A pier construction platform

By designing a pier column construction platform including walking platform and platform bracket, the problem of difficulty in erecting the overall bracket method in mountain bridge construction is solved, and the effect of shortening the construction period and improving construction efficiency is achieved.

CN222715812UActive Publication Date: 2025-04-04CHINA KANG GANG STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421460494.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2025-04-04
Estimated Expiration
2034-06-25

AI Technical Summary

Technical Problem

In the construction of mountainous bridges, the overall support method is difficult to erect, resulting in a long construction period and affecting the progress of the bridge construction.

Method used

A pier column construction platform is designed, including a walking platform and a platform bracket. By setting up multiple independent triangular brackets on the periphery of the pouring formwork, the walking platform is overlapped to form a detachable construction platform.

Benefits of technology

It realizes the pouring construction of pier columns without erecting brackets or scaffolding, shortens the construction period and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222715812U_ABST
    Figure CN222715812U_ABST
Patent Text Reader

Abstract

The present application relates to a pier column construction platform, including a walking platform and a platform bracket. The pier column is built with a casting template before forming, the platform bracket is arranged around the periphery of the casting template, and the walking platform is overlapped between the platform brackets; the platform bracket includes a plurality of independent triangular brackets, each of which includes a vertical support rod, a transverse support rod and a diagonal support rod of an integrated structure, the vertical support rod is detachably connected to the casting template, and the walking platform is detachably connected between the transverse support rods. The utility model can perform the casting construction of the pier column without setting up a bracket or scaffolding, thereby improving the construction limitations and disadvantages of the existing integral bracket method.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of civil construction, and in particular to a pier construction platform. Background Art

[0002] The pier is the most important foundation part of highway and railway bridge construction. The existing pier construction mostly adopts the integral support cast-in-place method.

[0003] The integral support method requires setting up supports around the bridge piers. However, in mountain bridge construction, due to the limitations of terrain and geological structure, it is difficult to set up integral supports, and safety is also affected. Therefore, the integral support method is limited.

[0004] Moreover, the integral support method is used, which takes a long time to construct and affects the construction progress of the bridge. Utility Model Content

[0005] The purpose of the present application is to provide a pier construction platform that can perform pier casting construction without setting up a support or scaffolding, thereby improving the construction limitations and disadvantages of the existing integral support method.

[0006] In order to achieve the above-mentioned purpose, the utility model provides a pier column construction platform, including a walking platform and a platform bracket. The pier column is built with a casting template before forming, the platform bracket is arranged around the periphery of the casting template, and the walking platform is overlapped between the platform brackets;

[0007] The platform bracket includes a plurality of independent triangular brackets, each of which includes a vertical support rod, a transverse support rod and a diagonal support rod of an integrated structure, the vertical support rod is detachably connected to the casting formwork, and the walking platform is detachably connected between the transverse support rods.

[0008] In an optional embodiment, the casting formwork includes a plurality of vertically distributed sections, and the platform bracket is arranged at the top position of each section of the casting formwork.

[0009] In an optional embodiment, ladders are provided between the walking platform and the ground, and between walking platforms at different levels, and the ladders are arranged alternately between the walking platforms at adjacent levels.

[0010] In an optional embodiment, manholes are provided on the walking platforms at different heights, and the manholes are provided at the top end of the ladder, including square manholes located on the walking platforms.

[0011] In an optional embodiment, the walking platform includes a plurality of independent platform panels, each of the platform panels includes a platform frame and a patterned plate connected to the platform frame, bolt holes are provided on the transverse support rods and the platform frame, and the platform frame and the transverse support rods are detachably connected by bolts.

[0012] In an optional embodiment, a protective net is arranged on the periphery of the walking platform, and the protective net includes a straight side net and an angle mold side net, the straight side net includes a rectangular mesh surface, and the angle mold side net includes a curved mesh surface.

[0013] In an optional embodiment, the outer end of the transverse support rod is connected to a vertically arranged protective rod, a cross beam is connected between the protective rods, and the cross beam is detachably connected to the protective rod.

[0014] In an optional embodiment, the protection net is arranged on the inner side of the protection rod, and the protection net is detachably connected to the crossbeam via a U-shaped clamp.

[0015] In an optional embodiment, at the same floor height, the platform brackets are evenly distributed at an equal distance around the periphery of the casting formwork, and each of the triangular brackets is arranged vertically to form a vertical support plane.

[0016] In an optional embodiment, a plurality of bolt holes are provided on the vertical support rod, the casting formwork includes a main reinforcement channel steel, the main reinforcement channel steel is provided with bolt holes, and the triangular bracket is detachably connected to the main reinforcement channel steel by bolts.

[0017] The walking platform can facilitate the pouring construction of the pier, and the platform bracket can effectively constitute the supporting structure of the walking platform to ensure the installation stability of the construction platform.

[0018] The platform bracket is arranged around the periphery of the casting formwork, and the walking platform is overlapped between the platform brackets, so as to form a construction platform around the pier column and meet the auxiliary use needs of the casting operation.

[0019] By setting the platform bracket as multiple independent triangular brackets, and combining each triangular bracket with an integrated vertical support rod, a transverse support rod and a diagonal support rod, the support body of the walking platform can be constructed in the form of separate independent installation. The triangular bracket has stable and reliable support performance, meeting the effective reliability of supporting the construction platform.

[0020] The vertical support rod is detachably connected to the casting template, which enables the detachable installation of the triangular bracket on the casting template and meets the need for repeated use of the triangular bracket.

[0021] Likewise, the walking platform is detachably connected between the transverse support rods, which can facilitate the disassembly and assembly of the walking platform on the tripod bracket.

[0022] Other features and advantages of the present application will be described in detail in the subsequent specific implementation section. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 This is a schematic diagram of the structure of the pier construction platform in this application;

[0025] Figure 2 for Figure 1 A schematic diagram of a top view structure;

[0026] Figure 3 This is a schematic diagram of the structure of the tripod bracket.

[0027] icon:

[0028] 1- Casting formwork;

[0029] 2-triangular support; 21-vertical support rod; 22-lateral support rod; 23-diagonal support rod; 24-protection rod;

[0030] 3- walking platform; 31- platform plate;

[0031] 4- crossbeam;

[0032] 5-protective net; 51-straight side net; 52-corner mold side net;

[0033] 6-Manhole;

[0034] 7- Climb the ladder. DETAILED DESCRIPTION

[0035] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.

[0036] In the description of this application, it should be noted that the terms "inside", "outside", etc. indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship in which the product of the application is usually placed when in use, which is only for the convenience of describing this application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application. In addition, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0037] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "disposed" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0038] The pier construction platform in this application is mainly used to assist in the casting construction of the pier. The construction platform is formed by relying on the casting formwork of the pier. The construction platform can be built without setting up additional supports or scaffolding. It is used to provide support for pier construction when the terrain conditions are complex, the construction period is tight, and the construction pressure is high.

[0039] The main components are assembled and installed in the form of detachable connections, which can facilitate the dismantling of the construction platform and the transportation of separate components, greatly improving the operating conditions and increasing construction efficiency.

[0040] See also Figure 1 , and combined with Figure 2-Figure 3 The pier construction platform in this application is mainly used for building a construction platform during the pier casting construction process. The main structure of the construction platform includes a walking platform 3 and a platform bracket. A casting template 1 is built before the pier is formed. The platform bracket relies on the structure of the casting template 1 and is arranged around the periphery of the casting template 1 to provide root support for the construction platform.

[0041] The walking platform 3 is overlapped between the platform brackets, and the walking platform 3 can be built on the basis of the platform brackets to meet the construction and use requirements of the walking platform 3.

[0042] From the perspective of support, the platform bracket includes a plurality of independent triangular brackets 2, each of which includes a vertical support rod 21, a horizontal support rod 22 and a diagonal support rod 23 of an integrated structure. The triangular bracket 2 is formed by the above-mentioned different support rods, which can effectively improve the structural strength of each platform bracket, and the triangular bracket 2 can form a separate support plane to ensure effective and reliable support.

[0043] The vertical support rod 21 is detachably connected to the casting template 1, so that the platform bracket can be connected to the casting template 1 to form a supporting base for the walking platform 3. At the same time, the detachable connection form facilitates the disassembly and assembly of the tripod bracket 2, which is conducive to turnover and reuse.

[0044] The walking platform 3 is detachably connected between the transverse support rods 22, so that the walking platform 3 and the tripod bracket 2 can also maintain a detachable connection relationship. On the basis of effectively forming a construction platform, the walking platform 3 can be disassembled and assembled to facilitate the turnover and reuse of the walking platform 3.

[0045] The casting formwork 1 in the utility model includes multiple sections distributed vertically. Specifically, the casting formwork 1 with multiple sections is constructed layer by layer from the bottom layer upwards. In order to facilitate construction at a high position, a platform bracket is arranged at the top position of each section of the casting formwork 1, which can effectively form a walking platform 3 located at the top of each section of the casting formwork 1, so as to facilitate the high-position construction casting of the entire section of the pier.

[0046] Based on the step-by-step construction of the casting formwork 1 from bottom to top, a ladder 7 is arranged between the walking platform 3 and the ground, and between walking platforms 3 of different heights. The arrangement of the ladder 7 can facilitate operators to climb between sections of different heights and improve the integrity of the pier construction platform.

[0047] In order to facilitate the climbing operation of personnel and to ensure the strength of the overall structure, the ladders 7 are arranged alternately between the walking platforms 3 of adjacent storeys.

[0048] The walking platforms 3 at different levels are all provided with manholes 6, which can be used for operators to climb or descend between the walking platforms 3 at different levels. Furthermore, the manhole 6 is arranged at the top of the ladder 7, opposite to the position of the ladder 7, and in order to facilitate entry and exit, the manhole 6 includes a square manhole 6 located on the walking platform 3, which is convenient for the reserved structure of the walking platform 3 during the overlapping process.

[0049] The walking platform 3 includes a plurality of independent platform panels 31 , and the plurality of platform panels 31 are assembled together to form the overall structure of the walking platform 3 .

[0050] Each platform plate 31 includes a platform outer frame and a patterned plate connected to the platform outer frame. Bolt holes are provided on the transverse support rod 22 and the platform outer frame. The platform outer frame and the transverse support rod 22 are detachably connected by bolts.

[0051] Through the above-mentioned arrangement, the disassembly and assembly of the platform plate 31 and the platform bracket can be facilitated, and the turnover utilization of the platform plate 31 can be effectively promoted while facilitating the construction of the overall structure of the walking platform 3.

[0052] From the perspective of protection, a protective net 5 is arranged on the periphery of the walking platform 3. The protective net 5 includes a straight side net 51 and an angle mold side net 52. The straight side net 51 includes a rectangular mesh surface, which is assembled with each other on the same side to form a protective net 5 structure on the side of the pier, while the angle mold side net 52 includes a curved mesh surface, which can follow and adapt to the end shape of the pier to form a relatively complete protective whole.

[0053] From the installation perspective of the protective net 5, the outer end of the transverse support rod 22 is connected to the vertically arranged protective rod 24, and the protective rods 24 are connected with a crossbeam 4. The crossbeam 4 and the protective rods 24 are detachably connected. The setting of the crossbeam 4 can provide an installation basis for the protective net 5.

[0054] Furthermore, the protective net 5 is arranged on the inner side of the protective rod 24, and the protective net 5 and the crossbeam 4 are detachably connected by a U-shaped clamp. Similarly, the detachable connection is conducive to the turnover application of the protective structure, and can reduce the difficulty of disassembly and assembly and improve construction efficiency.

[0055] At the same floor height, the platform brackets are evenly distributed around the casting formwork 1, and each triangular bracket 2 is arranged vertically to form a vertical support plane. Through multiple evenly distributed triangular support planes, a relatively uniform support can be formed to ensure the overall balance of the supporting force.

[0056] A plurality of bolt holes are arranged on the vertical support rod 21 , the casting formwork 1 comprises a main reinforcement channel steel, the main reinforcement channel steel is provided with bolt holes, and the triangular bracket 2 is detachably connected to the main reinforcement channel steel by bolts.

[0057] The triangular bracket 2 can be detachably installed on the casting template 1. The main reinforcement channel steel of the casting template 1 has a high structural strength and can provide a good supporting effect for the construction platform.

[0058] The pier column construction platform of the utility model, the casting template 1, the triangular bracket 2, the platform plate 31, the protective net 5 and the ladder 7 are all designed as independent structures, and the assembly between the components is realized by bolts. In this way, not only the structure of the entire construction platform can be simplified, but also the detachable connection of the construction platform can be realized, so as to facilitate the installation and transportation of the construction platform.

[0059] The vertical support rods 21, transverse support rods 22 and diagonal support rods 23 of the triangular bracket 2 are made of ∠75# equilateral angle steel, and the protective rods 24 are welded into a whole with □40 square tubes. The vertical support rods 21 are fixed to the main reinforcement channel steel on the outside of the pier column formwork by bolts, and the spacing between the vertical support rods 21 is not more than 1.2 meters.

[0060] The transverse support rods 22 are connected by platform plates 31, and the platform plates 31 are welded into a whole by ∠50# equilateral angle steel, 6 mm steel strip, and 3 mm patterned plate. The guard rod 24 is set at a height of 1.2 meters. The guard rods 24 are connected by beams 4 and protective nets 5 to form a circular guardrail. The protective net 5 is made of □40 square tubes and steel wire mesh welded into straight plate side nets 51 with rectangular surfaces and angle mold side nets 52 with curved surfaces.

[0061] The pier is cast in sections. First, a casting formwork 1 surrounding the bridge pier is installed at the bottom of the pier, and a triangular bracket 2 is installed around the formwork. The horizontal support rods 22 connect the walking platform 3 and the crossbeams 4 and the protective net 5 between the protective rods 24 to form a semi-enclosed construction platform.

[0062] The construction workers enter the construction platform through the ladder 7 and the manhole 6, and work on the construction platform to cast the first section of the pier column. After the first section is cast, the second section of the formwork is installed on the basis of the formwork of the first section to form a circular platform for the second section. The construction is carried out upward in sequence, and after the entire pier column is cast, the formwork is removed from top to bottom in sequence.

[0063] The entire pouring process does not require the erection of scaffolding and is not restricted by the terrain and geological structure around the pier.

[0064] In the specific steps, first install the bottom section pier column formwork, install the triangular bracket 2 on the formwork along the circumferential direction of the formwork, and complete the circumferential platform erection. Set the ladder 7 along the longitudinal direction of the formwork, use the construction platform as a pouring construction platform, and pour the first section pier column concrete;

[0065] After the first section of the pier column is poured, install the second section of the pier column reinforcement cage and set the guy rope;

[0066] Install the second section pier column formwork, construction platform and ladder 7 on the basis of the first section pier column formwork, set the formwork cable wind rope, and pour the second section pier column concrete;

[0067] Repeat the above steps and pour upwards in sequence until the top section of the pier column is poured with concrete;

[0068] The pier column formwork, construction platform and vertical ladder 7 are removed from top to bottom to complete the pier column pouring construction.

[0069] It should be noted that, in the absence of conflict, the features in the embodiments of this application may be combined with each other.

[0070] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A pier construction platform, characterized in that: It includes a walking platform and a platform bracket. The pier is built with a casting template before forming. The platform bracket is arranged around the periphery of the casting template, and the walking platform is overlapped between the platform brackets. The platform bracket includes a plurality of independent triangular brackets, each of which includes a vertical support rod, a transverse support rod and a diagonal support rod of an integrated structure, the vertical support rod is detachably connected to the casting formwork, and the walking platform is detachably connected between the transverse support rods.

2. The pier construction platform according to claim 1, characterized in that: The casting template includes a plurality of vertically distributed sections, and the platform bracket is arranged at the top position of each section of the casting template.

3. The pier construction platform according to claim 2, characterized in that: Ladders are arranged between the walking platform and the ground, and between walking platforms at different levels. The ladders are arranged alternately between the walking platforms at adjacent levels.

4. The pier construction platform according to claim 3, characterized in that: Manholes are arranged on the walking platforms at different levels, and the manholes are arranged at the top end of the ladder, including square manholes located on the walking platforms.

5. The pier construction platform according to claim 1, characterized in that: The walking platform includes a plurality of independent platform plates, each of which includes a platform outer frame and a patterned plate connected to the platform outer frame. Bolt holes are provided on the transverse support rods and the platform outer frame. The platform outer frame and the transverse support rods are detachably connected by bolts.

6. The pier construction platform according to claim 1, characterized in that: A protective net is arranged on the periphery of the walking platform, and the protective net includes a straight plate side net and an angle mold side net, the straight plate side net includes a rectangular net surface, and the angle mold side net includes a curved net surface.

7. The pier construction platform according to claim 6, characterized in that: The outer ends of the transverse support rods are connected to vertically arranged protection rods, and cross beams are connected between the protection rods. The cross beams are detachably connected to the protection rods.

8. The pier construction platform according to claim 7, characterized in that: The protection net is arranged on the inner side of the protection rod, and the protection net is detachably connected to the crossbeam via a U-shaped clamp.

9. The pier construction platform according to claim 1, characterized in that: At the same floor height, the platform brackets are evenly distributed at an equal distance around the periphery of the casting formwork, and each of the triangular brackets is arranged vertically to form a vertical support plane.

10. The pier construction platform according to claim 1, characterized in that: The vertical support rod is provided with a plurality of bolt holes, the casting template comprises a main reinforcement channel steel, the main reinforcement channel steel is provided with bolt holes, and the triangular bracket is detachably connected to the main reinforcement channel steel by bolts.