Auxiliary pipeline laying device

By designing a pipeline auxiliary laying device, the slide rail and electric push rod drive the slide plate to slide automatically, the pipeline is automatically connected, which solves the problem of large workload during manual docking and improves the laying efficiency.

CN222746748UActive Publication Date: 2025-04-11SHAANXI ZHONGZHOU COMM CONSTR ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202421612321.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2025-04-11
Estimated Expiration
2034-07-09

AI Technical Summary

Technical Problem

During the pipeline laying process, it is necessary to manually apply force to adjacent pipelines to achieve close contact, resulting in a significant increase in the workload of staff.

Method used

A pipe auxiliary laying device is designed, including a docking mechanism, which consists of a slide rail, an electric push rod, a slide plate, an adjustment assembly, a curved plate, an anti-slip pad and a positioning assembly. The slide plate is driven to slide through an electric push rod to drive the arc plate and the pipe movement to achieve automatic docking of the pipe.

Benefits of technology

It reduces the need to manually exert force on the pipeline, make adjacent pipelines in close contact, reduces the workload of workers, and improves the efficiency of pipeline laying.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222746748U_ABST
    Figure CN222746748U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pipeline laying, in particular to an auxiliary pipeline laying device which comprises a butt joint mechanism, the butt joint mechanism comprises a sliding rail, two electric push rods, two sliding plates, two adjusting assemblies, two arc-shaped plates, two non-slip mats and a positioning assembly, and two pipelines needing to be in butt joint are placed on the two arc-shaped plates respectively; adjusting assemblies are adjusted to enable the positioning assemblies to be aligned with each other, two sliding plates are driven to slide in the opposite directions through operation of two electric push rods, the two sliding plates drive the two arc-shaped plates and the two pipelines to move in the opposite directions, and when the two pipelines make contact with each other, the two electric push rods stop operating; by means of the structure, the problems that after the pipelines are hoisted in an installation site, when the two adjacent pipelines are in butt joint, acting force needs to be manually applied to the pipelines, the adjacent pipelines make close contact, and the workload of workers is greatly increased are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline laying, in particular to a pipeline auxiliary laying device. Background Art

[0002] Municipal pipelines are an important part of urban infrastructure, directly related to the normal operation of the city and the quality of life of residents. Auxiliary devices are usually used in the pipeline laying process. Usually, a crane is used to lift the pipeline and place it in an excavated trench. The crane is large in size and will take up more construction space.

[0003] The prior art CN220165637U discloses a municipal pipe network auxiliary laying device, including a connecting box, wherein rotatable spiral rods are symmetrically arranged on both sides of the lower end of the connecting box, and the two spiral rods are driven by a motor to realize synchronous rotation, and the bottom of the two spiral rods are respectively connected to a hanging frame, and a pair of relatively movable clamping arms are arranged at the lower end of the hanging frame, and a limit piece for limiting the rotation of the hanging frame is arranged at the upper end of the hanging frame. The two spiral rods are driven to rotate by the motor, and the hanging frame drives the clamping arm to move up or down under the restriction of the limit piece, without using large equipment such as a crane, thereby reducing the occupation of construction space.

[0004] However, in the above structure, after the pipelines are hoisted at the installation site, when two adjacent pipelines are butt-jointed, it is necessary to manually apply force to the pipelines to make the adjacent pipelines in close contact, which greatly increases the workload of the staff. Utility Model Content

[0005] The utility model aims to provide a pipeline auxiliary laying device, which solves the problem that after the pipelines are hoisted at the installation site, when two adjacent pipelines are butt-jointed, manual force needs to be applied to the pipelines to make the adjacent pipelines contact closely, which greatly increases the workload of the staff.

[0006] To achieve the above-mentioned purpose, the utility model provides a pipeline auxiliary laying device, including a docking mechanism, which includes a slide rail, two electric push rods, two slide plates, two adjustment components, two arc plates, two anti-slip pads and a positioning component. The two electric push rods are relatively arranged inside the slide rail, the two slide plates are fixedly connected to the output ends of the two electric push rods, and are respectively located inside the slide rail, the two adjustment components are respectively arranged above the two slide plates, the two arc plates are respectively arranged above the two adjustment components, the two anti-slip pads are respectively fixedly connected to the two arc plates, and are respectively located on the inner surfaces of the two arc plates, and the positioning component is arranged on the outer side wall of the arc plate.

[0007] Wherein, the adjustment assembly includes a cylinder, two adjustment rods and two springs, the cylinder is fixedly connected to the slide and is located above the slide, the arc plate is fixedly connected to the output end of the cylinder and is located above the cylinder, the two adjustment rods are fixedly connected between the slide and the arc plate, and the two adjustment rods are relatively located at two ends of the slide, and the two springs are respectively mounted on the outer side walls of the two adjustment rods.

[0008] Wherein, the positioning assembly includes a mounting block, a positioner, a connecting block and an auxiliary plate, the mounting block is fixedly connected to the arc plate and is located on the outer side wall of the arc plate, the positioner is fixedly connected to the mounting block and is located on the outer side wall of the mounting block, the connecting block is fixedly connected to the arc plate away from the positioner and is located on the outer side wall of the arc plate, and the auxiliary plate is fixedly connected to the connecting block and is located on the outer side wall of the connecting block.

[0009] Wherein, the pipeline auxiliary laying device also includes four connecting rods and four pulleys, the four connecting rods are fixedly connected to the slide rails and are respectively located below the slide rails, and the four pulleys are rotatably connected to the four connecting rods and are respectively located below the slide rails.

[0010] Wherein, the pipeline auxiliary laying device also includes a protection mechanism, and the protection mechanism is arranged above the slide rail.

[0011] Wherein, the protective mechanism includes two first covering plates, two first sliding plates, a second covering plate and a second sliding plate, the two first covering plates are fixedly connected to the two ends of the slide rail, the two first sliding plates are respectively fixedly connected to the two slides, and are respectively slidably connected to the two first covering plates, the second covering plate is slidably connected to the second sliding plate, and are respectively fixedly connected to the two slides, and are located between the two slides.

[0012] The utility model provides a pipeline auxiliary laying device, which places two pipelines that need to be butt-jointed on two arc plates respectively, adjusts the adjustment components to align the positioning components with each other, operates the two electric push rods to drive the two slide plates to slide in relative directions respectively, and the two slide plates drive the two arc plates and the two pipelines to move in relative directions. When the two pipelines contact each other, the two electric push rods stop operating, and the operator can butt-join the two pipelines at this time. The above structure solves the problem that after the pipelines are hoisted at the installation site, when the two adjacent pipelines are butt-jointed, manual force needs to be applied to the pipelines to make the adjacent pipelines contact closely, which greatly increases the workload of the staff. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0014] Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the utility model.

[0015] Figure 2 yes Figure 1 Enlarged view of point A in the middle.

[0016] Figure 3 yes Figure 1 Enlarged view of point B in the middle.

[0017] Figure 4 It is a schematic diagram of the overall structure of the second embodiment of the utility model.

[0018] Figure 5 It is a schematic structural diagram of the first telescopic plate and the second telescopic plate of the second embodiment of the utility model.

[0019] Figure 6 It is a structural schematic diagram of the third telescopic plate of the second embodiment of the utility model.

[0020] 101-slide rail, 102-electric push rod, 103-slide plate, 104-arc plate, 105-anti-slip pad, 106-cylinder, 107-adjusting rod, 108-spring, 109-mounting block, 110-positioner, 111-connecting block, 112-auxiliary plate, 113-connecting rod, 114-pulley, 201-first covering plate, 202-first sliding plate, 203-second covering plate, 204-second sliding plate. DETAILED DESCRIPTION

[0021] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0022] First embodiment

[0023] See also Figure 1 to Figure 3 , Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the utility model. Figure 2 yes Figure 1 Enlarged view of point A in the middle. Figure 3 yes Figure 1 Enlarged view of point B in the middle.

[0024] The utility model provides a pipeline auxiliary laying device: comprising a docking mechanism, the docking mechanism comprising a slide rail 101, two electric push rods 102, two slide plates 103, two adjustment components, two arc plates 104, two anti-skid pads 105, four connecting rods 113 and four pulleys 114, the adjustment component comprising a cylinder 106, two adjustment rods 107 and two springs 108, the positioning component comprising a mounting block 109, a positioner 110, a connecting block 111 and an auxiliary plate 112, and the above structure solves the problem that after the pipeline is hoisted at the installation site, when two adjacent pipelines are docked, it is still necessary to manually apply a force to the pipeline to make the adjacent pipelines in close contact, which greatly increases the workload of the staff.

[0025] According to a specific implementation, the two electric push rods 102 are relatively arranged inside the slide rail 101, the two slide plates 103 are respectively fixedly connected to the output ends of the two electric push rods 102 and are respectively located inside the slide rail 101, the two adjustment components are respectively arranged above the two slide plates 103, the two arc plates 104 are respectively arranged above the two adjustment components, the two anti-slip pads 105 are respectively fixedly connected to the two arc plates 104 and are respectively located on the inner surfaces of the two arc plates 104, the positioning component is arranged on the outer side wall of the arc plate 104, and the two pipes to be connected are respectively placed on the two On the arc plate 104, the adjustment component is adjusted to align the positioning components with each other, and the two electric push rods 102 are operated to drive the two slide plates 103 to slide in relative directions respectively. The two slide plates 103 drive the two arc plates 104 and the two pipes to move in relative directions. When the two pipes are in contact with each other, the two electric push rods 102 stop operating. At this time, the operator can dock the two pipes. The above structure solves the problem that after the pipes are hoisted at the installation site, when the two adjacent pipes are docked, manual force needs to be applied to the pipes to make the adjacent pipes in close contact, which greatly increases the workload of the staff.

[0026] Among them, the cylinder 106 is fixedly connected to the slide plate 103 and is located above the slide plate 103, the arc plate 104 is fixedly connected to the output end of the cylinder 106 and is located above the cylinder 106, the two adjusting rods 107 are fixedly connected between the slide plate 103 and the arc plate 104, and the two adjusting rods 107 are relatively located at the two ends of the slide plate 103, the two springs 108 are respectively sleeved on the outer side walls of the two adjusting rods 107, the adjusting rod 107 is composed of two rods that can slide relative to each other, when the heights of the two pipelines are inconsistent, by driving the cylinder 106 to operate, the cylinder 106 drives the arc plate 104 to move in the vertical direction, and the arc plate 104 drives the adjusting rod 107 to contract or extend, and the arc plate 104 and the pipeline are supported by the two adjusting rods 107 and the two springs 108.

[0027] The mounting block 109 is fixedly connected to the arc plate 104 and is located on the outer side wall of the arc plate 104. The positioner 110 is fixedly connected to the mounting block 109 and is located on the outer side wall of the mounting block 109. The connecting block 111 is fixedly connected to the arc plate 104 away from the positioner 110 and is located on the outer side wall of the arc plate 104. The auxiliary plate 112 is fixedly connected to the connecting block 111 and is located on the outer side wall of the connecting block 111. The mounting block 109 is used to install the positioner 110. The positioner 110 can be selected from a A laser generator, the connecting block 111 is used to connect the auxiliary plate 112. When the two arc plates 104 are of the same height, the light beam generated by the positioner 110 can be irradiated onto the auxiliary plate 112. When the two arc plates 104 need to be adjusted, the positioner 110 is turned on to drive the cylinder 106 on one side of the positioner 110 to operate. The cylinder 106 drives the arc plate 104 and the positioner 110 to move vertically. When the light beam emitted by the positioner 110 irradiates the auxiliary plate 112, the cylinder 106 is stopped. At this time, the pipes on the arc plates 104 are of the same height. Among them, the four connecting rods 113 are fixedly connected to the slide rails 101 and are respectively located under the slide rails 101. The four pulleys 114 are rotatably connected to the four connecting rods 113 and are respectively located under the slide rails 101. The connecting rods 113 are used to connect the pulleys 114 and the slide rails 101. When movement is required, the slide rails 101 are pulled and the pulleys 114 slide in the trench, which facilitates the overall movement of the pipeline auxiliary laying device.

[0028] When using the utility model to install a steel structure positioning bracket, the two pipes to be butted are placed on the two arc plates 104 respectively, the positioner 110 is turned on, and the cylinder 106 on one side of the positioner 110 is driven to operate, and the cylinder 106 drives the arc plate 104, the positioner 110 and the pipe to move in the vertical direction. When the light beam emitted from the positioner 110 irradiates the auxiliary plate 112, the cylinder 106 is stopped. At this time, the two pipes are at the same height, and the two electric push rods 102 are driven to operate. The two electric push rods 102 drive the two slides 103 to move in relative directions. When the two pipes contact each other, the two electric push rods 102 stop operating. At this time, the operator can butt the two pipes, which solves the problem that after the pipes are hoisted at the installation site, when the two adjacent pipes are butt-jointed, manual force needs to be applied to the pipes to make the adjacent pipes in close contact, which greatly increases the workload of the staff.

[0029] Second embodiment

[0030] See also Figures 4 to 6 , Figure 4 It is a schematic diagram of the overall structure of the second embodiment of the utility model. Figure 5 It is a schematic structural diagram of the first telescopic plate and the second telescopic plate of the second embodiment of the utility model. Figure 6 It is a structural schematic diagram of the third telescopic plate of the second embodiment of the utility model.

[0031] On the basis of the first embodiment, a pipeline auxiliary laying device of the utility model further includes a protection mechanism, which includes two first cover plates 201 , two first sliding plates 202 , a second cover plate 203 and a second sliding plate 204 .

[0032] According to a specific implementation, the protection mechanism is disposed above the slide rail 101 , and is used to prevent sand and gravel in the ditch from falling into the slide rail 101 and affecting the normal sliding of the slide plate 103 .

[0033] Among them, the two first covering plates 201 are fixedly connected to the two ends of the slide rail 101, the two first sliding plates 202 are fixedly connected to the two slide plates 103 respectively, and are slidably connected to the two first covering plates 201 respectively, the second covering plate 203 and the second sliding plate 204 are slidably connected, and are fixedly connected to the two slide plates 103 respectively, and are located between the two slide plates 103. When the two electric push rods 102 drive the two slide plates 103 to slide in relative directions, the two first sliding plates 202 respectively connected to the two slide plates 103 slide and extend relative to the two first covering plates 201. At the same time, since the two slide plates 103 move in relative directions, the second covering plates 203 and the second sliding plates 204 are compressed. Regardless of whether the two slide plates 103 move in relative or opposite directions, there is always a shield above the slide rail 101 to prevent sand and gravel in the ditch from falling into the slide rail 101 and affecting the normal sliding of the slide plate 103.

[0034] What is disclosed above is only one or more preferred embodiments of the present application, and cannot be used to limit the scope of rights of the present application. Ordinary technicians in this field can understand that all or part of the processes of implementing the above embodiments and equivalent changes made according to the claims of the present application are still within the scope covered by the present application.

Claims

1. A pipeline auxiliary laying device, characterized in that: It includes a docking mechanism, which includes a slide rail, two electric push rods, two slide plates, two adjustment components, two arc plates, two anti-slip pads and a positioning component. The two electric push rods are relatively arranged inside the slide rail, the two slide plates are fixedly connected to the output ends of the two electric push rods, and are respectively located inside the slide rail, the two adjustment components are respectively arranged above the two slide plates, the two arc plates are respectively arranged above the two adjustment components, the two anti-slip pads are respectively fixedly connected to the two arc plates, and are respectively located on the inner surfaces of the two arc plates, and the positioning component is arranged on the outer side wall of the arc plate.

2. A pipeline auxiliary laying device as claimed in claim 1, characterized in that: The adjustment assembly includes a cylinder, two adjustment rods and two springs. The cylinder is fixedly connected to the slide and is located above the slide. The arc plate is fixedly connected to the output end of the cylinder and is located above the cylinder. The two adjustment rods are fixedly connected between the slide and the arc plate, and the two adjustment rods are relatively located at two ends of the slide. The two springs are respectively mounted on the outer side walls of the two adjustment rods.

3. A pipeline auxiliary laying device as claimed in claim 1, characterized in that: The positioning assembly includes a mounting block, a positioner, a connecting block and an auxiliary plate. The mounting block is fixedly connected to the arc plate and is located on the outer side wall of the arc plate. The positioner is fixedly connected to the mounting block and is located on the outer side wall of the mounting block. The connecting block is fixedly connected to the arc plate away from the positioner and is located on the outer side wall of the arc plate. The auxiliary plate is fixedly connected to the connecting block and is located on the outer side wall of the connecting block.

4. A pipeline auxiliary laying device as claimed in claim 1, characterized in that: The pipeline auxiliary laying device also includes four connecting rods and four pulleys. The four connecting rods are fixedly connected to the slide rails and are respectively located below the slide rails. The four pulleys are rotatably connected to the four connecting rods and are respectively located below the slide rails.

5. The pipeline auxiliary laying device according to claim 1, characterized in that: The pipeline auxiliary laying device also includes a protection mechanism, and the protection mechanism is arranged above the slide rail.

6. A pipeline auxiliary laying device as claimed in claim 5, characterized in that: The protective mechanism includes two first covering plates, two first sliding plates, a second covering plate and a second sliding plate. The two first covering plates are fixedly connected to the two ends of the slide rail. The two first sliding plates are respectively fixedly connected to the two slides and are respectively slidably connected to the two first covering plates. The second covering plate is slidably connected to the second sliding plate and are respectively fixedly connected to the two slides and are located between the two slides.

Citation Information

Patent Citations

  • Laser transmitter

    CN217526372U

  • Auxiliary laying device for municipal pipe network

    CN220165637U