A construction professional simulated grouting device

By using the fixing method between magnetic suction parts and iron bottom and the sealing design of sealing gaskets and elastic clamps in professional building simulation grouting devices, the alignment problem of demonstration tubes and cover plate sealing holes is solved, and the effective sealing of the slurry and the accuracy of simulated grouting process is achieved.

CN222719981UActive Publication Date: 2025-04-04刘振涛
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420409418.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2025-04-04
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

The existing building professional simulation grouting device cannot ensure that the demonstration tube is aligned with the sealing holes on the cover plate, causing the slurry to penetrate and affect the simulation results.

Method used

A professional building simulation grouting device was designed, and the demonstration cylinder was fixed on the base using the mating method of magnetic suction parts and iron bottom, and a sealing gasket and elastic clamp were installed at the connection between the cylinder cover and the demonstration cylinder to ensure the sealing of the demonstration tube and the cylinder cover, while avoiding the soil entering the passage that should not be entered through the rubber cover.

Benefits of technology

It effectively avoids slurry leakage, ensures the sealing and accuracy of the simulated grouting process, and improves the stability and convenience of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222719981U_ABST
    Figure CN222719981U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of architectural teaching, and proposes an architectural simulation grouting device, comprising a demonstration tube and a base, wherein the demonstration tube is arranged on the base, two matching magnetic suction parts are arranged on the base, the bottom end of the demonstration tube is fixedly connected with an iron bottom matching with the magnetic suction part, the top end of the demonstration tube is threadedly connected with a tube cover, the top end of the tube cover is provided with a first through hole, a demonstration tube is arranged inside the first through hole, a sealing gasket is arranged between the demonstration tube and the first through hole, the outer side wall of the sealing gasket is fixedly connected with the first through hole, the top end of the tube cover is fixedly connected with a material inlet matching with the first through hole, the top end of the tube cover is provided with two matching soil inlets, a closing cover is rotatably connected to the soil inlet, an elastic card block is fixedly connected to the closing cover, and a card groove matching with the elastic card block is arranged on the outer side wall of the tube cover, so as to achieve the purpose of ensuring that the demonstration tube and the tube cover are in a connected state and avoiding leakage of slurry.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of architectural professional teaching, and in particular to an architectural professional simulation grouting device. Background Art

[0002] Grouting is the process of pouring certain solidifying materials, such as cement, lime or other chemical materials into the foundation rock and soil within a certain range under the foundation to fill the cracks and pores in the rock and soil, prevent foundation leakage, and improve the integrity, strength and stiffness of the rock and soil. At present, in the teaching process of architectural majors, simulated grouting devices are mostly used to demonstrate the grouting process to students in order to improve students' understanding.

[0003] After searching, China disclosed a new type of construction professional simulation grouting device with patent publication number CN215911102U on February 25, 2022. It is roughly described as follows: an outer buffer pad is fixedly connected to the inner wall of the base, and a symmetrical adsorption block is fixedly connected to the inner wall of the outer buffer pad. A filling pad is sealed and connected between the two symmetrical adsorption blocks. The adsorption block is made of magnetic material, and the inner surface of the adsorption block is adsorbed and connected with a lower iron edge. The new type of construction professional simulation grouting device can quickly and firmly fix the installation position of the demonstration tube and the base through the lower iron edge set on the demonstration tube and the adsorption block set on the base, which not only facilitates the demonstration of the simulated grouting process, but also facilitates the disassembly between the demonstration tube, the base and the demonstration tube, and facilitates the rapid cleaning of the internal soil. At the same time, the demonstration tube is composed of two semicircular tubes clamped together to avoid contact between the flow channel and the soil, and is convenient for disassembly and cleaning of the internal grouting material, which greatly improves the cleaning efficiency of the grouting device and improves its convenience of use.

[0004] Although the above-mentioned prior art solution is convenient for quick cleaning of internal soil, the device places the demonstration tube into the demonstration cylinder, adds soil, and finally covers it with a cover. Therefore, it cannot ensure that the sealing holes on the demonstration tube and the cover are aligned, which easily leads to slurry leakage and affects the simulation results. Utility Model Content

[0005] 1. Technical issues to be solved

[0006] In view of the deficiencies of the prior art, the utility model provides a construction professional simulation grouting device to solve the problem mentioned in the background technology that the demonstration tube cannot be aligned with the sealing hole on the cover plate, which easily leads to slurry leakage and affects the simulation results.

[0007] (II) Technical solution

[0008] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a construction professional simulation grouting device, including a demonstration tube, including a base, the demonstration tube is arranged on the base, the base is provided with two matching magnetic suction parts, the bottom end of the demonstration tube is fixedly connected with an iron bottom matching with the magnetic suction part, the top end of the demonstration tube is threadedly connected with a tube cover, the top end of the tube cover is provided with a first through hole, a demonstration tube is provided inside the first through hole, a sealing gasket is provided between the demonstration tube and the first through hole, the outer side wall of the sealing gasket is fixedly connected with the first through hole, the top end of the tube cover is fixedly connected with a feeding port matching with the first through hole, the top end of the tube cover is provided with two matching soil inlets, the soil inlet is rotatably connected with a closing cover, the closing cover is fixedly connected with an elastic card block, the outer side wall of the tube cover is provided with a card groove matching with the elastic card block, and the feeding port is provided with a rubber cover.

[0009] By adopting the above technical scheme, the magnetic suction piece cooperates with the iron bottom to connect the demonstration tube to the base by magnetic suction, so as to improve the stability of the equipment. The demonstration tube is first plugged into the tube cover, and the tube cover is threadedly connected to the demonstration tube. The sealing gasket is used to improve the sealing between the demonstration tube and the tube cover. The soil inlet cooperates with the closing cover to facilitate adding soil to the inside of the demonstration tube after the tube cover is connected to the demonstration tube. The closing cover is rotated to make the elastic card block engage with the card groove, so as to achieve the purpose of closing the soil inlet, so as to ensure that the demonstration tube and the tube cover are in a connected state and avoid leakage of slurry. The rubber cover is used to prevent soil from entering the demonstration tube through the feed port when adding soil to the soil inlet.

[0010] Optionally, four limiting members cooperating with the demonstration tube are fixedly connected to the top of the base.

[0011] By adopting the above technical solution, the limiting member is used to limit the demonstration tube, so as to prevent the demonstration tube from shaking and tilting, thereby achieving the purpose of improving the stability of the equipment.

[0012] Optionally, two matching first handles are fixedly connected to the outer side wall of the demonstration tube, and two matching second handles are fixedly connected to the outer side wall of the base.

[0013] By adopting the above technical solution, the first handle is used to facilitate holding and lifting the demonstration tube, and the second handle is used to facilitate lifting the base and the demonstration tube at the same time when the demonstration tube is placed on the base, so as to facilitate holding and moving the device, thereby achieving the purpose of improving the flexibility of the device.

[0014] Optionally, a filling pad is provided between the base and the demonstration tube.

[0015] By adopting the above technical solution, the filling pad is used to fill the gap between the demonstration tube and the base to prevent soil from seeping out of the demonstration tube, thereby improving the sealing of the equipment and avoiding waste of materials.

[0016] Optionally, a conical anti-slip pad is fixedly connected to the bottom end of the base.

[0017] By adopting the above technical solution, the conical anti-skid pad is used to increase the friction between the base and the desktop, reducing the probability of the device sliding, thereby achieving the purpose of improving the stability of the device.

[0018] (III) Beneficial effects

[0019] In summary, the present invention includes at least one of the following beneficial technical effects:

[0020] 1. This construction professional simulated grouting device, the magnetic suction piece cooperates with the iron bottom, which is used to magnetically connect the demonstration tube to the base, so as to improve the stability of the equipment. First, the demonstration tube is plugged into the tube cover, and the tube cover is threadedly connected to the demonstration tube. The sealing gasket is used to improve the sealing between the demonstration tube and the tube cover. The soil inlet cooperates with the closing cover, which is used to add soil to the inside of the demonstration tube after the tube cover is connected to the demonstration tube. The closing cover is rotated to make the elastic block engage with the card slot, so as to achieve the purpose of closing the soil inlet, so as to ensure that the demonstration tube and the tube cover are in a connected state and avoid leakage of slurry. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a first side structural schematic diagram of the utility model;

[0022] Figure 2 This is a schematic diagram of the first cross-sectional structure of the utility model;

[0023] Figure 3 For this utility model Figure 2 A schematic diagram of the local enlarged structure at point A in the middle;

[0024] Figure 4 This is a schematic diagram of the second cross-sectional structure of the utility model;

[0025] Figure 5 For this utility model Figure 4 Schematic diagram of the local enlarged structure at point B in the middle.

[0026] In the figure: 1. Demonstration tube; 2. Base; 3. Magnetic element; 4. Iron bottom; 5. Tube cover; 6. Demonstration tube; 7. Sealing gasket; 8. Feed inlet; 9. Closing cover; 10. Elastic block; 11. Slot; 12. Rubber cover; 13. Limiting piece; 14. First handle; 15. Second handle; 16. Filling pad; 17. Conical anti-slip pad. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0028] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0029] Reference Figure 1-Figure 5 A construction professional simulation grouting device comprises a demonstration tube 1, comprising a base 2, the demonstration tube 1 is arranged on the base 2, two matching magnetic suction parts 3 are arranged on the base 2, the bottom end of the demonstration tube 1 is fixedly connected with an iron bottom 4 matching with the magnetic suction part 3, the top end of the demonstration tube 1 is threadedly connected with a tube cover 5, the top end of the tube cover 5 is provided with a first through hole, a demonstration tube 6 is arranged inside the first through hole, a sealing gasket 7 is arranged between the demonstration tube 6 and the first through hole, the outer side wall of the sealing gasket 7 is fixedly connected with the first through hole, the top end of the tube cover 5 is fixedly connected with a feeding port 8 matching with the first through hole, the top end of the tube cover 5 is provided with two matching soil inlets, a closing cover 9 is rotatably connected to the soil inlet, an elastic card block 10 is fixedly connected to the closing cover 9, and a sealing gasket 7 matching with the elastic card block 10 is arranged on the outer side wall of the tube cover 5 The card slot 11, the magnetic suction piece 3 cooperates with the iron bottom 4, and is used to magnetically connect the demonstration tube 1 to the base 2, so as to improve the stability of the equipment. First, the demonstration tube 6 is inserted into the tube cover 5, and the tube cover 5 is threadedly connected to the demonstration tube 1. The sealing gasket 7 is used to improve the sealing between the demonstration tube 6 and the tube cover 5. The soil inlet cooperates with the closing cover 9, which is used to add soil to the inside of the demonstration tube 1 after the tube cover 5 is connected to the demonstration tube 1. The closing cover 9 is rotated so that the elastic card block 10 is engaged with the card slot 11, so as to achieve the purpose of closing the soil inlet, so as to achieve the purpose of ensuring that the demonstration tube 6 and the tube cover 5 are in a connected state and avoiding the leakage of slurry. A rubber cover 12 is provided on the feed port 8. The rubber cover 12 is used to prevent soil from entering the demonstration tube 6 through the feed port when adding soil to the soil inlet.

[0030] Reference Figure 1 and Figure 2 The top of the base 2 is fixedly connected with four limiting members 13 that match the demonstration tube 1. The limiting members 13 are used to limit the demonstration tube 1 to prevent the demonstration tube 1 from shaking and tilting, thereby achieving the purpose of improving the stability of the equipment.

[0031] Reference Figure 1 and Figure 2Two matching first grips 14 are fixedly connected to the outer wall of the demonstration tube 1, and two matching second grips 15 are fixedly connected to the outer wall of the base 2. The first grip 14 is used to facilitate holding and lifting the demonstration tube 1, and the second grip 15 is used to facilitate simultaneously lifting the base 2 and the demonstration tube 1 when the demonstration tube 1 is placed on the base 2. This makes it easier to hold and move the device, thereby achieving the purpose of improving the flexibility of the device.

[0032] Reference Figure 4 A filling pad 16 is provided between the base 2 and the demonstration tube 1. The filling pad 16 is used to fill the gap between the demonstration tube 1 and the base 2 to prevent soil from seeping out of the demonstration tube 1, thereby improving the sealing of the equipment and avoiding waste of materials.

[0033] Reference Figure 1 and Figure 2 The bottom end of the base 2 is fixedly connected with a conical anti-skid pad 17, which is used to increase the friction between the base 2 and the desktop and reduce the probability of the device sliding, thereby achieving the purpose of improving the stability of the device.

[0034] In summary, the working principle and working process of the construction professional simulation grouting device are as follows: when in use, first, the magnetic suction piece 3 cooperates with the iron bottom 4 to magnetically connect the demonstration tube 1 to the base 2 to improve the stability of the equipment; first, the demonstration tube 6 is plugged into the tube cover 5, and the tube cover 5 is threadedly connected to the demonstration tube 1; the sealing gasket 7 is used to improve the sealing between the demonstration tube 6 and the tube cover 5; the soil inlet cooperates with the closing cover 9 to facilitate adding soil to the inside of the demonstration tube 1 after the tube cover 5 is connected to the demonstration tube 1; the closing cover 9 is rotated to make the elastic card block 10 engage with the card slot 11, so as to This achieves the purpose of closing the soil inlet, thereby ensuring that the demonstration tube 6 and the tube cover 5 are in a connected state and preventing the slurry from leaking out. The rubber cover 12 is used to prevent the soil from entering the demonstration tube 6 through the feed port when adding soil to the soil inlet. The limiter 13 is used to limit the demonstration tube 1 to prevent the demonstration tube 1 from shaking and tilting, thereby improving the stability of the equipment. The first handle 14 is used to facilitate the holding and lifting of the demonstration tube 1. The second handle 15 is used to facilitate the simultaneous lifting of the base 2 and the demonstration tube 1 when the demonstration tube 1 is placed on the base 2. This makes it easier to hold and move the equipment, thereby improving the flexibility of the equipment. The filling pad 16 is used to fill the gap between the demonstration tube 1 and the base 2 to prevent soil from seeping out of the demonstration tube 1, thereby improving the sealing of the equipment and avoiding waste of materials. The conical anti-skid pad 17 is used to increase the friction between the base 2 and the desktop to reduce the probability of the equipment sliding, thereby improving the stability of the equipment.

[0035] The above-mentioned embodiments only express the specific implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the utility model. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model.

Claims

1. A construction professional simulated grouting device, comprising a demonstration tube (1), characterized in that: The invention comprises a base (2), wherein the demonstration tube (1) is arranged on the base (2), and the base (2) is provided with two matching magnetic suction parts (3). The bottom end of the demonstration tube (1) is fixedly connected with an iron bottom (4) matching with the magnetic suction part (3). The top end of the demonstration tube (1) is threadedly connected with a tube cover (5). The top end of the tube cover (5) is provided with a first through hole. A demonstration tube (6) is arranged inside the first through hole. A sealing gasket (7) is arranged between the demonstration tube (6) and the first through hole. The outer wall of the sealing gasket (7) is fixedly connected with the first through hole. The top end of the tube cover (5) is fixedly connected with a feed port (8) matching with the first through hole. The top end of the tube cover (5) is provided with two matching soil inlets. A closing cover (9) is rotatably connected to the soil inlet. An elastic clamping block (10) is fixedly connected to the closing cover (9). A clamping groove (11) matching with the elastic clamping block (10) is arranged on the outer wall of the tube cover (5).

2. A construction professional simulated grouting device according to claim 1, characterized in that: The feed inlet (8) is provided with a rubber cover (12).

3. A construction professional simulated grouting device according to claim 1, characterized in that: Four limiting members (13) matching with the demonstration tube (1) are fixedly connected to the top end of the base (2).

4. A construction professional simulated grouting device according to claim 1, characterized in that: Two matching first handles (14) are fixedly connected to the outer side wall of the demonstration tube (1), and two matching second handles (15) are fixedly connected to the outer side wall of the base (2).

5. The construction professional simulated grouting device according to claim 1, characterized in that: A filling pad (16) is provided between the base (2) and the demonstration tube (1).

6. A construction professional simulated grouting device according to claim 1, characterized in that: A conical anti-slip pad (17) is fixedly connected to the bottom end of the base (2).

Citation Information

Patent Citations

  • Novel special grouting simulation device for building

    CN215911102U