evenly and equidistantly, and the first fixing frames and the second fixing frames are arranged in a rectangular array.
[0021] By adopting the above technical solution, since a plurality of first fixing frames and second fixing frames are provided, and the plurality of first fixing frames and second fixing frames are provided with a plurality of equidistant and evenly arranged, the first fixing frames and the second fixing frames serve as the skeleton of the pipe gallery and provide necessary support for the entire structure.
[0022] Furthermore, an outer surface of the embedded plate is provided with a mounting groove, and the mounting groove is detachably connected to the external mounting plate.
[0023] By adopting the above technical solution, since the outer surface of the embedded plate is provided with a mounting groove, the external pipeline fixing frame can be effectively installed through the mounting groove.
[0024] Furthermore, the embedded plate is arranged in a rectangular structure.
[0025] By adopting the above technical solution, the embedded plate provides a more direct and convenient laying path, reduces the bends and turns of the pipeline, and reduces the difficulty of construction.
[0026] In summary, the present invention has the following beneficial effects:
[0027] 1. The utility model sets a pre-embedded mechanism. First, the pre-embedded rod needs to be inserted according to the bridge of the first fixing frame and the second fixing frame to ensure that the pre-embedded rod can be effectively engaged with the first fixing frame and the second fixing frame. Then, the plug-in block can be plugged into the pre-embedded rod through the socket. After the plug-in, the elastic card plate can effectively engage with the ratchet, so that the plug-in block cannot be withdrawn from the pre-embedded rod, thereby achieving a fixing effect. The above-mentioned arrangement can make it faster and more effective to install and fix the pre-embedded mechanism. Moreover, the four pre-embedded rods can further improve the overall stability of the pre-embedded mechanism.
[0028] 2. The utility model provides the first buckle groove and the second buckle groove. After the plug-in block is plugged into the embedded rod, the first buckle groove and the second buckle groove can ensure that the plug-in block can be buckled with the first fixing frame and the second fixing frame, thereby further improving the stability of the embedded mechanism. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0030] Figure 2 This is a schematic diagram of a partial three-dimensional structure of the embedded mechanism of the present utility model;
[0031] Figure 3 This is a schematic diagram of the side cross-sectional three-dimensional structure of the embedded mechanism of the present invention;
[0032] Figure 4 For this utility model Figure 3Schematic diagram of the structure enlarged at point A in the middle.
[0033] In the figure: 1. Base frame; 2. Top frame; 3. First fixing frame; 4. Embedded mechanism; 401. Embedded plate; 402. Mounting slot; 403. Embedded seat; 404. Embedded rod; 405. Insert block; 406. Ratchet; 407. Socket; 408. Card; 5. First buckle slot; 6. Second buckle slot; 7. Second fixing frame. DETAILED DESCRIPTION
[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. The embodiments described below with reference to the drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0035] The following describes an embodiment of the present invention based on its overall structure.
[0036] Example 1:
[0037] An underground integrated pipe gallery pre-buried device, such as Figure 1-Figure 4 As shown, it includes a base frame 1 and a top frame 2. A first fixing frame 3 is provided between the base frame 1 and the top frame 2. A second fixing frame 7 is welded to the back of the first fixing frame 3. An embedded mechanism 4 is provided on the outer surface of the first fixing frame 3. The embedded mechanism 4 includes an embedded plate 401. An embedded seat 403 is provided on the back of the embedded plate 401. An embedded rod 404 is provided on the back of the embedded seat 403.
[0038] An insert block 405 is provided on the back of the embedded rod 404, a ratchet 406 is provided at the rear end of the embedded rod 404, a socket 407 is provided inside the insert block 405, and a clamping plate 408 is provided inside the socket 407. The first fixing frame 3 and the second fixing frame 7 can be effectively installed through the base frame 1 and the top frame 2, and the embedded mechanism 4 can be lowered more quickly and effectively for installation and fixation, and the overall stability of the embedded mechanism 4 can be further improved by the four embedded rods 404.
[0039] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4 The embedded rod 404 is plugged into the plug block 405, and the ratchet 406 is engaged with the card plate 408, so the embedded rod 404 can be effectively inserted into the interior of the plug block 405, and the embedded mechanism 4 can be effectively locked through the cooperation of the ratchet 406 and the card plate 408.
[0040] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4There are multiple embedded mechanisms 4, and the multiple embedded mechanisms 4 are arranged equidistantly in a linear array. Multiple embedded plates 401 can be effectively installed through the multiple embedded mechanisms 4, and the multiple embedded mechanisms 4 will not interfere with each other.
[0041] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4 There are multiple groups of embedded rods 404, and each group of embedded rods 404 is provided with four. The four embedded rods 404 are respectively connected to the first fixing frame 3 and the second fixing frame 7. The four embedded rods 404 can ensure that the embedded seat 403 can be effectively installed on the first fixing frame 3 and the second fixing frame 7, and the four embedded rods 404 can further ensure that the embedded mechanism 4 can be stably fixed.
[0042] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4 There are multiple embedded seats 403, and multiple embedded seats 403 are provided in multiple groups, and each group is provided with three. The three embedded seats 403 are arranged equidistantly from top to bottom. Through the three embedded seats 403, an embedded plate 401 can be effectively installed and fixed, and the multiple embedded seats 403 will not interfere with each other.
[0043] Example 2:
[0044] See Figure 1 、 Figure 2 、 Figure 3 The front end of the insert block 405 is provided with a first buckle groove 5 and a second buckle groove 6, which are respectively engaged with the first fixing frame 3 and the second fixing frame 7. The first buckle groove 5 and the second buckle groove 6 can ensure that the insert block 405 can be buckled with the first fixing frame 3 and the second fixing frame 7, thereby further improving the stability of the embedded mechanism 4.
[0045] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4The first fixing frame 3 and the second fixing frame 7 are made of stainless steel, and the overall material of the embedded mechanism 4 is aluminum alloy. Stainless steel is a high-strength material with good tensile strength and compressive strength, which enables the stainless steel steel frame to withstand various loads during the construction process, including its own weight, the weight of construction equipment and materials, etc., to ensure the safety and stability of the pipeline corridor construction. At the same time, the durability of stainless steel is also very good, and it can maintain its mechanical properties and structural stability for a long time. Since the overall material of the embedded mechanism 4 is aluminum alloy, the strength of the embedded mechanism 4 can also meet the engineering requirements and ensure the stability and safety of the embedded device. In addition, aluminum alloy also has good corrosion resistance and can resist the erosion of moisture, chemicals and other corrosive substances in the soil, thereby extending the service life of the embedded device.
[0046] See Figure 1 、 Figure 2 、 Figure 3 There are multiple first fixing frames 3 and second fixing frames 7, and multiple first fixing frames 3 and second fixing frames 7 are arranged in an equidistant and uniform manner. The first fixing frames 3 and second fixing frames 7 are arranged in a rectangular array. There are multiple first fixing frames 3 and second fixing frames 7, and multiple first fixing frames 3 and second fixing frames 7 are arranged in an equidistant and uniform manner. Therefore, the first fixing frames 3 and second fixing frames 7 serve as the skeleton of the pipe gallery, providing necessary support for the entire structure, and the first fixing frames 3 and second fixing frames 7 can effectively control the deformation and cracks that may occur after concrete pouring.
[0047] See Figure 1 、 Figure 2 、 Figure 3 、 Figure 4 The outer surface of the embedded plate 401 is provided with a mounting groove 402, which is detachably connected to the external mounting plate. The external pipeline fixing frame can be effectively installed through the mounting groove 402, and the mounting plate can be effectively removed from the mounting groove 402 after being damaged, so as to facilitate subsequent maintenance.
[0048] The implementation principle of the present invention is as follows: first, the bottom frame 1 and the top frame 2 need to be fixed by welding through the first fixing frame 3, and then the second fixing frame 7 is fixed by welding to the first fixing frame 3. After that, the embedded rod 404 needs to be inserted according to the bridge of the first fixing frame 3 and the second fixing frame 7 to ensure that the embedded rod 404 can be effectively engaged with the first fixing frame 3 and the second fixing frame 7. Then, the plug 405 can be plugged into the embedded rod 404 through the socket 407. After the plugging, the elastic card plate 408 can effectively engage with the ratchet 406, so that the plug 405 cannot be pushed out of the embedded rod 404, thereby achieving a fixing effect.
[0049] Afterwards, it is only necessary to pour concrete on the underground integrated pipe gallery to effectively lower the embedded mechanism 4 for fixation, and then the embedded plate 401 exposed on the inner wall of the pipe gallery can be installed with the wiring rack through the installation groove 402.
[0050] Parts not involved in the present invention are the same as those in the prior art or can be implemented by using the prior art, and will not be described in detail here.
[0051] Although embodiments of the present invention have been shown and described, these specific embodiments are merely explanations of the present invention and are not limitations on the present invention. The specific features, structures, materials, or characteristics described may be combined in a suitable manner in any one or more embodiments or examples. After reading this specification, those skilled in the art may make modifications, substitutions, and variations to the embodiments as needed without departing from the principles and purpose of the present invention, but as long as they are within the scope of the claims of the present invention, they are protected by patent law.
Claims
1. An underground comprehensive pipe gallery pre-buried device, characterized in that: The invention comprises a bottom frame (1) and a top frame (2), wherein a first fixing frame (3) is arranged between the bottom frame (1) and the top frame (2), a second fixing frame (7) is welded to the back of the first fixing frame (3), an embedded mechanism (4) is arranged on the outer surface of the first fixing frame (3), the embedded mechanism (4) comprises an embedded plate (401), an embedded seat (403) is arranged on the back of the embedded plate (401), and an embedded rod (404) is arranged on the back of the embedded seat (403); The back of the embedded rod (404) is provided with an insert block (405), the rear end of the embedded rod (404) is provided with a ratchet (406), a socket (407) is provided inside the insert block (405), and a clamping plate (408) is provided inside the socket (407).
2. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The embedded rod (404) is plugged into the plug block (405), and the ratchet (406) is engaged with the clamping plate (408).
3. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: A plurality of the pre-embedded mechanisms (4) are provided, and the plurality of the pre-embedded mechanisms (4) are arranged at equal intervals in a linear array.
4. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The embedded rods (404) are provided in multiple groups, and each group of embedded rods (404) is provided with four embedded rods, and the four embedded rods (404) are respectively clamped with the first fixing frame (3) and the second fixing frame (7).
5. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The embedded seats (403) are provided in plurality, and the plurality of embedded seats (403) are provided in a plurality of groups, and each group is provided with three embedded seats, and the three embedded seats (403) are arranged equidistantly from top to bottom.
6. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The front end of the insert block (405) is provided with a first buckle groove (5) and a second buckle groove (6), and the first buckle groove (5) and the second buckle groove (6) are respectively engaged with the first fixing frame (3) and the second fixing frame (7).
7. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The first fixing frame (3) and the second fixing frame (7) are made of stainless steel, and the entire material of the embedded mechanism (4) is made of aluminum alloy.
8. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: A plurality of the first fixing frames (3) and the second fixing frames (7) are provided, and the plurality of the first fixing frames (3) and the second fixing frames (7) are arranged evenly and equidistantly, and the first fixing frames (3) and the second fixing frames (7) are arranged in a rectangular array.
9. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The outer surface of the embedded plate (401) is provided with a mounting groove (402), and the mounting groove (402) is detachably connected to the external mounting plate.
10. The pre-buried device for underground comprehensive pipe gallery according to claim 1 is characterized in that: The embedded plate (401) is arranged in a rectangular structure.