Prefabricated assembled box culvert structure

By prefabricated assembled box culvert structures, using porous box culvert structural units and bolted connections, combined with the use of rubber water stop rings, the problems of slow construction speed, difficult to guarantee quality and high construction risks in the prior art are solved, and fast, safe and high-quality box culvert construction is achieved.

CN222758751UActive Publication Date: 2025-04-15WUHAN MUNICIPAL ENG MECHANIZED CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421537070.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-01
Publication Date
2025-04-15
Estimated Expiration
2034-07-01

AI Technical Summary

Technical Problem

In the existing construction methods, the on-site pouring speed of box culvert concrete structures is slow, the quality is difficult to guarantee, and they are easily affected by the weather, and the construction risk is high.

Method used

The prefabricated assembled box culvert structure is adopted, and a complete box culvert structure is connected by bolts through multiple porous box culvert structures, and a rubber water stop ring is used to seal at the connection.

Benefits of technology

The speed of box culvert construction has been accelerated, the quality of construction has been improved, the construction risk has been reduced, the dependence on the weather has been reduced, and the site occupied by on-site construction has been reduced through prefabricated parts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222758751U_ABST
    Figure CN222758751U_ABST
Patent Text Reader

Abstract

A porous box culvert structure unit comprises a top plate, a bottom plate, side walls and a plurality of middle partition walls, a plurality of bolt holes penetrating through the end faces and the surfaces of the top plate and the bottom plate are formed in the two ends of the top plate and the two ends of the bottom plate respectively, and a plurality of bolt holes penetrating through the end faces and the side faces of the side walls are formed in the two ends of the side walls and the middle partition walls respectively. One end of each bolt is located in the bolt hole of one of the two adjacent porous box culvert structure units, and the other end of each bolt is located in the bolt hole of the other porous box culvert structure unit, so that the two adjacent porous box culvert structure units are connected. The prefabricated box culvert has the beneficial effects that the box culvert construction speed can be increased, the construction quality can be improved, the construction risk can be reduced, the weather influence is small, in addition, the assembled box culvert structure can be used as a temporary road and an operation platform, so that the site occupation or temporary land acquisition is reduced, and the construction cost is reduced. And the system has superiority in areas without conditions for setting temporary shortcuts.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a prefabricated assembled box culvert structure. Background Art

[0002] Due to urban development, we often face the need to transform old river channels into the ground, or to transform drainage pipes and ditches. The common construction method is to excavate the foundation pit first, and then cast the box culvert concrete structure on site. The on-site construction speed is slow, the quality cannot be guaranteed, and it is easily affected by the weather. In addition, since on-site construction requires the establishment of formwork support frames and scaffolding, the construction risk is high. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide a prefabricated assembled box culvert structure to overcome the deficiencies in the above-mentioned prior art.

[0004] The utility model provides a technical solution to the above-mentioned technical problems as follows: a prefabricated assembled box culvert structure, comprising: bolts and a plurality of porous box culvert structural units arranged in sequence, the porous box culvert structural units comprising: a top plate, a bottom plate, a side wall and a plurality of intermediate partition walls, the top plate and the bottom plate are provided with a plurality of bolt holes penetrating the end faces and surfaces at both ends, the side walls and the intermediate partition walls are provided with a plurality of bolt holes penetrating the end faces and sides at both ends, one end of the bolt is located in the bolt hole of one of the two adjacent porous box culvert structural units, and the other end is located in the bolt hole of the other porous box culvert structural unit, so as to connect the two adjacent porous box culvert structural units.

[0005] On the basis of the above technical solution, the present invention can also be improved as follows.

[0006] Furthermore, a rubber water stop ring is provided between two adjacent porous box culvert structural units.

[0007] Furthermore, the end surface of the porous box culvert structural unit has an annular groove adapted to the rubber water stop ring.

[0008] Furthermore, the surfaces of the top plate and the bottom plate are provided with avoidance grooves at the opening of each bolt hole, and the surfaces of the side walls and the middle partition wall are provided with avoidance grooves at the opening of each bolt hole.

[0009] Furthermore, the porous box culvert structural unit is formed by integrally casting reinforced concrete.

[0010] Furthermore, the porous box culvert structural unit is a straight line segment, an arc segment, or a combination of both.

[0011] The beneficial effects of the utility model are as follows: the prefabricated assembly box culvert technology can speed up the box culvert construction speed, improve the construction quality, reduce the construction risk, and is less affected by the weather. In addition, since the on-site construction requires a large site, a temporary access road needs to be set up, and the prefabricated assembly technology can use the assembled box culvert structure as a temporary road and operation platform, thereby reducing site occupation or reducing temporary land acquisition. It is more advantageous in areas where there are no conditions for setting up temporary access roads. The number of box culvert holes is set according to actual needs. The structure is mainly used for river channel reconstruction, water passage, etc. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 The prefabricated assembled box culvert structure in the utility model is assembled from a plurality of straight-segment porous box culvert structure units;

[0013] Figure 2 The prefabricated assembled box culvert structure in the utility model is assembled from a plurality of straight line segments and a plurality of arc segment porous box culvert structure units;

[0014] Figure 3 It is a structural diagram of a porous box culvert structural unit in the utility model;

[0015] Figure 4 It is a bottom plate structure diagram of the porous box culvert structural unit in the utility model;

[0016] Figure 5 This is a structural diagram of the bottom plates of two porous box culvert structural units in the utility model being assembled by bolts;

[0017] Figure 6 This is a structural diagram of the side walls / middle partition walls of two porous box culvert structural units in the utility model being assembled by bolts.

[0018] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0019] 1. Porous box culvert structural unit, 110, top plate, 120, bottom plate, 130, side wall, 140, middle partition wall, 150, bolt hole, 160, avoidance groove, 2, bolt, 3, rubber water stop ring. DETAILED DESCRIPTION

[0020] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.

[0021] Example 1

[0022] like Figure 1 to Figure 6As shown, a prefabricated assembled box culvert structure comprises: a bolt 2 and a plurality of porous box culvert structural units 1 arranged in sequence, each porous box culvert structural unit 1 comprises: a top plate 110, a bottom plate 120, a side wall 130 and a plurality of middle partition walls 140, the top plate 110 is provided with a plurality of bolt holes 150 penetrating its end face and lower surface at both ends, the bottom plate 120 is provided with a plurality of bolt holes 150 penetrating its end face and upper surface at both ends, the side wall 130 is provided with a plurality of bolt holes 150 penetrating its end face and inner side surface at both ends, and the middle partition wall 140 is provided with a plurality of bolt holes 150 penetrating its end face and side surface at both ends; one end of the bolt 2 is located in the bolt hole 150 of one of the two adjacent porous box culvert structural units 1, and the other end of the bolt 2 is located in the bolt hole 150 of the other porous box culvert structural unit 1, so as to connect the two adjacent porous box culvert structural units 1.

[0023] Example 2

[0024] like Figure 3 As shown, this embodiment is a further improvement on the basis of embodiment 1, and the details are as follows:

[0025] There is a rubber water stop ring 3 between two adjacent porous box culvert structural units 1. When the two adjacent porous box culvert structural units 1 are connected by bolts 2, the rubber water stop ring 3 will be squeezed to seal the gap between the two adjacent porous box culvert structural units 1 to prevent leakage.

[0026] Furthermore: the end surface of the porous box culvert structure unit 1 has an annular groove adapted to the rubber water stop ring 3, so as to facilitate the installation of the rubber water stop ring 3.

[0027] Example 3

[0028] like Figure 4 , Figure 5 , Figure 6 As shown, this embodiment is a further improvement on the basis of Embodiment 1 or 2, and the details are as follows:

[0029] The lower surface of the top plate 110 is provided with an avoidance groove 160 at the opening of each bolt hole 150, the upper surface of the bottom plate 120 is provided with an avoidance groove 160 at the opening of each bolt hole 150, the inner surface of the side wall 130 is provided with an avoidance groove 160 at the opening of each bolt hole 150, and the surface of the middle partition wall 140 is provided with an avoidance groove 160 at the opening of each bolt hole 150. The bolts 2 are respectively located in the avoidance grooves 160, and the introduction of the avoidance grooves 160 facilitates the installation of the bolts 2.

[0030] Example 4

[0031] like Figure 3As shown, this embodiment is a further improvement on the basis of Embodiment 1, 2 or 3, and the details are as follows:

[0032] The porous box culvert structural unit 1 is integrally cast by reinforced concrete. To match the line shape of the box culvert, the porous box culvert structural unit 1 can be one of two standard segments, a straight line segment and an arc segment, or a combination of the two.

[0033] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A prefabricated assembled box culvert structure, characterized in that: include: A bolt (2) and a plurality of porous box culvert structural units (1) arranged in sequence, wherein the porous box culvert structural unit (1) comprises: a top plate (110), a bottom plate (120), a side wall (130) and a plurality of intermediate partition walls (140), the top plate (110) and the bottom plate (120) are respectively provided with a plurality of bolt holes (150) penetrating their end faces and surfaces at both ends, the side wall (130) and the intermediate partition wall (140) are respectively provided with a plurality of bolt holes (150) penetrating their end faces and side faces at both ends, one end of the bolt (2) is located in the bolt hole (150) of one of the two adjacent porous box culvert structural units (1), and the other end is located in the bolt hole (150) of the other porous box culvert structural unit (1), so as to connect the two adjacent porous box culvert structural units (1).

2. A prefabricated assembled box culvert structure according to claim 1, characterized in that: A rubber water stop ring (3) is provided between two adjacent porous box culvert structural units (1).

3. A prefabricated assembled box culvert structure according to claim 2, characterized in that: The end surface of the porous box culvert structural unit (1) has an annular groove adapted to the rubber water stop ring (3).

4. The prefabricated assembled box culvert structure according to claim 1, characterized in that: The surfaces of the top plate (110) and the bottom plate (120) are provided with avoidance grooves (160) at the openings of each bolt hole (150), and the surfaces of the side walls (130) and the middle partition wall (140) are provided with avoidance grooves (160) at the openings of each bolt hole (150).

5. The prefabricated assembled box culvert structure according to claim 1, characterized in that: The porous box culvert structural unit (1) is integrally cast by reinforced concrete.

6. A prefabricated assembled box culvert structure according to any one of claims 1 to 5, characterized in that: The porous box culvert structural unit (1) is a straight line segment, an arc segment, or a combination of the two.