Novel construction site three-stage sedimentation tank
By designing a new three-stage sedimentation tank that is quickly disassembled and installed, the problems of cumbersome construction and one-time use of existing masonry sedimentation tanks have been solved, and the construction efficiency is improved and the sustainable utilization of resources is achieved.
Patent Information
- Application Number
- CN202421296767.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2025-03-07
- Estimated Expiration
- 2034-06-07
AI Technical Summary
The existing masonry-type three-stage sedimentation tank is cumbersome and one-time use during the construction process, resulting in waste of resources, high construction costs and environmental protection incompatibility.
A new three-stage sedimentation tank was designed, adopting a quick disassembly structure, including bottom plate, horizontal plate, side plate and partition. It can achieve rapid installation and disassembly through the clamping and cooperation of components such as slide grooves, sliders, round rods and rectangular grooves.
The new sedimentation tank reduces the total construction time, saves manpower and material costs, shortens the construction cycle, reduces equipment leasing and wage expenditure, improves construction efficiency, and reduces pollutant emissions.
Smart Images

Figure CN222566899U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sedimentation tanks, and more specifically, to a novel three-level sedimentation tank on a construction site. Background Art
[0002] The tertiary sedimentation tank is a common water treatment equipment, which is mainly used to remove suspended matter in sewage, precipitate organic matter, reduce the content of organic matter and suspended matter in water, and improve the transparency and water quality of water. In the current construction site, the tertiary sedimentation tank plays a pivotal role. It is mainly used to collect and treat sewage generated during the construction process to ensure that the impact of construction activities on the environment is minimized.
[0003] However, the three-stage sedimentation tanks widely used at present are mainly masonry-type. Although this design method meets the construction needs to a certain extent, its limitations are also increasingly prominent. The construction process of the masonry-type three-stage sedimentation tank is relatively cumbersome. First of all, earth excavation needs to be carried out according to the actual situation of the construction site. The depth and size of the excavation need to be accurately calculated to ensure that the sedimentation tank can meet the expected sewage treatment capacity. Then, in the excavated foundation pit, the steel bars are arranged and the concrete is poured. This process not only requires a large amount of building materials, but also requires a professional construction team and technical support, so the construction cost is relatively high. However, the biggest problem with this masonry-type three-stage sedimentation tank is its one-time use characteristics. Once the construction is completed, these sedimentation tanks are fixed in a specific position and cannot be easily moved. When the project is completed, these sedimentation tanks are often abandoned or demolished, resulting in a great waste of resources. For construction teams that need to frequently transfer sites, new sedimentation tanks need to be rebuilt every time, which not only increases the construction cost, but also prolongs the construction period and affects the construction efficiency. In addition, from an environmental protection perspective, this disposable sedimentation tank is not in line with the concept of sustainable development. With the continuous improvement of environmental awareness, how to reduce the impact of construction on the environment has become an urgent problem to be solved. However, the one-time use characteristics of the masonry type three-stage sedimentation tank are obviously contrary to this trend. Utility Model Content
[0004] In order to overcome the deficiencies of the prior art, the utility model provides a novel three-stage sedimentation tank for construction sites, which has the advantage of rapid disassembly and assembly of the sedimentation tank.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a new type of three-stage sedimentation tank at a construction site, comprising a bottom plate, a slide groove is provided on the side of the bottom plate, a slide bar is fixedly installed on the side of another bottom plate, and the slide bar is clamped in the inside of the slide groove, the number of the bottom plates is three, and the three bottom plates are clamped in sequence, a circular groove 1 is provided on the top of the bottom plate, a horizontal plate 1 is movably installed on the top of the bottom plate, a round rod 1 is fixedly installed on the bottom of the horizontal plate 1 and is movably installed in the inside of the circular groove 1, a horizontal plate 2 is movably installed between the two horizontal plates 1, and a round rod 1 is fixedly installed on the bottom of the horizontal plate 2 and is movably installed in the inside of the circular groove 1. The bottom plate is movably mounted inside the circular groove one, a circular groove two is provided on the top of the bottom plate, a side plate is movably mounted on the top of the bottom plate, a round rod two is fixedly mounted on the bottom of the side plate and is movably mounted inside the circular groove two, a rectangular groove is provided on the inner side of the cross plate one, a rectangular bar is fixedly mounted on the side of the side plate and the rectangular bar is movably mounted inside the rectangular groove, a partition is movably mounted on the surface of the connection between the two bottom plates, an overflow pipe is fixedly mounted inside the partition and extends to both ends, two clips are fixedly mounted on the side of the partition, clip grooves are provided on the inner sides of the cross plate one and the cross plate two, and the clips are located inside the clip grooves.
[0006] As a preferred technical solution of the utility model, an upper reinforcement block is provided at the connection between the transverse plate 1 and the side plate, and a lower reinforcement block is provided at the connection between the bottom plate, the transverse plate 1 and the side plate.
[0007] As a preferred technical solution of the utility model, there are two baffles, the two baffles are evenly distributed on the surface of the connection of the three bottom plates, and the heights of the two overflow pipes decrease successively.
[0008] As a preferred technical solution of the utility model, the inner diameter of the slide groove is equal to the outer diameter of the slide bar, and the inner diameter of the rectangular groove is equal to the outer diameter of the rectangular bar.
[0009] As a preferred technical solution of the utility model, the number of the upper reinforcement blocks and the number of the lower reinforcement blocks are both four, and the four upper reinforcement blocks and the four lower reinforcement blocks are evenly distributed at their connections.
[0010] As a preferred technical solution of the utility model, the bottom plate, the first horizontal plate, the second horizontal plate, the side plates and the partition plates are all made of stainless steel, and a waterproof layer is provided on the surface of the bottom plate.
[0011] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0012] The utility model is that after the staff installs the three bottom plates through the clamping connection of the slide groove and the slide bar, the horizontal plate one and the horizontal plate two are installed through the cooperation of the round rod one and the round groove one, and the side plates are installed through the cooperation of the round rod two and the round groove two, and the horizontal plate one and the side plates are fixed through the cooperation between the rectangular bar and the rectangular groove, and finally the partition is installed by clamping the clamping bar inside the clamping groove. Compared with the traditional device, this device reduces the total construction time of the project, which can significantly save the manpower and material costs in the construction process, thereby shortening the construction period, reducing the equipment rental costs and staff salary expenses, and further reducing the total project cost. At the same time, it can ensure that the project is carried out as planned, reduce the progress loss caused by construction delays, thereby helping to optimize resource allocation, improve overall construction efficiency, and ensure that the three-stage sedimentation tank is put into use in time, so as to play its role in sewage treatment as soon as possible, thereby helping to reduce the discharge of pollutants and improve the water quality treatment effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the structure of the utility model;
[0014] Figure 2 This is a schematic diagram of the front structure of the utility model;
[0015] Figure 3 This is a schematic diagram of the explosion structure of the utility model;
[0016] Figure 4 This is a schematic diagram of the side panel structure of the utility model;
[0017] Figure 5 For this utility model Figure 1 Schematic diagram of the local enlarged structure at point A in the middle.
[0018] In the figure: 1, bottom plate; 2, slide groove; 3, slide bar; 4, circular groove one; 5, horizontal plate one; 6, round rod one; 7, circular groove two; 8, side plate; 9, round rod two; 10, rectangular groove; 11, rectangular bar; 12, slot; 13, partition; 14, clip bar; 15, horizontal plate two; 16, lower reinforcement block; 17, upper reinforcement block; 18, overflow pipe. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] like Figures 1 to 5As shown, the utility model provides a new type of three-stage sedimentation tank for construction sites, including a bottom plate 1, a chute 2 is provided on the side of the bottom plate 1, a slide bar 3 is fixedly installed on the side of another bottom plate 1, and the slide bar 3 is clamped in the inside of the chute 2, there are three bottom plates 1, and the three bottom plates 1 are clamped in sequence, a circular groove 4 is provided on the top of the bottom plate 1, a horizontal plate 5 is movably installed on the top of the bottom plate 1, a round rod 6 is fixedly installed on the bottom of the horizontal plate 5 and is movably installed in the inside of the circular groove 4, a horizontal plate 2 15 is movably installed between the two horizontal plates 5, a round rod 6 is fixedly installed on the bottom of the horizontal plate 2 15 and is movably installed in the inside of the circular groove 4, and the bottom plate A circular groove 27 is provided on the top of the bottom plate 1, a side plate 8 is movably installed on the top of the bottom plate 1, a round rod 29 is fixedly installed on the bottom of the side plate 8 and is movably installed inside the circular groove 27, a rectangular groove 10 is provided on the inner side of the cross plate 15, a rectangular strip 11 is fixedly installed on the side of the side plate 8 and the rectangular strip 11 is movably installed inside the rectangular groove 10, a partition 13 is movably installed on the surface of the connection between the two bottom plates 1, an overflow pipe 18 is fixedly installed inside the partition 13 and extends to both ends, two clamping strips 14 are fixedly installed on the side of the partition 13, and a clamping groove 12 is provided on the inner side of the cross plate 15 and the cross plate 2 15, and the clamping strip 14 is located inside the clamping groove 12;
[0021] During installation, the staff will clamp the three bottom plates 1 in turn by clamping the slide bar 3 into the inside of the slide groove 2, and then clamp the round rod 6 at the bottom of the horizontal plate 1 5 and the horizontal plate 2 15 into the inside of the circular groove 1 4, and then clamp the round rod 2 9 at the bottom of the side plate 8 into the inside of the circular groove 2 7, and clamp the rectangular strip 11 on the side of the side plate 8 into the inside of the rectangular groove 10 on the inner side of the horizontal plate 1 5, and then clamp the two clamping strips 14 on the side of the partition 13 into the clamping groove 12 on the inner side of the horizontal plate 1 5 and the horizontal plate 2 15, and complete the installation of the sedimentation tank;
[0022] After the staff installs the three bottom plates 1 by clamping the slide groove 2 and the slide bar 3, they then install the cross plate 1 5 and the cross plate 2 15 by the cooperation of the round rod 1 6 and the round groove 1 4, and then install the side plate 8 by the cooperation of the round rod 2 9 and the round groove 2 7, and fix the cross plate 1 5 and the side plate 8 by the cooperation between the rectangular bar 11 and the rectangular groove 10, and finally install the partition 13 by clamping the clamping bar 14 inside the clamping groove 12. Compared with the traditional device, this device reduces the total construction time of the project, which can significantly save manpower and material costs during the construction process, thereby shortening the construction period, reducing equipment rental costs and employee salary expenses, and further reducing the total project cost. At the same time, it can ensure that the project proceeds as planned and reduce progress losses caused by construction delays, which is helpful to optimize resource allocation and improve overall construction efficiency, and can ensure that the tertiary sedimentation tank is put into use in time, so as to play its role in sewage treatment as soon as possible, thereby helping to reduce the emission of pollutants and improve water quality treatment effects.
[0023] Among them, an upper reinforcement block 17 is provided at the connection between the transverse plate 1 5 and the side plate 8, and a lower reinforcement block 16 is provided at the connection between the bottom plate 1, the transverse plate 1 5 and the side plate 8;
[0024] An upper reinforcement block 17 is provided at the connection between the transverse plate 5 and the side plate 8, and a lower reinforcement block 16 is provided at the connection between the bottom plate 1, the transverse plate 5 and the side plate 8. By using the lower reinforcement block 16 and the upper reinforcement block 17, the connection can be reinforced, thereby improving the stability of the device when in use.
[0025] There are two baffles 13, which are evenly distributed on the surfaces of the connection of the three bottom plates 1, and the heights of the two overflow pipes 18 decrease in sequence;
[0026] There are two baffles 13, which are evenly distributed on the surfaces of the connection of the three bottom plates 1. The heights of the two overflow pipes 18 decrease successively. This design can form a height difference, thereby achieving a better sedimentation effect.
[0027] The inner diameter of the slide groove 2 is equal to the outer diameter of the slide bar 3, and the inner diameter of the rectangular groove 10 is equal to the outer diameter of the rectangular bar 11;
[0028] The inner diameter of the slide groove 2 is set to be equal to the outer diameter of the slide bar 3, and the inner diameter of the rectangular groove 10 is set to be equal to the outer diameter of the rectangular bar 11, so that the slide bar 3 fits more tightly when it is clipped into the inside of the slide groove 2, so that the rectangular bar 11 is more stable inside the rectangular groove 10.
[0029] There are four upper reinforcement blocks 17 and four lower reinforcement blocks 16, and the four upper reinforcement blocks 17 and four lower reinforcement blocks 16 are evenly distributed at their connection points.
[0030] There are four upper reinforcement blocks 17 and four lower reinforcement blocks 16, which are evenly distributed at their connections. The use of the four lower reinforcement blocks 16 and the upper reinforcement blocks 17 can strengthen the connection between them, thereby achieving a better fixing effect.
[0031] Among them, the bottom plate 1, the horizontal plate 1 5, the horizontal plate 2 15, the side plate 8 and the partition 13 are all made of stainless steel, and the surface of the bottom plate 1 is provided with a waterproof layer;
[0032] The bottom plate 1, the horizontal plate 1 5, the horizontal plate 2 15, the side plate 8 and the partition 13 are all made of stainless steel. Stainless steel has excellent corrosion resistance and is not easily corroded by external factors such as water, air, and chemicals, thereby reducing damage and failure caused by corrosion. This enables stainless steel products to maintain good performance and appearance during long-term use. A waterproof layer is provided on the surface of the bottom plate 1, which can effectively block liquid penetration and prevent the diffusion and penetration of pollutants.
[0033] The working principle and use process of this utility model:
[0034] During installation, the staff will clamp the three bottom plates 1 in turn by clamping the sliding bar 3 into the inside of the sliding groove 2, and then clamp the round rod 6 at the bottom of the horizontal plate 1 5 and the horizontal plate 2 15 into the inside of the circular groove 4, and then clamp the round rod 2 9 at the bottom of the side plate 8 into the inside of the circular groove 2 7, and clamp the rectangular strip 11 on the side of the side plate 8 into the inside of the rectangular groove 10 on the inner side of the horizontal plate 1 5, and then clamp the two clamping strips 14 on the side of the partition 13 into the clamping groove 12 on the inner side of the horizontal plate 1 5 and the horizontal plate 2 15 to complete the installation of the sedimentation tank.
[0035] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0036] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A novel construction site three-stage sedimentation tank, comprising a bottom plate (1), characterized in that: A slide groove (2) is provided on the side of the bottom plate (1), a slide bar (3) is fixedly installed on the side of the bottom plate (1), and the slide bar (3) is clamped in the inside of the slide groove (2), the number of the bottom plates (1) is three, and the three bottom plates (1) are clamped in sequence, a circular groove (4) is provided on the top of the bottom plate (1), a horizontal plate (5) is movably installed on the top of the bottom plate (1), a round rod (6) is fixedly installed on the bottom of the horizontal plate (5) and is movably installed in the inside of the circular groove (4), a horizontal plate (15) is movably installed between the two horizontal plates (5), a round rod (6) is fixedly installed on the bottom of the horizontal plate (15) and is movably installed in the inside of the circular groove (4), a circular groove (7) is provided on the top of the bottom plate (1), and the A side plate (8) is movably mounted on the top of the bottom plate (1), a round rod (9) is fixedly mounted on the bottom of the side plate (8) and is movably mounted inside the round groove (7), a rectangular groove (10) is provided on the inner side of the first horizontal plate (5), a rectangular strip (11) is fixedly mounted on the side of the side plate (8) and the rectangular strip (11) is movably mounted inside the rectangular groove (10), a partition (13) is movably mounted on the surface of the connection between the two bottom plates (1), an overflow pipe (18) is fixedly mounted inside the partition (13) and extends to both ends, two clip strips (14) are fixedly mounted on the side of the partition (13), and a clip groove (12) is provided on the inner side of the first horizontal plate (5) and the second horizontal plate (15), and the clip strip (14) is located inside the clip groove (12).
2. The novel construction site three-stage sedimentation tank according to claim 1 is characterized in that: An upper reinforcing block (17) is provided at the connection between the transverse plate 1 (5) and the side plate (8), and a lower reinforcing block (16) is provided at the connection between the bottom plate (1), the transverse plate 1 (5) and the side plate (8).
3. The novel construction site three-stage sedimentation tank according to claim 1 is characterized in that: There are two partitions (13), and the two partitions (13) are evenly distributed on the surfaces of the connection points of the three bottom plates (1). The heights of the two overflow pipes (18) decrease in sequence.
4. The novel construction site three-stage sedimentation tank according to claim 1 is characterized in that: The inner diameter of the slide groove (2) is equal to the outer diameter of the slide bar (3), and the inner diameter of the rectangular groove (10) is equal to the outer diameter of the rectangular bar (11).
5. The novel construction site three-stage sedimentation tank according to claim 2 is characterized in that: The number of the upper reinforcement blocks (17) and the number of the lower reinforcement blocks (16) are both four, and the four upper reinforcement blocks (17) and the four lower reinforcement blocks (16) are evenly distributed at their connection points.
6. The novel construction site three-stage sedimentation tank according to claim 1 is characterized by: The bottom plate (1), the first horizontal plate (5), the second horizontal plate (15), the side plate (8) and the partition plate (13) are all made of stainless steel, and a waterproof layer is provided on the surface of the bottom plate (1).