A beam-column core area concrete pouring interception device

By designing a concrete pouring intercept device for the core area of ​​beam and column including beam stirrups and mesh frame units, the problems of poor quality, low efficiency and long cycle during the construction process of traditional devices are solved, and tight fit and efficient construction during concrete pouring are achieved.

CN222716500UActive Publication Date: 2025-04-04WINAM CONSTR CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421331825.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2025-04-04
Estimated Expiration
2034-06-12

AI Technical Summary

Technical Problem

The traditional concrete pouring intercepting device in the core area of ​​beam and column has problems of poor quality, low efficiency and long cycle during the construction process. Especially the poor quality of the wire mesh is tied in a narrow space, which can easily lead to the concrete being knocked out of the wire mesh and affect the construction quality.

Method used

A concrete pouring intercept device for the beam and column core area including beam stirrups and mesh frame units was designed. The mesh frame unit consists of keel and wire mesh. The keel is connected by welding. The wire mesh covers the edge of the keel, with tight locking edges and firmly tied edges.

Benefits of technology

By equiping keels on the outside of the wire mesh, the concrete will not deform during pouring, the mesh surface will be tightly fitted, the welded connection of the keels will be firmly, the wire mesh will cover the edges of the keels, the lock edges will be tight, and the edges will be tied firmly, which will improve the construction quality and efficiency and meet the construction period requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222716500U_ABST
    Figure CN222716500U_ABST
Patent Text Reader

Abstract

The utility model discloses a beam-column core area concrete pouring interception device, comprising beam stirrups, mesh frame units for concrete pouring interception are arranged in the beam stirrups, and there are three mesh frame units, the inner wall of the beam stirrups is located outside the mesh frame units and is evenly and equidistantly fixedly connected with the first beam main reinforcement, the surface of the mesh frame units in the beam stirrups is arranged with the third beam main reinforcement, points between the mesh frame units and the first beam main reinforcement form wire mesh tying points, the mesh frame units comprise a keel and a steel mesh, the steel mesh is tied to the outside of the keel, the keel has an overall mesh-shaped structure, the keel comprises a first round steel and a second round steel, there are two first round steels, and the two first round steels are symmetrically arranged, and there are four second round steels. The beam-column core area concrete pouring interception device is simple to manufacture and easy to install, can not only ensure construction quality, but also meet construction period requirements, and has certain promotion value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a concrete pouring interception device for the core area of ​​a beam and column. Background Art

[0002] The core area of ​​the beam-column node is the area where the beam and column meet. It is the node area where the beam and column meet. When pouring the core area of ​​the beam and column, concrete of different grades are used for pouring. Therefore, a concrete pouring interception device for the core area of ​​the beam and column is required during pouring.

[0003] The traditional interception device for concrete pouring in the core area of ​​beams and columns is usually carried out by workers on site to tie the wire mesh. Due to the loose connection between the work processes of various types of work, it is easy for the workers to tie the wire mesh when the beam side formwork has been installed, resulting in the inability to complete the interception measure. If it is to be completed, the side formwork needs to be removed and then closed after the construction is completed; when there is a densified area at the end of the beam (spacing is 100mm) and there are multi-legged hoops, twist bars, and hooks, the workers' construction efficiency reduction behavior will be more obvious; due to the small construction space, the operators tie the wire mesh with poor quality during construction, and when pouring concrete, the concrete is likely to break off the wire mesh, resulting in poor construction quality, low construction efficiency and long construction period. For this reason, we propose a concrete pouring interception device for the core area of ​​beams and columns. Utility Model Content

[0004] The utility model aims to provide a device for intercepting concrete pouring in the core area of ​​a beam and column, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a device for intercepting concrete pouring in the core area of ​​a beam and column, comprising beam stirrups, wherein a mesh skeleton unit for intercepting concrete pouring is arranged inside the beam stirrups, and there are three mesh skeleton units, the inner wall of the beam stirrups is located outside the mesh skeleton unit and is evenly fixedly connected with a first beam main reinforcement, a third beam main reinforcement is arranged on the surface of the mesh skeleton unit inside the beam stirrups, a wire mesh tying point is formed at a point between the mesh skeleton unit and the first beam main reinforcement, the mesh skeleton unit comprises a keel and a wire mesh, and the outside of the keel is tied with a wire mesh.

[0006] Preferably, the keel has an overall mesh-shaped structure, and the keel includes a first round steel and a second round steel, wherein there are two first round steels, and the two first round steels are symmetrically arranged, and there are four second round steels, and the four second round steels are equidistantly fixedly connected between the two first round steels.

[0007] Preferably, two ends of the four second round steels are fixed to the two first round steels by welding respectively.

[0008] Preferably, the steel wire mesh is located on one side of the keel, and the steel wire mesh is fixed to the outside of the keel by means of tying wires.

[0009] Preferably, the first round steel and the second round steel are both No. 6 round steel.

[0010] Compared with the prior art, the utility model has the following beneficial effects: the utility model can ensure that there is no deformation during concrete pouring by equipping the outside of the wire mesh with a keel, the mesh surface fits tightly, the keel is connected by welding, the welding is firm, the wire mesh covers the edge of the keel, the edge is tightly locked, the edge is firmly tied, the processing and manufacturing are simple, and the installation is easy, which not only ensures the construction quality, but also meets the construction period requirements, and has certain promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0012] Figure 2 It is a schematic diagram of the main view structure of the utility model;

[0013] Figure 3 This is a schematic diagram of the mesh skeleton unit structure of the utility model;

[0014] Figure 4 It is a schematic diagram of the connection structure of the keel and the wire mesh of the utility model.

[0015] In the figure: 1. Beam stirrups; 2. Mesh skeleton unit; 3. First beam main reinforcement; 5. Third beam main reinforcement; 6. Keel; 7. Wire mesh; 8. First round steel; 9. Second round steel; 10. Wire mesh tying points. DETAILED DESCRIPTION

[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0017] See also Figure 1-4 The utility model provides a technical solution: a concrete pouring interception device for the core area of ​​a beam and column, comprising a beam stirrup 1, wherein a mesh frame unit 2 for concrete pouring interception is arranged inside the beam stirrup 1, and the mesh frame units 2 are three.

[0018] It should be noted that the mesh skeleton unit 2 is composed of a keel 6 and two layers of steel mesh 7. By arranging the keel 6 outside the steel mesh 7, it can be ensured that the concrete is not deformed during pouring and the mesh surface fits more closely.

[0019] The inner wall of the beam stirrup 1 is located outside the mesh skeleton unit 2 and is evenly and fixedly connected with the first beam main reinforcement 3. The third beam main reinforcement 5 is arranged on the surface of the mesh skeleton unit 2 inside the beam stirrup 1. The point between the mesh skeleton unit 2 and the first beam main reinforcement 3 forms a wire mesh tying point 10. The mesh skeleton unit 2 includes a keel 6 and a wire mesh 7. The outside of the keel 6 is tied with a wire mesh 7.

[0020] It should be noted that the utility model has a beam cross-sectional size of 400*600 according to the field test, and needs to be equipped with three keels 6 and covered with wire mesh 7 for double-layer tying. When equipping the keel 6, each keel 6 needs two first round steels 8 and four second round steels 9. The four second round steels 9 are welded between the two first round steels 8 at equal intervals, and the ends of the two second round steels 9 located at both ends of the first round steels 8 are welded and fixed to the ends of the first round steels 8. The equipped keel 6 forms a mesh-shaped structure as a whole, and then the wire mesh 7 is tied to both sides of each keel 6 in turn, so that the wire mesh 7 covers the edge of the keel, the edge is locked tightly, and the edge is tied firmly, so that the mesh frame unit 2 is equipped. Three mesh frame units 2 are equipped, and a beam is fixed on the outside of the main reinforcement 3 of the first beam. Stirrups 1, three mesh skeleton units 2 are set in the beam stirrups 1, the mesh skeleton units 2 are placed horizontally and fixed on the beam stirrups 1, the upper part of the mesh skeleton unit 2 is fixed on the previous beam stirrup 1 along with the beam stirrups 1, and after the next beam stirrup 1 is installed, the lower end of the mesh skeleton unit 2 is fixed on the top of the next beam stirrup 1 to form a 45° angle, and so on to form a 45° interception of the entire beam section, and the mesh skeleton unit 2 is tied and fixed according to its designed position. After tying, the gap between the mesh skeleton unit 2 and the oblique section of the beam stirrup 1 is small, which ensures the flatness of the interception surface, and double strands of No. 22 wire are used to tie and fix the beam stirrup 1 and the third beam main reinforcement 5 to ensure that the position of the mesh skeleton unit 2 is correct and does not move during the concrete pouring process.

[0021] The keel 6 has an overall structure in the shape of a U-shaped letter "J". The keel 6 includes a first round steel 8 and a second round steel 9. There are two first round steels 8, and the two first round steels 8 are symmetrically arranged. There are four second round steels 9, and the four second round steels 9 are equidistantly fixedly connected between the two first round steels 8.

[0022] It should be noted that each keel 6 requires two first round steels 8 and four second round steels 9, so that the keel 6 does not need to be prepared on site and can be prepared in advance for use.

[0023] Two ends of the four second round steels 9 are respectively fixed to the two first round steels 8 by welding.

[0024] It should be noted that the four second round steels 9 are welded between the two first round steels 8 at equal intervals, so that the keel 6 is more stable as a whole and has better supporting strength.

[0025] The wire mesh 7 is located on one side of the keel 6 , and the wire mesh 7 is fixed to the outside of the keel 6 by means of binding wires.

[0026] It should be noted that the assembled keel 6 is in a mesh-shaped structure as a whole, and then the wire mesh 7 is tied to one side of each keel 6 in turn, so that the wire mesh 7 covers the edge of the keel 6, the edge is tightly locked, and the edge is firmly tied, so that the mesh skeleton unit 2 is assembled.

[0027] The first round steel 8 and the second round steel 9 are both No. 6 round steels.

[0028] It should be noted that the first round steel 8 and the second round steel 9 both use No. 6 round steel as the keel 6, and the wire mesh 7 covers all edges of the keel 6 and is tied firmly, so that the mesh skeleton unit 2 does not need to be tied at the construction site and can be directly equipped and placed at the construction site for use.

[0029] In the description of the present invention, it should be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "the other end", "upper", "one side", "top", "inside", "front", "center", "both ends" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0030] In addition, the terms "first", "second", "third" and "fourth" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first", "second", "third" and "fourth" may explicitly or implicitly include at least one of such features.

[0031] In the present utility model, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the utility model according to the specific circumstances.

[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A device for intercepting concrete pouring in the core area of ​​a beam column, comprising a beam stirrup (1), characterized in that: A mesh frame unit (2) for intercepting concrete pouring is arranged inside the beam stirrup (1), and there are three mesh frame units (2). The inner wall of the beam stirrup (1) is located outside the mesh frame unit (2) and is evenly and fixedly connected with a first beam main reinforcement (3). A third beam main reinforcement (5) is arranged on the surface of the mesh frame unit (2) inside the beam stirrup (1). A wire mesh tying point (10) is formed at a point between the mesh frame unit (2) and the first beam main reinforcement (3). The mesh frame unit (2) includes a keel (6) and a steel mesh (7), and the steel mesh (7) is tied to the outside of the keel (6).

2. A beam-column core area concrete pouring interception device according to claim 1, characterized in that: The keel (6) is in the shape of a mesh as a whole, and comprises a first round steel (8) and a second round steel (9), wherein there are two first round steels (8) and the two first round steels (8) are symmetrically arranged, and there are four second round steels (9) and the four second round steels (9) are equidistantly fixedly connected between the two first round steels (8).

3. A beam-column core area concrete pouring interception device according to claim 2, characterized in that: The two ends of the four second round steels (9) are respectively fixed to the two first round steels (8) by welding.

4. A beam-column core area concrete pouring interception device according to claim 3, characterized in that: The steel wire mesh (7) is located on one side of the keel (6), and the steel wire mesh (7) is fixed to the outside of the keel (6) by means of binding wires.

5. A beam-column core area concrete pouring interception device according to claim 4, characterized in that: The first round steel (8) and the second round steel (9) are both No. 6 round steels.