Grating positioning device for packed tower and packed tower

By using side and top pressing beams in the filler tower to crimp the grating plate and fixing them through a detachable connection structure, the problems of inconvenient installation and low accuracy in the existing technology are solved, and high-precision positioning and stable use effects are achieved.

CN222586601UActive Publication Date: 2025-03-11SINOPEC ENGINEERING INCORPORATION +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420610865.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2025-03-11
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

In the prior art, the grating plate in the filler tower is installed above the support rod by wire or bolts, resulting in inconvenient installation, low installation accuracy, poor positioning effect, and the wire or bolts are prone to break, affecting the effectiveness of the grating plate.

Method used

The side pressing beam and the top pressing beam are respectively pressed on the upper side of the abutment portion and the docking portion of the grating plate in the packing tower, and are detachably connected to the inner wall of the packing tower through the first connecting structure to realize the positioning and fixing of the grating plate.

Benefits of technology

It improves the installation accuracy and positioning effect of the grating plate, simplifies the installation process, avoids errors and failure problems caused by wire or bolt connections, and extends the operating cycle of the packing tower.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222586601U_ABST
    Figure CN222586601U_ABST
Patent Text Reader

Abstract

The utility model provides a grating positioning device for a packed tower and the packed tower, which relate to the technical field of packed towers and are used for positioning at least two groups of grating plates, the contact position of each group of grating plates and the inner wall of the packed tower forms an abutting part, the mutual abutting position of the adjacent groups of grating plates forms an abutting part, and the grating positioning device comprises a side pressing beam and a top pressing beam, the side pressing beam and the top pressing beam are pressed on the upper sides of the abutting part and the butt joint part respectively, the outer side of the side pressing beam is connected with the inner wall of the packed tower, and the two ends of the top pressing beam are detachably connected with the inner wall of the packed tower through first connecting structures; the problems that in the prior art, a grating plate in a packed tower is installed above a supporting rod through an iron wire or a bolt, installation is inconvenient, installation precision is low, and the positioning effect is poor are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of packed towers, and more specifically relates to a grid positioning device for a packed tower and a packed tower. Background Art

[0002] A catalyst is arranged in the packed tower, and a packing pressure plate is arranged above the catalyst. The packing pressure plate is pressed on the top of the catalyst to prevent the catalyst from being driven to move upward when the reaction medium flows upward from the bottom of the packed tower, thereby destroying the designed stacking structure of the catalyst and affecting the catalytic effect of the catalyst.

[0003] In the prior art, the packing plate includes a wire mesh and a grid plate, and the wire mesh cover is arranged above the catalyst and fixed by the grid plate. When the inner diameter of the packing tower is large, for example, when the inner diameter of the packing tower exceeds 3m, the required grid plate diameter is also large. In addition, the grid plate needs to be installed in the packing tower after the catalyst is loaded, resulting in the grid plates needing to be put into the packing tower one by one and then assembled in the packing tower.

[0004] At present, the following method is generally used to prevent the grid plates from moving upward in the packed tower: support rods are installed on the inner wall of the packed tower, and the grid plates are installed on the top of the support rods by wires or bolts. The above installation method has the following problems: multiple grid plates need to be connected to the support rods one by one by construction workers through wires or bolts, which increases the difficulty of installing the grid plates and is time-consuming and labor-intensive; in addition, when the wires or bolts are connected to the grid plates, the grid plates will be displaced under the traction of the wires or bolts to produce installation errors, affecting the installation accuracy of the grid plates; and the wires or bolts are prone to breakage and other failures after long-term use, which leads to the failure of the grid plates. After the grid plates fail, they cannot effectively limit the catalyst, and the catalyst may be carried upward by the reaction medium, shortening the operation cycle of the packed tower. Utility Model Content

[0005] The utility model aims to solve the problems in the prior art that the grid plates in the packing tower are installed above the support rods by wires or bolts, which result in inconvenient installation, low installation accuracy and poor positioning effect.

[0006] In order to achieve the above-mentioned object, the utility model provides a grid positioning device for a packed tower, which is used to position at least two groups of grid plates, wherein the positions where the grid plates of each group contact the inner wall of the packed tower form abutment portions, and the positions where the grid plates of adjacent groups butt against each other form butt joint portions, comprising:

[0007] A side pressure beam and a top pressure beam, wherein the side pressure beam and the top pressure beam are respectively pressed on the upper sides of the abutting portion and the docking portion, the outer side of the side pressure beam is connected to the inner wall of the packing tower, and the two ends of the top pressure beam are detachably connected to the inner wall of the packing tower through a first connecting structure.

[0008] Optionally, the side pressure beam is annular, and the outer periphery of the side pressure beam is connected to the inner wall of the packing tower.

[0009] Optionally, one end of the first connecting structure is connected to the inner wall of the packing tower, and the end of the top pressure beam is detachably connected to the other end of the first connecting structure. When the two ends of the top pressure beam are respectively connected to one of the first connecting structures, at least part of the top pressure beam is located inside the side pressure beam.

[0010] Optionally, the top pressure beam includes a pressure plate and a connecting plate arranged on a side of the pressure plate away from the grid plate, and the connecting plate is connected to the pressure plate to form an inverted T-shaped structure.

[0011] Optionally, the first connecting structure includes a first L-shaped plate and a second L-shaped plate, the first L-shaped plate and the second L-shaped plate are arranged back to back, the connecting plate is detachably connected to the vertical end of the first L-shaped plate by a bolt fastening assembly, and the plane ends of the first L-shaped plate and the second L-shaped plate are respectively threadedly connected with clamping bolts, and the clamping bolts are used to clamp the top pressure beam.

[0012] Optionally, the length of the second L-shaped plate is smaller than that of the first L-shaped plate, and a avoidance zone is formed at one end of the second L-shaped plate close to the interior of the packed tower, the avoidance zone being used to avoid the connecting plate.

[0013] Optionally, the connecting plate is provided with a first connecting hole, and the vertical end of the first L-shaped plate is provided with a second connecting hole, and the bolt tightening assembly connects the connecting plate to the first L-shaped plate through the first connecting hole and the second connecting hole, the first connecting hole is a long waist hole extending along the length direction of the top pressure beam, and the second connecting hole is a long waist hole extending vertically.

[0014] Optionally, the top pressure beam further includes a reinforcing plate, and the reinforcing plate is arranged on a side of the pressure plate away from the grid plate or on a side edge of the pressure plate.

[0015] Optionally, it further includes a supporting beam, which is arranged on the lower side of the docking portion, and both ends of the supporting beam are detachably connected to the inner wall of the packing tower through a second connecting structure.

[0016] The utility model also provides a packed tower, comprising the above-mentioned grid positioning device for the packed tower.

[0017] The utility model provides a grid positioning device for a packing tower and a packing tower, which have the beneficial effects that: the grid positioning device for the packing tower adopts side pressure beams and top pressure beams to press the upper sides of the abutting parts and the docking parts of the grid plates in the packing tower respectively, so as to realize the positioning of the grid plates and prevent the grid plates from moving upwards; the side pressure beams are connected to the inner wall of the packing tower, the grid plates can be inserted and installed under the side pressure beams, and the two ends of the top pressure beams are detachably connected to the inner wall of the packing tower through a first connecting structure; after the grid plates are placed, it is only necessary to connect the top pressure beams to the first connecting structure; the operation is convenient, the installation precision is high, and the installation is reliable; the positioning effect of the grid plates is stable, the service life is long, and the operation cycle of the packing tower can be extended.

[0018] Other features and advantages of the present invention will be described in detail in the subsequent specific implementation section. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The above and other objects, features and advantages of the present invention will become more apparent through a more detailed description of exemplary embodiments of the present invention in conjunction with the accompanying drawings, wherein the same reference numerals generally represent the same components in the exemplary embodiments of the present invention.

[0020] Figure 1 A schematic diagram of the positioning structure of a grid plate by a grid positioning device for a packed tower according to the first embodiment of the utility model is shown.

[0021] Figure 2 Shows Figure 1 Schematic diagram of the cross-sectional structure in the A direction.

[0022] Figure 3 The schematic diagram of the structure of the grid plate in the packed tower according to the first embodiment of the utility model is shown.

[0023] Figure 4 A structural schematic diagram of a grid positioning device for a packed tower according to Embodiment 1 of the utility model is shown.

[0024] Figure 5 Shows Figure 4 Schematic diagram of the cross-sectional structure in the B direction.

[0025] Figure 6 A schematic structural diagram of a top pressure beam of a grid positioning device for a packed tower according to the first embodiment of the utility model is shown.

[0026] Figure 7 A structural schematic diagram of a grid positioning device for a packed tower according to a second embodiment of the utility model is shown.

[0027] Figure 8 Shows Figure 7Schematic diagram of the top view structure.

[0028] Description of reference numerals:

[0029] 1. Grid plate; 2. Abutment portion; 3. Docking portion; 4. Side pressure beam; 5. Top pressure beam; 6. First connection structure; 7. Pressure plate; 8. Connection plate; 9. First L-shaped plate; 10. Second L-shaped plate; 11. Holding bolt; 12. Bolt fastening assembly; 13. Avoidance area; 14. First connection hole; 15. Second connection hole; 16. Reinforcement plate; 17. Support beam; 18. Inner wall of packing tower; 19. Second connection structure. DETAILED DESCRIPTION

[0030] The preferred embodiments of the present invention will be described in more detail below. Although the preferred embodiments of the present invention are described below, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to make the present invention more thorough and complete, and to fully convey the scope of the present invention to those skilled in the art.

[0031] Embodiment 1

[0032] like Figures 1 to 6 As shown, the utility model provides a grid positioning device for a packed tower, which is used to position at least two groups of grid plates 1, where each group of grid plates 1 contacts the inner wall 18 of the packed tower to form an abutment portion 2, and where adjacent groups of grid plates 1 butt against each other to form a butt joint portion 3, including:

[0033] The side pressure beam 4 and the top pressure beam 5 are respectively pressed on the upper sides of the abutting part 2 and the docking part 3, the outer side of the side pressure beam 4 is connected to the inner wall 18 of the packing tower, and the two ends of the top pressure beam 5 are detachably connected to the inner wall 18 of the packing tower through the first connecting structure 6.

[0034] Specifically, in order to solve the problem that the grating plate 1 in the packing tower is installed above the support rod by iron wire or bolts in the prior art, which is inconvenient to install, has low installation accuracy and poor positioning effect; the grating positioning device for the packing tower provided by the utility model adopts side pressure beams 4 and top pressure beams 5 to be pressed on the upper sides of the abutment part 2 and the docking part 3 of the grating plate 1 in the packing tower, respectively, to realize the positioning of the grating plate 1 and prevent the grating plate 1 from moving upward, the side pressure beams 4 are connected to the inner wall 18 of the packing tower, the grating plate 1 can be inserted and installed under the side pressure beams 4, and the two ends of the top pressure beams 5 are detachably connected to the inner wall 18 of the packing tower through the first connecting structure 6. After the grating plate 1 is placed, it is only necessary to connect the top pressure beam 5 to the first connecting structure 6. It is easy to operate, has high installation accuracy and reliable installation, has a stable positioning effect on the grating plate 1, has a long service life, and can extend the operation cycle of the packing tower.

[0035] In order to prevent the catalyst from being driven upward when the reaction medium flows upward from the bottom of the packed tower, at least two groups of grid plates 1 are arranged in the packed tower. In order to facilitate the placement of the grid plates 1 in the packed tower, at least two groups of grid plates 1 are spliced ​​to install them in the packed tower. The edges of the at least two groups of grid plates 1 close to the inner wall 18 of the packed tower are arranged to form an arc shape that matches the inner wall 18 of the packed tower. Each group of grid plates 1 forms a butt joint 2 near its arc position. The edges of the two adjacent groups of grid plates 1 that are in contact with each other are arranged to be flush. Each group of grid plates 1 forms a butt joint 3 near its flush position. Each group of grid plates 1 includes several grid plates 1, which can be arranged as needed; such as Figure 3 As shown, in this embodiment, three groups of grid plates 1 are arranged in the packed tower, and each group of grid plates 1 includes six grid plates 1 .

[0036] Optionally, the side pressure beam 4 is annular, and the outer periphery of the side pressure beam 4 is connected to the inner wall 18 of the packed tower.

[0037] Specifically, the side pressure beam 4 adopts an annular structure and is pressed on the upper side of the abutment portion 2 of the grid plate 1 close to the inner wall 18 of the packing tower, thereby playing a good positioning role for the grid plate 1. The cross-section of the side pressure beam 4 can be strip-shaped or L-shaped, and its outer periphery can be welded to the inner wall 18 of the packing tower, or it can be fixed to the inner wall 18 of the packing tower at intervals by welding a pad to form a fixed connection with the packing tower. When installing the grid plate 1, the grid plate 1 can be inserted into the lower side of the side pressure beam 4.

[0038] Optionally, one end of the first connecting structure 6 is connected to the inner wall 18 of the packing tower, and the end of the top pressure beam 5 is detachably connected to the other end of the first connecting structure 6. When the two ends of the top pressure beam 5 are respectively connected to a first connecting structure 6, at least part of the top pressure beam 5 is located inside the side pressure beam 4.

[0039] Specifically, one end of the first connecting structure 6 can be fixed on the inner wall 18 of the packing tower to form a fixed connection with the packing tower. After the grid plate 1 is placed, the top pressure beam 5 is installed on the other end of the first connecting structure 6 to achieve the fixation of the top pressure beam 5. The grid plate 1 is crimped and positioned using the top pressure beam 5. One top pressure beam 5 can press the upper side of the docking portion 3 of two adjacent groups of grid plates 1 inside the packing tower. The length of the top pressure beam 5 is smaller than the inner circumferential diameter of the side pressure beam 4, so that when the top pressure beam 5 is installed on the first connecting structure 6, the top pressure beam 5 is inside the side pressure beam 4, and is pressed on the upper side of the grid plate 1 by the side pressure beam 4 and the top pressure beam 5.

[0040] Optionally, the top pressure beam 5 includes a pressure plate 7 and a connecting plate 8 arranged on a side of the pressure plate 7 away from the grid plate 1 , and the connecting plate 8 is connected to the pressure plate 7 to form an inverted T-shaped structure.

[0041] Specifically, when the top pressure beam 5 is pressed onto the upper side of the grid plate 1 , the pressure plate 7 is arranged horizontally, and the connecting plate 8 is arranged vertically, and they are connected in one piece to form an inverted T-shaped structure. The connecting plate 8 can be used to realize a detachable connection between the top pressure beam 5 and the first connecting structure 6 .

[0042] Optionally, the first connecting structure 6 includes a first L-shaped plate 9 and a second L-shaped plate 10, and the first L-shaped plate 9 and the second L-shaped plate 10 are arranged back to back. The connecting plate 8 is detachably connected to the vertical end of the first L-shaped plate 9 by a bolt fastening assembly 12, and the plane ends of the first L-shaped plate 9 and the second L-shaped plate 10 are respectively threadedly connected with clamping bolts 11, and the clamping bolts 11 are used to clamp the top pressure beam 5.

[0043] Specifically, one end of the first L-shaped plate 9 and the second L-shaped plate 10 of the first connecting structure 6 are connected to the inner wall 18 of the packing tower by welding, and the connecting plate 8 and the vertical end of the first L-shaped plate 9 are detachably connected by a bolt fastening assembly 12. The clamping bolts 11 on the plane ends of the first L-shaped plate 9 and the second L-shaped plate 10 can be used to extend the pressure plate 7 downward to clamp the top pressure beam 5, thereby ensuring the stability of the pressure plate 7 crimped to the grid plate 1.

[0044] Optionally, the length of the second L-shaped plate 10 is smaller than that of the first L-shaped plate 9 , and an escape zone 13 is formed at one end of the second L-shaped plate 10 close to the interior of the packed tower, and the escape zone 13 is used to escape the connecting plate 8 .

[0045] Specifically, the second L-shaped plate 10 is shorter than the first L-shaped plate 9, and the short part forms an avoidance area 13 at one end of the second L-shaped plate 10 near the packing tower, that is, there is a vertical end of the first L-shaped plate 9 on one side of this position, but there is no vertical end of the second L-shaped plate 10 on the other side. In this way, when the top pressure beam 5 is installed, the connecting plate 8 on the top pressure beam 5 can pass through the avoidance area 13 until the connecting plate 8 contacts and connects with the vertical end of the first L-shaped plate 9 at this position, thereby facilitating the installation of the top pressure beam 5 on the first connecting structure 6.

[0046] Optionally, the connecting plate 8 is provided with a first connecting hole 14, and the vertical end of the first L-shaped plate 9 is provided with a second connecting hole 15. The bolt tightening assembly connects the connecting plate 8 to the first L-shaped plate 9 through the first connecting hole 14 and the second connecting hole 15. The first connecting hole 14 is a long waist hole extending along the length direction of the top pressure beam 5, and the second connecting hole 15 is a long waist hole extending vertically.

[0047] Specifically, the first connecting hole 14 is a long waist hole extending in the horizontal direction, so as to allow the top pressure beam 5 and the first connecting structure 6 to move relative to each other when the packing tower expands or contracts, thereby avoiding stress at the connection between the two; the second connecting hole 15 is a long waist hole extending in the vertical direction, so that the top pressure beam 5 can be displaced in the vertical direction relative to the first connecting structure 6, so as to be tightened on the pressure plate 7 of the top pressure beam 5 by the tightening bolts 11 on the planar ends of the first L-shaped plate 9 and the second L-shaped plate 10, and the pressure plate 7 is effectively crimped on the grid plate 1.

[0048] Optionally, the top pressure beam 5 further includes a reinforcing plate 16 , and the reinforcing plate 16 is arranged on a side of the pressure plate 7 away from the grid plate 1 .

[0049] Specifically, the cross section of the position where the reinforcing plate 16 is connected to the pressure plate 7 forms an inverted T shape, and the reinforcing plate 16 increases the strength of the top pressure beam 5, thereby improving its service life and the positioning effect on the grid plate 1.

[0050] In this embodiment, if Figure 6 As shown, the reinforcing plate 16 and the connecting plate 8 are an integrated structure.

[0051] Optionally, a supporting beam 17 is further included. The supporting beam 17 is arranged at the lower side of the docking portion 3 , and both ends of the supporting beam 17 are detachably connected to the inner wall 18 of the packing tower through a second connecting structure 19 .

[0052] Specifically, the supporting beam 17 is detachably connected to the second connecting structure 19, and the second connecting structure 19 is fixed to the inner wall 18 of the packing tower. Each supporting beam 17 is arranged under a top pressure beam 5 to support and position the grating plate 1. The cooperation between the top pressure beam 5 and the supporting beam 17 can vertically fix the grating plate 1 to prevent the grating plate 1 from moving upward and downward; the supporting beam 17 can be a support rod or an angle steel, etc., and the second connecting structure 19 can be a welded structure or a detachable connecting structure, as long as it can be fixed on the inner wall 18 of the packing tower. For example, each second connecting structure 19 can include two welding plates, and the two welding plates are welded to the inner side of the inner wall 18 of the packing tower at intervals. The supporting beam 17 can be connected to the welding plate by screwing or riveting.

[0053] Embodiment 2

[0054] like Figure 7 and Figure 8 As shown, the difference between this embodiment and the first embodiment is that:

[0055] In this embodiment, the reinforcing plate 16 is arranged on the side of the pressing plate 7 .

[0056] Specifically, the reinforcing plate 16 can also be set on the side of the pressing plate 7, and the reinforcing plate 16 can be set on one side or both sides. The reinforcing plate 16 extends along the length direction of the pressing plate 7 and can be formed by bending the steel plate to reduce the difficulty of processing.

[0057] In this embodiment, reinforcing plates 16 are provided on both sides of the pressing plate 7. The reinforcing plates 16 are connected to the pressing plate 7 to form a U-shaped structure to ensure its reinforcing effect.

[0058] Embodiment 3

[0059] The utility model also provides a packed tower, comprising the above-mentioned grid positioning device for the packed tower.

[0060] Specifically, the above-mentioned grid positioning device for the packed tower is installed on the inner wall 18 of the packed tower, and can respectively press and position the abutting part 2 and the docking part 3 of the grid plate 1 through the side pressure beam 4 and the top pressure beam 5, effectively preventing the grid plate 1 and the catalyst thereunder from moving upward with the upward movement of the reaction medium, reducing the difficulty of installing the grid plate 1, saving time and effort; the top pressure beam 5 and the side pressure beam 4 are pressed on the grid plate 1, and there is no need to be connected to the grid plate 1, avoiding the installation error of the grid plate 1 caused by connecting with wire or bolts in the prior art, and improving the installation accuracy; the top pressure beam 5 and the side pressure beam 4 have high structural strength and long service life, which extend the operation cycle of the packed tower.

[0061] The various embodiments of the utility model have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes are obvious to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments.

Claims

1. A grid positioning device for a packed tower, used for positioning at least two groups of grid plates, wherein the positions where the grid plates of each group contact the inner wall of the packed tower form abutment portions, and the positions where the grid plates of adjacent groups butt against each other form butt joint portions, characterized in that: include: A side pressure beam and a top pressure beam, wherein the side pressure beam and the top pressure beam are respectively pressed on the upper sides of the abutting portion and the docking portion, the outer side of the side pressure beam is connected to the inner wall of the packing tower, and the two ends of the top pressure beam are detachably connected to the inner wall of the packing tower through a first connecting structure.

2. The grid positioning device for a packed tower according to claim 1, characterized in that: The side pressure beam is annular, and the outer periphery of the side pressure beam is connected to the inner wall of the packing tower.

3. The grid positioning device for a packed tower according to claim 1, characterized in that: One end of the first connecting structure is connected to the inner wall of the packing tower, and the end of the top pressure beam is detachably connected to the other end of the first connecting structure. When the two ends of the top pressure beam are respectively connected to one of the first connecting structures, at least part of the top pressure beam is located inside the side pressure beam.

4. The grid positioning device for a packed tower according to claim 1, characterized in that: The top pressure beam comprises a pressure plate and a connecting plate arranged on a side of the pressure plate away from the grid plate, and the connecting plate is connected with the pressure plate to form an inverted T-shaped structure.

5. The grid positioning device for a packed tower according to claim 4, characterized in that: The first connecting structure includes a first L-shaped plate and a second L-shaped plate, the first L-shaped plate and the second L-shaped plate are arranged back to back, the connecting plate is detachably connected to the vertical end of the first L-shaped plate by a bolt fastening assembly, and the plane ends of the first L-shaped plate and the second L-shaped plate are respectively threadedly connected with clamping bolts, and the clamping bolts are used to clamp the top pressure beam.

6. The grid positioning device for a packed tower according to claim 5, characterized in that: The length of the second L-shaped plate is smaller than that of the first L-shaped plate. An escape zone is formed at one end of the second L-shaped plate close to the interior of the packed tower, and the escape zone is used to escape the connecting plate.

7. The grid positioning device for a packed tower according to claim 5, characterized in that: The connecting plate is provided with a first connecting hole, and the vertical end of the first L-shaped plate is provided with a second connecting hole. The bolt tightening assembly connects the connecting plate with the first L-shaped plate through the first connecting hole and the second connecting hole. The first connecting hole is a long waist hole extending along the length direction of the top pressure beam, and the second connecting hole is a long waist hole extending vertically.

8. The grid positioning device for a packed tower according to claim 4, characterized in that: The top pressure beam also includes a reinforcing plate, which is arranged on a side of the pressure plate away from the grid plate or on a side edge of the pressure plate.

9. The grid positioning device for a packed tower according to claim 1, characterized in that: It also includes a supporting beam, which is arranged on the lower side of the docking portion, and both ends of the supporting beam are detachably connected to the inner wall of the packing tower through a second connecting structure.

10. A packed tower, characterized in that: It comprises a grid positioning device for a packed tower according to any one of claims 1-9.