Auxiliary device for rapid and stable propelling of anchor rod installation
By designing an anchor rod installation auxiliary device including main rod, sliding seat, connecting rod assembly and branch pipe, the problems of low construction efficiency and complex installation angle in traditional anchor rod installation methods are solved, and rapid and stable propulsion and high-precision installation of anchor rod installation are achieved.
Patent Information
- Application Number
- CN202421585675.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-07-05
AI Technical Summary
The traditional anchor rod installation methods have problems such as high construction strength, low construction efficiency, complex installation angle and difficult to monitor, especially under complex soil conditions.
An auxiliary device for fast and stable propulsion of anchor rod installation is designed. Through the combination of main rod, sliding seat, connecting rod assembly and branch pipe, multiple anchor rods can be promoted at one time, and friction losses are reduced through buffer blocks.
It realizes rapid and stable propulsion of anchor rod installation, improves construction efficiency and installation accuracy, and is suitable for construction under different soil conditions.
Smart Images

Figure CN222686708U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of anchor rod installation, in particular to an auxiliary device for fast and stable advancement of anchor rod installation. Background Art
[0002] With the rapid development of hydropower projects and road projects, the construction speed is getting faster and faster, and the quality requirements are getting higher and higher. Therefore, the requirements for anchor bolt installation are also getting higher and higher. Traditional anchor bolt installation uses manual advancement, but there are the following problems in actual construction:
[0003] 1. The anchor body is large in mass, the number of anchor rods installed is large, the construction intensity is high, and the construction workers are prone to fatigue, resulting in reduced construction efficiency.
[0004] 2. The soil conditions during construction are complex, and it is difficult to predict the internal conditions of the borehole. It is impossible to monitor the occurrence of hole collapse in a timely manner, which makes manual advancement of anchor installation difficult and the installation speed slow.
[0005] 3. The installation angle in actual anchor construction is complex, resulting in installation angle deviation, which requires manual hand support for stability, affecting installation efficiency and accuracy.
[0006] The patent application number is "202021440000.0", "A cavern advance anchor impact transmission device", which uses a hand-held pneumatic drill to impact the anchor into the cave wall. However, the device can only drill one anchor at a time, which still cannot really improve efficiency. Summary of the invention
[0007] The technical problem to be solved by the utility model is to provide an auxiliary device for fast and stable advancement of anchor rod installation, which can carry out advancement operations of multiple anchor rods at one time.
[0008] In order to solve the above technical problems, the technical solution adopted by the utility model is:
[0009] An auxiliary device for fast and stable advancement of anchor rod installation comprises a main rod, a fixed seat and a sliding seat are arranged at the front and rear of the main rod, the fixed seat is fixed on the main rod, and the sliding seat is slidably set on the main rod and locked; a plurality of first connecting rods are hinged on each fixed seat, and a plurality of second connecting rods are hinged on each sliding seat, the other end of each first connecting rod is hinged to the corresponding branch pipe, and the other end of each second connecting rod is hinged to the corresponding first connecting rod; a through hole matching the drill rod is arranged on one side of the main rod.
[0010] The number of branch pipes is two, three, four or five.
[0011] The main rod is provided with a plurality of adjustment holes along the circumferential direction, and the corresponding sliding seat is provided with threaded holes along the radial direction, and the bolts are screwed into the threaded holes and inserted into the corresponding adjustment holes.
[0012] Buffer blocks are arranged in the through holes and the branch pipes.
[0013] The utility model provides an auxiliary device for fast and stable advancement of anchor installation, which has the following technical effects:
[0014] 1) By setting a main rod with multiple branch pipes, insert the drill rod into the main rod for advancement, insert the anchor rod into the branch pipe, and the anchor rod is directly opposite to the drill hole. In this way, multiple anchor rods can be advanced at one time to improve work efficiency.
[0015] 2) By using the connecting rod assembly, the spacing between multiple branch pipes can be adjusted to ensure that when drilling holes at different spacings in different projects, each branch pipe can be pushed forward in line with the drill hole, thereby improving versatility and flexibility. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The utility model is further described below in conjunction with the accompanying drawings and embodiments:
[0017] Figure 1 This is a schematic diagram of the structure of the utility model (first perspective).
[0018] Figure 2 It is a schematic diagram of the structure of the utility model (second viewing angle).
[0019] Figure 3 It is a partial cross-sectional view of the utility model (working state).
[0020] In the figure: main rod 1, fixed seat 2, sliding seat 3, first connecting rod 4, second connecting rod 5, branch pipe 6, drill rod 7, through hole 8, anchor rod 9, adjustment hole 10, bolt 11, buffer block 12. DETAILED DESCRIPTION
[0021] like Figure 1-3 As shown, an auxiliary device for fast and stable advancement of anchor rod installation comprises a main rod 1, and a fixed seat 2 and a sliding seat 3 are provided at the front and rear of the main rod 1, that is, the fixed seat 2 is in two groups, and the sliding seat 3 is also in two groups. The fixed seat 2 is fixed on the main rod 1, and the sliding seat 3 is slidably arranged on the main rod 1 and locked by bolts. Multiple pairs of ear plates are fixed circumferentially on each fixed seat 2, and one end of the first connecting rod 4 is rotatably connected to the corresponding ear plate through a pin. Multiple pairs of ear plates are fixed circumferentially on each sliding seat 3, and one end of the second connecting rod 5 is rotatably connected to the corresponding ear plate through a pin. The number of the first connecting rod 4 and the second connecting rod 5 is the same and the position is corresponding. Multiple pairs of ear plates are also fixed at the front and rear ends of the corresponding branch pipes 6, and the other end of each first connecting rod 4 is hinged to the corresponding branch pipe 6, and the other end of each second connecting rod 5 is hinged to the end of the corresponding first connecting rod 4. In addition, a through hole 8 matching the drill rod 7 is provided on one side of the main rod 1, and the main rod 1 can also adopt a tube body, and a limit plate is provided in the tube body to facilitate the insertion and limit of the drill rod 7.
[0022] The branch pipes 6 are two, three, four or five. Three are preferred, because on the one hand, the weight is lighter than that of four, five or six. On the other hand, the existing anchor rod arrangement adopts a plum blossom arrangement, and the three-rod arrangement matches the existing actual situation, and three anchor rods can be pushed at the same time.
[0023] The main rod 1 is provided with a plurality of adjustment holes 10 along the circumferential direction, and the corresponding sliding seat 3 is provided with threaded holes along the radial direction, and the bolts 11 are screwed into the threaded holes and inserted into the corresponding adjustment holes 10. By providing a plurality of groups of adjustment holes 10, when the bolts 11 are screwed out, the sliding seat 3 is pushed forward and backward to adjust the spacing between the branch pipes 6, so as to match different drilled holes. After adjustment, the bolts 11 are screwed in again to tighten the limit.
[0024] The through hole 8 and the branch pipe 6 are filled with a buffer material 12. The buffer material is foam, braided fabric, soft cloth, etc., which ensures the soft connection between the anchor rod and the sleeve, the drill rod and the sleeve, reduces the hard friction loss, and can also reduce the gap between the sleeve wall and increase stability.
[0025] Working principle and process:
[0026] 1) Drill holes and inject grout in advance at the location where the anchor rod 9 needs to be installed on site. During installation, first fill an appropriate amount of buffer material into the main rod 1 and the branch pipe 6, then cut the impact head of the drill rod 7 of the hand drill and extend it into the through hole 8, and insert the anchor rod 9 to be installed into the branch pipe 6.
[0027] 2) After the device is connected, slide the two sliding seats 3, adjust the spacing between the branch pipes 6 to match the drill hole, and after the adjustment, fix the two sets of sliding seats 3 at the corresponding adjustment holes 10 by bolts. Then manually align the anchor rod 9 with the drill hole, start the hand pneumatic drill, and the device moves forward under the propulsion force of the drill rod 7.
[0028] 3) As the device moves forward, the anchor rod 9 is also pushed forward until it reaches the specified depth of the borehole. If it cannot be pushed forward, stop the hand drill in time, find out the cause and continue to push forward. The part that cannot be pushed forward is manually hit with a hammer. After the anchor rod 9 in the branch pipe 6 is installed, the buffer material is supplemented or replaced to enter the next cycle.
Claims
1. An auxiliary device for fast and stable advancement of anchor installation, characterized in that: The invention comprises a main rod (1), wherein a fixed seat (2) and a sliding seat (3) are respectively provided at the front and rear of the main rod (1), wherein the fixed seat (2) is fixed on the main rod (1), and the sliding seat (3) is slidably arranged on the main rod (1) and locked; a plurality of first connecting rods (4) are hingedly connected to each fixed seat (2), and a plurality of second connecting rods (5) are hingedly connected to each sliding seat (3); the other end of each first connecting rod (4) is hingedly connected to a corresponding branch pipe (6), and the other end of each second connecting rod (5) is hingedly connected to a corresponding first connecting rod (4); and a through hole (8) matching a drill rod (7) is provided on one side of the main rod (1).
2. The auxiliary device for rapid and stable advancement of anchor installation according to claim 1, characterized in that: The number of branch pipes (6) is two, three, four or five.
3. The auxiliary device for rapid and stable advancement of anchor installation according to claim 1, characterized in that: The main rod (1) is provided with a plurality of adjustment holes (10) along the circumferential direction, and the corresponding sliding seat (3) is provided with threaded holes along the radial direction, and the bolts (11) are screwed into the threaded holes and inserted into the corresponding adjustment holes (10).
4. The auxiliary device for rapid and stable advancement of anchor installation according to claim 1, characterized in that: A buffer block (12) is provided in the through hole (8) and the branch pipe (6).
Citation Information
Patent Citations
Ahead anchor rod impact transmission device for cavern
CN213360000U