A concrete curing room
By setting up electric telescopic rods and movable plates in the inner cavity of the concrete curing box, the height of the placement plates is adjusted, which solves the problem of unadjustable height of the placement plates in the prior art, and improves the flexibility of placement and maintenance of concrete test blocks of different sizes and heights.
Patent Information
- Application Number
- CN202420524620.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2025-04-01
- Estimated Expiration
- 2034-03-18
AI Technical Summary
In the existing concrete curing box, the height of the storage plate cannot be adjusted and cannot be adapted to concrete test blocks of different sizes, resulting in inflexible placement space.
A concrete curing chamber is designed. By symmetrically setting the fixing rod in the inner cavity and alternately setting the electric telescopic rod, the moving plate and the placing plate on the fixing rod, the electric telescopic rod is used to drive the moving plate and the placing plate to move up and down, so as to adjust the height of the placing plate.
Flexible placement and maintenance of concrete test blocks of different sizes and heights is achieved, and the problem of unadjustable height of the storage plate in the prior art is solved.
Smart Images

Figure CN222697508U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of concrete curing, in particular to a concrete curing room. Background Art
[0002] With the booming development of the construction industry, people have higher and higher requirements for the performance of concrete. In order to meet the needs of the market, various types of concrete have emerged. In the process of concrete research and development, different concretes need to be tested before production and sales. The concrete curing box is an important equipment for providing constant temperature and humidity standard curing of concrete test blocks.
[0003] Generally, in the existing concrete curing box, multiple layers of storage plates for placing concrete test blocks are arranged in the inner box body, and the two sides of the storage plates are fixed by support rods, and the height of the storage plates cannot be adjusted, and the placement space cannot be adjusted according to the concrete test blocks of different sizes. Therefore, the present application proposes a concrete curing room. Utility Model Content
[0004] The present application proposes a concrete curing room, which solves the problem of the existing concrete curing box by setting up a series of structures, in which multiple layers of storage plates for placing concrete test blocks are set in the inner box body, and the two sides of the storage plates are fixed by support rods, and the height of the storage plates cannot be adjusted, and the placement space cannot be adjusted according to concrete test blocks of different sizes.
[0005] The present application proposes a concrete curing chamber, including a concrete curing chamber body, wherein two fixing rods are symmetrically arranged in the inner cavity of the concrete curing chamber body, and the two ends of the two fixing rods are respectively fixedly connected to the top and the bottom of the inner cavity of the concrete curing chamber body, and a plurality of lifting components and fixing components are alternately arranged on the fixing rods from bottom to top;
[0006] The lifting component includes an electric telescopic rod fixed to one side of the fixed rod, one end of the electric telescopic rod is fixed to the bottom of the inner cavity of the concrete curing chamber body, and the other end of the electric telescopic rod is fixed with a moving plate, the moving plate is slidably sleeved on the fixed rod, and the two moving plates are connected to a placing plate through a first clamping component, and a limiting component is arranged on the placing plate;
[0007] The fixing component comprises a fixing plate fixedly sleeved on the fixing rod, and the two fixing plates are connected to a placing plate via a second clamping component.
[0008] Furthermore, the first clamping component includes a first groove opened on one side of the movable plate, baffles are fixed at both ends of the placement plate, and the ends of the baffles are provided with protrusions matching the first groove, and the protrusions are located in the first groove.
[0009] Furthermore, the second clamping component includes a second groove opened on one side of the fixing plate, and the protrusions fixed at both ends of the placement plate are located in the second groove.
[0010] Furthermore, the limiting component includes multiple sliding sleeves slidably mounted on the placement plate, a sliding limiting plate is fixed on the top of the multiple sliding sleeves, a plurality of first limiting holes are evenly opened on one side of the placement plate, a second limiting hole matching the first limiting hole is opened on the sliding sleeve, and also includes a limiting rod, which is inserted into the second limiting hole and the first limiting hole in sequence.
[0011] Furthermore, a sealing gasket is provided on the outer periphery of the protrusion.
[0012] Furthermore, two fixing rods are provided, and the two fixing rods are symmetrically located on both sides of the electric telescopic rod.
[0013] It can be seen from the above technical scheme that when in use, the box door of the concrete curing chamber body is first opened, and the concrete test block is placed on the placement board set in the inner cavity of the concrete curing chamber. Specifically, when concrete test blocks of different sizes are placed, by simultaneously starting two electric telescopic rods on the same horizontal plane, when the electric telescopic rod is extended, the movable plate is driven to move upward. Since the movable plate is slidably sleeved on the fixed rod, the placement board connected to the movable plate can be driven to move upward at the same time. When the electric telescopic rod is retracted, the movable plate is driven to move downward, and the placement board connected to it is driven to move downward at the same time. In this way, the height of the placement board in the lifting mechanism can be adjusted, which is convenient for concrete test blocks of different sizes and heights. Placement and maintenance: It should be noted here that the two electric telescopic rods located on the same horizontal plane are connected to the same controller to ensure that they are started and stopped at the same time. By setting the first clamping component and the second clamping component, the placement plate can be disassembled and replaced. By setting the fixed plate, supporting force is provided for the second lifting component located above the fixed plate. Finally, the concrete test block is fixed again by the limiting component set on the placement plate, which solves the problem of the existing concrete curing box, in which multiple layers of placement plates for placing concrete test blocks are set in the inner box body, and the two sides of the placement plates are fixed by support rods, and the height of the placement plates cannot be adjusted, and the placement space cannot be adjusted according to concrete test blocks of different sizes.
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] 1. The present application can adjust the height of the placement plate by setting a series of structures. Specifically, first open the box door of the concrete curing chamber body, and simultaneously start the two electric telescopic rods on the same horizontal plane to drive the movable plate to move up and down. Since the movable plate is slidably sleeved on the fixed rod, the placement plate connected to the movable plate can be driven to move up and down at the same time. In this way, the height of the placement plate in the lifting mechanism can be adjusted, which is convenient for placing and curing concrete test blocks of different sizes and heights. It should be noted here that the two electric telescopic rods located on the same horizontal plane are connected to the same controller to ensure that they are started and stopped at the same time. By setting the fixed plate, a supporting force is provided for the second lifting component located above the fixed plate. Finally, the concrete test block is fixed again by the limiting component set on the placement plate, which solves the problem of the existing concrete curing box, in which multiple layers of placement plates for placing concrete test blocks are set in the inner box body, and the two sides of the placement plates are fixed by support rods, and the height of the placement plates cannot be adjusted, and the placement space cannot be adjusted according to concrete test blocks of different sizes. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solution of the present application, the following is a brief introduction to the drawings required for use in the implementation cases. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.
[0017] Figure 1 This is a structural schematic diagram of a concrete curing room proposed by the utility model;
[0018] Figure 2 A schematic diagram of the supplementary structure of a concrete curing room proposed by the utility model;
[0019] Figure 3 This is an enlarged schematic diagram of point A in a concrete curing room proposed by the utility model;
[0020] Figure 4 This is an enlarged schematic diagram of point B in a concrete curing room proposed by the utility model;
[0021] Illustration Description:
[0022] Wherein: 1. concrete curing chamber body, 2. fixing rod, 3. electric telescopic rod, 4. moving plate, 5. placing plate, 6. fixing plate, 7. first groove, 8. baffle, 9. protrusion, 10. second groove, 11. sliding sleeve, 12. sliding limit plate, 13. first limit hole, 14. second limit hole, 15. limit rod, 16. sealing gasket. DETAILED DESCRIPTION
[0023] In order to enable those skilled in the art to better understand the technical solutions in the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the accompanying drawings.
[0024] See also Figure 1-Figure 4 .
[0025] Generally, in the existing concrete curing box, multiple layers of placing plates for placing concrete test blocks are arranged in its inner box body, and the two sides of the placing plates are fixed by support rods, and the height of the placing plates cannot be adjusted, and the placing space cannot be adjusted according to the concrete test blocks of different sizes. Therefore, the present application proposes a concrete curing chamber, including a concrete curing chamber body 1, wherein two fixing rods 2 are symmetrically arranged in the inner cavity of the concrete curing chamber body 1, and the two ends of the two fixing rods 2 are respectively fixedly connected to the top and the bottom of the inner cavity of the concrete curing chamber body 1, and a plurality of lifting components and fixing components are alternately arranged on the fixing rods 2 from bottom to top;
[0026] The lifting component includes an electric telescopic rod 3 fixed to one side of the fixed rod 2, one end of the electric telescopic rod 3 is fixed to the bottom of the inner cavity of the concrete curing chamber body 1, and the other end of the electric telescopic rod 3 is fixed with a moving plate 4, which is slidably sleeved on the fixed rod 2. The two moving plates 4 are connected to a placement plate 5 through a first clamping component. The placement plate 5 is provided with a limited position component. Specifically, the box door of the concrete curing chamber body 1 is opened first, and the concrete test block is placed on the placement plate 5 provided in the inner cavity of the concrete curing chamber. When placing concrete test blocks of different sizes, the same horizontal plane is started at the same time. When the electric telescopic rod 3 is extended, the movable plate 4 is driven to move upward. Since the movable plate 4 is slidably sleeved on the fixed rod 2, the placement plate 5 connected to the movable plate 4 can be driven to move upward at the same time. When the electric telescopic rod 3 is retracted, the movable plate 4 is driven to move downward, and the placement plate 5 connected thereto is driven to move downward at the same time. In this way, the height of the placement plate 5 in the lifting mechanism can be adjusted, which is convenient for placing and curing concrete test blocks of different sizes and heights. It should be noted here that the two electric telescopic rods 3 located on the same horizontal plane are connected to the same controller;
[0027] The fixing component includes a fixing plate 6 fixedly sleeved on the fixing rod 2. The two fixing plates 6 are connected to a placement plate 5 via a second clamping component. Specifically, by setting the fixing plate 6, a supporting force is provided for the second lifting component located above the fixing plate 6.
[0028] Furthermore, the first clamping component includes a first groove 7 opened on one side of the movable plate 4, baffles 8 are fixed at both ends of the placement plate 5, and the ends of the baffles 8 are provided with protrusions 9 matching the first groove 7, and the protrusions 9 are located in the first groove 7. The second clamping component includes a second groove 10 opened on one side of the fixed plate 6, and the protrusions 9 fixed at both ends of the placement plate 5 are located in the second groove 10. Specifically, when the placement plate 5 needs to be disassembled and replaced, the placement plate 5 is horizontally pulled out from the fixed plate 6 and the movable plate 4, so that the protrusions 9 are separated from the first groove 7 and the second groove 10, and the placement plate 5 can be disassembled and replaced.
[0029] Furthermore, the limiting component includes a plurality of sliding sleeves 11 slidably mounted on the placement plate 5, a sliding limiting plate 12 is fixed on the top of the plurality of sliding sleeves 11, a plurality of first limiting holes 13 are evenly opened on one side of the placement plate 5, a second limiting hole 14 matching the first limiting hole 13 is opened on the sliding sleeve 11, and also includes a limiting rod 15, the limiting rod 15 is inserted into the second limiting hole 14 and the first limiting hole 13 in sequence. Specifically, after the concrete test block is placed, the sliding sleeve 11 is horizontally slid to drive the sliding limiting plate 12 to move horizontally. When moving to the optimal position, the first limiting holes 13 evenly opened on one side of the placement plate 5 are aligned with the second limiting holes 14 opened on the sliding sleeve 11, and then the limiting rod 15 is inserted to fix the sliding sleeve 11, thereby further fixing the sliding limiting plate 12, and finally fixing the concrete test block on the placement plate 5 to prevent it from moving at will and affecting the maintenance effect.
[0030] Furthermore, a sealing gasket 16 is provided on the outer periphery of the protrusion 9. Specifically, by providing the sealing gasket 16, the protrusion 9 and the first groove 7 and the second groove 10 can be more firmly connected.
[0031] Furthermore, two fixed rods 2 are provided, and the two fixed rods 2 are symmetrically located on both sides of the electric telescopic rod 3. Specifically, by providing two fixed rods 2, the electric telescopic rod 3 can provide guidance for the movable plate 4 to slide up and down, thereby achieving stable sliding of the movable plate 4.
[0032] It can be seen from the above technical scheme that when in use, the box door of the concrete curing chamber body 1 is first opened, and the concrete test block is placed on the placement plate 5 set in the inner cavity of the concrete curing chamber. Specifically, when concrete test blocks of different sizes are placed, the two electric telescopic rods 3 on the same horizontal plane are started at the same time. When the electric telescopic rod 3 is extended, the movable plate 4 is driven to move upward. Since the movable plate 4 is slidably sleeved on the fixed rod 2, by setting two fixed rods 2, the electric telescopic rod 3 can provide a guide for the movable plate 4 to slide up and down, so as to achieve stable sliding of the movable plate 4, so that the placement plate 5 connected to the movable plate 4 can be driven to move upward at the same time. When the electric telescopic rod 3 is retracted, the movable plate 4 is driven to move downward, and the placement plate 5 connected thereto is driven downward at the same time. Move, this method can adjust the height of the placement plate 5 in the lifting mechanism, which is convenient for placing and curing concrete test blocks of different sizes and heights. It should be noted here that the two electric telescopic rods 3 located on the same horizontal plane are connected to the same controller to ensure that they are started and stopped at the same time. When the placement plate 5 needs to be disassembled and replaced, the placement plate 5 is horizontally pulled out from the fixed plate 6 and the movable plate 4, so that the protrusion 9 is separated from the first groove 7 and the second groove 10, and the placement plate 5 can be disassembled and replaced. By arranging a sealing gasket 16 around the protrusion 9, the protrusion 9 and the first groove 7 and the second groove 10 can be made more secure. By arranging the fixed plate 6, a supporting force is provided for the second lifting component located above the fixed plate 6;
[0033] Finally, the concrete test block is fixed again by the limiting components arranged on the placement plate 5. Specifically, after the concrete test block is placed, the sleeve 11 is horizontally slid to drive the sliding limiting plate 12 to move horizontally. When it moves to the optimal position, the first limiting hole 13 evenly opened on one side of the placement plate 5 is aligned with the second limiting hole 14 opened on the sleeve 11, and then the limiting rod 15 is inserted to fix the sleeve 11, thereby further fixing the sliding limiting plate 12, and finally fixing the concrete test block on the placement plate 5 to prevent it from moving at will and affecting the curing effect, thereby solving the problem of the existing concrete curing box, in which multiple layers of placing plates for placing concrete test blocks are arranged in the inner box body, and the two sides of the placing plates are fixed by support rods, and the height of the placing plates cannot be adjusted, and the placement space cannot be adjusted according to concrete test blocks of different sizes.
[0034] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the application disclosed herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary techniques in the art that are not disclosed in the present application. The specification and examples are intended to be exemplary only, and the true scope of the present application is indicated by the claims.
[0035] It should be understood that the present application is not limited to the precise structure described above and shown in the drawings, and various modifications and changes can be made without departing from its scope. The above-described embodiments of the present application do not constitute a limitation on the scope of protection of the present application.
Claims
1. A concrete curing room, characterized in that: It comprises a concrete curing chamber body (1), wherein the inner cavity of the concrete curing chamber body (1) is symmetrically provided with two fixing rods (2), the two ends of the two fixing rods (2) are respectively fixedly connected to the top and the bottom of the inner cavity of the concrete curing chamber body (1), and the fixing rods (2) are alternately provided with a plurality of lifting components and fixing components in sequence from bottom to top; The lifting component comprises an electric telescopic rod (3) fixed to one side of the fixed rod (2), one end of the electric telescopic rod (3) is fixed to the bottom of the inner cavity of the concrete curing chamber body (1), and the other end of the electric telescopic rod (3) is fixed with a movable plate (4), the movable plate (4) is slidably sleeved on the fixed rod (2), and the two movable plates (4) are connected to a placement plate (5) via a first clamping component, and a limiting component is provided on the placement plate (5); The fixing component comprises a fixing plate (6) fixedly sleeved on the fixing rod (2), and the two fixing plates (6) are connected to a placement plate (5) via a second clamping component.
2. A concrete curing chamber according to claim 1, characterized in that: The first clamping component comprises a first groove (7) opened on one side of the movable plate (4); baffles (8) are fixed at both ends of the placement plate (5); and the ends of the baffles (8) are provided with protrusions (9) matching the first groove (7); the protrusions (9) are located in the first groove (7).
3. A concrete curing chamber according to claim 2, characterized in that: The second clamping component comprises a second groove (10) formed on one side of the fixing plate (6), and the protrusions (9) fixed at both ends of the placement plate (5) are located in the second groove (10).
4. A concrete curing chamber according to claim 1, characterized in that: The limiting component comprises a plurality of sliding sleeves (11) slidably mounted on the placement plate (5), a sliding limiting plate (12) being fixed on the top of each of the plurality of sliding sleeves (11), a plurality of first limiting holes (13) being evenly arranged on one side of the placement plate (5), a second limiting hole (14) matching the first limiting hole (13) being arranged on the sliding sleeve (11), and a limiting rod (15) being inserted into the second limiting hole (14) and the first limiting hole (13) in sequence.
5. A concrete curing chamber according to claim 2, characterized in that: A sealing gasket (16) is provided on the outer periphery of the protrusion (9).
6. A concrete curing chamber according to claim 1, characterized in that: Two fixing rods (2) are provided, and the two fixing rods (2) are symmetrically located on both sides of the electric telescopic rod (3).