High-voltage electrician simulation examination equipment

By designing high-voltage electrical simulation assessment equipment and using transformers and lines to mount protective ground wire assessment systems, the problem of difficulty in dynamic operation training in existing training is solved, and students are trained in an environment that combines theory and practice, which significantly improves the training effect.

CN222762569UActive Publication Date: 2025-04-15HEFEI YAOAN TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421296904.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-07
Publication Date
2025-04-15
Estimated Expiration
2034-06-07

AI Technical Summary

Technical Problem

The existing high-voltage electrician practical teaching assessment training is difficult to effectively carry out dynamic operation training on the premise of ensuring the safety of students, resulting in the teaching being able to stay in theory, making it difficult for students to master the operation process, and the training effect is not good.

Method used

Design a high-voltage electrical simulation assessment equipment, including a transformer assessment system and a line-mounted protective ground wire assessment system, and use touch screen all-in-one machine, control board, wire post, transformer, power box, insulated column, power cable, drop fuse and wind direction indicator light to simulate the operation process of the high-voltage electrical. After the simulation assessment is carried out through the computer assessment simulation system, it will be directly transferred to the actual operation.

Benefits of technology

Through the simulation system, students can train in an environment that combines theory and practice, improve their understanding and mastery of high-voltage electrician operations, significantly improve the training effect, and ensure that students have sufficient skills and safety awareness during on-site operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222762569U_ABST
    Figure CN222762569U_ABST
Patent Text Reader

Abstract

The utility model provides high-voltage electrician simulation examination equipment, and relates to the technical field of electrician simulation examination, the high-voltage electrician simulation examination equipment comprises a transformer examination system and a line hanging protection grounding wire examination system, the transformer examination system comprises a touch screen all-in-one machine, a control panel, a wire column, a transformer, a power box, an insulation column, a power cable, a drop-out fuse and a wind direction indicating lamp, the line hanging protection grounding wire examination system comprises a grounding box, a grounding wire, a grounding rod and an insulating rod. The technical key points are that a touch screen all-in-one machine, a control panel, a wire column, a transformer, a power box, an insulating column, a power cable, a drop-out fuse and a wind direction indicating lamp are utilized to form a transformer examination system, and a grounding box, an electroscope, a grounding wire and a grounding rod are added to form a line hanging protection grounding wire examination system. According to the invention, after a student re-completes simulation examination work in an existing computer examination simulation system, practical operation can be carried out, so that theoretical and practical operation training of the student is ensured, and the training effect is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electrician simulation assessment, in particular to high-voltage electrician simulation assessment equipment. Background Art

[0002] High-voltage electricians are electricians who apply voltage, current, power, frequency, temperature and other factors to equipment at the same time, causing it to not work properly or even damage electrical equipment. The working principle of high-voltage electricians is to use high-voltage power supply to lead equipment or lines out of the earth through insulating materials, so that it is separated from the ground or suspended in the air, or various operations are performed in the air, so that the equipment cannot work properly. "High voltage" has many meanings, such as artificial electric shock applied to high-voltage power grids, application of high-voltage electric shocks and breakdown caused by discharge of high-voltage insulators.

[0003] Before carrying out actual high-voltage electrician work, workers need to undergo a high-voltage electrician assessment. Only after passing the assessment and obtaining the corresponding high-voltage electrician qualifications can they proceed to the actual site to ensure construction safety.

[0004] In the field of high-voltage electrician practical teaching and assessment training, due to the danger of high-voltage lines, very high skills are required of students. Students should have certain practical operation experience. However, there are certain differences between the equipment on site and the equipment in the actual examination, and the examination equipment is generally not powered on to ensure the safety of students' examinations. Training teachers can only use the combination of high-voltage electrician assessment objects and book courseware to conduct high-voltage electrician theory and practical explanations, so the dynamic process of the entire operation cannot be explained vividly, and training teachers cannot conduct detailed physical operation training. Teaching can only remain in theory. It is difficult for students to grasp the entire operation process, and it is impossible to combine theory with practical operations, and the training effect is poor. Utility Model Content

[0005] In order to overcome the shortcomings of the existing high-voltage electrician practical teaching and assessment training, which adopts the method of combining high-voltage electrician assessment objects with book courseware knowledge to explain high-voltage electrician theory and practice, it cannot vividly explain the dynamic process of the entire operation, and the training teachers cannot conduct detailed physical operation training. The teaching can only remain in theory, and the trainees find it difficult to master the entire operation process. It is impossible to combine theory with actual operation, and the training effect is not good. The embodiment of the present application provides a high-voltage electrician simulation assessment equipment, which utilizes a touch screen all-in-one machine, a control panel, a power pole, a transformer, a power box, an insulating pole, a power cable, a drop-type fuse and a wind direction indicator to form a transformer assessment system, and utilizes a touch screen all-in-one machine, a control panel, a grounding box, a tester, a grounding wire, a grounding rod and a power cable to form a line hanging protection grounding wire assessment system. After the trainees complete the simulation assessment work in the existing computer assessment simulation system, they can directly switch to practical operation, which is conducive to ensuring that the trainees are trained in both theory and practice and ensuring the training effect.

[0006] The technical solution adopted by the embodiment of the present application to solve the technical problem is:

[0007] A high-voltage electrician simulation assessment equipment, including a transformer assessment system and a line hanging protective grounding wire assessment system;

[0008] The line hanging protection grounding wire assessment system is set on one side of the transformer assessment system;

[0009] Among them, the transformer assessment system includes a touch screen all-in-one machine, a control panel, a power pole, a transformer, a power box, an insulating pole, a power cable, a drop-out fuse and a wind direction indicator light, and the line hanging protective grounding wire assessment system includes a grounding box, a grounding wire, a grounding rod and a link rod.

[0010] In a possible implementation, a circuit breaker and a control panel are provided inside the power box, the circuit breaker switch signal is connected to the control panel, the touch screen integrated machine is provided on one side of the power box, and the control panel and the touch screen integrated machine communicate through a serial port.

[0011] In a possible implementation, three drop-out fuses are provided, and magnets and Hall sensors are mounted on the three drop-out fuses, and the Hall sensors are connected to the interior of a control board.

[0012] In a possible implementation, three electric poles are provided, the transformer is provided between two electric poles on one side, three insulating poles are provided and all are mounted on the top of the transformer, and the three insulating poles are respectively connected to three drop-out fuses through test wires.

[0013] In a possible implementation, a plurality of insulating columns are provided, two wind direction indicator lights are provided, and trusses are assembled and connected between the middle parts and the tops of the two electric poles located on one side, three of the plurality of insulating columns are assembled and connected to the bottom truss, and the remaining plurality of insulating columns are respectively assembled and connected to the tops of the two electric poles, and the two wind direction indicator lights are respectively assembled and connected at both ends of the top truss.

[0014] In a possible implementation, three power cables are provided, and a reed switch magnetic sensor is provided outside the three power cables. The three power cables are respectively connected to a plurality of insulating posts on the top of the electric pole.

[0015] In a possible implementation, three linker rods are provided, one end of the three linker rods are respectively overlapped on the outside of three power cables, and the other ends of the three linker rods are connected to a grounding box through a test wire.

[0016] In a possible implementation, a plurality of grounding wires and a plurality of grounding rods are provided, one end of the plurality of grounding wires is respectively connected to one end of the plurality of grounding rods, and the other ends of the plurality of grounding rods are buried underground.

[0017] In summary, the present invention includes at least one of the following beneficial technical effects:

[0018] By utilizing a touch screen all-in-one machine, a control panel, electric poles, transformers, power boxes, insulating poles, power cables, drop-out fuses and wind direction indicator lights to form a transformer assessment system, and utilizing a touch screen all-in-one machine, a control panel, a grounding box, a tester, a grounding wire, a grounding rod and power cables to form a line hanging protective grounding wire assessment system, trainees can directly switch to practical operations after completing the simulation assessment work on the existing computer assessment simulation system, which is conducive to ensuring that trainees are trained in both theory and practice, and ensuring the training effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0020] Description of the drawings: 1. Drop-out fuse; 2. Wind direction indicator light; 3. Insulation column; 4. Power cable; 5. Link rod; 6. Electric pole; 7. Test wire; 8. Grounding box; 9. Transformer; 10. Power box. DETAILED DESCRIPTION

[0021] The technical solution in the embodiment of the present application is to solve the problems of the above-mentioned background technology, and the overall idea is as follows:

[0022] Embodiment 1:

[0023] This embodiment introduces a specific structure of a transformer assessment system for high-voltage electrician simulation assessment equipment. Figure 1 As shown, the transformer assessment system includes a touch screen integrated machine, a control panel, a power pole 6, a transformer 9, a power box 10, an insulating pole 3, a power cable 4, a drop-out fuse 1 and a wind direction indicator light 2. Three power poles 6 are provided, and the transformer 9 is provided between two power poles 6 located on one side;

[0024] There are three insulating columns 3, all of which are mounted on the top of the transformer 9. The three insulating columns 3 are connected to the three drop-out fuses 1 through the test wires 7.

[0025] like Figure 1 As shown, multiple insulating columns 3 are provided, two wind direction indicator lights 2 are provided, and trusses are assembled and connected between the middle and top of two electric poles 6 on one side;

[0026] Among them, three of the multiple insulating columns 3 are assembled and connected to the bottom truss, the remaining multiple insulating columns 3 are assembled and connected to the tops of two electric poles 6, and the two wind direction indicator lights 2 are assembled and connected to the two ends of the top truss respectively;

[0027] Secondly, there are three drop-out fuses 1, and magnets and Hall sensors are installed on the three drop-out fuses 1. The Hall sensors are connected to the inside of the control board. When the drop-out fuse 1 is closed, the magnet on the drop-out fuse 1 will approach the Hall sensor directly on it, and the Hall sensor outputs high and low level signals to the control board, and the control board can collect whether the drop-out fuse is closed;

[0028] At the same time, the two wind direction indicator lights 2 are both powered by 12V DC, and the control board controls the on and off of the two wind direction indicator lights 2 through two sets of relays to simulate the three states of no wind in the upwind direction and downwind direction;

[0029] Furthermore, a circuit breaker and a control panel are provided inside the power box 10, and the touch screen integrated machine is provided on one side of the power box 10. The switch signal of the circuit breaker is connected to the control panel, and the control panel is used to collect the opening and closing status of the circuit breaker. The control panel and the touch screen integrated machine communicate through the serial port, and the test situation can be reflected on the touch screen integrated machine;

[0030] When using the high-voltage electrician simulation assessment equipment transformer assessment system to enable trainees to perform transformer power outage operations on a 10kV pole:

[0031] First, based on the existing practical assessment system, identity verification is performed on the computer, and the power outage operation ticket of the 10kV high-voltage switchgear is filled out;

[0032] Then, based on the existing computer assessment software program, simulate the actual operation, install the operation ticket content and simulate the operation content on the computer;

[0033] Next, choose appropriate labor protection articles, go to the transformer 9, wear the labor protection articles correctly, perform the power-off operation of the 10kV pole-mounted transformer, first pull down the circuit breaker in the power box 10, and then pull down the three drop-out fuses 1 in sequence according to the status of the wind direction indicator light 2, hang a signboard with the words "Do not close the switch, someone is working" under the drop-out fuse 1, and hang a signboard with the words "Do not close the switch, someone is working" on the handle of the low power cabinet of the transformer 9. The control panel will send every step of the trainee's operation to the computer software of the touch screen all-in-one in real time. After comparing the software with the correct operation steps, the assessment score will be directly obtained and uploaded to the examination server platform for the trainees to query the score.

[0034] Embodiment 2:

[0035] This embodiment introduces a specific structure of a high-voltage electrician simulation test equipment line hanging protective grounding wire test system. Figure 1 As shown, it is arranged on one side of the transformer assessment system, the line hanging protection grounding wire assessment system includes a grounding box 8, a grounding wire, a grounding rod and a link rod 5, three power cables 4 are arranged, and the outsides of the three power cables 4 are all provided with a reed switch magnetic sensor. There are three link rods 5;

[0036] Among them, by connecting three power cables 4 to multiple insulating columns 3 on the top of the power pole 6, one end of three linker rods 5 are respectively overlapped on the outside of the three power cables 4, and the other ends of the three linker rods 5 are connected to the grounding box 8 through the test wire 7, the connection work of the grounding line can be completed;

[0037] Secondly, multiple grounding wires and grounding rods are provided, one end of each of the multiple grounding wires is connected to one end of each of the multiple grounding rods, and the other ends of the multiple grounding rods are buried underground. When an external tester is brought into contact with the test position on the power cable 4, the reed switch magnetic sensor outputs high and low levels to the control board, and the control board detects whether the trainee performs the test and the order in which the test can be detected;

[0038] At the same time, the other end of the multiple power cables 4 has a grounding wire position, and a metal proximity sensor is installed on the line at the same time. When the grounding wire is hung or removed, the metal proximity sensor outputs a high or low level signal to the control board, and the control board detects whether the grounding wire is hung;

[0039] In addition, the three grounding rods set on the grounding box 8 are inserted into the ground with different depths of 600mm, 500mm, and 450mm for students to choose. Only 600mm is the correct grounding depth, and the other two are wrong options. Metal proximity sensors are installed under the three grounding rod jacks of the grounding box 8, and the metal proximity sensors are connected to the control board. When the student inserts or pulls out the metal grounding rod, the metal sensor is triggered, and the metal outputs high and low levels, and the single-chip microcomputer knows which grounding hole the student has inserted.

[0040] When using the high-voltage electrician simulation assessment equipment line hanging protective grounding wire assessment system to allow trainees to hang protective grounding wires on 10kV lines:

[0041] First, based on the existing practical assessment system, identity verification is performed on the computer, and the power outage operation ticket of the 10kV high-voltage switchgear is filled out;

[0042] Then, based on the existing computer assessment software program, simulate the actual operation, install the operation ticket content and simulate the operation content on the computer;

[0043] Next, choose the appropriate labor protection equipment, come to the transformer 9, wear the labor protection equipment correctly, first use the test rod to test the electricity", then insert the ground rod, insert the ground rod into the hole with a depth of 600MM, then hang the ground wire on the cable, finally remove the ground wire and put the tool back".

[0044] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A high voltage electrician simulation assessment device, characterized in that: include: Transformer assessment system; The line hanging protective grounding wire assessment system is set on one side of the transformer assessment system; The transformer assessment system comprises a touch screen integrated machine, a control panel, a power pole (6), a transformer (9), a power box (10), an insulating pole (3), a power cable (4), a drop-out fuse (1) and a wind direction indicator light (2); and the line hanging protective grounding wire assessment system comprises a grounding box (8), a grounding wire, a grounding rod and a link rod (5).

2. A high voltage electrician simulation assessment device as claimed in claim 1, characterized in that: A circuit breaker and a control panel are arranged inside the power box (10), and a switch signal of the circuit breaker is connected to the control panel; The touch screen integrated machine is arranged on one side of the power box (10), and the control panel and the touch screen integrated machine communicate via a serial port.

3. A high voltage electrician simulation assessment device as claimed in claim 1, characterized in that: Three drop-out fuses (1) are provided, and magnets and Hall sensors are installed on the three drop-out fuses (1), and the Hall sensors are connected to the inside of the control board.

4. A high voltage electrician simulation assessment device as claimed in claim 1, characterized in that: The electric poles (6) are provided in three numbers, the transformer (9) is provided between two electric poles (6) located on one side, the insulating poles (3) are provided in three numbers, and are all mounted on the top of the transformer (9), and the three insulating poles (3) are respectively connected to three drop-out fuses (1) via test wires (7).

5. A high voltage electrician simulation assessment device as claimed in claim 4, characterized in that: The insulating columns (3) are provided in plurality, the wind direction indicator lights (2) are provided in two, and trusses are assembled and connected between the middle parts and the tops of the two electric poles (6) located on one side; Among them, three of the plurality of insulating columns (3) are assembled and connected to the bottom truss, the remaining plurality of insulating columns (3) are respectively assembled and connected to the tops of two electric poles (6), and the two wind direction indicator lights (2) are respectively assembled and connected at the two ends of the top truss.

6. A high voltage electrician simulation assessment device as claimed in claim 5, characterized in that: Three power cables (4) are provided, and a reed switch magnetic sensor is provided outside each of the three power cables (4). The three power cables (4) are respectively connected to a plurality of insulating columns (3) at the top of the electric pole (6).

7. A high voltage electrician simulation assessment device as claimed in claim 6, characterized in that: Three linker rods (5) are provided, one end of each of the three linker rods (5) is respectively overlapped on the outside of three power cables (4), and the other ends of each of the three linker rods (5) are connected to a grounding box (8) via a test wire (7).

8. The high voltage electrician simulation assessment equipment according to claim 1, characterized in that: A plurality of grounding wires and grounding rods are provided, one end of each of the plurality of grounding wires is connected to one end of each of the plurality of grounding rods, and the other ends of each of the plurality of grounding rods are buried underground.

Citation Information

Cited By

  • Intelligent pole-mounted transformer platform complete equipment and control method

    CN120914007A