Preheating device of tunnel furnace in front section of developing roller spraying process
By using a dual output shaft motor to drive the chain transmission system in the developing roller transmission system and using hydraulic cylinders to adjust the chain tightness, the looseness and jumping problems of the chain when the gears are meshed are solved, and the stable transmission and efficient preheating of the developing roller are achieved.
Patent Information
- Application Number
- CN202421345072.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2025-04-08
- Estimated Expiration
- 2034-06-12
AI Technical Summary
The existing developing roller transmission chains are prone to loosening and jumping when the gears are meshed, affecting the efficiency of transmission preheating.
A development roller spraying process front section tunnel furnace preheating device is designed, using a dual output shaft motor to drive the chain transmission, and the tightness of the chain is adjusted through the hydraulic cylinder to ensure stable meshing between the chain and the gear.
It effectively avoids the chain's jump when the gears rotate, ensures stable transmission and preheating of the developing roller, and improves the efficiency and reliability of the process.
Smart Images

Figure CN222724754U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of developing rollers, in particular to a tunnel furnace preheating device in the front section of a developing roller spraying process. Background Art
[0002] The developer roller is an important component in the printing device. The developer roller can provide toner to the surface of the photosensitive drum, thereby converting the electrostatic latent image on the surface of the photosensitive drum into a visible image.
[0003] In the production process of the developing roller, in order to enhance the bonding force between the metal core shaft and the conductive rubber outer layer, it is necessary to coat the surface of the core shaft with glue before assembling the core shaft and the conductive rubber layer, and the developing roller needs to be preheated before coating with glue, so as to facilitate the processing efficiency in the subsequent coating process. However, in the process of preheating the developing roller during transportation, the existing device usually requires an adapter to install the chain for transmitting the developing roller, but the transmission chain is prone to loosening and jumping when meshing with the gears, and is therefore prone to the risk of being out of gear meshing. Utility Model Content
[0004] The utility model provides a tunnel furnace preheating device for the front section of a developing roller spraying process, which solves the problem in the related art that the chain for transmitting the developing roller is difficult to adjust in tightness and easily jumps between gears, affecting the transmission preheating of the developing roller.
[0005] The technical solution of the utility model is as follows: it comprises two groups of supporting legs, and the side surfaces of the two groups of supporting legs close to each other are fixedly connected with the first cross bar and the first cross column, and the upper surfaces of the first cross bar and the first cross column are fixedly connected with two vertical columns, each group of the supporting legs and the upper ends of the vertical columns are fixedly connected with a cross plate, each group of the supporting legs and the vertical columns are fixedly connected with the second cross column on the side surfaces close to each other, and an adjustment mechanism is provided on the upper part of the supporting legs.
[0006] The adjustment mechanism includes a fixed block fixedly connected to the upper surface of each second horizontal column, and the side surfaces of the two groups of fixed blocks close to each other are rotatably connected to a rotating rod, and the outer surface of the rotating rod is fixedly connected to two first gears, and the outer surface of the left rotating rod is installed with a dual output shaft motor, and the two output shafts of the dual output shaft motor are fixedly connected to the rotating rod.
[0007] A fixing plate is fixedly connected to one side of the two second left cross columns that are close to each other, and a hydraulic cylinder is installed on the bottom surface of the fixing plate. Guide plates are fixedly connected to the bottom surfaces of the two second left cross columns, and guide grooves are provided on the outer surfaces of the guide plates. Slidable adjusting rods are provided on the inner walls of the two guide grooves, and the outer surfaces of the adjusting rods are hinged to the output ends of the hydraulic cylinders. The outer surfaces of the adjusting rods are rotatably connected to two second gears. Two chains are provided on the upper part of the supporting legs, and the chains are meshed with the first gear and the second gear.
[0008] Preferably, the upper surfaces of the two left second horizontal columns are fixedly connected with a mounting plate, and the left side of the mounting plate is fixedly connected with a connecting plate, and the upper surface of the connecting plate is fixedly connected to the bottom surface of the dual-output shaft motor. By setting the mounting plate, the connecting plate can be easily installed and fixed, and the dual-output shaft motor can be fixed through the connecting plate, thereby preventing the dual-output shaft motor from rotating and shaking during operation.
[0009] Preferably, two telescopic sleeves are fixedly connected to the bottom surface of the fixed plate, and the lower ends of the telescopic sleeves are hinged to the outer surface of the adjusting rod. By providing the telescopic sleeves, it is possible to better facilitate the limiting of the adjusting rod when it is lifted or lowered, thereby avoiding the risk of the adjusting rod being offset and tilted during the lifting process.
[0010] Preferably, the side surfaces of the two groups of support legs that are close to each other are fixedly connected with a third cross column, and the lower end of each support leg is fixedly connected with a support foot. By providing the third cross column, the stability of the overall device can be better improved, thereby preventing the overall device from shaking when preheating the developing roller and affecting the transportation of the developing roller.
[0011] Preferably, the upper surface of each of the horizontal plates is fixedly connected to a fixing frame, and the inner bottom wall of the fixing frame is fixedly connected to an electric push rod. By providing the fixing frame, the electric push rod can be more conveniently installed and fixed, and by providing the electric push rod, the developing roller storage and transportation component can be clamped.
[0012] Preferably, the output end of each of the electric push rods passes through the fixed frame on the same side and is fixedly connected to a clamping plate, and the clamping plate is made of a flexible material. By setting the clamping plate, it is possible to better facilitate the limiting clamping of the developing roller storage and transportation component, thereby facilitating the developing roller storage and transportation component to be in a horizontal position.
[0013] Preferably, the outer surfaces of the two chains are installed with placement blocks arranged at equal distances, and the outer surfaces of the two chains are installed with pushing plates arranged at equal distances. By setting the placement blocks, the developing roller storage and transportation components can be more easily placed stably, thereby enabling stable transportation of the developing roller.
[0014] Preferably, a preheating box is installed on one side where the two groups of columns are close to each other, and two protective plates are fixedly connected to the inner wall of the preheating box. By providing the preheating box, the developing roller can be preheated more conveniently, so that after the developing roller is preheated, it can be transferred to the subsequent gluing process for gluing, thereby improving the work efficiency of gluing the developing roller.
[0015] The working principle and beneficial effects of the utility model are:
[0016] 1. In the utility model, a dual-output shaft motor is provided and started. The two output shafts of the dual-output shaft motor drive the first gear to rotate through the rotating rod, so that the first gear drives the chain to transmit, and then the developing roller storage and transportation component can be transmitted through the chain, and the developing roller is transmitted to the preheating area for preheating. When the chain is easily loosened after installation and jumps when the first gear rotates, the hydraulic cylinder is started, and the output end of the hydraulic cylinder drives the adjusting rod and the two second gears to descend under the limiting action of the guide groove, so that the tightness of the chain can be adjusted, thereby avoiding the chain from jumping when the first gear rotates, and avoiding affecting the transportation of the developing roller. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The utility model is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0018] Figure 1 It is a three-dimensional structural schematic diagram of the overall device of the utility model;
[0019] Figure 2 It is a three-dimensional structural schematic diagram of the dual-output shaft motor of the utility model;
[0020] Figure 3 It is a three-dimensional structural schematic diagram of the hydraulic cylinder of the utility model;
[0021] Figure 4 It is a three-dimensional structural schematic diagram of the adjustment mechanism of the utility model.
[0022] In the figure: 1. supporting leg; 2. first cross bar and first cross column; 3. vertical column; 4. cross plate; 5. second cross column; 6. adjusting mechanism; 601. fixing block; 602. rotating rod; 603. first gear; 604. double output shaft motor; 605. fixing plate; 606. hydraulic cylinder; 607. guide plate; 608. guide groove; 609. adjusting rod; 6010. second gear; 6011. chain; 6012. mounting plate; 6013. connecting plate; 6014. telescopic sleeve; 7. third cross column; 8. supporting foot; 9. fixing frame; 10. electric push rod; 11. clamping plate; 12. placing block; 13. pushing plate; 14. preheating box; 15. protective plate. DETAILED DESCRIPTION
[0023] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] Example 1
[0025] like Figure 1 to Figure 4 As shown, this embodiment proposes a tunnel furnace preheating device for the front section of the developing roller spraying process, including two groups of supporting legs 1, the side surfaces of the two groups of supporting legs 1 close to each other are fixedly connected with a first cross bar and a first cross column 2, and the upper surfaces of the first cross bar and the first cross column 2 are fixedly connected with two vertical columns 3, each group of supporting legs 1 and the upper ends of the vertical columns 3 are fixedly connected with a cross plate 4, each supporting leg 1 and the side surfaces of the vertical columns 3 close to each other are fixedly connected with a second cross column 5, and an adjustment mechanism 6 is provided on the upper part of the supporting legs 1.
[0026] refer to Figures 1 to 4 The setting of the first cross bar and the first cross column 2 can better facilitate the stable assembly of the overall device, thereby improving the bearing capacity of the overall device and improving the stability of the overall device. The setting of the cross plate 4 and the second cross column 5 can better facilitate the installation of the transmission device and the clamping device, and can improve the stability of the overall device.
[0027] The side surfaces of the two groups of supporting legs 1 that are close to each other are fixedly connected with a third horizontal column 7, and the lower end of each supporting leg 1 is fixedly connected with a supporting foot 8. By setting the third horizontal column 7, the stability of the overall device can be better improved, thereby preventing the overall device from shaking when preheating the developing roller and affecting the transportation of the developing roller. The setting of the supporting foot 8 can better facilitate the placement and movement of the overall device, and can greatly improve the friction and contact force between the overall device and the ground, thereby greatly improving the stability of the overall device.
[0028] The upper surface of each horizontal plate 4 is fixedly connected to a fixing frame 9, and the inner bottom wall of the fixing frame 9 is fixedly connected to an electric push rod 10. By setting the fixing frame 9, the electric push rod 10 can be more conveniently installed and fixed, and by setting the electric push rod 10, the developing roller storage and transportation component can be clamped, so that the developing roller storage and transportation component can be stably transported to the preheating area, avoiding the developing roller from shifting and tilting in the preheating area, thereby avoiding affecting the preheating effect of the developing roller.
[0029] The output end of each electric push rod 10 passes through the fixed frame 9 on the same side and is fixedly connected to a clamping plate 11, and the clamping plate 11 is made of flexible material. By setting the clamping plate 11, it is easier to limit and clamp the developing roller storage and transportation components, so that the developing roller storage and transportation components can be in a horizontal position, avoiding tilting during transportation and affecting the subsequent preheating of the developing roller.
[0030] A preheating box 14 is installed on one side where the two groups of columns 3 are close to each other, and two protective plates 15 are fixedly connected to the inner wall of the preheating box 14. By setting up the preheating box 14, it is easier to preheat the developing roller, so that it is easier to transfer the developing roller to the subsequent gluing process for gluing after preheating, so as to improve the working efficiency of gluing the developing roller. The setting of the protective plate 15 can protect the heat and avoid excessive heat loss to increase cost loss.
[0031] The adjusting mechanism 6 includes a fixed block 601 fixedly connected to the upper surface of each second horizontal column 5, and the side surfaces of the two groups of fixed blocks 601 close to each other are rotatably connected to a rotating rod 602, and the outer surface of the rotating rod 602 is fixedly connected to two first gears 603, and the outer surface of the left rotating rod 602 is installed with a dual output shaft motor 604, and the two output shafts of the dual output shaft motor 604 are fixedly connected to the rotating rod 602.
[0032] In this embodiment, reference Figures 1 to 4 The setting of the fixed block 601 can better facilitate the stable rotation of the rotating rod 602, and a protective component is provided at the connection between the rotating rod 602 and the first gear 603, which can better facilitate the rotation of the first gear 603. By setting a dual-output shaft motor 604, the dual-output shaft motor 604 can operate intermittently, so that the developing roller in the preheating area can be uniformly preheated, and the subsequent gluing process can be intermittently operated for the taking time of the developing roller.
[0033] The upper surfaces of the two left second horizontal columns 5 are fixedly connected with a mounting plate 6012, and the left side of the mounting plate 6012 is fixedly connected with a connecting plate 6013, and the upper surface of the connecting plate 6013 is fixedly connected to the bottom surface of the dual-output shaft motor 604. By setting the mounting plate 6012, the connecting plate 6013 can be easily installed and fixed, and the dual-output shaft motor 604 can be fixed by the connecting plate 6013, thereby preventing the dual-output shaft motor 604 from rotating and shaking during operation, greatly improving the transmission effect of the dual-output shaft motor 604 on the transmission components, and greatly improving the work of the overall device on the transmission of the developing roller.
[0034] Example 2
[0035] like Figure 1 to Figure 4As shown, based on the same concept as the above-mentioned embodiment 1, this embodiment further proposes that a fixing plate 605 is fixedly connected to one side of the two second horizontal columns 5 on the left side that are close to each other, and a hydraulic cylinder 606 is installed on the bottom surface of the fixing plate 605, and the bottom surfaces of the two second horizontal columns 5 on the left side are fixedly connected to guide plates 607, and the outer surfaces of the guide plates 607 are provided with guide grooves 608, and the inner walls of the two guide grooves 608 are provided with slidable adjustment rods 609, and the outer surfaces of the adjustment rods 609 are hinged to the output ends of the hydraulic cylinders 606, and the outer surfaces of the adjustment rods 609 are rotatably connected to two second gears 6010, and two chains 6011 are provided on the upper part of the supporting leg 1, and the chains 6011 are meshed with the first gear 603 and the second gear 6010.
[0036] In this embodiment, reference Figures 1 to 4 When adjusting the tightness between the chain 6011 and the first gear 603 and the second gear 6010, by starting the hydraulic cylinder 606, the output end of the hydraulic cylinder 606 drives the adjusting rod 609 and the two second gears 6010 to descend under the limiting action of the guide groove 608, so as to adjust the tightness of the chain 6011, thereby avoiding the chain 6011 from jumping when the first gear 603 rotates, and avoiding affecting the transportation of the developing roller.
[0037] Two telescopic sleeves 6014 are fixedly connected to the bottom surface of the fixed plate 605, and the lower end of the telescopic sleeve 6014 is hinged to the outer surface of the adjusting rod 609. By setting the telescopic sleeve 6014, it is easier to limit the adjusting rod 609 when it is lifted or lowered, thereby avoiding the risk of the adjusting rod 609 being offset and tilted during the lifting process, greatly improving the use effect of the overall device and improving the stability of the overall device when in use.
[0038] The outer surfaces of the two chains 6011 are both installed with placement blocks 12 arranged at equal distances, and the outer surfaces of the two chains 6011 are both installed with pushing plates 13 arranged at equal distances. By setting the placement blocks 12, it is easier to stably place the developing roller storage and transportation components, thereby enabling stable transportation of the developing rollers, and by setting the pushing plates 13, it is easier to push the developing roller storage and transportation components for stable transportation, and the distance of the developing rollers during transportation can be controlled to avoid accumulation of the developing rollers during storage and transportation.
[0039] Working principle: When preheating and transporting the developing roller, firstly, the developing roller storage component is placed on the chain 6011, and the developing roller storage and transportation component is stably placed and pushed by the placement block 12 and the push plate 13. After placement, the electric push rod 10 is started, and the output end of the electric push rod 10 pushes the placement block 12 to clamp the developing roller storage and transportation component, thereby adjusting the horizontal position of the developing roller storage and transportation component. At this time, the dual-output shaft motor 604 is started, and the two output shafts of the dual-output shaft motor 604 drive the first gear 603 to rotate through the rotating rod 602, so that the first gear 603 drives the chain 6011 to transmit, and then it can The developing roller storage and transportation component is transported by chain 6011, and the developing roller is transported to the preheating area for preheating. After the preheating is completed, the developing roller can be transported to the subsequent gluing process for gluing. When the chain 6011 is easily loosened after installation and jumps when the first gear 603 rotates, the hydraulic cylinder 606 is started, and the output end of the hydraulic cylinder 606 drives the adjusting rod 609 and the two second gears 6010 to descend under the limiting action of the guide groove 608, so that the tightness of the chain 6011 can be adjusted, thereby avoiding the chain 6011 from jumping when the first gear 603 rotates, and avoiding affecting the transportation of the developing roller.
[0040] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. The tunnel furnace preheating device for the front section of the developing roller spraying process is characterized by: The invention comprises two groups of supporting legs (1), wherein the side surfaces of the two groups of supporting legs (1) close to each other are fixedly connected to a first cross bar and a first cross column (2), and the upper surfaces of the first cross bar and the first cross column (2) are fixedly connected to two upright columns (3), the upper ends of each group of supporting legs (1) and the upright columns (3) are fixedly connected to a cross plate (4), the side surfaces of each supporting leg (1) and the upright columns (3) close to each other are fixedly connected to a second cross column (5), and an adjusting mechanism (6) is provided on the upper part of the supporting legs (1); The adjustment mechanism (6) comprises a fixed block (601) fixedly connected to the upper surface of each second horizontal column (5); the side surfaces of the two sets of fixed blocks (601) close to each other are rotatably connected to a rotating rod (602), and the outer surface of the rotating rod (602) is fixedly connected to two first gears (603); the outer surface of the left rotating rod (602) is installed with a dual-output shaft motor (604), and the two output shafts of the dual-output shaft motor (604) are fixedly connected to the rotating rod (602); A fixing plate (605) is fixedly connected to one side of the two second transverse columns (5) on the left side that are close to each other, and a hydraulic cylinder (606) is installed on the bottom surface of the fixing plate (605). The bottom surfaces of the two second transverse columns (5) on the left side are fixedly connected to guide plates (607), and the outer surfaces of the guide plates (607) are provided with guide grooves (608). The inner walls of the two guide grooves (608) are provided with slidable adjustment rods (609), and the outer surfaces of the adjustment rods (609) are hinged to the output ends of the hydraulic cylinders (606). The outer surfaces of the adjustment rods (609) are rotatably connected to two second gears (6010). Two chains (6011) are provided on the upper part of the support leg (1), and the chains (6011) are meshed with the first gear (603) and the second gear (6010).
2. The preheating device for the front tunnel furnace of the developing roller spraying process according to claim 1 is characterized in that: The upper surfaces of the two left second transverse columns (5) are fixedly connected to a mounting plate (6012), and the left side surface of the mounting plate (6012) is fixedly connected to a connecting plate (6013), and the upper surface of the connecting plate (6013) is fixedly connected to the bottom surface of the dual-output shaft motor (604).
3. The preheating device for the front section tunnel furnace of the developing roller spraying process according to claim 1 is characterized in that: Two telescopic sleeves (6014) are fixedly connected to the bottom surface of the fixed plate (605), and the lower ends of the telescopic sleeves (6014) are hinged to the outer surface of the adjustment rod (609).
4. The preheating device for the front tunnel furnace of the developing roller spraying process according to claim 1, characterized in that: The side surfaces of the two groups of support legs (1) that are close to each other are fixedly connected to a third cross column (7), and the lower end of each support leg (1) is fixedly connected to a support foot (8).
5. The preheating device for the front section tunnel furnace of the developing roller spraying process according to claim 1 is characterized in that: The upper surface of each of the transverse plates (4) is fixedly connected to a fixing frame (9), and the inner bottom wall of the fixing frame (9) is fixedly connected to an electric push rod (10).
6. The preheating device for the front tunnel furnace of the developing roller spraying process according to claim 5, characterized in that: The output end of each electric push rod (10) passes through the fixed frame (9) on the same side and is fixedly connected to a clamping plate (11), and the clamping plate (11) is made of a flexible material.
7. The preheating device for the front tunnel furnace of the developing roller spraying process according to claim 1, characterized in that: The outer surfaces of the two chains (6011) are both installed with placement blocks (12) arranged at equal distances, and the outer surfaces of the two chains (6011) are both installed with pushing plates (13) arranged at equal distances.
8. The preheating device for the front tunnel furnace of the developing roller spraying process according to claim 1, characterized in that: A preheating box (14) is installed on one side of the two groups of columns (3) close to each other, and two protective plates (15) are fixedly connected to the inner wall of the preheating box (14).