A slope operating platform for water conservancy construction

By designing an adjustable water conservancy construction slope operation table, the problem that traditional operating tables are difficult to meet slope operation needs is solved, the operation convenience and safety are improved, and the transportation and storage process is simplified.

CN222731038UActive Publication Date: 2025-04-08SICHUAN XINPING CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421425016.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-20
Publication Date
2025-04-08
Estimated Expiration
2034-06-20

AI Technical Summary

Technical Problem

Traditional fixed operating tables are difficult to meet the needs of slope operations in water conservancy construction, and there are problems of inconvenience in operation and safety hazards.

Method used

A slope operation table for water conservancy construction is designed. The tabletop is supported by four sleeves and a first screw. The protruding length of the first screw can be adjusted by rotary engaging, and the support plate is fitted with the slope to ensure the level of the tabletop. At the same time, guardrails are arranged around the top of the countertop to prevent construction workers from falling.

Benefits of technology

The operating table can be flexibly adjusted to meet the needs of different slopes, improves the convenience and safety of construction operations, reduces the space occupied by the operating table, and is easy to transport and store.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222731038U_ABST
    Figure CN222731038U_ABST
Patent Text Reader

Abstract

The present application provides a slope operating platform for water conservancy construction, which relates to the field of construction operating platforms. The slope operating platform for water conservancy construction includes a table top, three sides of the top of the table top are installed with guardrails, and the bottom of the table top is symmetrically provided with four adjustment components to ensure the level of the table top; the adjustment component includes a sleeve installed at the bottom of the table top and provided with a thread inside, a first screw connected to the sleeve by thread, and a support plate movably connected to the bottom of the first screw, and the support plate is rotatably connected to the first screw. The slope operating platform for water conservancy construction can ensure the level of the table top by setting the adjustment component to meet the needs of slope construction, and the guardrails arranged around the top of the table top can improve the safety during use, and the use effect is good. At the same time, the operating platform components are connected in a movable connection manner, which is simple and efficient to install, and is also conducive to the removal of the sleeve and guardrails, so as to reduce the space occupied by the operating platform as a whole, which is conducive to transportation and storage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of construction operating platforms, and in particular to a slope operating platform for water conservancy construction. Background Art

[0002] Water conservancy construction refers to the work of building water conservancy projects in accordance with the requirements of the design for engineering structure, quantity, quality, progress and cost. It includes construction preparation, construction technology and construction management. Its task is to transform the design results into engineering entities at the construction site according to the requirements of water conservancy project construction, and to continuously, comprehensively and scientifically organize, plan, coordinate and control the construction process in order to achieve the goal of engineering construction.

[0003] During water conservancy construction, it is often necessary to perform operations on slopes, such as concrete pouring, slope leveling, laying waterproof materials, etc. However, due to the different inclination angles and heights of the slopes, traditional fixed operating platforms are difficult to meet construction needs, and there are problems such as inconvenient operation and potential safety hazards. Therefore, those skilled in the art provide a slope operating platform for water conservancy construction to solve the problems raised in the above background technology. Utility Model Content

[0004] 1. Technical issues to be resolved

[0005] In view of the deficiencies in the prior art, the present application provides a slope operating platform for water conservancy construction, which solves the problems mentioned in the above background technology.

[0006] (II) Technical solution

[0007] To achieve the above objectives, the present application is implemented through the following technical solutions: A slope operating platform for water conservancy construction, comprising a table top, three sides of the top of the table top are equipped with guardrails, and the bottom of the table top is symmetrically and equidistantly provided with four adjustment components to ensure the level of the table top;

[0008] The adjustment assembly comprises a sleeve installed at the bottom of the table and provided with threads inside, a first screw rod threadedly connected to the sleeve, and a support plate movably connected to the bottom of the first screw rod, wherein the support plate is rotatably connected to the first screw rod.

[0009] By adopting the above technical solution, the table top is supported by four sleeves and the first screw, the first screw is connected to the sleeve by screwing, the extension length of the first screw can be adjusted by rotating the first screw, and the support plate at the bottom of the first screw fits the slope surface, and the extension length of the first screw can be adjusted to ensure the level of the table top to meet the needs of slope construction. When the table top is used for construction workers to stand and operate, the guardrail is set around the top of the table top to prevent construction workers from accidentally falling, which improves safety during use and has a good use effect.

[0010] Preferably, the top of the sleeve is fixedly connected with a second screw rod, and a threaded hole matched with the second screw rod is provided inside the bottom side of the table top, and the second screw rod is screwed and connected with the adjacent threaded hole.

[0011] By adopting the above technical solution, the sleeve is rotated so that the second screw is screwed and connected with the threaded hole, and the installation of the sleeve and the tabletop can be completed. The installation work is simple and the connection is stable. At the same time, the movable connection method is convenient for the removal of the sleeve, so as to reduce the external space occupied by the entire operating table, which is convenient for transportation and storage.

[0012] Preferably, three insertion rods are fixedly connected to the bottom of the guardrail at equal distances, and slots for matching with the insertion rods are provided inside the top side of the table top, and the insertion rods are plugged into adjacent slots.

[0013] By adopting the above technical solution, the guardrail is installed on the tabletop through the cooperation and connection between the plug rod and the slot, making the disassembly and assembly of the guardrail simple and convenient.

[0014] Preferably, ground pins are inserted into the interior of the support plates, the bottom of the ground pins is configured as a conical structure, and the top is fixedly connected with a pull ring.

[0015] By adopting the above technical solution, the ground latch can be inserted into the slope according to the use requirements to enhance the stability of the support plate placement, so as to ensure the stability of the operating table when in use.

[0016] Preferably, the bottom of the support plate is provided with serrations.

[0017] By adopting the above technical solution, the friction between the support plate and the slope surface can be increased to prevent the operating table from sliding.

[0018] Preferably, the table top and guardrail are both made of aluminum alloy.

[0019] By adopting the above technical solution, the aluminum alloy table top and guardrail are lighter in weight, which facilitates the handling and transportation of the operating table.

[0020] (III) Beneficial effects

[0021] The present application provides a slope operating platform for water conservancy construction. The beneficial effects are as follows:

[0022] 1. The slope operation table for water conservancy construction is supported by four sleeves and a first screw rod. The first screw rod is connected to the sleeve by screwing. The extension length of the first screw rod can be adjusted by rotating the first screw rod. After the support plate at the bottom of the first screw rod is fitted with the slope surface, the extension length of the first screw rod can be adjusted to ensure the levelness of the table surface to meet the needs of slope construction. When the table surface is used for construction workers to stand and operate, a guardrail is set around the top of the table surface to prevent construction workers from accidentally falling, thereby improving safety during use and achieving good use effects.

[0023] 2. The slope operating platform used for water conservancy construction has sleeves, guardrails and the platform connected to it in a movable manner. The installation is simple and efficient, and it is also convenient for the removal of the sleeves and guardrails to reduce the space occupied by the operating platform as a whole, which is convenient for transportation and storage. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a schematic diagram of the first overall structure of this application.

[0025] Figure 2 This is a second overall structural diagram of the present application.

[0026] Figure 3 This is a schematic diagram of the third overall structure of this application.

[0027] Figure 4 This is a schematic diagram of the structure of the table and adjustment components illustrated in this application.

[0028] In the figure: 1, table top; 2, sleeve; 3, first screw; 4, support plate; 5, guardrail; 6, plug rod; 7, second screw; 8, threaded hole; 9, ground pin; 10, serration; 11, slot. DETAILED DESCRIPTION

[0029] The present application is further described in detail below through drawings and examples.

[0030] Reference Figure 1 and Figure 2The embodiment of the present application provides a slope operation platform for water conservancy construction, including a tabletop 1, a top of the tabletop 1, three sides are equipped with guardrails 5, and four adjustment components are symmetrically arranged at the bottom to ensure the level of the tabletop 1. The adjustment component includes: a sleeve 2 provided at the bottom of the tabletop 1 and having a thread inside, a first screw 3 threadedly connected to the sleeve 2, and a support plate 4 movably connected to the bottom of the first screw 3, and the support plate 4 is rotatably connected to the first screw 3. Specifically, the tabletop 1 is supported by four sleeves 2 and the first screw 3, and the first screw 3 is connected to the sleeve 2 in a screwing manner. The extension length of the first screw 3 can be adjusted by rotating the first screw 3. After the support plate 4 at the bottom of the first screw 3 is in contact with the slope, the extension length of the first screw 3 can be adjusted to ensure the level of the tabletop 1 to meet the needs of slope construction. When the tabletop 1 is used for construction personnel to stand and operate, the guardrail 5 is arranged around the top of the tabletop 1, which can be used to prevent construction personnel from accidentally falling, improve the safety during use, and have a good use effect.

[0031] Reference Figure 1 , Figure 2 and Figure 3 The top of the sleeve 2 is fixedly connected with a second screw 7, and the bottom of the table 1 is provided with a threaded hole 8 that cooperates with the second screw 7. The second screw 7 is screwed together with the adjacent threaded hole 8. Specifically, the sleeve 2 is rotated so that the second screw 7 is screwed together with the threaded hole 8, and the installation of the sleeve 2 and the table 1 can be completed. The installation work is simple and the connection is stable. At the same time, the use of a movable connection method is conducive to the removal of the sleeve 2, so as to reduce the external space occupied by the entire operating table, which is convenient for transportation and storage.

[0032] Reference Figure 1 , Figure 2 , Figure 3 and Figure 4 Three plug rods 6 are equidistantly fixedly connected to the bottom of the guardrail 5, and a slot 11 is provided inside the top side of the table top 1 to cooperate with the plug rod 6. The plug rod 6 is plugged into the adjacent slot 11. Specifically, the guardrail 5 is installed with the table top 1 through the cooperation between the plug rod 6 and the slot 11, which makes the disassembly and assembly of the guardrail 5 simple and convenient.

[0033] Reference Figure 2 The bottom of the support plate 4 is provided with saw teeth 10, which are used to increase the friction between the support plate 4 and the slope surface to prevent the operating table from sliding. A ground pin 9 is inserted into the support plate 4. The bottom of the ground pin 9 is set as a cone structure, and a pull ring is fixedly connected to the top. The ground pin 9 can be inserted into the slope surface according to the use requirements to enhance the stability of the support plate 4 and ensure the stability of the operating table when it is used.

[0034] The table top 1 and the guardrail 5 are both made of aluminum alloy. The aluminum alloy table top 1 and the guardrail 5 are light in weight, which facilitates the handling and transportation of the operating table.

[0035] Working principle:

[0036] The table top 1 is supported by four sleeves 2 and a first screw 3. The first screw 3 is connected to the sleeve 2 by screwing. The extension length of the first screw 3 can be adjusted by rotating the first screw 3. After the support plate 4 at the bottom of the first screw 3 is fitted with the slope, the extension length of the first screw 3 can be adjusted to ensure the levelness of the table top 1 to meet the needs of slope construction. When the table top 1 is used for construction workers to stand and operate, the guardrail 5 is set around the top of the table top 1 to prevent construction workers from accidentally falling, thereby improving safety during use and having a good use effect.

[0037] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. A slope operation platform for water conservancy construction, comprising a platform (1), characterized in that: Guardrails (5) are installed on three sides of the top of the table top (1), and four adjustment components for ensuring the levelness of the table top (1) are symmetrically arranged at equal distances on the bottom of the table top (1); The adjustment assembly comprises a sleeve (2) installed at the bottom of the table (1) and having a thread inside, a first screw rod (3) threadedly connected to the sleeve (2), and a support plate (4) movably connected to the bottom of the first screw rod (3), wherein the support plate (4) is rotatably connected to the first screw rod (3).

2. A slope operating platform for water conservancy construction according to claim 1, characterized in that: The top of the sleeve (2) is fixedly connected with a second screw rod (7), and the bottom side of the table top (1) is provided with a threaded hole (8) that cooperates with the second screw rod (7), and the second screw rod (7) is screwed and connected with the adjacent threaded hole (8).

3. A slope operating platform for water conservancy construction according to claim 2, characterized in that: The bottom of the guardrail (5) is fixedly connected with three insertion rods (6) at equal intervals, and the top side of the table top (1) is provided with slots (11) that cooperate with the insertion rods (6), and the insertion rods (6) are plugged into adjacent slots (11).

4. The slope operation platform for water conservancy construction according to claim 3 is characterized by: The support plates (4) are all penetrated by ground pins (9), the bottom of the ground pins (9) is arranged as a conical structure, and the top is fixedly connected with a pull ring.

5. The slope operation platform for water conservancy construction according to claim 4, characterized in that: The bottom of each support plate (4) is provided with saw teeth (10).