High-altitude cantilever structure erecting platform
By using a triangular support structure formed between the support rods, inclined rods and buildings in the construction of cantilever structures, the problems of high construction costs, large space occupation and low construction efficiency in the prior art are solved, and lower erecting height, lower cost and higher construction efficiency are achieved.
Patent Information
- Application Number
- CN202421501058.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-27
- Publication Date
- 2025-04-22
- Estimated Expiration
- 2034-06-27
AI Technical Summary
In the construction of existing cantilever structures, the floor-standing formwork support system has problems such as high cost and large space occupation. In addition, the steel cantilever scaffolding needs to strictly control the positioning of embedded parts such as wire ropes and steel pull rods to prevent the concrete from shifting during pouring, resulting in low construction efficiency.
A triangular support structure is formed between the support rod, oblique rod and the building. Through the combination of support rod, oblique rod and support rod, stable support is provided, the demand for embedded parts is reduced, and construction efficiency is improved.
Compared with floor-standing cantilever support, the overall erection height is smaller, the cost is reduced, the demand for embedded parts is reduced, and the construction efficiency is improved.
Smart Images

Figure CN222782192U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of high-altitude cantilever structures, and in particular to a high-altitude cantilever structure erection platform. Background Art
[0002] With the diversification of modern architectural design functions, in order to meet the visual effect of the facade floating in the air and meet the requirements of large indoor areas, cantilever structure has become one of the important technical means to achieve unique architectural design.
[0003] In the construction of cantilever beams, support platforms are usually used for support. Some existing support platforms are ground-type formwork support systems. This support method has the problems of high cost and large space occupation. Therefore, some people choose to use steel cantilever scaffolding, which adopts I-beam cantilever, uses steel wire ropes and steel tie rods for upward inclined tensioning, and steel for downward inclined support. This cantilever support method has strict requirements on the length of the I-beam, and requires a large number of embedded parts such as steel wire ropes and steel tie rods. In addition, the positioning of embedded parts needs to be strictly controlled to prevent displacement during concrete pouring. The time spent and the accuracy are high, which affects the subsequent construction efficiency, so further improvement is needed. Utility Model Content
[0004] In order to reduce the impact on the overall construction work efficiency, the present application provides a high-altitude cantilever structure erection platform.
[0005] The application provides a high-altitude cantilever structure erection platform, which adopts the following technical solutions:
[0006] A high-altitude cantilever structure erection platform includes a support rod connected to the side wall of a building, a formwork frame arranged above the support rod, an inclined rod arranged below the support rod, and a support rod arranged on the inclined rod, wherein the length direction of the support rod is parallel to the upper surface of the building, the upper end of the inclined rod is fixedly connected to the end of the support rod away from the floor slab, the lower end of the inclined rod is fixedly connected to the side wall of the building, one end of the support rod is fixedly connected to the middle part of the support rod, and the other end of the support rod is fixedly connected to the support rod.
[0007] By adopting the above technical solution, a triangular support is formed between the support rod, the diagonal rod and the building. Due to the high stability of the triangle, it provides support for the formwork frame set on the support rod and the subsequent cantilever structure. Compared with the ground-type cantilever support, the overall erection height is smaller and the cost is also reduced. Compared with the cantilever beam structure supported by the steel wire rope diagonal brace, the required embedded parts are also reduced, and the impact on the overall construction efficiency is also lower.
[0008] Preferably, the support rod comprises a first support rod connected to one end of the support rod close to the building and a second support rod fixedly connected to the middle part of the support rod.
[0009] By adopting the above technical solution, the support rods include the first support rod and the second support rod, and form multiple triangles between the support rod and the diagonal rod, so as to increase the connection between the support rod and the diagonal rod, and also increase the support for the upper vertical rod and the cantilever structure.
[0010] Preferably, support members are provided on both sides of the middle portion of the oblique rod.
[0011] By adopting the above technical solution, when the support rod connected to the middle part of the diagonal support is subjected to the gravity of the upper formwork frame, the pressure on the middle part of the support rod increases. At this time, a support member is provided to provide a certain supporting load strength for the diagonal rod.
[0012] Preferably, the support member includes support plates fixedly connected to both sides of the oblique rod.
[0013] By adopting the above technical solution, support is provided for the wing plate in the diagonal rod.
[0014] Preferably, the support member is a supporting I-beam, the diagonal rod is an I-beam, the two wing plates of the supporting I-beam are respectively fixed to the surfaces of the two wing plates in the diagonal rod that are close to each other, and the web of the supporting I-beam is vertically fixed to the web in the diagonal rod.
[0015] By adopting the above technical solution, the support members and the diagonal rods are I-beams, which reduces the time required for precise positioning during fixation, is more convenient, and the bearing capacity of the diagonal rods is also improved.
[0016] Preferably, the formwork frame includes a vertical pole fixedly connected to the support rod, the length direction of the vertical pole is perpendicular to the length direction of the support rod, a plurality of vertical poles are arranged at intervals along the length direction of the support rod, and shear braces are fixedly connected between the vertical poles near both ends of the support rod.
[0017] By adopting the above technical solution, the shear brace is provided to improve the connection between the vertical poles at both ends of the support rod, thereby improving the connection effect of the vertical poles far away from the building.
[0018] Preferably, the formwork frame also includes a cross bar fixedly connected to the vertical pole, the length direction of the cross bar is parallel to the length direction of the support pole, a plurality of cross bars are arranged at intervals along the height direction of the vertical pole, and the ends of the shear braces are fixedly connected to the cross bar.
[0019] By adopting the above technical solution, the connection strength between adjacent vertical poles is improved by setting the cross bar, and the shear brace is also convenient for fixing, so as to reduce the difficulty of installing the shear brace on the vertical pole.
[0020] Preferably, the spacing between adjacent uprights gradually decreases in a direction away from the building.
[0021] By adopting the above technical solution, the supporting effect of the support rod on the vertical pole is gradually reduced when it is arranged in the direction away from the building. Therefore, by gradually reducing the distance between adjacent vertical poles in the direction away from the building, the connection effect between the vertical poles away from the building and the building is improved, thereby improving the supporting effect of the subsequent cantilever structure.
[0022] Preferably, the formwork support frame further comprises a guy brace, the lower end of which is fixedly connected to the upper surface of the floor slab, and the upper end of which is inclined toward the direction close to the vertical pole and fixedly connected to the vertical pole.
[0023] By adopting the above technical solution and setting a guy brace, the connection strength between the opposing poles and the building can be further improved.
[0024] In summary, the utility model has the following beneficial effects:
[0025] 1. A triangular support is formed between the support rod, the diagonal rod and the building. Due to the high stability of the triangle, it provides support for the formwork frame set on the support rod and the subsequent cantilever structure. Compared with the ground-type cantilever support, the overall erection height is smaller and the cost is also reduced. Compared with the cantilever beam structure supported by the steel wire rope diagonal brace, the required embedded parts are also reduced, and the impact on the overall construction efficiency is also lower.
[0026] 2. By providing support members, a certain supporting load strength is provided to the diagonal rod. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0028] Figure 2 is a schematic diagram of the structure of the support rod in an embodiment of the present application;
[0029] Figure 3 yes Figure 2 A local enlarged schematic diagram of part A in FIG.
[0030] Figure 4 yes Figure 2 A partial enlarged schematic diagram of part B in FIG.
[0031] Figure 5 yes Figure 2A local enlarged schematic diagram of part C in FIG.
[0032] Figure 6 It is a schematic diagram of the structure of the support member in an embodiment of the present application.
[0033] Explanation of the accompanying drawings: 1. Building; 11. Embedded parts; 111. First plate body; 112. Anchor bars; 113. Second plate body; 114. First mounting plate; 2. Support rods; 3. Formwork frame; 31. Connecting rods; 32. Vertical rods; 33. Crossbars; 34. Steering braces; 35. Shear braces; 4. Diagonal rods; 41. Second mounting plate; 5. Struts; 51. First struts; 52. Second struts; 6. Bolts; 61. Nuts; 7. Third mounting plate; 8. Pull rod bolts; 9. Support parts. DETAILED DESCRIPTION
[0034] The following is combined with Figure 1-6 , further details of this application are given.
[0035] The embodiment of the present application discloses a high-altitude cantilever structure erection platform.
[0036] Example:
[0037] A high-altitude cantilever structure erection platform, refer to Figure 1 , Figure 2 , including a support rod 2 connected to the side wall of the building 1, a formwork frame 3 arranged above the support rod 2, an inclined rod 4 arranged below the support rod 2, and a support rod 5 arranged on the inclined rod 4. In this embodiment, the support rod 2, the inclined rod 4 and the support rod 5 are all arranged by I-beams, and the I-beam specifically includes two wing plates arranged opposite to each other and a web fixedly connected between the wing plates.
[0038] Reference Figure 2 , Figure 3In this embodiment, the support rod 2 is specifically fixedly connected to the side wall of the floor slab, and the length direction of the support rod 2 is parallel to the upper surface of the floor slab. The fixing method is specifically through connection with the embedded parts 11 embedded in the floor slab. The embedded parts 11 include a first plate body 111, an anchor bar 112 fixedly penetrated through the first plate body 111, a second plate body 113 fixedly connected to the anchor bar 112, and a first mounting plate 114 fixedly connected to the first plate body 111. Four anchor bars 112 are arranged at intervals along the length direction of the first plate body 111, and two are arranged at intervals along the width direction of the first plate body 111. The number of the second plate bodies 113 is the same as the number of the first plate bodies 111. Among them, the first mounting plate 114 is fixedly connected to the surface of the first plate body 111 away from the anchor bar 112, two first mounting plates 114 are provided and two are arranged at intervals along the width direction of the first plate body 111, the width of the first mounting plate 114 is lower than the spacing between the two wing plates, and there is space between the two first mounting plates 114 for the web plate in the support rod 2 to be installed, and the two first mounting plates 114 abut against the two opposite surfaces of the web plate in the support rod 2, and the first mounting plate 114 is threaded with bolts 6, and a number of bolts 6 are respectively arranged at intervals along the length direction and width direction of the first mounting plate 114, and the bolts 6 are threadedly connected with nuts 61 to install the support rod 2 on the side wall of the floor plate.
[0039] Reference Figure 2 , Figure 4 , wherein the upper end of the inclined rod 4 is fixedly connected to the end of the support rod 2 away from the floor plate, specifically, the upper end surface of the inclined rod 4 is fixedly connected with a second mounting plate 41, the second mounting plate 41 abuts against the wing plate located below the support rod 2, and the second mounting plate 41 is threaded with bolts 6, and a plurality of bolts 6 are respectively arranged along the length direction and the width direction of the second mounting plate 41, and the bolts 6 are threadedly connected with nuts 61, so as to install the lower end of the inclined rod 4 on the support rod 2. The lower end of the inclined rod 4 is also fixedly connected to the floor plate through the embedded part 11, and the lower end of the inclined rod 4 and the end of the support rod 2 connected to the floor plate are arranged in the same vertical plane, so that the triangle formed by the support rod 2, the inclined rod 4 and the floor plate is arranged in a right triangle.
[0040] Reference Figure 2 , Figure 3, wherein the brace 5 is arranged between the support rod 2 and the diagonal rod 4, and the brace 5 specifically includes a first brace 51 connected to one end of the support rod 2 close to the floor plate and a second brace 52 fixedly connected to the middle of the support rod 2, and one end of the first brace 51 and the second brace 52 far from the support rod 2 are both fixedly connected to the middle of the upper wing plate in the diagonal rod 4. The fixing method of the brace 5 is specifically that the wing plate at the bottom of the support rod 2 and the wing plate at the top of the diagonal rod 4 are protrudingly fixed with a third mounting plate 7, two third mounting plates 7 are arranged along the width direction of the wing plate, and the two third mounting plates 7 form a mounting cavity for the web plate of the brace 5 to be installed, and the third mounting plate 7 is penetrated by bolts 6, and a plurality of bolts 6 are arranged at intervals along the length direction of the third mounting plate 7, specifically two bolts are arranged, and the bolts 6 are threadedly connected with nuts 61 to install the brace 5 between the support rod 2 and the diagonal rod 4.
[0041] Reference Figure 1 , Figure 4 The formwork frame 3 specifically includes a connecting rod 31 fixedly connected to the support rod 2, a vertical rod 32 fixedly connected to the connecting rod 31, a cross rod 33 fixedly connected to the vertical rod 32, and a catapult 34 connected to the vertical rod 32. In this embodiment, the length direction of the connecting rod 31 is parallel to the width direction of the wing plate in the support rod 2, and a plurality of connecting rods 31 are arranged at intervals along the length direction of the support rod 2. The connecting rod 31 is also an I-beam. The connection method between the connecting rod 31 and the support rod 2 is specifically that a pull rod bolt 8 is wound around the connecting rod 31, and the pull rod bolt 8 is arranged in an inverted U shape. The two ends of the pull rod bolt 8 are respectively abutted against the two sides of the support rod 2, and the two ends of the pull rod bolt 8 are penetrated by connecting plates, and nuts 61 are threadedly connected to fix the connection with the support rod 2.
[0042] In this embodiment, the length direction of the vertical pole 32 is perpendicular to the length direction of the support pole 2. A plurality of vertical poles 32 are arranged at intervals along the length direction of the support pole 2, and the spacing between adjacent vertical poles 32 gradually decreases in the direction away from the building 1. In this embodiment, the length direction of the cross bar 33 is perpendicular to the length direction of the vertical pole 32. A plurality of cross bars 33 are arranged at intervals along the length direction of the vertical pole 32, and are fixedly connected to the vertical pole 32 by connecting fasteners, specifically cross fasteners. Since the connecting fasteners are prior art, they will not be described in detail here. Among them, the lower end of the guy 34 is fixedly connected to the upper surface of the floor plate, and is fixedly connected to at least two vertical poles 32.
[0043] Furthermore, in order to improve the connection strength between the vertical rods 32 at both ends of the support rod 2, in this embodiment, a shear brace 35 is fixedly connected between the vertical rods 32 near the two ends of the support rod 2, and the end of the shear brace 35 is specifically fixedly connected to the cross bar 33.
[0044] Reference Figure 2 , Figure 5Further, in order to improve the supporting effect of the formwork frame 3, that is, the bearing capacity of the subsequent cantilever structure of the formwork frame 3, support members 9 are provided on both sides of the middle of the diagonal rod 4. In this embodiment, the support members 9 can be specifically support plates fixedly connected to both sides of the diagonal rod 4. The support plates are fixedly connected between the two wing plates in the two diagonal rods 4 and fixedly connected to the web plates in the diagonal rods 4, and can be fixed by welding. Or as Figure 6 As shown, the support member 9 is specifically a supporting I-beam, and the two wing plates of the supporting I-beam are respectively fixed to the surfaces of the two wing plates in the diagonal rod 4 that are close to each other, and the web of the supporting I-beam is vertically fixed to the web in the diagonal rod 4.
[0045] The implementation principle of the high-altitude cantilever structure erection platform in the embodiment of the present application is: a triangular support is formed between the support rod 2, the diagonal rod 4 and the building 1. Due to the high stability of the triangle, it provides support for the formwork frame 3 set on the support rod 2 and the subsequent cantilever structure. Compared with the ground-type cantilever support, the overall erection height is smaller and the cost is also reduced. Compared with the cantilever beam structure supported by the steel wire rope diagonal brace, the required embedded parts 11 are also reduced, and the impact on the overall construction efficiency is also lower.
[0046] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A high-altitude cantilever structure erection platform, characterized in that: The invention comprises a support rod (2) connected to the side wall of a building (1), a formwork frame (3) arranged above the support rod (2), an inclined rod (4) arranged below the support rod (2), and a support rod (5) arranged on the inclined rod (4), wherein the length direction of the support rod (2) is parallel to the upper surface of the building (1), the upper end of the inclined rod (4) is fixedly connected to an end of the support rod (2) away from the floor slab, the lower end of the inclined rod (4) is fixedly connected to the side wall of the building (1), one end of the support rod (5) is fixedly connected to the middle part of the support rod (2), and the other end of the support rod (5) is fixedly connected to the support rod (2).
2. The high-altitude cantilever structure erection platform according to claim 1, characterized in that: The support rod (5) comprises a first support rod (51) connected to an end of the support rod (2) close to the building (1), and a second support rod (52) fixedly connected to the middle part of the support rod (2).
3. The high-altitude cantilever structure erection platform according to claim 1, characterized in that: Support members (9) are provided on both sides of the middle portion of the oblique rod (4).
4. The high-altitude cantilever structure erection platform according to claim 3, characterized in that: The support member (9) comprises a support plate fixedly connected to both sides of the diagonal rod (4), the diagonal rod (4) being an I-beam, the support plate fixedly connected between two wing plates in the two diagonal rods (4) and fixedly connected to a web plate in the diagonal rod (4).
5. The high-altitude cantilever structure erection platform according to claim 3, characterized in that: The support member (9) is a supporting I-beam, the diagonal rod (4) is an I-beam, the two wing plates of the supporting I-beam are respectively fixed to surfaces of two wing plates in the diagonal rod (4) close to each other, and the web of the supporting I-beam is vertically fixed to the web in the diagonal rod (4).
6. The high-altitude cantilever structure erection platform according to claim 1, characterized in that: The formwork frame (3) comprises a vertical rod (32) fixedly connected to the support rod (2); the length direction of the vertical rod (32) is perpendicular to the length direction of the support rod (2); a plurality of vertical rods (32) are arranged at intervals along the length direction of the support rod (2); and a shear brace (35) is fixedly connected between the vertical rods (32) near the two ends of the support rod (2).
7. The high altitude cantilever structure erection platform according to claim 6, characterized in that: The formwork frame (3) further comprises a cross bar (33) fixedly connected to the vertical bar (32); the length direction of the cross bar (33) is parallel to the length direction of the support bar (2); a plurality of cross bars (33) are arranged at intervals along the height direction of the vertical bar (32); and the ends of the shear braces (35) are fixedly connected to the cross bar (33).
8. The high-altitude cantilever structure erection platform according to claim 7, characterized in that: The spacing between adjacent upright poles (32) gradually decreases in a direction away from the building (1).
9. The high-altitude cantilever structure erection platform according to claim 6, characterized in that: The formwork support (3) further comprises a prop (34), the lower end of which is fixedly connected to the upper surface of the floor slab, and the upper end of which is inclined towards the vertical pole (32) and fixedly connected to the vertical pole (32).