Hanging basket structure for bridge construction
By designing a hanging basket structure for bridge construction, the rapid connection between anchor rods and positioning blocks and the reinforcement structure enhancement, the shortcomings of traditional hanging basket structures in terms of construction efficiency, stability and safety are solved, and a more efficient, stable and safe construction process is achieved.
Patent Information
- Application Number
- CN202421252718.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-03
- Publication Date
- 2025-04-15
- Estimated Expiration
- 2034-06-03
AI Technical Summary
The traditional bridge construction hanging basket structure has shortcomings in construction efficiency, structural stability and safety, especially when the position needs to be adjusted, large-scale dismantling and reorganization are required, which increases the construction complexity and risks.
A hanging basket structure for bridge construction is designed, which is connected to the through hole of the positioning block through the anchor rod to quickly fix the front end of the sliding mechanism, and disassemble the anchor rod outside the slide rail to translate the slide rail and reposition it. At the same time, the overall strength is enhanced by the reinforcement structure, and a pulley is provided at the bottom of the extension plate to slide in and out to ensure stability during movement.
It improves construction efficiency, reduces the workload of dismantling and reinstallation, enhances the stability and safety of the structure, and reduces construction risks.
Smart Images

Figure CN222758746U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge construction, in particular to a hanging basket structure for bridge construction. Background Art
[0002] In the field of bridge construction, the hanging basket structure is an important construction auxiliary equipment and is widely used in bridge casting, installation and other operations. Although the traditional bridge construction hanging basket structure can meet basic construction needs, it still needs to be improved in terms of construction efficiency, structural stability and safety.
[0003] Specifically, when building a bridge body, the traditional bridge construction basket structure usually needs to be disassembled and reinstalled for the translation of the slide rail, which not only consumes a lot of manpower and time, but also affects the progress of the entire construction. At the same time, since the connection method between the slide rail and the extension plate is not flexible enough, during the bridge deck laying process, once the position needs to be adjusted, the entire basket structure needs to be disassembled and reorganized on a large scale, which undoubtedly increases the complexity and risk of construction. Therefore, in response to the above technical problems, a basket structure for bridge construction is proposed herein. Utility Model Content
[0004] The purpose of the utility model is to provide a hanging basket structure for bridge construction. When the construction range needs to be expanded, it can be connected with the through hole of the positioning block through the anchor rod, and the front end of the sliding mechanism can be quickly fixed. The anchor rod outside the slide rail can be removed to translate the slide rail and reposition it, thereby improving construction efficiency. The overall strength can be enhanced by the reinforcing rod. In addition, the pulley at the bottom of the extension plate is connected and slid with the slide groove to ensure stability during movement, reduce shaking, and improve construction efficiency and safety.
[0005] The utility model is realized by the following technical solutions:
[0006] The top end of the anchor bolt is provided with a groove, and the bottom end of the anchor bolt is provided with a groove.
[0007] Preferably, piers are cast at the bottom of the bridge body.
[0008] Preferably, the reinforcement structure includes a vertical pole, a horizontal plate and a first reinforcing rod, the vertical pole is fixedly connected to the extension plate, the horizontal plate is fixedly connected to the vertical pole, the first reinforcing rod is fixedly connected to the vertical pole and the horizontal plate, and the first reinforcing rod is installed at an angle.
[0009] Preferably, a second reinforcing rod is fixedly connected between the vertical rod and the mounting rod, and the second reinforcing rod is installed at an angle.
[0010] Preferably, a baffle is fixedly connected to the outside of the hanging basket body, and the inside of the baffle is a hollow structure, and a plurality of groups of vertically arranged blocking rods are fixedly connected to the inside of the baffle.
[0011] Preferably, the sliding limit assembly includes a connecting member and a pulley, the connecting member and the slide bar are fixedly connected, the pulley and the connecting member are rotatably connected, and the pulley is rotatably connected to the inner side of the slide groove and adapted thereto.
[0012] The technical solution of the utility model has at least the following beneficial effects:
[0013] The utility model proposes a hanging basket structure for bridge construction. When a part of the bridge body is built by the hanging basket structure, the positioning block can be conveniently positioned and connected by the anchor rod and the through hole, so as to fix the front end of the sliding mechanism. When the slide rail needs to be translated to expand the construction range, it is only necessary to remove the anchor rod outside the slide rail, so that the slide rail can be easily slid forward and repositioned, thereby greatly improving the construction efficiency. At the same time, the first reinforcing rod and the second reinforcing rod of the reinforcement structure can effectively enhance the overall strength of the hanging basket structure. In addition, a pulley is arranged at the bottom of the extension plate, and it is engaged and slid with the slide groove in the slide rail, so that the hanging basket structure can maintain overall stability when moving, avoiding shaking or tilting caused by movement, and further improving construction efficiency and safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0015] Figure 2 It is a second overall structural schematic diagram of the utility model;
[0016] Figure 3 for Figure 2 A magnified view of middle;
[0017] Figure 4 for Figure 1 Enlarged view of middle B;
[0018] Figure 5 for Figure 1 Enlarged view of middle C;
[0019] Figure 6 It is a partial front cross-sectional view of the utility model;
[0020] Figure 7 for Figure 6 Enlarged view of middle D;
[0021] Icons: 1. Bridge body; 2. Pier; 3. Slide rail; 4. Mounting plate; 5. Anchor rod; 6. Slide bar; 7. Extension plate; 8. Positioning block; 9. Through hole; 10. Vertical pole; 11. Cross plate; 12. First reinforcing rod; 13. Mounting rod; 14. Second reinforcing rod; 15. Connecting rod; 16. Basket body; 17. Baffle; 18. Blocking rod; 19. Slide chute; 20. Connecting piece; 21. Pulley. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] See also Figure 1-7 The utility model proposes a hanging basket structure for bridge construction, including a hanging basket body 16, which is arranged at the bridge body 1 of the bridge, the upper side of the bridge body 1 is fixedly connected with a slide rail 3, the inner side of the slide rail 3 is slidably connected with a slide bar 6, the upper side of the slide bar 6 is fixedly connected with an extension plate 7, the end of the extension plate 7 is fixedly connected with a positioning block 8, and the bottom of the positioning block 8 is flush with the upper surface of the bridge body 1, a through hole 9 is opened on the upper side of the positioning block 8, and a reinforcement structure is installed on the upper side of the extension plate 7, and the outer sides of the reinforcement structure are fixedly connected It is connected to a mounting rod 13, the bottom of which is fixedly connected to a connecting rod 15, and a hanging basket body 16 is fixedly connected to the connecting rod 15, the internal cross-section of the hanging basket body 16 is slightly larger than the bridge body 1, and a mounting plate 4 is fixedly connected to the bottom of the slide rail 3, an anchor rod 5 passes through the upper side of the mounting plate 4, and the end of the anchor rod 5 is embedded in the interior of the bridge body 1, the slide rail 3 can be installed at the edge of the bridge body 1 through the anchor rod 5, a slide groove 19 is provided at the inner bottom of the anchor rod 5, and a sliding limit assembly is installed at the bottom of the slide bar 6.
[0024] A pier 2 is cast at the bottom of the bridge body 1 .
[0025] The reinforcement structure includes a vertical pole 10, a horizontal plate 11 and a first reinforcing rod 12. The vertical pole 10 is fixedly connected to the extension plate 7, the horizontal plate 11 is fixedly connected to the vertical pole 10, the first reinforcing rod 12 is fixedly connected to the vertical pole 10 and the horizontal plate 11, and the first reinforcing rod 12 is installed at an angle. Supported by the first reinforcing rod 12, the stability of the overall structure can be improved. A second reinforcing rod 14 is fixedly connected between the vertical pole 10 and the mounting rod 13, and the second reinforcing rod 14 is installed at an angle.
[0026] The outside of the hanging basket body 16 is fixedly connected with a baffle 17, and the inside of the baffle 17 is a hollow structure. The inside of the baffle 17 is fixedly connected with multiple groups of vertically arranged blocking rods 18. The baffle 17 and the blocking rods 18 are used for shielding to ensure the safety of workers during construction.
[0027] The sliding limit assembly includes a connecting member 20 and a pulley 21. The connecting member 20 and the slide bar 6 are fixedly connected, and the pulley 21 and the connecting member 20 are rotatably connected. The pulley 21 is rotatably connected to the inner side of the slide groove 19 and adapted thereto. The pulley 21 is engaged and slidably engaged with the slide groove 19 in the slide rail 3, so that the hanging basket structure can maintain overall stability when moving.
[0028] The working principle of a hanging basket structure for bridge construction based on the embodiment is that an extension plate 7 is slidably installed on the slide rail 3, a positioning block 8 is set at the bottom of the end of the extension plate 7, and a through hole 9 is opened outside the positioning block 8. When a part of the bridge body 1 is built by the hanging basket structure, the positioning block 8 can be conveniently positioned and connected through the anchor rod 5 and the through hole 9, so as to fix the front end of the sliding mechanism. When the slide rail 3 needs to be translated to expand the construction range, it is only necessary to remove the anchor rod 5 outside the slide rail 3, and the slide rail 3 can be easily slid forward and repositioned through the sliding connection between the slide rail 3 and the extension plate 7, thereby greatly The construction efficiency is improved and the workload of disassembly and reinstallation is reduced. At the same time, in order to further enhance the stability of the hanging basket structure, the first reinforcing rod 12 and the second reinforcing rod 14 of the reinforcement structure can effectively enhance the overall strength of the hanging basket structure and improve its stability in the high-altitude working environment, thereby reducing the construction risk and ensuring the construction safety. In addition, a pulley 21 is provided at the bottom of the extension plate 7 and is engaged and slid with the slide groove 19 in the slide rail 3, so that the hanging basket structure can maintain overall stability when moving, avoiding shaking or tilting caused by movement, and further improving the construction efficiency and safety.
[0029] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A hanging basket structure for bridge construction, characterized in that: The invention comprises a hanging basket body (16), which is arranged at the bridge body (1) of the bridge, the upper side of the bridge body (1) is fixedly connected with a slide rail (3), the interior of the slide rail (3) is slidably connected with a slide bar (6), the upper side of the slide bar (6) is fixedly connected with an extension plate (7), the end of the extension plate (7) is fixedly connected with a positioning block (8), and the bottom of the positioning block (8) is flush with the upper surface of the bridge body (1), the upper side of the positioning block (8) is provided with a through hole (9), the upper side of the extension plate (7) is installed with a reinforcement structure, and the outer sides of the reinforcement structure are fixedly connected to the A mounting rod (13) is connected, the bottom of the mounting rod (13) is fixedly connected to a connecting rod (15), and a hanging basket body (16) and the connecting rod (15) are fixedly connected, the internal cross-section of the hanging basket body (16) is slightly larger than the bridge body (1), the bottom of the slide rail (3) is fixedly connected to a mounting plate (4), the upper side of the mounting plate (4) is penetrated by an anchor rod (5), and the end of the anchor rod (5) is embedded in the interior of the bridge body (1), the inner bottom of the anchor rod (5) is provided with a slide groove (19), and the bottom of the slide bar (6) is installed with a sliding limit assembly.
2. A hanging basket structure for bridge construction according to claim 1, characterized in that: A pier (2) is cast at the bottom of the bridge body (1).
3. The hanging basket structure for bridge construction according to claim 1 is characterized in that: The reinforcement structure comprises a vertical pole (10), a horizontal plate (11) and a first reinforcing rod (12); the vertical pole (10) and the extension plate (7) are fixedly connected; the horizontal plate (11) and the vertical pole (10) are fixedly connected; the first reinforcing rod (12) and the vertical pole (10) and the horizontal plate (11) are fixedly connected; and the first reinforcing rod (12) is installed in an inclined manner.
4. A hanging basket structure for bridge construction according to claim 3, characterized in that: A second reinforcing rod (14) is fixedly connected between the vertical rod (10) and the mounting rod (13), and the second reinforcing rod (14) is installed in an inclined manner.
5. The hanging basket structure for bridge construction according to claim 1 is characterized in that: The outside of the hanging basket body (16) is fixedly connected with a baffle (17), and the inside of the baffle (17) is a hollow structure. The inside of the baffle (17) is fixedly connected with a plurality of groups of vertically arranged blocking rods (18).
6. The hanging basket structure for bridge construction according to claim 1 is characterized in that: The sliding limit assembly comprises a connecting member (20) and a pulley (21); the connecting member (20) and the slide bar (6) are fixedly connected, the pulley (21) and the connecting member (20) are rotatably connected, and the pulley (21) is rotatably connected to the inner side of the slide groove (19) and is adapted thereto.