Assembled integral dike engineering structure

By assembling the integrated embankment engineering structure, using prefabricated components and superimposed pouring technology, the problems of long construction period and difficult to guarantee the quality of traditional embankment projects are solved, and the construction period is shortened and the quality is reliable, which is suitable for complex environments and emergency flood prevention needs.

CN222809932UActive Publication Date: 2025-04-29中国水利水电第七工程局有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421819597.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2025-04-29
Estimated Expiration
2034-07-30

AI Technical Summary

Technical Problem

Traditional embankment projects have problems such as long construction periods, difficult to guarantee quality, and heavy impacts due to flood seasons and typhoons. The construction area is narrow and long and the environment is complex, making it difficult to ensure the construction quality and construction period.

Method used

The integrated embankment engineering structure is adopted, including prefabricated vertical pile wall embankment protection structure, cast-in pile structure, prefabricated interphase overlapping beams, overlapping road substrates, prefabricated retaining walls and concrete structures. The embankment engineering structure is quickly formed through the hoisting and superposition of prefabricated components.

Benefits of technology

It has achieved a shortened construction period and reliable quality embankment construction, avoiding poor forming quality and hole collapse problems in traditional construction, and is suitable for complex environments and emergency flood prevention needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222809932U_ABST
    Figure CN222809932U_ABST
Patent Text Reader

Abstract

The utility model provides an assembled integral type embankment engineering structure which is used for carrying out water retaining protection on a river channel and comprises a prefabricated vertical type pile wall embankment protection structure, a cast-in-place pile structure, a prefabricated alternate superposed beam, a superposed roadbed plate, a prefabricated retaining wall and a concrete structure. The prefabricated vertical pile wall embankment protection structure is arranged on the side edge of a river channel. The prefabricated interphase superposed beams are arranged on earthwork on one side of the river channel and located above the prefabricated vertical type pile wall embankment protection structure, one ends of the prefabricated interphase superposed beams convexly extend to the position above the river channel in a suspended mode, and the other ends of the prefabricated interphase superposed beams are located on one sides of the second exposed steel bars; the laminated roadbed plate is arranged above the prefabricated interphase laminated beam; the prefabricated retaining wall is positioned above the suspended end part of the prefabricated alternate superposed beam in the horizontal direction; and the concrete structure is arranged above the prefabricated vertical pile wall embankment protection structure, the cast-in-place pile structure and the prefabricated alternate superposed beam and is connected to one side of the prefabricated retaining wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to an assembled embankment engineering structure. Background Art

[0002] According to the country's future environmental governance policy, river regulation and levee projects will be the focus of environmental governance; for levee projects, flood control, water-friendliness, landscape and road traffic are highly valued. There is broad room for the development of levee projects in urban waters, but at the same time, higher requirements are placed on the construction period, construction efficiency and construction quality of levee projects. However, traditional levee projects have the following problems: First, the implementation mode of traditional levee structure construction is on-site pouring, which requires on-site reinforcement binding and planting of concrete structures, formwork installation and scaffolding, so it requires a lot of manpower and material resources, and the construction period is long, and the pouring quality cannot be guaranteed; second, the surrounding environment of levee projects is usually complex. On the one hand, it is restricted by the width of the river, the presence or absence of river beaches outside the levee, and existing roads and buildings. The construction area of ​​levee projects is relatively narrow and long, and the construction surface is limited. On the other hand, the construction site is open-air, which is greatly affected by the flood season and typhoons, and the construction period cannot be guaranteed.

[0003] Therefore, it is necessary to provide at least one assembled integral embankment engineering structure which can shorten the construction period and has reliable quality. Utility Model Content

[0004] The utility model aims to provide an assembled integral embankment engineering structure which can shorten the construction period and has reliable quality.

[0005] To achieve the above-mentioned purpose, the utility model provides an assembled integral embankment engineering structure for water retaining protection of a river channel, comprising a prefabricated upright pile wall embankment protection structure, a cast-in-place pile structure, a prefabricated alternating composite beam, a composite roadbed, a prefabricated retaining wall and a concrete structure; the prefabricated upright pile wall embankment protection structure is arranged on the side of the river channel, and the prefabricated upright pile wall embankment protection structure has a first exposed steel bar protruding above the earthwork of the river channel; the cast-in-place pile structure is inserted into the earthwork on one side of the river channel and is arranged at intervals with the prefabricated upright pile wall embankment protection structure, and the cast-in-place pile structure has a second exposed steel bar protruding above the earthwork of the river channel; the prefabricated alternating composite beam is arranged on the earthwork on one side of the river channel, and the prefabricated alternating composite beam is located above the prefabricated upright pile wall embankment protection structure, and one end of the prefabricated alternating composite beam in the horizontal direction is suspended The prefabricated alternating composite beam protrudes to the top of the river channel, the other end of the prefabricated alternating composite beam in the horizontal direction is located on one side of the second exposed steel bar, and the first exposed steel bar is passed through the prefabricated alternating composite beam in the up and down direction; a plurality of the composite roadbed plates are respectively arranged above the prefabricated alternating composite beam in the horizontal direction; the prefabricated retaining wall is vertically connected to the top of the composite roadbed plate and is located above the end of the prefabricated alternating composite beam that is suspended in the horizontal direction; the concrete structure is arranged above the prefabricated upright pile wall embankment protection structure, the cast-in-place pile structure and the prefabricated alternating composite beam and is connected to one side of the prefabricated retaining wall, and the concrete structure covers the first exposed steel bar and the second exposed steel bar, thereby connecting the prefabricated upright pile wall embankment protection structure, the cast-in-place pile structure, the prefabricated alternating composite beam, the composite roadbed plate and the prefabricated retaining wall together.

[0006] Compared with the prior art, the assembled integral embankment engineering structure of the utility model realizes the initial protection of the bank of the river channel by setting the prefabricated upright pile wall embankment protection structure on the side of the river channel, and then by setting a cast-in-place pile structure on the earthwork on one side of the river channel, the prefabricated alternating composite beam is hoisted on the earthwork on one side of the river channel, so that there is an initial position connection relationship between the prefabricated alternating composite beam and the first exposed steel bars of the prefabricated upright pile wall embankment protection structure and the second exposed steel bars of the cast-in-place pile structure, and then by arranging a prefabricated retaining wall on the composite roadbed, and setting the concrete structure on the prefabricated upright pile wall embankment protection structure The concrete structure is cast above the cast-in-place pile structure and the prefabricated interlaced composite beam, so that the concrete structure connects the prefabricated upright pile wall embankment protection structure, the cast-in-place pile structure, the prefabricated interlaced composite beam, the composite roadbed, and the prefabricated retaining wall together, thereby quickly forming an assembled integral embankment engineering structure for water retaining protection of the river channel, so as to realize the transformation of the implementation mode of embankment structure construction from traditional cast-in-place to assembled construction, avoiding the problems of poor molding quality and collapsed holes caused by the traditional use of only cast-in-place pile construction and only on-site casting of the overall embankment engineering structure, and ensuring the quality reliability of the embankment engineering. Moreover, assembled construction can complete the assembly of flood control roadbed, retaining wall and face protection of the embankment engineering in a short time, and the technical characteristics of prefabricated construction without formwork can immediately enter the composite casting construction link, greatly shortening the overall construction period of the embankment engineering, and has the characteristics of short construction period in the flood control field that is affected by the complex surrounding environment and flood season and races against time to rush for construction period.

[0007] Preferably, the prefabricated interlaced composite beam includes a cantilevered composite beam portion, a simply supported composite beam portion and a connecting I-beam, the cantilevered composite beam portion and the simply supported composite beam portion are arranged at intervals in the horizontal direction to form an installation interval, and the connecting I-beam is located in the installation interval and connected between the cantilevered composite beam portion and the simply supported composite beam portion, the cantilevered composite beam portion protrudes above the river channel in a suspended manner, the simply supported composite beam portion is located on one side of the second exposed steel bar, and the first exposed steel bar is passed through the installation interval.

[0008] Preferably, the concrete structure includes an upper concrete part and a first lower concrete part and a second lower concrete part respectively connected to the lower part of the upper concrete part, the upper concrete part is located above the prefabricated alternating composite beams and is used to connect the prefabricated alternating composite beams, the composite roadbed plate and the prefabricated retaining wall together, the first lower concrete part is filled in the installation interval and covers the first exposed steel bar and the connecting I-beam, the first lower concrete part is used to connect the upper concrete part, the prefabricated alternating composite beams and the prefabricated upright pile wall embankment protection structure together, the second lower concrete part is connected to one side of the simply supported composite beam part and covers the second exposed steel bar, and the second lower concrete part is used to connect the upper concrete part, the prefabricated alternating composite beams and the cast-in-place pile structure together.

[0009] Preferably, a first beam body steel bar is provided above the cantilevered composite beam portion, and the first beam body steel bar is inserted into the upper concrete portion; a second beam body steel bar is provided above the simply supported composite beam portion, and the second beam body steel bar is inserted into the upper concrete portion.

[0010] Preferably, a third beam body reinforcement is provided on one side of the simply supported composite beam portion, and the third beam body reinforcement is inserted into the second lower concrete portion.

[0011] Preferably, the prefabricated interlaced composite beam further comprises beam body connecting steel bars, the beam body connecting steel bars are located at the installation interval and connected between the cantilevered composite beam portion and the simply supported composite beam portion, and the first lower layer concrete portion covers the beam body connecting steel bars.

[0012] Preferably, it further comprises a first crown beam reinforcement cage, wherein the first crown beam reinforcement cage is arranged in the installation interval and sleeved on the first exposed reinforcement, and the upper concrete part and the first lower concrete part respectively cover the first crown beam reinforcement cage.

[0013] Preferably, it further includes a second crown beam reinforcement cage, which is arranged on one side of the simply supported composite beam portion and sleeved on the second exposed steel bars, and the upper concrete portion and the second lower concrete portion respectively cover the second crown beam reinforcement cage.

[0014] Preferably, it further comprises a shaped steel mesh, wherein the shaped steel mesh is arranged above the composite roadbed plate, and the concrete structure covers the shaped steel mesh.

[0015] Preferably, the prefabricated upright pile wall embankment protection structure includes a prefabricated unit and reinforced concrete for connecting to the river bank, the prefabricated unit is provided with a first reserved hole and a reserved half hole, the first reserved hole and the reserved half hole both penetrate the prefabricated unit in the up and down direction, the reserved half hole is arranged on the side wall of the prefabricated unit, the two adjacent prefabricated units on the left and right are spliced ​​to form a protective layer, the reserved half holes of the two adjacent prefabricated units on the left and right are spliced ​​to form a second reserved hole, a plurality of the protective layers are stacked in the up and down direction, the two adjacent first reserved holes on the upper and lower sides are opposite to each other and connected to form a first pouring hole position, the two adjacent second reserved holes on the upper and lower sides are opposite to each other and connected to form a second pouring hole position, a plurality of the reinforced concrete are respectively penetrated into the first pouring hole position and the second pouring hole position, and the upper end of the reinforced concrete protrudes above the earthwork of the river channel and forms the first exposed steel bar. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural diagram of the assembled integral embankment engineering structure of the utility model.

[0017] Figure 2 It is a structural diagram of the prefabricated alternately laminated beams of the assembled integral embankment engineering structure of the utility model.

[0018] Figure 3 It is a three-dimensional structural diagram of a prefabricated upright pile wall embankment protection structure of an assembled integral embankment engineering structure of the utility model.

[0019] Figure 4 It is a three-dimensional structural diagram of a prefabricated unit of a prefabricated upright pile wall embankment protection structure of an assembled integral embankment engineering structure of the utility model.

[0020] Figure 5 It is a structural diagram of the construction method of the utility model for assembling an integral embankment engineering structure when constructing a prefabricated upright pile wall embankment protection structure and a cast-in-place pile structure.

[0021] Figure 6 The utility model is a structural diagram of the construction method of the assembled integral embankment engineering structure when installing prefabricated alternately superimposed beams.

[0022] Figure 7 It is a structural diagram of the construction method of the utility model for assembling an integral embankment engineering structure when installing a superimposed road base plate.

[0023] Figure 8 It is a structural diagram of the construction method of the utility model of the assembled integral embankment engineering structure after the superimposed road base plate is installed.

[0024] Fig. 9 It is a structural diagram of the construction method of the utility model of the assembled integral embankment engineering structure after the prefabricated retaining wall is installed.

[0025] Fig.10 It is a structural diagram of the construction method of the assembled integral embankment engineering structure of the utility model after the first crown beam steel cage, the second crown beam steel cage and the formed steel mesh are installed.

[0026] Fig.11 It is a structural diagram of the construction method of the assembled integral embankment engineering structure of the utility model after the prefabricated drainage ditch is installed.

[0027] Fig.12 It is a structural diagram of the construction method of the assembled integral embankment engineering structure of the utility model after the concrete structure is poured.

[0028] Fig.13 It is a structural diagram of the construction method of the assembled integral embankment engineering structure of the utility model after the pavement structure is set. DETAILED DESCRIPTION

[0029] In order to explain the technical content and structural features of the present invention in detail, further description will be given below in combination with the embodiments and the accompanying drawings.

[0030] See also Figures 1 to 12The assembled integral embankment engineering structure 100 of the utility model is used for water retaining protection of a river channel, and comprises a prefabricated upright pile wall embankment protection structure 1, a cast-in-place pile structure 2, a prefabricated alternating composite beam 3, a composite roadbed 4, a prefabricated retaining wall 5 and a concrete structure 6; the prefabricated upright pile wall embankment protection structure 1 is arranged on the side of the river channel, and the prefabricated upright pile wall embankment protection structure 1 has a first exposed steel bar 121 protruding above the earthwork of the river channel; the cast-in-place pile structure 2 is inserted into the earthwork on one side of the river channel and is arranged at intervals with the prefabricated upright pile wall embankment protection structure 1, and the cast-in-place pile structure 2 has a second exposed steel bar 21 protruding above the earthwork of the river channel; the prefabricated alternating composite beam 3 is arranged on the earthwork on one side of the river channel, and the prefabricated alternating composite beam 3 is located above the prefabricated upright pile wall embankment protection structure 1, and one end of the prefabricated alternating composite beam 3 in the horizontal direction is suspended The prefabricated alternating composite beam 3 protrudes above the river channel, the other end of the prefabricated alternating composite beam 3 in the horizontal direction is located on one side of the second exposed steel bar 21, and the first exposed steel bar 121 is passed through the prefabricated alternating composite beam 3 in the up and down direction; a number of composite roadbed plates 4 are respectively arranged above the prefabricated alternating composite beam 3 in the horizontal direction; the prefabricated retaining wall 5 is vertically connected to the top of the composite roadbed plate 4 and is located above the end of the prefabricated alternating composite beam 3 in the horizontal direction that is suspended; the concrete structure 6 is arranged above the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2 and the prefabricated alternating composite beam 3 and is connected to one side of the prefabricated retaining wall 5, and the concrete structure 6 covers the first exposed steel bar 121 and the second exposed steel bar 21, thereby connecting the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternating composite beam 3, the composite roadbed plate 4, and the prefabricated retaining wall 5 together.

[0031] See also Figure 1 and Figure 2 In one embodiment, the prefabricated interlaced composite beam 3 includes a cantilevered composite beam portion 31, a simply supported composite beam portion 32 and a connecting I-beam 33. The cantilevered composite beam portion 31 and the simply supported composite beam portion 32 are arranged at intervals in the horizontal direction to form an installation interval 34, and the connecting I-beam 33 is located in the installation interval 34 and connected between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32. The cantilevered composite beam portion 31 protrudes above the river channel in a suspended manner, the simply supported composite beam portion 32 is located on one side of the second exposed steel bar 21, and the first exposed steel bar 121 is penetrated in the installation interval 34. Taking into account the landscape and hydrophilic functions of embankment projects, cantilever structures are often provided on the water surface. In order to avoid overturning during the installation of prefabricated cantilever beams, the utility model adopts a cantilevered composite beam portion 31, a simply supported composite beam portion 32 and a connecting I-beam 33 to form a two-span continuous beam, and the deadweight of the simply supported composite beam portion 32 is used to provide an anti-overturning moment for the composite beam of the cantilevered composite beam portion 31; at the same time, the installation interval 34 between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32 can be used for the first exposed steel bar 121 to pass through and for the concrete structure 6 to be poured and filled, thereby playing a role in connecting with other components.

[0032] See also Figure 1 as well as Figures 5 to 12 In one embodiment, the concrete structure 6 includes an upper concrete part 61 and a first lower concrete part 62 and a second lower concrete part 63 respectively connected to the lower part of the upper concrete part 61. The upper concrete part 61 is located above the prefabricated alternating composite beam 3 and is used to connect the prefabricated alternating composite beam 3, the composite roadbed 4 and the prefabricated retaining wall 5 together. The first lower concrete part 62 is filled in the installation interval 34 and covers the first exposed steel bar 121 and the connecting I-beam 33. The first lower concrete part 62 is used to connect the upper concrete part 61, the prefabricated alternating composite beam 3 and the prefabricated upright pile wall embankment protection structure 1 together. The second lower concrete part 63 is connected to one side of the simply supported composite beam part 32 and covers the second exposed steel bar 21. The second lower concrete part 63 is used to connect the upper concrete part 61, the prefabricated alternating composite beam 3 and the cast-in-place pile structure 2 together. Furthermore, a first beam body steel bar 35 is provided above the cantilevered composite beam portion 31, and the first beam body steel bar 35 is inserted into the upper concrete portion 61; a second beam body steel bar 36 is provided above the simply supported composite beam portion 32, and the second beam body steel bar 36 is inserted into the upper concrete portion 61, thereby strengthening the stability of the connection structure. Furthermore, a third beam body steel bar 37 is provided on one side of the simply supported composite beam portion 32, and the third beam body steel bar 37 is inserted into the second lower concrete portion 63, thereby further strengthening the stability of the connection structure.

[0033] See also Figure 1 as well as Figures 5 to 12 In one embodiment, the prefabricated alternating composite beam 3 also includes a beam body connecting steel bar 38, which is located at the installation interval 34 and connected between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32, and the first lower layer concrete portion 62 covers the beam body connecting steel bar 38, which on the one hand improves the structural stability of the connection between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32, and on the other hand improves the overall structural stability after pouring the concrete structure 6.

[0034] See also Figure 1 as well as Figures 5 to 12 In one embodiment, the assembled integral embankment engineering structure 100 of the utility model also includes a first crown beam steel cage 7, which is arranged in the installation interval 34 and is sleeved on the first exposed steel bar 121, and the upper concrete part 61 and the first lower concrete part 62 respectively cover the first crown beam steel cage 7, thereby enhancing the stability of the concrete structure 6.

[0035] See also Figure 1 as well as Figures 5 to 12In one embodiment, the assembled integral embankment engineering structure 100 of the utility model also includes a second crown beam steel cage 8, which is arranged on one side of the simply supported composite beam portion 32 and is sleeved on the second exposed steel bar 21, and the upper concrete portion 61 and the second lower concrete portion 63 respectively cover the second crown beam steel cage 8, thereby enhancing the stability of the concrete structure 6.

[0036] See also Figure 1 as well as Figures 5 to 12 In one embodiment, the assembled integral embankment engineering structure 100 of the utility model also includes a molded steel mesh 9, which is arranged above the composite roadbed plate 4, and the concrete structure 6 covers the molded steel mesh 9, thereby enhancing the stability of the concrete structure 6.

[0037] See also Figures 1 to 5 In one embodiment, the prefabricated upright pile wall embankment protection structure 1 includes a prefabricated unit 11 and reinforced concrete 12 for connecting to the river bank. The prefabricated unit 11 is provided with a first reserved hole 111 and a reserved half hole 112. The first reserved hole 111 and the reserved half hole 112 both penetrate the prefabricated unit 11 in the up-down direction. The reserved half hole 112 is arranged on the side wall of the prefabricated unit 11. The left and right adjacent prefabricated units 11 are spliced ​​to form a protective layer. The reserved half holes 112 of the left and right adjacent prefabricated units 11 are spliced ​​to form a second reserved hole. Several protective layers are stacked in the up-down direction. The upper and lower adjacent first reserved holes 111 are opposite to each other and connected to form a first pouring hole position. The upper and lower adjacent second reserved holes are opposite to each other and connected to form a second pouring hole position. Several reinforced concretes 12 are respectively penetrated in the first pouring hole position and the second pouring hole position, and the upper end of the reinforced concrete 12 protrudes above the earthwork of the river channel and forms a first exposed steel bar 121. Among them, the structure and principle of the prefabricated upright pile wall embankment protection structure 1 are existing technologies, so they are not described here in detail.

[0038] Combined with reference Figures 1 to 13 The utility model also provides a construction method for assembling an integral embankment engineering structure 100, and the specific embodiments are as follows:

[0039] Embodiment 1:

[0040] S1, construct a prefabricated upright pile wall embankment protection structure 1 on the side of the river channel, and make the first exposed steel bar 121 at the upper end of the prefabricated upright pile wall embankment protection structure 1 exposed and protrude above the earthwork of the river channel; construct a cast-in-place pile structure 2 on the earthwork on one side of the river channel, and make the second exposed steel bar 21 of the cast-in-place pile structure 2 protrude above the earthwork of the river channel; prefabricate the prefabricated alternate composite beams 3, the composite roadbed 4 and the prefabricated retaining wall 5;

[0041] S2, hoist the prefabricated interlaced composite beam 3 on the earthwork on one side of the river channel and make the prefabricated interlaced composite beam 3 be located above the prefabricated upright pile wall embankment protection structure 1, extend one end of the prefabricated interlaced composite beam 3 in the horizontal direction to the top of the river channel in a suspended manner, set the other end of the prefabricated interlaced composite beam 3 in the horizontal direction on one side of the second exposed steel bar 21, and make the first exposed steel bar 121 pass through the prefabricated interlaced composite beam 3 in the up-down direction;

[0042] S3, a plurality of laminated roadbeds 4 are respectively arranged above the prefabricated interlaced laminated beams 3 in the horizontal direction; a prefabricated retaining wall 5 is temporarily supported vertically above the laminated roadbed 4, and the prefabricated retaining wall 5 is located above the end of the prefabricated interlaced laminated beam 3 that is suspended in the horizontal direction;

[0043] S4, construct side formwork on the outer periphery of the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternate composite beam 3 and the composite roadbed 4, and form a concrete pouring space between the side formwork and the prefabricated retaining wall 5, and set a local formwork for blocking on the same outer side of the prefabricated retaining wall 5, the composite roadbed 4 and the prefabricated alternate composite beam 3;

[0044] S5, pouring the concrete structure 6 in the concrete pouring space, so that the concrete structure 6 is arranged above the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2 and the prefabricated alternating composite beam 3 and connected to one side of the prefabricated retaining wall 5, and the concrete structure 6 covers the first exposed steel bar 121 and the second exposed steel bar 21, thereby connecting the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternating composite beam 3, the composite roadbed plate 4, and the prefabricated retaining wall 5 together.

[0045] Embodiment 2:

[0046] S11, construct a prefabricated upright pile wall embankment protection structure 1 on the side of the river channel, and make the first exposed steel bar 121 at the upper end of the prefabricated upright pile wall embankment protection structure 1 exposed and protruding above the earthwork of the river channel; construct a cast-in-place pile structure 2 on the earthwork on one side of the river channel, and make the second exposed steel bar 21 of the cast-in-place pile structure 2 protrude above the earthwork of the river channel; prefabricated alternating composite beams 3, composite roadbed plates 4 and prefabricated retaining walls 5 are prefabricated; the prefabricated alternating composite beams 3 include a cantilevered composite beam portion 31, a simply supported composite beam portion 32 and a connecting I-beam 33, the cantilevered composite beam portion 31 and the simply supported composite beam portion 32 are arranged at intervals in the horizontal direction and form an installation interval 34, and the connecting I-beam 33 is located in the installation interval 34 and connected between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32;

[0047] S12, hoisting the prefabricated interlaced composite beam 3 on the earthwork at one side of the river channel and making the prefabricated interlaced composite beam 3 located above the prefabricated upright pile wall embankment protection structure 1, making the cantilevered composite beam portion 31 of the prefabricated interlaced composite beam 3 protrude above the river channel in a suspended manner at one end in the horizontal direction, making the simply supported composite beam portion 32 located at one side of the second exposed steel bar 21, and inserting the first exposed steel bar 121 into the installation interval 34;

[0048] S3, a plurality of laminated roadbeds 4 are respectively arranged above the prefabricated interlaced laminated beams 3 in the horizontal direction; a prefabricated retaining wall 5 is temporarily supported vertically above the laminated roadbed 4, and the prefabricated retaining wall 5 is located above the end of the prefabricated interlaced laminated beam 3 that is suspended in the horizontal direction;

[0049] S4, construct side formwork on the outer periphery of the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternate composite beam 3 and the composite roadbed 4, and form a concrete pouring space between the side formwork and the prefabricated retaining wall 5, and set a local formwork for blocking on the same outer side of the prefabricated retaining wall 5, the composite roadbed 4 and the prefabricated alternate composite beam 3;

[0050] S5, pouring a concrete structure 6 in the concrete pouring space, so that the concrete structure 6 is arranged above the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2 and the prefabricated interlaced composite beam 3 and connected to one side of the prefabricated retaining wall 5, and the concrete structure 6 covers the first exposed steel bar 121 and the second exposed steel bar 21, wherein the concrete structure 6 includes an upper concrete part 61 and a first lower concrete part 62 and a second lower concrete part 63 respectively connected to the lower part of the upper concrete part 61, the upper concrete part 61 is located above the prefabricated interlaced composite beam 3 and is used to place the prefabricated interlaced composite beam 3. The composite beam 3, the composite roadbed slab 4 and the prefabricated retaining wall 5 are connected together, the first lower concrete portion 62 is filled in the installation interval 34 and covers the first exposed steel bar 121 and the connecting I-beam 33, the first lower concrete portion 62 is used to connect the upper concrete portion 61, the prefabricated alternating composite beam 3 and the prefabricated upright pile wall embankment protection structure 1 together, the second lower concrete portion 63 is connected to one side of the simply supported composite beam portion 32 and covers the second exposed steel bar 21, the second lower concrete portion 63 is used to connect the upper concrete portion 61, the prefabricated alternating composite beam 3 and the cast-in-place pile structure 2 together.

[0051] Embodiment three:

[0052] S21, construct a prefabricated upright pile wall embankment protection structure 1 on the side of the river channel, and make the first exposed steel bar 121 at the upper end of the prefabricated upright pile wall embankment protection structure 1 exposed and protrude above the earthwork of the river channel; construct a cast-in-place pile structure 2 on the earthwork on one side of the river channel, and make the second exposed steel bar 21 of the cast-in-place pile structure 2 protrude above the earthwork of the river channel; prefabricated alternate composite beams 3, composite roadbed slabs 4 and prefabricated retaining walls 5 are prefabricated; the prefabricated alternate composite beams 3 include a cantilever composite beam portion 31, a simply supported composite beam portion 32, a connecting I-beam 33 and a beam body connecting steel bar 3 8. The cantilevered composite beam portion 31 and the simply supported composite beam portion 32 are arranged at intervals in the horizontal direction to form an installation interval 34, and the connecting I-beam 33 is located in the installation interval 34 and connected between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32, and the beam body connecting steel bars 38 are located in the installation interval 34 and connected between the cantilevered composite beam portion 31 and the simply supported composite beam portion 32; a first beam body steel bar 35 is arranged above the cantilevered composite beam portion 31, and a second beam body steel bar 36 is arranged above the simply supported composite beam portion 32; and a third beam body steel bar 37 is arranged on one side of the simply supported composite beam portion 32;

[0053] S22, hoisting the prefabricated interlaced composite beam 3 on the earthwork at one side of the river channel and making the prefabricated interlaced composite beam 3 located above the prefabricated upright pile wall embankment protection structure 1, making the cantilevered composite beam portion 31 of the prefabricated interlaced composite beam 3 protrude above the river channel in a suspended manner at one end in the horizontal direction, making the simply supported composite beam portion 32 located at one side of the second exposed steel bar 21, and inserting the first exposed steel bar 121 into the installation interval 34;

[0054] S23, a plurality of composite roadbed plates 4 are respectively arranged above the prefabricated interlaced composite beams 3 in the horizontal direction; a prefabricated retaining wall 5 is temporarily supported vertically above the composite roadbed plates 4, and the prefabricated retaining wall 5 is located above the end of the prefabricated interlaced composite beams 3 that is suspended in the horizontal direction; a first crown beam steel cage 7 is arranged in the installation interval 34, and the first crown beam steel cage 7 is sleeved on the first exposed steel bar 121, and a second crown beam steel cage 8 is arranged on one side of the simply supported composite beam portion 32, and the second crown beam steel cage 8 is sleeved on the second exposed steel bar 21; a formed steel mesh 9 is laid above the composite roadbed plates 4;

[0055] S24, construct side formwork on the outer periphery of the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternating composite beam 3 and the composite roadbed 4, and form a concrete pouring space between the side formwork and the prefabricated retaining wall 5, and set a local formwork for blocking on the same outer side of the prefabricated retaining wall 5, the composite roadbed 4 and the prefabricated alternating composite beam 3; set a prefabricated drainage ditch 200 on the side of the concrete structure 6 on the earthwork on one side of the river channel;

[0056] S25, pouring a concrete structure 6 in the concrete pouring space, so that the concrete structure 6 is arranged above the prefabricated upright pile wall embankment protection structure 1, the cast-in-place pile structure 2 and the prefabricated alternating composite beam 3 and connected to one side of the prefabricated retaining wall 5, and the concrete structure 6 covers the first exposed steel bar 121 and the second exposed steel bar 21, wherein the concrete structure 6 includes an upper concrete part 61 and a first lower concrete part 62 and a second lower concrete part 63 respectively connected to the lower part of the upper concrete part 61, the upper concrete part 61 is located above the prefabricated alternating composite beam 3 and is used to connect the prefabricated alternating composite beam 3, the composite roadbed slab 4 and the prefabricated retaining wall 5 together, the first lower concrete part 62 is filled in the installation interval 34 and covers the first exposed steel bar 121 and the connecting I-beam 33, the first lower concrete part 62 is used to connect the upper concrete part 61, the prefabricated alternating composite beam 3, the composite roadbed slab 4 and the prefabricated retaining wall 5 together. The interlayer composite beam 3 and the prefabricated upright pile wall embankment protection structure 1 are connected together, the second lower concrete part 63 is connected to one side of the simply supported composite beam part 32 and covers the second exposed steel bar 21, and the second lower concrete part 63 is used to connect the upper concrete part 61, the prefabricated interlayer composite beam 3 and the cast-in-place pile structure 2 together; wherein, the first beam body steel bar 35 is inserted in the upper concrete part 61; the second beam body steel bar 36 is inserted in the upper concrete part 61, the third beam body steel bar 37 is inserted in the second lower concrete part 63, the first lower concrete part 62 covers the beam body connecting steel bar 38, the upper concrete part 61 and the first lower concrete part 62 respectively cover the first crown beam steel bar cage 7, the upper concrete part 61 and the second lower concrete part 63 respectively cover the second crown beam steel bar cage 8, and the upper concrete part 61 of the concrete structure 6 covers the formed steel mesh 9.

[0057] S6, laying a pavement structure 300 on the concrete structure 6.

[0058] In summary, the utility model realizes the initial protection of the bank of the river channel by setting the prefabricated upright pile wall embankment protection structure 1 on the side of the river channel, and then sets the cast-in-place pile structure 2 on the earthwork on one side of the river channel, and hoists the prefabricated interlaced composite beam 3 on the earthwork on one side of the river channel, so that the prefabricated interlaced composite beam 3 and the first exposed steel bars 121 of the prefabricated upright pile wall embankment protection structure 1 and the second exposed steel bars 21 of the cast-in-place pile structure 2 have an initial position connection relationship, and then arranges the prefabricated retaining wall 5 on the composite roadbed 4, and sets the concrete structure 6 on the prefabricated upright pile wall embankment protection structure 1 and the cast-in-place pile structure 2. The concrete structure 6 is cast above the prefabricated alternating composite beam 3 and the prefabricated vertical pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternating composite beam 3, the composite roadbed 4, and the prefabricated retaining wall 5, so that the concrete structure 6 connects the prefabricated vertical pile wall embankment protection structure 1, the cast-in-place pile structure 2, the prefabricated alternating composite beam 3, the composite roadbed 4, and the prefabricated retaining wall 5 together, thereby quickly forming an assembled integral embankment engineering structure 100 for water retaining protection of the river channel, so as to realize the transformation of the implementation mode of embankment structure construction from traditional cast-in-place to assembled construction, avoiding the problems of poor molding quality and collapsed holes caused by the traditional use of only cast-in-place pile construction and only on-site casting of the integral embankment engineering structure, and ensuring the quality reliability of the embankment engineering. Secondly, assembled construction can complete the assembly of flood control roadbed, retaining wall and face protection of the embankment engineering in a short time, and the technical characteristics of prefabricated construction without formwork can immediately enter the composite casting construction link, greatly shortening the overall construction period of the embankment engineering, and has the characteristics of short construction period in the flood control field that is affected by the complex surrounding environment and flood season and races against time to rush for construction period. Thirdly, the prefabricated upright pile wall embankment protection structure 1, prefabricated interlaced composite beams 3, composite roadbed 4, prefabricated retaining wall 5 and other components of the utility model can be standardized and modularized. Through standardized design, different prefabricated components can be universally used, reducing design and manufacturing costs, which is conducive to reducing component weight, special-shaped contour demoulding and achieving clear concrete surface, making production, transportation and installation more efficient. In addition, the utility model is suitable for complex basin construction environments and is not affected by the construction needs of complex basin construction environments such as no beach outside the embankment, restrictions on existing buildings, and poor foundation soil. Furthermore, the utility model can reduce the construction intensity. The embankment project is constructed in strips along both sides of the river, and the project volume is large. The prefabrication and assembly of the structural components of the embankment project can realize direct installation on the construction site, reducing the construction intensity of steel bar binding and concrete pouring on the traditional embankment project site. In addition, the bored piles, flood control walls and flood control roads can be well streamlined for construction, and the construction and installation are mainly construction hoisting. The construction process reduces the deployment of on-site personnel, reduces the input and dependence of labor, saves labor costs and is conducive to safe production. The construction site reduces construction waste, saves energy, is environmentally friendly and easy to maintain, and is particularly suitable for projects with high requirements for on-site safe and civilized construction.

[0059] The above disclosure is only a preferred example of the present invention, which cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are all within the scope of the present invention.

Claims

1. An assembled integral embankment engineering structure for water retaining protection of a river channel, characterized in that: Including prefabricated vertical pile wall embankment protection structure, cast-in-place pile structure, prefabricated interlaced composite beams, composite roadbed, prefabricated retaining wall and concrete structure; The prefabricated upright pile wall embankment protection structure is arranged on the side of the river channel, and the prefabricated upright pile wall embankment protection structure has a first exposed steel bar protruding above the earthwork of the river channel; The cast-in-place pile structure is inserted into the earthwork on one side of the river channel and is arranged at intervals with the prefabricated upright pile wall embankment protection structure, and the cast-in-place pile structure has a second exposed steel bar protruding above the earthwork of the river channel; The prefabricated interlaced composite beam is arranged on the earthwork on one side of the river channel, and the prefabricated interlaced composite beam is located above the prefabricated upright pile wall embankment protection structure, one end of the prefabricated interlaced composite beam in the horizontal direction is suspended and protrudes above the river channel, and the other end of the prefabricated interlaced composite beam in the horizontal direction is located on one side of the second exposed steel bar, and the first exposed steel bar is passed through the prefabricated interlaced composite beam in the up-down direction; A plurality of the laminated roadbed plates are respectively arranged above the prefabricated alternately laminated beams in the horizontal direction; The prefabricated retaining wall is vertically connected to the top of the composite road base plate and is located above the end of the prefabricated interlaced composite beam that is suspended in the horizontal direction; The concrete structure is arranged above the prefabricated upright pile wall embankment protection structure, the cast-in-place pile structure and the prefabricated alternating composite beams and is connected to one side of the prefabricated retaining wall, and the concrete structure covers the first exposed steel bars and the second exposed steel bars, thereby connecting the prefabricated upright pile wall embankment protection structure, the cast-in-place pile structure, the prefabricated alternating composite beams, the composite roadbed plate and the prefabricated retaining wall together.

2. The assembled integral embankment engineering structure according to claim 1 is characterized in that: The prefabricated interlaced composite beam includes a cantilevered composite beam portion, a simply supported composite beam portion and a connecting I-beam. The cantilevered composite beam portion and the simply supported composite beam portion are arranged at intervals in the horizontal direction to form an installation interval, and the connecting I-beam is located in the installation interval and connected between the cantilevered composite beam portion and the simply supported composite beam portion. The cantilevered composite beam portion protrudes above the river channel in a suspended manner, and the simply supported composite beam portion is located on one side of the second exposed steel bar, and the first exposed steel bar is passed through the installation interval.

3. The assembled integral embankment engineering structure according to claim 2 is characterized in that: The concrete structure includes an upper concrete part and a first lower concrete part and a second lower concrete part respectively connected to the lower part of the upper concrete part. The upper concrete part is located above the prefabricated alternating composite beams and is used to connect the prefabricated alternating composite beams, the composite roadbed plate and the prefabricated retaining wall together. The first lower concrete part is filled in the installation interval and covers the first exposed steel bar and the connecting I-beam. The first lower concrete part is used to connect the upper concrete part, the prefabricated alternating composite beams and the prefabricated upright pile wall embankment protection structure together. The second lower concrete part is connected to one side of the simply supported composite beam part and covers the second exposed steel bar. The second lower concrete part is used to connect the upper concrete part, the prefabricated alternating composite beams and the cast-in-place pile structure together.

4. The assembled integral embankment engineering structure according to claim 3 is characterized in that: A first beam body steel bar is provided above the cantilevered composite beam portion, and the first beam body steel bar is inserted into the upper concrete portion; a second beam body steel bar is provided above the simply supported composite beam portion, and the second beam body steel bar is inserted into the upper concrete portion.

5. The assembled integral embankment engineering structure according to claim 3 is characterized in that: A third beam body reinforcement is provided on one side of the simply supported composite beam portion, and the third beam body reinforcement is inserted into the second lower concrete portion.

6. The assembled integral embankment engineering structure according to claim 3 is characterized in that: The prefabricated interlaced composite beam also includes beam body connecting steel bars, which are located at the installation interval and connected between the cantilevered composite beam portion and the simply supported composite beam portion, and the first lower layer concrete portion covers the beam body connecting steel bars.

7. The assembled integral embankment engineering structure according to claim 3 is characterized in that: It also includes a first crown beam steel cage, which is arranged in the installation interval and sleeved on the first exposed steel bar, and the upper concrete part and the first lower concrete part respectively cover the first crown beam steel cage.

8. The assembled integral embankment engineering structure according to claim 3 is characterized in that: It also includes a second crown beam steel cage, which is arranged on one side of the simply supported composite beam part and sleeved on the second exposed steel bars, and the upper concrete part and the second lower concrete part respectively cover the second crown beam steel cage.

9. The assembled integral embankment engineering structure according to claim 1, characterized in that: It also includes a shaped steel mesh, which is arranged above the composite roadbed plate, and the concrete structure covers the shaped steel mesh.

10. The assembled integral embankment engineering structure according to claim 1, characterized in that: The prefabricated upright pile wall embankment protection structure includes a prefabricated unit and reinforced concrete for connecting to the river bank, the prefabricated unit is provided with a first reserved hole and a reserved half hole, the first reserved hole and the reserved half hole both penetrate the prefabricated unit in the up and down direction, the reserved half hole is arranged on the side wall of the prefabricated unit, the two adjacent prefabricated units on the left and right are spliced ​​to form a protective layer, the reserved half holes of the two adjacent prefabricated units on the left and right are spliced ​​to form a second reserved hole, a plurality of the protective layers are stacked in the up and down direction, the two adjacent first reserved holes on the upper and lower sides are opposite to each other and connected to form a first pouring hole position, the two adjacent second reserved holes on the upper and lower sides are opposite to each other and connected to form a second pouring hole position, a plurality of the reinforced concrete are respectively penetrated in the first pouring hole position and the second pouring hole position, and the upper end of the reinforced concrete protrudes above the earthwork of the river channel and forms the first exposed steel bar.