Intelligent construction site sewage discharge detector
By using clamping blocks and drive parts to fix the detection probe in the sewage detector, the problem of corrosion caused by impurities in the sewage hole is solved, and the convenient removal and operation of the detection probe is improved.
Patent Information
- Application Number
- CN202420876364.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2025-04-22
- Estimated Expiration
- 2034-04-24
AI Technical Summary
During the inspection process of existing sewage detectors, impurities in the sewage can easily enter the threaded hole through the gap between the detection probe and the threaded hole, resulting in corrosion of the threaded hole and increasing the difficulty of removing the detection probe.
A smart construction site sewage discharge detector is designed, and the detection probe is fixed using clamping blocks and drive parts. The clamping block is located outside the drainage pipe to avoid contact with sewage, and the probe is fixed by rotating the disk to drive the clamping blocks to simplify operation.
It effectively avoids impurities entering the threaded hole, reduces the risk of corrosion, simplifies the removal process of the detection probe, and improves the convenience and safety of operation.
Smart Images

Figure CN222784498U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sewage detectors, and in particular to a smart construction site sewage discharge detector. Background Art
[0002] With the development of society, factories have been opened in cities large and small across the country to supply production. While these factories are developing rapidly, they are also gradually destroying our living environment, and it is necessary to detect the wastewater discharged by the factories in real time.
[0003] The existing detection method is to install a sewage detector on the drain pipe, open a threaded hole on the drain pipe, and insert the detection probe of the sewage detector into the drain pipe through the threaded hole for detection.
[0004] However, sewage detection is generally a long-term detection. Impurities in the sewage will enter the threaded hole through the gap between the detection probe and the threaded hole. After a period of use, the impurities will corrode the threaded hole. When the detection probe of the sewage detector needs to be maintained or replaced, the detection probe must be removed from the drain pipe. However, since the threaded hole has been corroded by impurities, the detection probe is not easy to separate from the threaded hole, which increases the difficulty of operation. Utility Model Content
[0005] Therefore, the technical problem to be solved by the utility model is to overcome the defect that after the sewage detector in the prior art is inserted into the drain pipe through the threaded hole, impurities in the sewage will enter the threaded hole through the gap between the detection probe and the threaded hole, corroding the threaded hole, and the detection probe is not easy to separate from the threaded hole, increasing the operational defects, thereby providing a smart construction site sewage discharge detector.
[0006] In order to solve the above technical problems, the utility model provides a smart construction site sewage discharge detector, comprising: a detector body, suitable for being installed on a drainage pipe, a detection probe being electrically connected to the detector body, and the drainage pipe having an opening for inserting the detection probe;
[0007] A clamping block, movably mounted on the drain pipe, the clamping block having a plurality of circumferentially distributed around the detection probe;
[0008] A driving member, a driving end of which is connected to the plurality of clamping blocks, and the driving member is used to drive the plurality of clamping blocks to move toward the detection probe to fix the detection probe.
[0009] Optionally, a base is fixedly connected to the drain pipe, the base is a circular ring structure, the detection probe is located at the center of the base, and the clamping block is radially slidably installed on the base.
[0010] Optionally, the driving member is a rotating disk rotatably mounted on the base, the rotating disk is sleeved on the outer side of the base, and the rotating disk is connected to each of the clamping blocks via a transmission structure.
[0011] Optionally, the transmission structure includes a transmission rod, one end of which is rotatably connected to the clamping block, and the other end of which is rotatably connected to the rotating disk.
[0012] Optionally, it further comprises: a locking member, a locking end of which is suitable for connecting with the rotating disk, and the locking member is used to fix the rotating disk.
[0013] Optionally, the locking member includes a locking box fixedly mounted on the drain pipe and a limiting rod slidably mounted in the locking box, one end of the limiting rod passes through the locking box and is connected to a limiting block, and the outer side surface of the rotating disk has a limiting groove that cooperates with the limiting block.
[0014] Optionally, it further includes: a first elastic member connected to the limiting rod, the first elastic member having an elastic force driving the limiting rod to move toward the rotating disk.
[0015] Optionally, the first elastic member is a spring, which is arranged in the locking box and sleeved on the outside of the limiting rod, one end of the spring abuts against the inner wall of the locking box, and the other end of the spring abuts against the movable plate on the limiting rod.
[0016] Optionally, it further comprises: a cleaning ring, which is sleeved on the outer side of the detection probe, and the cleaning ring has a cleaning groove for passing the detection probe.
[0017] Optionally, a plurality of first connecting rods are rotatably connected to the detection probe, a plurality of second connecting rods are rotatably connected to the cleaning ring, and the plurality of first connecting rods are rotatably connected to the plurality of second connecting rods respectively;
[0018] A second elastic member is disposed between the first connecting rods and the second connecting rods, and the second elastic member has an elastic force for driving the first connecting rods and the second connecting rods to move away from each other.
[0019] The technical solution of the utility model has the following advantages:
[0020] 1. The intelligent construction site sewage discharge detector provided by the utility model has a detection probe of the detector body that is fixed by a clamping block. The clamping block is located on the outside of the drain pipe and will not come into contact with impurities in the sewage. When the detection probe needs to be taken out, the two can be easily separated. The opening on the drain pipe is only used to insert the detection probe and does not play a fixing role, thereby ensuring that the detection probe can be smoothly taken out of the drain pipe.
[0021] 2. The intelligent construction site sewage discharge detector provided by the utility model can simultaneously drive multiple clamping blocks to move toward the detection probe by rotating the disk, thereby completing the fixation of the detection probe. Not only is the fixing effect better, but the operation is also very convenient.
[0022] 3. The intelligent construction site sewage discharge detector provided by the utility model, when the detection probe is taken out from the drain pipe, the cleaning ring can clean the impurities attached to the surface of the detection probe to avoid the impurities remaining on the detection probe, thereby ensuring the cleanliness of the detection probe. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0024] Figure 1 This is a front view of the smart construction site sewage discharge detector provided in the first embodiment of the utility model;
[0025] Figure 2 for Figure 1 A magnified view of the middle base;
[0026] Figure 3 for Figure 1 A cross-sectional view of the middle locking box;
[0027] Figure 4 for Figure 1 A magnified view of the detection probe in the middle;
[0028] Figure 5 for Figure 4 A cross-sectional view of the connection between the first connecting rod and the second connecting rod.
[0029] Description of reference numerals:
[0030] 1. Detector body; 2. Drain pipe; 3. Detection probe; 4. Opening; 5. Clamping block; 6. Base; 7. Rotating disk; 8. Transmission rod; 9. Locking piece; 10. Locking box; 11. Limit rod; 12. Limit block; 13. Limit groove; 14. Spring; 15. Movable plate; 16. Cleaning ring; 17. Cleaning groove; 18. First connecting rod; 19. Second connecting rod; 20. Second elastic piece. DETAILED DESCRIPTION
[0031] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0032] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0033] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0034] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0035] like Figure 1 , Figure 2 As shown, a specific implementation manner of the smart construction site sewage discharge detector provided in this embodiment includes: a detector body 1, a clamping block 5 and a driving member, the detector body 1 is suitable for being installed on the drain pipe 2, the detector body 1 is electrically connected with a detection probe 3, the drain pipe 2 has an opening 4 for inserting the detection probe 3, the clamping block 5 is movably installed on the drain pipe 2, the clamping block 5 has a plurality of circumferentially distributed with the detection probe 3 as the center, the driving end of the driving member is connected to the plurality of clamping blocks 5, and the driving member is used to drive the plurality of clamping blocks 5 to move toward the detection probe 3 to fix the detection probe 3.
[0036] It should be noted that the opening 4 on the drain pipe 2 is smooth and only serves to allow the detection probe 3 to be inserted into the drain pipe 2 .
[0037] The smart construction site sewage discharge detector provided in this embodiment has a detection probe 3 of the detector body 1 that is fixed by a clamping block 5. The clamping block 5 is located on the outside of the drain pipe 2 and will not come into contact with impurities in the sewage. When the detection probe 3 needs to be taken out, the two can be easily separated. The opening 4 on the drain pipe 2 is only used to insert the detection probe 3 and does not play a fixing role, thereby ensuring that the detection probe 3 can be smoothly taken out of the drain pipe 2.
[0038] like Figure 1 , Figure 2 As shown, in the smart construction site sewage discharge detector provided by the present embodiment, a base 6 is fixedly connected to the drain pipe 2, and the base 6 is a circular ring structure. The detection probe 3 is located at the center of the base 6, and the clamping block 5 is radially slidably installed on the base 6. Specifically, the base 6 has four radially distributed slide grooves, and the clamping block 5 is installed in the slide grooves. The detection probe 3 can be fixed by driving the sliding of the clamping block 5. In addition, as a replaceable embodiment, the clamping block 5 can also be rotatably installed on the base 6, for example, one end of the clamping block 5 is rotatably installed on the base 6. When the detection probe 3 needs to be fixed, the clamping block 5 is rotated to rotate the free end of the clamping block 5 toward the detection probe 3. The detection probe 3 is fixed by multiple clamping blocks 5.
[0039] like Figure 1 , Figure 2 As shown, in the smart construction site sewage discharge detector provided by this embodiment, the driving member is a rotating disk 7 rotatably mounted on the base 6, and the rotating disk 7 is sleeved on the outer side of the base 6. The rotating disk 7 is connected to each clamping block 5 through a transmission structure. Specifically, two symmetrically distributed arc grooves are arranged on the rotating disk 7, and a cylindrical structure inserted into the arc groove is arranged on the base 6. The cylindrical structure is inserted into the arc groove from bottom to top. The rotating connection between the rotating disk 7 and the base 6 is realized by the cooperation of the arc groove and the cylindrical structure. When in use, the rotating disk 7 can simultaneously drive multiple clamping blocks 5 to move toward the detection probe 3, thereby completing the fixing of the detection probe 3. Not only is the fixing effect better, but the operation is also very convenient. In addition, as an alternative embodiment, the driving member can also be a bolt, and each clamping block 5 corresponds to a bolt. One end of the bolt passes through the base 6 and abuts against the clamping block 5. The bolt is also threadedly connected to the base 6. The clamping block 5 can be pushed to move toward the detection probe 3 by rotating the bolt.
[0040] like Figure 2As shown, in the smart construction site sewage discharge detector provided by this embodiment, the transmission structure includes a transmission rod 8, one end of the transmission rod 8 is rotatably connected to the clamping block 5, and the other end of the transmission rod 8 is rotatably connected to the rotating disk 7. The number of transmission rods 8 is the same as the number of clamping blocks 5. When the rotating disk 7 rotates, the transmission rod 8 is driven to rotate, thereby driving the clamping block 5 to move. In addition, as an alternative embodiment, the transmission structure can also be a slider with an inclined surface, and sliders with corresponding inclined surfaces are respectively provided on the clamping block 5 and the rotating disk 7. When the rotating disk 7 rotates, the inclined surface of the slider on the rotating disk 7 cooperates with the inclined surface of the slider on the clamping block 5, thereby driving the clamping block 5 to move.
[0041] like Figures 1 to 3 As shown, the smart construction site sewage discharge detector provided in this embodiment also includes: a locking member 9, the locking end of the locking member 9 is suitable for connecting with the rotating disk 7, and the locking member 9 is used to fix the rotating disk 7. When the rotating disk 7 rotates to a certain angle, the rotating disk 7 can be fixed under the action of the locking member 9 to prevent the rotating disk 7 from continuing to move.
[0042] like Figures 1 to 3 As shown, in the smart construction site sewage discharge detector provided in this embodiment, the locking member 9 includes a locking box 10 fixedly mounted on the drain pipe 2 and a limiting rod 11 slidably mounted in the locking box 10. One end of the limiting rod 11 passes through the locking box 10 and is connected to the limiting block 12. The outer side of the rotating disk 7 has a limiting groove 13 that matches the limiting block 12. By inserting the limiting block 12 into the limiting groove 13, the rotating disk 7 can be locked. In addition, as an alternative embodiment, the limiting block 12 and the limiting groove 13 can also be replaced by two friction plates, and the friction force can be used to fix the rotating disk 7.
[0043] like Figure 3 As shown, the smart construction site sewage discharge detector provided in this embodiment also includes: a first elastic member connected to the limit rod 11, the first elastic member has an elastic force driving the limit rod 11 to move toward the rotating disk 7, and the limit rod 11 will always remain connected to the rotating disk 7 under the action of the first elastic member to ensure the fixing effect of the rotating disk 7. In addition, as an alternative implementation, the first elastic member can also be replaced by a bolt, one end of the bolt is threadedly connected to the locking box 10, and is rotatably connected to the limit rod 11, and the limit rod 11 can be driven to move by rotating the bolt.
[0044] like Figure 3As shown, in the smart construction site sewage discharge detector provided by this embodiment, the first elastic member is a spring 14, which is arranged in the locking box 10 and sleeved on the outside of the limit rod 11. One end of the spring 14 abuts against the inner wall of the locking box 10, and the other end of the spring 14 abuts against the movable plate 15 on the limit rod 11. The spring 14 can drive the limit rod 11 to move, and the spring 14 is coaxially arranged with the limit rod 11, which has a larger operating space. In addition, as an alternative embodiment, the first elastic member can also be an airbag, a rubber pad, etc.
[0045] like Figure 4 As shown, the smart construction site sewage discharge detector provided in this embodiment also includes: a cleaning ring 16, which is sleeved on the outside of the detection probe 3. The cleaning ring 16 has a cleaning groove 17 for passing the detection probe 3. When the detection probe 3 is taken out from the drain pipe 2, the cleaning ring 16 can clean the impurities attached to the surface of the detection probe 3 to avoid impurities remaining on the detection probe 3, thereby ensuring the cleanliness of the detection probe 3.
[0046] like Figure 4 , Figure 5 As shown, in the smart construction site sewage discharge detector provided by the present embodiment, a plurality of first connecting rods 18 are rotatably connected to the detection probe 3, a plurality of second connecting rods 19 are rotatably connected to the cleaning ring 16, the plurality of first connecting rods 18 are rotatably connected to the plurality of second connecting rods 19 respectively, a second elastic member 20 is arranged between the plurality of first connecting rods 18 and the second connecting rods 19, the second elastic member 20 has an elastic force for driving the first connecting rod 18 and the second connecting rod 19 away from each other. In the present embodiment, the second elastic member 20 is a torsion spring, which is installed at the connection between the first connecting rod 18 and the second connecting rod 19. Under the action of the torsion spring, the first connecting rod 18 and the second connecting rod 19 are moved away from each other, so that the cleaning rod moves along the detection probe 3 to clean the detection probe 3.
[0047] The method for using the smart construction site sewage discharge detector provided in this embodiment is as follows:
[0048] First, insert the detection probe 3 into the drain pipe 2 from the opening 4 of the drain pipe 2, then move the limit rod 11 to separate the limit block 12 from the limit groove 13, rotate the rotating disk 7, and the rotating disk 7 drives the multiple clamping blocks 5 to move toward the detection probe 3 through the transmission rod 8 to complete the fixation of the detection probe 3, then loosen the limit rod 11, and under the action of the spring 14, the limit block 12 is reinserted into the limit groove 13 to fix the rotating disk 7.
[0049] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from these are still within the scope of protection of the present utility model.
Claims
1. A smart construction site sewage discharge detector, characterized in that: include: A detector body (1) is suitable for being installed on a drain pipe (2); a detection probe (3) is electrically connected to the detector body (1); and the drain pipe (2) has an opening (4) for inserting the detection probe (3); A clamping block (5) is movably mounted on the drain pipe (2), and the clamping block (5) has a plurality of clamping blocks distributed along the circumference with the detection probe (3) as the center; A driving member, a driving end of which is connected to the plurality of clamping blocks (5), and the driving member is used to drive the plurality of clamping blocks (5) to move toward the detection probe (3) to fix the detection probe (3).
2. The smart construction site sewage discharge detector according to claim 1, characterized in that: The drain pipe (2) is fixedly connected to a base (6), the base (6) is a circular ring structure, the detection probe (3) is located at the center of the base (6), and the clamping block (5) is radially slidably mounted on the base (6).
3. The smart construction site sewage discharge detector according to claim 2 is characterized in that: The driving member is a rotating disk (7) rotatably mounted on the base (6); the rotating disk (7) is sleeved on the outside of the base (6); and the rotating disk (7) is connected to each of the clamping blocks (5) via a transmission structure.
4. The smart construction site sewage discharge detector according to claim 3 is characterized in that: The transmission structure comprises a transmission rod (8), one end of which is rotationally connected to the clamping block (5), and the other end of which is rotationally connected to the rotating disk (7).
5. The smart construction site sewage discharge detector according to claim 3 is characterized in that: Also includes: A locking member (9), wherein the locking end of the locking member (9) is suitable for being connected to the rotating disk (7), and the locking member (9) is used to fix the rotating disk (7).
6. The smart construction site sewage discharge detector according to claim 5, characterized in that: The locking member (9) comprises a locking box (10) fixedly mounted on the drain pipe (2) and a limiting rod (11) slidably mounted in the locking box (10); one end of the limiting rod (11) passes through the locking box (10) and is connected to a limiting block (12); and the outer side surface of the rotating disk (7) has a limiting groove (13) matched with the limiting block (12).
7. The smart construction site sewage discharge detector according to claim 6, characterized in that: Also includes: A first elastic member is connected to the limiting rod (11), and the first elastic member has an elastic force for driving the limiting rod (11) to move toward the rotating disk (7).
8. The smart construction site sewage discharge detector according to claim 7, characterized in that: The first elastic member is a spring (14), which is arranged in the locking box (10) and sleeved on the outer side of the limiting rod (11); one end of the spring (14) abuts against the inner wall of the locking box (10), and the other end of the spring (14) abuts against the movable plate (15) on the limiting rod (11).
9. The smart construction site sewage discharge detector according to any one of claims 1 to 8, characterized in that: Also includes: A cleaning ring (16) is sleeved on the outer side of the detection probe (3), and the cleaning ring (16) has a cleaning groove (17) for passing the detection probe (3).
10. The smart construction site sewage discharge detector according to claim 9, characterized in that: The detection probe (3) is rotatably connected to a plurality of first connecting rods (18), the cleaning ring (16) is rotatably connected to a plurality of second connecting rods (19), and the plurality of first connecting rods (18) are rotatably connected to the plurality of second connecting rods (19) respectively; A second elastic member (20) is arranged between the plurality of first connecting rods (18) and the second connecting rods (19), and the second elastic member (20) has an elastic force for driving the first connecting rod (18) and the second connecting rod (19) to move away from each other.