Water level marker post for water conservancy and hydropower

By adding an embedded section and baffle structure at the bottom of the measuring section of the water level benchmark, the problems of inconvenience and instability of the traditional water level benchmark are solved, and more convenient installation and more stable use are achieved.

CN222774070UActive Publication Date: 2025-04-18SICHUAN HENGYUAN ENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421746736.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2025-04-18
Estimated Expiration
2034-07-23

AI Technical Summary

Technical Problem

It is difficult to observe the burial of the traditional water level benchmark when installing, resulting in inconvenient installation and the water level benchmark when used is not stable enough.

Method used

A water conservancy and hydropower water level benchmark is designed. The bottom of the measuring section is equipped with an embedded section, and the side of the embedded section is fixed to connect the limit plate, and the first and second baffles are provided. Through these structures, the baffles are fixed to the outside of the limit plate before installation, so as to prevent the measurement section from being buried into the ground during hammering installation. At the same time, by increasing the design of vertical rods and threaded rods, the contact area with the ground is increased and the installation stability is improved.

Benefits of technology

The design of the water level benchmark makes the installation process more convenient, avoiding the phenomenon of the measurement section being buried underground. At the same time, due to the increased contact area, the installation of the water level benchmark is more stable.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222774070U_ABST
    Figure CN222774070U_ABST
Patent Text Reader

Abstract

The utility model discloses a water conservancy and hydropower water level marker post which comprises a measuring section, a pre-buried section is arranged at the bottom of the measuring section, a limiting plate is fixedly connected to the side face of the pre-buried section, a first baffle is arranged on the side face of the pre-buried section, a second baffle is arranged on the side face of the pre-buried section, and a first fixing plate is fixedly connected to the side face of the first baffle. The side face of the second baffle is fixedly connected with a second fixing plate. According to the water conservancy and hydropower water level marker post, the embedded section is additionally arranged at the bottom of the measuring section, the second fixing plate is installed on the side face of the second baffle, and before the water level marker post needs to be installed, the first baffle and the second baffle are directly installed between the two limiting plates; the first baffle and the second baffle can be fixed outside the embedded section through the first fixing plate and the second fixing plate, when the water level gauge is beaten into the ground and the ground makes contact with the bottom plate, the water level gauge rod can be continuously beaten into the ground at the moment, the measuring section is effectively prevented from being embedded into the ground, and the water level gauge rod is more convenient to fix.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of water conservancy and hydropower, and in particular relates to a water conservancy and hydropower water level benchmark. Background Art

[0002] The general water level gauge is used to monitor surface water. It is made of metal or non-metallic materials, marked with scales. The accuracy is generally measured in centimeters. In water conservancy, 1 meter is generally used as a section, and pure red or blue is used as a piece. Water level gauges on the market can be divided into electronic water gauges, stainless steel water gauges, etc. according to high, medium and low grades.

[0003] The water level markers currently on the market have the following problems when used:

[0004] 1. When installing a traditional water level benchmark, it is generally necessary to hammer the top of the measuring section to hammer the embedded section into the ground. When it needs to be installed in a river and the water level is high, it is difficult to observe the embedded section, making it easy to bury the measuring section into the soil, which is not convenient for installation;

[0005] 2. When installing the traditional water level marker, the water level marker is directly inserted into the soil, the silt is soft, and the water flow is unstable, so the water level marker is not stable enough when in use. Utility Model Content

[0006] The utility model aims to provide a water conservancy and hydropower water level benchmark to solve the technical problems raised in the background technology.

[0007] To achieve the above-mentioned objectives, the specific technical scheme of the utility model is as follows: a water conservancy and hydropower water level benchmark, a pre-embedded section is provided at the bottom of the measuring section, the side of the pre-embedded section is fixedly connected to a limit plate, a first baffle is provided on the side of the pre-embedded section, a second baffle is provided on the side of the pre-embedded section, the side of the first baffle is fixedly connected to a first fixed plate, and the side of the second baffle is fixedly connected to the second fixed plate.

[0008] Preferably, vertical rods are inserted inside the first fixing plate and the second fixing plate, the top of the vertical rods is fixedly connected to the top plate, the side of the top plate is fixedly connected to the side plate, the surface of the first baffle plate and the second baffle plate is fixedly connected to the threaded rod, and the outside of the threaded rod is socketed with a butterfly nut.

[0009] Preferably, a plug rod is fixedly connected to the side surface of the first baffle, and a plug hole is provided on the side surface of the second baffle, and the plug rod is inserted into the plug hole.

[0010] Preferably, the surface of the second fixing plate is fixedly connected to a fixing rod, and two fixing rods are provided.

[0011] Preferably, a rubber ring is embedded in the first fixing plate, and two rubber rings are provided.

[0012] Preferably, one end of the fixing rod is fixedly connected to a ball head, and the ball heads are symmetrically distributed.

[0013] The utility model of a water conservancy and hydropower water level benchmark has the following advantages:

[0014] 1. A water conservancy and hydropower water level benchmark is provided by adding a pre-buried section at the bottom of the measuring section, installing a limit plate on the side of the pre-buried section, adding a first baffle plate on the side of the pre-buried section, adding a second baffle plate on the side of the pre-buried section, installing a first fixed plate on the side of the first baffle plate, and installing a second fixed plate on the side of the second baffle plate. Before the water level benchmark needs to be installed, the first baffle plate and the second baffle plate are directly installed between the two limit plates, and the first baffle plate and the second baffle plate can be fixed to the outside of the pre-buried section by the first fixed plate and the second fixed plate. When the water level gauge is hammered into the ground and the ground contacts the bottom plate, the water level benchmark can continue to be driven into the ground, which effectively prevents the measuring section from being buried underground and makes it more convenient to fix it.

[0015] 2. A water conservancy and hydropower water level benchmark, wherein a vertical rod is inserted into a first fixing plate and a second fixing plate, a top plate is installed on the top of the vertical rod, a side plate is installed on the side of the top plate, a threaded rod is installed on the surface of the first baffle plate and the second baffle plate, and a butterfly nut is sleeved on the outside of the threaded rod. Before installation, the vertical rod is inserted into the first fixing plate and the second fixing plate, and then the threaded rod is directly inserted into the side plate of the top plate, and then the butterfly nut is directly fixed on the outside of the threaded rod. At this time, the vertical rod can be fixed. When installing the water level benchmark, the vertical rod can be directly inserted into the ground at the same time, thereby increasing its contact area with the ground and making its installation more stable. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solution of the implementation mode of the utility model, the drawings required for use in the implementation mode will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0018] Figure 2 This is a schematic diagram of the fixing rod structure of the utility model;

[0019] Figure 3 It is a schematic diagram of the top plate structure of the utility model;

[0020] Figure 4 For the utility model Figure 3 Enlarged view of part A.

[0021] Explanation of the markings in the figure: 1. Measuring section; 2. First baffle; 3. First fixing plate; 4. Second fixing plate; 5. Embedded section; 6. Second baffle; 7. Insert rod; 8. Ball head; 9. Rubber ring; 10. Socket; 11. Limit plate; 12. Side plate; 13. Top plate; 14. Vertical rod; 15. Butterfly nut; 16. Threaded rod; 17. Fixing rod. DETAILED DESCRIPTION

[0022] In the following, only some exemplary embodiments are briefly described. As those skilled in the art will appreciate, the described embodiments may be modified in various ways without departing from the spirit or scope of the embodiments of the present invention. Therefore, the drawings and descriptions are considered to be exemplary and non-restrictive in nature.

[0023] In the description of the embodiments of the present invention, it should be understood that the terms "length", "vertical", "horizontal", "top", "bottom", etc. indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the embodiments of the present invention.

[0024] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present utility model, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined.

[0025] In the embodiments of the present utility model, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or a communication; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present utility model can be understood according to specific circumstances.

[0026] The disclosure below provides many different embodiments or examples for realizing different structures of the embodiments of the present utility model. In order to simplify the disclosure of the embodiments of the present utility model, the components and settings of specific examples are described below. Of course, they are only examples, and the purpose is not to limit the embodiments of the present utility model. In addition, the embodiments of the present utility model can repeat reference numbers and / or reference letters in different examples, and this repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed.

[0027] In order to better understand the purpose, structure and function of the utility model, the utility model is further described in detail below in conjunction with the accompanying drawings.

[0028] like Figure 1-4 As shown, a water conservancy and hydropower water level benchmark of the utility model comprises a measuring section 1, a pre-buried section 5 is provided at the bottom of the measuring section 1, a limit plate 11 is fixedly connected to the side of the pre-buried section 5, a first baffle 2 is provided on the side of the pre-buried section 5, a second baffle 6 is provided on the side of the pre-buried section 5, the first baffle 2 is fixedly connected to the first fixed plate 3 on the side, and the second baffle 6 is fixedly connected to the second fixed plate 4 on the side, by adding a pre-buried section 5 at the bottom of the measuring section 1, installing a limit plate 11 on the side of the pre-buried section 5, adding a first baffle 2 on the side of the pre-buried section 5, and adding a second baffle 6 on the side of the pre-buried section 5. Plate 6, the first fixing plate 3 is installed on the side of the first baffle plate 2, and the second fixing plate 4 is installed on the side of the second baffle plate 6. Before the water level mark needs to be installed, the first baffle plate 2 and the second baffle plate 6 are directly installed between the two limit plates 11. The first baffle plate 2 and the second baffle plate 6 can be fixed to the outside of the embedded section 5 through the first fixing plate 3 and the second fixing plate 4. When the water level gauge is hammered into the ground and the ground contacts the bottom plate, the water level mark can be further driven into the ground, which effectively prevents the measuring section 1 from being buried underground, making it more convenient to fix it.

[0029] A vertical rod 14 is inserted into the first fixing plate 3 and the second fixing plate 4, the top of the vertical rod 14 is fixedly connected to the top plate 13, the side of the top plate 13 is fixedly connected to the side plate 12, the first baffle plate 2 and the second baffle plate 6 are fixedly connected to the threaded rod 16, and the butterfly nut 15 is sleeved on the outside of the threaded rod 16. By inserting the vertical rod 14 into the first fixing plate 3 and the second fixing plate 4, the top plate 13 is installed on the top of the vertical rod 14, the side plate 12 is installed on the top plate 13, the threaded rod 16 is installed on the surface of the first baffle plate 2 and the second baffle plate 6, and the butterfly nut 15 is sleeved on the outside of the threaded rod 16. Before installation, the vertical rod 14 is inserted into the first fixing plate 3 and the second fixing plate 4, and then the threaded rod 16 is directly inserted into the side plate 12 on the side of the top plate 13, and then the butterfly nut 15 is directly fixed on the outside of the threaded rod 16. At this time, the vertical rod 14 can be fixed. When installing the water level mark, the vertical rod 14 can be directly inserted into the ground at the same time, which increases its contact area with the ground and makes its installation more stable.

[0030] The first baffle plate 2 is fixedly connected to the plug rod 7 on the side, and the second baffle plate 6 has a hole 10 on the side, and the plug rod 7 is inserted into the hole 10. By installing the plug rod 7 on the side of the first baffle plate 2 and the hole 10 on the side of the second baffle plate 6, the plug rod 7 is installed in the hole 10, and the first baffle plate 2 and the second baffle plate 6 can be preliminarily fixed.

[0031] The surface of the second fixing plate 4 is fixedly connected to the fixing rods 17 , and two fixing rods 17 are provided. By installing the fixing rods 17 on the surface of the second fixing plate 4 , the first fixing plate 3 and the second fixing plate 4 can be fixed by inserting the fixing rods 17 into the first fixing plate 3 .

[0032] The first fixing plate 3 is inlaid with a rubber ring 9 , and two rubber rings 9 are provided. The rubber ring 9 is installed inside the first fixing plate 3 , so that the fixing rod 17 can be easily inserted into the first fixing plate 3 .

[0033] One end of the fixing rod 17 is fixedly connected to the ball head 8 , and the ball heads 8 are symmetrically distributed. By adding the ball head 8 at one end of the fixing rod 17 , the fixing rod 17 is prevented from falling out from the first fixing plate 3 .

[0034] The working principle of the water conservancy and hydropower water level benchmark: when using the water level benchmark, the first baffle plate 2 and the second baffle plate 6 are directly installed between the two limit plates 11, and the first baffle plate 2 and the second baffle plate 6 can be fixed to the outside of the embedded section 5 through the first fixing plate 3 and the second fixing plate 4, and the plug rod 7 is installed in the socket 10. At this time, the first baffle plate 2 and the second baffle plate 6 can be initially fixed, and the fixing rod 17 and the ball head 8 can be inserted into the first fixing plate 3 to fix the first fixing plate 3 and the second fixing plate 4, and the vertical rod 14 is inserted into the socket 10. Insert the first fixing plate 3 and the second fixing plate 4, then insert the threaded rod 16 directly into the side plate 12 of the top plate 13, and then fix the butterfly nut 15 directly on the outside of the threaded rod 16. At this time, the vertical rod 14 can be fixed. When installing the water level mark, the vertical rod 14 can be directly inserted into the ground at the same time, which increases its contact area with the ground. When the water level gauge is hammered into the ground and the ground contacts the bottom plate, the water level mark can continue to be driven into the ground, which effectively prevents the measuring section 1 from being buried in the ground, making it more convenient to fix it.

[0035] It is understood that the present invention is described by some embodiments, and those skilled in the art are aware that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the scope of protection of the present invention.

Claims

1. A water level benchmark for water resources and hydropower, comprising a measuring section (1), characterized in that: The bottom of the measuring section (1) is provided with an embedded section (5), the side of the embedded section (5) is fixedly connected to a limit plate (11), the side of the embedded section (5) is provided with a first baffle plate (2), the side of the embedded section (5) is provided with a second baffle plate (6), the side of the first baffle plate (2) is fixedly connected to a first fixed plate (3), and the side of the second baffle plate (6) is fixedly connected to a second fixed plate (4).

2. The water conservancy and hydropower water level benchmark according to claim 1, characterized in that: A vertical rod (14) is inserted into the first fixing plate (3) and the second fixing plate (4); the top of the vertical rod (14) is fixedly connected to the top plate (13); the side of the top plate (13) is fixedly connected to the side plate (12); the surface of the first baffle plate (2) and the second baffle plate (6) is fixedly connected to a threaded rod (16); the outside of the threaded rod (16) is sleeved with a butterfly nut (15).

3. The water conservancy and hydropower water level benchmark according to claim 1, characterized in that: The first baffle plate (2) is fixedly connected to a plug rod (7) on its side, and a plug hole (10) is provided on the second baffle plate (6) side, and the plug rod (7) is inserted into the plug hole (10).

4. The water conservancy and hydropower water level benchmark according to claim 1, characterized in that: The surface of the second fixing plate (4) is fixedly connected to a fixing rod (17), and two fixing rods (17) are provided.

5. The water conservancy and hydropower water level benchmark according to claim 1, characterized in that: A rubber ring (9) is embedded inside the first fixing plate (3), and two rubber rings (9) are provided.

6. The water conservancy and hydropower water level benchmark according to claim 4, characterized in that: One end of the fixing rod (17) is fixedly connected to a ball head (8), and the ball heads (8) are symmetrically distributed.