Through type service tunnel with functions of auxiliary construction, ventilation, drainage and rescue

By designing a through-type service tunnel, the difficulties in construction, ventilation, drainage and rescue of long-distance railway tunnels have been solved, and versatility and safety have been improved.

CN222797494UActive Publication Date: 2025-04-25CHINA RAILWAY FIRST SURVEY & DESIGN INST GRP
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420934526.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-30
Publication Date
2025-04-25
Estimated Expiration
2034-04-30

AI Technical Summary

Technical Problem

Long-distance and extremely long-distance railway tunnels have difficult and difficult problems in construction, ventilation, drainage and rescue, especially when fires occur, it is difficult for people to escape and rescue.

Method used

A through-type service tunnel is designed, including a left-line horizontal channel, a vertical shaft, a service channel and a right-line horizontal channel. The service channel is arranged vertically between the left-line tunnel and the right-line tunnel. The vertical shaft is connected to the top, and the horizontal channel is connected horizontally to the tunnel and the service channel. A side ditch and a central ditch are set at the bottom of the service channel, and annular pipes and fans are installed inside for ventilation, drainage and rescue.

Benefits of technology

It realizes the multifunctionality of assisting construction, ventilation, drainage and rescue, increases the construction ventilation and drainage capabilities, ensures operation ventilation and drainage, and provides rapid escape and rescue channels in the event of fire, improving the safety of personnel in the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222797494U_ABST
    Figure CN222797494U_ABST
Patent Text Reader

Abstract

The utility model relates to a through-type service tunnel with functions of auxiliary construction, ventilation, drainage and rescue. Long-distance and extra-long-distance tunnels have the problems that the construction difficulty is large, ventilation and drainage are difficult, and escape and rescue are difficult when safety accidents happen. The system is arranged on the whole line between a left line tunnel and a right line tunnel and comprises a left line transverse channel, a vertical shaft, a service channel and a right line transverse channel, the service channels are longitudinally arranged between the left-line tunnel and the right-line tunnel and arranged on the whole line, and the tops of the service channels are connected into the vertical shafts; the left-line transverse channel is transversely connected between the left-line tunnel and the service channel, and the right-line transverse channel is transversely connected between the right-line tunnel and the service channel. The tunnel serves as an auxiliary service tunnel, is additionally arranged on the side of a main track tunnel, has the functions of auxiliary construction, ventilation, drainage and rescue, increases the construction working face, guarantees the air quality in the main track, can be used as a drainage tunnel, and can be used as an escape channel to guarantee the safety of personnel in the tunnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel engineering, in particular to a through-type service tunnel with the functions of auxiliary construction, ventilation, drainage and rescue. Background Art

[0002] With the development of railway construction projects, the scale and number of long-distance railway tunnels are increasing. Long-distance tunnels are not only difficult to construct, but also bring about the emergence of tunnel railway operation safety issues. Especially for extra-long-distance railway tunnels, due to their long length, it is difficult for trains to drive out of the tunnel within a safe time when a fire occurs in the tunnel, which will pose a great threat to the safety of personnel and the tunnel structure.

[0003] Therefore, long-distance and extra-long-distance tunnels have problems such as great construction difficulty, difficulty in ventilation and drainage, and difficulty in escape and rescue in the event of a safety accident. It is of great significance to design a multifunctional service tunnel to solve the construction, ventilation, drainage and rescue problems of auxiliary tunnels for long-distance tunnel construction. Summary of the invention

[0004] The purpose of the utility model is to provide a through service tunnel with the functions of auxiliary construction, ventilation, drainage and rescue, so as to at least solve the problems of great construction difficulty, ventilation and drainage difficulty, and difficulty in escape and rescue in the event of a safety accident existing in long-distance and extra-long-distance tunnels.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] A through-type service tunnel with the functions of auxiliary construction, ventilation, drainage and rescue, wherein the through-type service tunnel is set up along the entire line between the left-line tunnel and the right-line tunnel, and includes a left-line cross passage, a vertical shaft, a service passage and a right-line cross passage;

[0007] The service channel is longitudinally arranged between the left-line tunnel and the right-line tunnel, arranged along the entire line, and connected to the vertical shaft at the top;

[0008] The left-line cross channel is transversely connected between the left-line tunnel and the service channel, and the right-line cross channel is transversely connected between the right-line tunnel and the service channel.

[0009] Furthermore, the left-line transverse channel and the right-line transverse channel are staggered in the longitudinal direction.

[0010] Furthermore, the vertical shaft position corresponds to a node where the left-line cross channel connects to the service channel.

[0011] Furthermore, the vertical shaft position corresponds to a node where the right-line cross channel connects to the service channel.

[0012] Furthermore, the service channel is arranged lower than the left-line tunnel and the right-line tunnel, and the left-line transverse channel and the right-line transverse channel are connected to the service channel obliquely downward from the left-line tunnel and the right-line tunnel respectively.

[0013] Furthermore, longitudinal side ditches are arranged on both sides of the bottom of the service channel, and an annular pipe is arranged in the lining structure of the service channel, and the bottom end of the annular pipe is connected to the side ditch.

[0014] Furthermore, a longitudinal central ditch is provided at the center of the bottom of the service channel, and the side ditches are connected to the central ditch through transverse connecting pipes.

[0015] Furthermore, a transverse transverse channel center ditch is provided at the center of the bottom of the left-line transverse channel and the right-line transverse channel.

[0016] Furthermore, fans are arranged on both lateral sides of the service channel.

[0017] Furthermore, fans are provided on both lateral sides of the left-line transverse channel and the right-line transverse channel.

[0018] Compared with the prior art, the beneficial effects of the utility model are as follows:

[0019] As an auxiliary service tunnel, the utility model is added beside the main line tunnel and has the functions of auxiliary construction, ventilation, drainage and rescue:

[0020] 1. During the construction period, the utility model can be used as a through level guide to assist construction, increase the construction working surface, and assist in tunnel construction ventilation and construction drainage.

[0021] 2. During operation, fans and valves are installed in service channels and cross channels as needed as ventilation ducts. Fans are used to guide the airflow to form a segmented ventilation mode for operational ventilation to ensure the air quality within the main line.

[0022] 3. For tunnels in severe cold and cold areas, the utility model can be used as a drainage tunnel to avoid freezing damage such as ice hanging in the tunnel and siltation in the drainage ditch.

[0023] 4. When a fire or emergency occurs in the main line tunnel, personnel can quickly escape into the service channel through the cross channel to ensure the safety of personnel in the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.

[0025] Figure 1 It is a plan view of an embodiment of the utility model.

[0026] Figure 2 It is a schematic elevation view of an embodiment of the utility model.

[0027] Figure 3 This is a schematic diagram of the fan layout in the horizontal channel.

[0028] The symbols in the figure are:

[0029] 1-left line tunnel, 2-left line cross passage, 3-vertical shaft, 4-service passage, 5-right line cross passage, 6-right line tunnel, 7-fan, 8-side ditch, 9-center ditch. DETAILED DESCRIPTION

[0030] In order to facilitate the understanding of the present invention, the present invention will be described more comprehensively with reference to the relevant drawings. The drawings provide preferred embodiments of the present invention. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly and comprehensively understood.

[0031] In the description of this patent, it should be understood that the terms "center", "left", "right", "top", "bottom", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing this patent and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on this patent.

[0032] In the description of this patent, it should be noted that, unless otherwise clearly specified and limited, the terms "access", "setting", etc. should be understood in a broad sense, for example, it can be fixedly connected, set, or detachably connected, set, or integrally connected, set. For ordinary technicians in this field, the specific meanings of the above terms in this patent can be understood according to specific circumstances.

[0033] The utility model provides a through-type service tunnel with the functions of auxiliary construction, ventilation, drainage and rescue, which achieves the purpose of assisting the ventilation and drainage of the mainline tunnel construction, ensuring the ventilation and drainage of the operation, and ensuring the safety of the personnel in the tunnel in case of fire or emergency.

[0034] like Figure 1 , the direction of the left-line tunnel 1 and the right-line tunnel 6 in the figure is defined as the longitudinal direction, and the direction perpendicular to the direction of the left-line tunnel 1 and the right-line tunnel 6 is the transverse direction. The through-type service tunnel is set up between the left-line tunnel 1 and the right-line tunnel 6, including the left-line cross channel 2, the vertical shaft 3, the service channel 4 and the right-line cross channel 5. The service channel 4 is set up longitudinally between the left-line tunnel 1 and the right-line tunnel 6, and is set up along the entire line, and is connected to the vertical shaft 3 at the top. The left-line cross channel 2 is laterally connected between the left-line tunnel 1 and the service channel 4, and the right-line cross channel 5 is laterally connected between the right-line tunnel 6 and the service channel 4.

[0035] The vertical shaft 3 can directly utilize the existing structure during the tunnel construction. The position of the vertical shaft 3 corresponds to the node where the left-line cross channel 2 connects to the service channel 4 or the node where the right-line cross channel 5 connects to the service channel 4. Multiple locations are set at intervals. The lateral distance between the service channel 4 and the left-line tunnel 1 and the right-line tunnel 6 is roughly the same.

[0036] Figure 1 In the middle, the left-line transverse channel 2 and the right-line transverse channel 5 are staggered front and back longitudinally to avoid the transverse channels on both sides of the service channel 4 to correspond horizontally and the ventilation on both sides to affect each other.

[0037] like Figure 2 The service channel 4 is set lower than the left-line tunnel 1 and the right-line tunnel 6, and the left-line transverse channel 2 and the right-line transverse channel 5 are respectively connected to the service channel 4 obliquely downward from the left-line tunnel 1 and the right-line tunnel 6. The utility model has a drainage function, and the oblique downward transverse channel is more conducive to drainage.

[0038] The structure of the service channel 4 can adopt a general tunnel structure with a lining and a drainage system, such as longitudinal side ditches 8 on both sides of the bottom and a longitudinal central ditch 9 in the center of the bottom. An annular pipe is arranged in the lining structure of the service channel 4, and the bottom end of the annular pipe is connected to the side ditch 8. The side ditch 8 is connected to the central ditch 9 through a transverse connecting pipe, and the side ditch itself has a drainage function.

[0039] A transverse channel center ditch is arranged at the center of the bottom of the left-line transverse channel 2 and the right-line transverse channel 5 for channel drainage. The transverse channel center ditch can be connected to the center ditch 9 for confluence and discharge.

[0040] like Figure 3 Fans 7 are arranged on both sides of the service channel 4, and fans 7 are arranged on both sides of the left-line horizontal channel 2 and the right-line horizontal channel 5, all of which are installed on fan brackets.

[0041] During the construction period, the service tunnel of the utility model can be used as a through-level guide to assist in construction, increase the construction working surface, and assist in tunnel construction ventilation and construction drainage.

[0042] During operation, fans and valves are installed in the service channel 4 and the cross channel as needed. The service tunnel of the utility model is used as a ventilation duct. Based on the fan to guide the airflow, a segmented ventilation mode is formed for operational ventilation to ensure the air quality in the main line.

[0043] For tunnels in severe cold and cold areas, the service tunnel of the utility model can be used as a drainage tunnel to avoid freezing damage such as ice hanging in the tunnel and siltation in the drainage ditch.

[0044] When a fire or emergency occurs in the main line tunnel, personnel can quickly escape into the service channel through the cross channel to ensure the safety of personnel in the tunnel.

[0045] The above specific examples are used to illustrate the present invention, which are only used to help understand the present invention and are not intended to limit the present invention. For those skilled in the art of the present invention, some simple deductions, deformations or substitutions can be made based on the idea of ​​the present invention.

Claims

1. A through-type service tunnel with the functions of auxiliary construction, ventilation, drainage and rescue, characterized in that: The through-type service tunnel is arranged along the entire line between the left-line tunnel (1) and the right-line tunnel (6), and includes a left-line cross passage (2), a vertical shaft (3), a service passage (4) and a right-line cross passage (5); The service channel (4) is longitudinally arranged between the left-line tunnel (1) and the right-line tunnel (6), is arranged along the entire line, and is connected to the vertical shaft (3) at the top; The left-lane transverse passage (2) is transversely connected between the left-lane tunnel (1) and the service passage (4), and the right-lane transverse passage (5) is transversely connected between the right-lane tunnel (6) and the service passage (4); the service passage (4) is arranged below the left-lane tunnel (1) and the right-lane tunnel (6), and the left-lane transverse passage (2) and the right-lane transverse passage (5) are connected to the service passage (4) obliquely downward from the left-lane tunnel (1) and the right-lane tunnel (6), respectively; The service channel (4) adopts a tunnel structure, has a lining and a drainage system, and is provided with longitudinal side ditches (8) on both sides of the bottom. An annular pipe is arranged in the lining structure of the service channel (4), and the bottom end of the annular pipe is connected to the side ditch (8); a longitudinal central ditch (9) is provided in the center of the bottom of the service channel (4), and the side ditch (8) is connected to the central ditch (9) through a transverse connecting pipe; a transverse central ditch is provided in the center of the bottom of the left-line transverse channel (2) and the right-line transverse channel (5); Fans (7) are arranged on both sides of the service channel (4); Fans (7) are arranged on both sides of the left-line transverse channel (2) and the right-line transverse channel (5).

2. A through-type service tunnel with auxiliary construction, ventilation, drainage and rescue functions according to claim 1, characterized in that: The left-line transverse channel (2) and the right-line transverse channel (5) are arranged staggered front to back in the longitudinal direction.

3. A through-type service tunnel with auxiliary construction, ventilation, drainage and rescue functions according to claim 2, characterized in that: The position of the vertical shaft (3) corresponds to the node where the left-line cross channel (2) connects to the service channel (4).

4. A through-type service tunnel with auxiliary construction, ventilation, drainage and rescue functions according to claim 2, characterized in that: The position of the vertical shaft (3) corresponds to the node where the right-line cross channel (5) connects to the service channel (4).

Citation Information

Cited By

  • Multi-technology combined measurement method for ultra-long seabed double-hole railway tunnel and service tunnel

    CN120947594A

  • Multi-technology joint measurement method for ultra-long undersea twin-tunnel railway tunnel plus service tunnel

    CN120947594B