Super high-rise building hanging basket suspension mechanism
By designing a suspended basket mechanism of super high-rise buildings in construction, using the fixing method of through-wall bolt eyes and pre-embedded tie rings, combined with I-shaped steel structure and multi-layer safety devices, the problem of inability to install suspended baskets in a timely manner in the prior art is solved, and the construction period is shortened and safety is improved.
Patent Information
- Application Number
- CN202421445222.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2034-06-24
AI Technical Summary
The prior art cannot install the hanging basket in a timely manner during the construction of high-rise buildings, and when the main body is still under construction in the next stage after the structure is accepted in segments, resulting in an extension of the construction period.
A super-high-rise building hanging basket suspension mechanism is designed. By leaving the wall-through bolt eye and embedded knot ring on the wall, the wall-through fixing bolts and tied wire ropes are used to fix the suspension mechanism, and through the I-shaped steel main beam and legs, combined with the first and second steel rope hanging rings, pulleys and fall-proof devices, the effective support and use of the hanging basket wire rope is achieved.
This technology allows the main body to be installed immediately after the structure is accepted in segments, significantly shortening the construction period and improving the safety of the hanging basket through multi-layer safety devices.
Smart Images

Figure CN222667573U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction tools, in particular to a hanging basket suspension mechanism for a super high-rise building. Background Art
[0002] The hanging basket is a construction tool for high-altitude operations in construction projects, used for curtain wall installation and exterior wall cleaning. The hanging basket is a new type of high-altitude operation equipment that can replace traditional scaffolding, reduce labor intensity, improve work efficiency, and can be reused. The use of construction hanging baskets has gradually become a trend and has been widely recognized in high-altitude operations such as exterior wall construction, curtain wall installation, insulation construction, and exterior wall maintenance and cleaning of high-rise and multi-story buildings. It can also be used for operations in large tanks, bridges, dams and other projects.
[0003] After searching, the patent number "CN220747605U" mentioned in the text that "the utility model discloses a hanging basket and its hanging mechanism, the hanging mechanism includes a hanging mechanism body, and also includes: a hanging arm and a driving mechanism; the first part of the hanging arm can be slid along the first direction and is arranged on the hanging beam of the hanging mechanism body, and the second part extends out of the suspended end of the hanging beam and is used to hang the hanging platform, the first direction is parallel to the length direction of the hanging beam; the driving mechanism is used to drive the first part of the hanging arm to slide relative to the hanging beam along the first direction. In this scheme, the driving mechanism drives the first part of the hanging arm to slide back and forth along the first direction relative to the hanging beam, so that the second part of the hanging arm can slide along the suspended side of the hanging beam. By sliding back and forth in the first direction, the suspension component of the hanging basket suspension mechanism can have a telescopic function, so that the distance between the suspension platform and the outer wall can be adjusted, solving the problem that the hanging basket cannot be moved downward when encountering a building with a cantilever structure. When in use, the driving mechanism can be used to make the suspension component of the hanging basket suspension mechanism have a telescopic function, so that the distance between the suspension platform and the outer wall can be adjusted, solving the problem that the hanging basket cannot be moved downward when encountering a building with a cantilever structure. However, this utility model cannot be adapted to high-rise buildings that are still under construction, and cannot install the hanging basket after the structure acceptance of the previous stage while the main body of the next stage is still under construction, and cannot shorten the construction period.
[0004] Therefore, we provide a super high-rise building hanging basket suspension mechanism to solve the above problems. Utility Model Content
[0005] The utility model aims to provide a hanging basket suspension mechanism for a super high-rise building, so as to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a hanging mechanism for a hanging basket of a super high-rise building, comprising a wall, a surface of the wall is provided with a plurality of through-wall bolt holes, a support steel plate is installed on one side of the wall, a steel backing plate is installed on the other side of the wall, through-wall fixing bolts penetrate the inner sides of the through-wall bolt holes, the support steel plate and the steel backing plate are fixed to the two sides of the wall by the through-wall fixing bolts, and the other side of the support steel plate is fixedly connected with a hanging mechanism;
[0007] The suspension mechanism includes an I-beam main beam and an I-beam support leg. The other side of the support steel plate is fixedly connected to the I-beam main beam, the bottom end of the I-beam main beam is fixedly connected to the I-beam support leg, and a positioning hole is opened on the inner side of the I-beam main beam.
[0008] Preferably, in a hanging basket suspension mechanism for a super high-rise building, the number of through-wall bolt holes provided on the wall surface is ≥8, the number of positioning holes provided on the I-beam main beam is ≤4, and the spacing is ≥10 cm.
[0009] Preferably, in a hanging mechanism for a hanging basket of a super high-rise building, a first steel rope eye is provided on the outer side of the positioning hole, a pre-buried tie ring is provided above the support steel plate, and the first steel rope eye and the pre-buried tie ring are connected by a tie wire rope.
[0010] Preferably, in a hanging basket suspension mechanism for a super high-rise building, a second steel rope eye is provided on one side of the first steel rope eye, a pin shaft penetrates the bottom end of the second steel rope eye, a pulley is rotatably connected to the outer side of the pin shaft, and a hanging basket wire rope is provided on the outer side of the pulley.
[0011] Preferably, a hanging basket suspension mechanism for a super high-rise building is provided, wherein a hoist is provided at one end of the hanging basket wire rope, a working platform is fixedly connected to the bottom end of the hoist, a fall arrester is provided at the other end of the hanging basket wire rope, and a limiting device is installed at one end of the hanging basket wire rope close to the fall arrester.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] 1. Through the through-wall bolt holes and through-wall fixing bolts, the support steel plate and the steel pad can be firmly fixed on the wall, and then the suspension mechanism can be fixed. Through the design of the first steel rope lifting ring and the embedded tie ring, the tie wire rope can further support the suspension mechanism, greatly improving its safety. After the structural acceptance in sections, the next stage of the main body is still under construction, and the hanging basket construction can be installed immediately, which greatly shortens the construction period;
[0014] 2. The steel wire rope of the hanging basket can be passed through the second steel rope eye, pin shaft and pulley to reduce wear. The steel wire rope of the hanging basket passes through the pulley and is connected to the fall arrester to form a closed loop. The working platform can be raised and lowered by the hoist. The limit device can prevent the steel wire rope of the hanging basket from being reeled in beyond the specified range to prevent danger. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the overall appearance structure of the utility model;
[0016] Figure 2 This is a schematic diagram of the wall cross-section structure of the utility model;
[0017] Figure 3 This is a schematic diagram of the second steel rope lifting ring structure of the utility model;
[0018] Figure 4 It is a schematic diagram of the overall front view structure of the utility model;
[0019] Figure 5 It is a schematic diagram of the enlarged structure of point A of the utility model;
[0020] Figure 6 It is an enlarged structural diagram of B of the utility model;
[0021] Figure 7 It is a schematic diagram of the enlarged structure of point C of the utility model.
[0022] Numbers in the figure: 1. Wall; 2. Through-wall bolt eye; 3. Support steel plate; 4. Steel pad; 5. Through-wall fixing bolt; 6. Suspension mechanism; 601. I-beam main beam; 602. I-beam support leg; 603. Positioning hole; 7. First steel rope lifting eye; 8. Embedded tie ring; 9. Tie wire rope; 10. Second steel rope lifting eye; 11. Pin shaft; 12. Pulley; 13. Hanging basket wire rope; 14. Hoist; 15. Working platform; 16. Fall arrester; 17. Limit device. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] The utility model embodiment provides a super high-rise building hanging basket suspension mechanism, such as Figure 1-7As shown, it includes a wall surface 1, a plurality of through-wall bolt holes 2 are opened on the surface of the wall surface 1, a support steel plate 3 is installed on one side of the wall surface 1, a steel backing plate 4 is installed on the other side of the wall surface 1, through-wall fixing bolts 5 penetrate the inner side of the through-wall bolt holes 2, the support steel plate 3 and the steel backing plate 4 are fixed to the two sides of the wall surface 1 by the through-wall fixing bolts 5, and the other side of the support steel plate 3 is fixedly connected with a hanging mechanism 6;
[0025] The suspension mechanism 6 includes an I-beam main beam 601 and an I-beam support leg 602 . The other side of the support steel plate 3 is fixedly connected to the I-beam main beam 601 . The bottom end of the I-beam main beam 601 is fixedly connected to the I-beam support leg 602 . A positioning hole 603 is opened on the inner side of the I-beam main beam 601 .
[0026] Furthermore, the number of through-wall bolt holes 2 opened on the surface of the wall 1 is ≥8, the number of positioning holes 603 opened on the I-beam main beam 601 is ≤4, and the spacing is ≥10cm, the surface of the wall 1 opens 4 through-wall bolt holes 2 as a group, and at least two groups are set for fixing the working platform 15, and the positioning holes 603 limit the number of holes and the spacing to prevent its physical properties from deteriorating.
[0027] Furthermore, a first steel rope eye 7 is provided on the outer side of the positioning hole 603, and a pre-buried tie ring 8 is provided above the support steel plate 3. The first steel rope eye 7 and the pre-buried tie ring 8 are connected by a tie wire rope 9. The pre-buried tie ring 8 is connected to the first steel rope eye 7 by the tie wire rope 9, which can give an upward force to the I-beam main beam 601 to better support the working platform 15.
[0028] Furthermore, a second steel rope eye 10 is provided on one side of the first steel rope eye 7, a pin shaft 11 passes through the bottom end of the second steel rope eye 10, a pulley 12 is rotatably connected to the outer side of the pin shaft 11, a hanging basket wire rope 13 is provided on the outer side of the pulley 12, the second steel rope eye 10 can fix the pin shaft 11, the pin shaft 11 can fix the pulley 12, and the pulley 12 can allow the hanging basket wire rope 13 to slide thereon.
[0029] Furthermore, a hoist 14 is provided at one end of the hanging basket wire rope 13, and a working platform 15 is fixedly connected to the bottom end of the hoist 14. A fall arrester 16 is provided at the other end of the hanging basket wire rope 13. A limiting device 17 is installed at one end of the hanging basket wire rope 13 close to the fall arrester 16. The working platform 15 can be raised by tightening the hanging basket wire rope 13 by the hoist 14. The hanging basket wire rope 13 is fixed by the fall arrester 16 to improve safety. The limiting device 17 can prevent the hanging basket wire rope 13 from being wound beyond the prescribed range to prevent danger.
[0030] Working principle: first, a super high-rise building hanging basket suspension mechanism is moved to the working position. When in use, the first step is to reserve through-wall bolt eyes 2 and pre-embed tie rings 8 on the pre-layered floor wall 1 during the main construction stage of the high-rise building. The second step is to weld the I-beam main beam 601 and the I-beam support leg 602 to the support steel plate 3, and install the first steel rope eye 7 and the second steel rope eye 10 through the positioning hole 603. The third step is to install the support steel plate 3 and the steel pad 4 at the reserved through-wall bolt eyes 2 through the through-wall fixing bolts 5. The fourth step is to connect and tighten the first steel rope eye 7 and the pre-embedded tie ring 8 through the tie wire rope 9. The fifth step is to pass the hanging basket steel wire rope 13 through the pulley 12, fix it through the anti-fall device 16, install the limit device 17 at the appropriate position of the hanging basket steel wire rope 13, and then lift the working platform 15 through the hoist 14. This completes the use process of a super high-rise building hanging basket suspension mechanism.
[0031] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A hanging basket suspension mechanism for a super high-rise building, comprising a wall surface (1), characterized in that: The surface of the wall surface (1) is provided with a plurality of through-wall bolt holes (2); a support steel plate (3) is installed on one side of the wall surface (1); a steel backing plate (4) is installed on the other side of the wall surface (1); through-wall fixing bolts (5) penetrate the inner sides of the through-wall bolt holes (2); the support steel plate (3) and the steel backing plate (4) are fixed to the two sides of the wall surface (1) by means of the through-wall fixing bolts (5); and a hanging mechanism (6) is fixedly connected to the other side of the support steel plate (3); The suspension mechanism (6) comprises an I-beam main beam (601) and an I-beam support leg (602); the other side of the support steel plate (3) is fixedly connected to the I-beam main beam (601); the bottom end of the I-beam main beam (601) is fixedly connected to the I-beam support leg (602); and a positioning hole (603) is provided on the inner side of the I-beam main beam (601).
2. A super high-rise building hanging basket suspension mechanism according to claim 1, characterized in that: The wall surface (1) is provided with ≥8 through-wall bolt holes (2), and the I-beam main beam (601) is provided with ≤4 positioning holes (603) with a spacing of ≥10 cm.
3. A super high-rise building hanging basket suspension mechanism according to claim 1, characterized in that: A first steel rope eye (7) is arranged outside the positioning hole (603), a pre-buried tie ring (8) is arranged above the support steel plate (3), and the first steel rope eye (7) and the pre-buried tie ring (8) are connected via a tie wire rope (9).
4. A super high-rise building hanging basket suspension mechanism according to claim 3, characterized in that: A second steel rope eye (10) is provided on one side of the first steel rope eye (7), a pin shaft (11) passes through the bottom end of the second steel rope eye (10), a pulley (12) is rotatably connected to the outer side of the pin shaft (11), and a hanging basket steel wire rope (13) is provided on the outer side of the pulley (12).
5. A super high-rise building hanging basket suspension mechanism according to claim 4, characterized in that: A hoist (14) is provided at one end of the hanging basket steel wire rope (13), a working platform (15) is fixedly connected to the bottom end of the hoist (14), a fall arrester (16) is provided at the other end of the hanging basket steel wire rope (13), and a limit device (17) is installed at one end of the hanging basket steel wire rope (13) close to the fall arrester (16).
Citation Information
Patent Citations
Hanging basket and hanging mechanism thereof
CN220747605U