Coastal assembly type pipe gallery connecting joint
By using metal sleeve butt and cement support in the coastal pipeline system and combining metal frame design, the problems of unstable and leakage of pipe corridor parts are solved, and higher structural stability and sealing are achieved.
Patent Information
- Application Number
- CN202421825385.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2025-04-29
- Estimated Expiration
- 2034-07-31
AI Technical Summary
During the assembly process, the coastal pipeline system is not supported by insufficient base surface support, which leads to unstable connection between pipe pipeline components, which is prone to leakage and structural damage.
The metal sleeve is used to butt and cement support is poured on the bottom of the pipe gallery. Combined with the metal frame design, the concrete core is poured inside the metal frame to enhance connection stability and sealing.
It significantly improves the overall stability of the pipeline system, avoids leakage and structural damage, and enhances the sealing and durability of the connecting nodes.
Smart Images

Figure CN222810075U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of construction structures, and in particular relates to a coastal assembled pipe gallery connection node. Background Art
[0002] A pipe gallery is a municipal utility tunnel space built underground in a city. It lays various municipal utility pipelines in one structure. By pouring concrete in a mold, a single pipe gallery is formed, and an underground foundation pit is dug. Both ends of the foundation pit are connected for assembly.
[0003] The current coastal pipeline corridor system has the following defects during assembly:
[0004] 1. Due to the reasons of the coastal underground base, the base support in the pit is insufficient, especially the connection between adjacent pipe gallery parts is not stable enough, the support is insufficient, the pipe gallery system has uneven bending force, and leakage and structural damage occur at the later connection nodes.
[0005] 2. Adjacent pipe gallery parts are connected by prefabricated plug-in structures, and rubber rings are installed on the protruding ends of the pipe gallery parts. They are hoisted and connected to the embedded ends of adjacent pipe gallery parts to achieve a sealing effect. However, damage to the rubber ring structure and later aging will lead to leakage problems. The protruding ends of the pipe gallery parts are connected with the embedded ends of the pipe gallery parts. During the later use, the protruding ends of the pipe gallery parts will be broken due to external forces.
[0006] In summary, the connection nodes of the current coastal pipeline corridor system are not stable enough and are prone to leakage. Therefore, we propose a coastal prefabricated pipeline corridor connection node. Utility Model Content
[0007] The utility model aims to provide a coastal assembled pipe gallery connection node to solve the technical problems of unstable connection and easy leakage at the connection node, so as to achieve the purpose of improving the structural stability of the connection node and avoiding water seepage.
[0008] In order to solve the above technical problems, the utility model provides a coastal assembled pipe gallery connection node, including: a foundation pit opened based on a preset line of the pipe gallery system and a single pipe gallery component built and connected in the foundation pit, the pipe gallery system is formed in the foundation pit through the pipe gallery components, adjacent pipe gallery components are connected by metal sleeves, cement supports are cast on both sides of the bottom of the pipe gallery components close to adjacent pipe gallery components, a metal frame is provided on the outer sleeve of the joint between adjacent pipe gallery components, the metal frame is designed to be open towards the surface and top of the pipe gallery component, and concrete is cast inside the metal frame to form a core, and the metal frame is connected to the joint between adjacent pipe gallery components through the core.
[0009] Furthermore, the two ends of the pipe gallery component are a protruding end and an embedded end respectively, the metal sleeve is larger than the outer wall size of the protruding end and smaller than the inner wall size of the embedded end, and is clamped around the outer wall of the protruding end.
[0010] Furthermore, the cement support is cast in the foundation pit through a mold, and during the casting process, a number of supporting columns are inserted through the interior of the cement support and connected to the base surface below the foundation pit.
[0011] Furthermore, a clamping groove is formed at the top of the cement support during the pouring process, and the length of the clamping groove is matched with the bottom length of the pipe gallery component.
[0012] Furthermore, the metal frame is made of iron metal, and steel bars are arranged inside the metal frame.
[0013] Furthermore, the metal frame adopts an upper and lower split design, including a lower frame and an upper frame, the lower frame is located at the bottom of the joints between adjacent pipe gallery parts, and the upper frame is located on both sides and the top of the joints between adjacent pipe gallery parts, and the inner wall size of the metal frame is adapted to the outer wall size of the pipe gallery parts.
[0014] Furthermore, docking pieces and plug-in pieces are welded to the two sides of the lower frame and the upper frame respectively, and the plug-in piece is inserted into the docking piece to complete the assembly of the metal frame.
[0015] The beneficial effects of the utility model are:
[0016] 1. By using metal sleeves to connect adjacent pipe gallery components and pouring cement supports on both sides of the bottom of the pipe gallery components, the overall stability of the pipe gallery system is greatly enhanced. In particular, in view of the problem of insufficient support of the coastal underground base, the cement supports and their internal supporting columns effectively improve the supporting capacity of the base surface in the pit and reduce the structural damage of the pipe gallery system caused by uneven bending force;
[0017] The above improves the structural stability, thereby preventing the structure at the joint of adjacent pipe gallery components from being subjected to external pressure and being squeezed, resulting in damage and leakage at the joint.
[0018] 2. The design of the metal sleeve and metal frame, combined with the concrete core cast inside, effectively improves the sealing of the joints of the corridor components. Compared with the traditional rubber ring sealing method, this design is extremely stable, not easy to age or damage, and avoids the possibility of leakage at the connection nodes.
[0019] By changing the connection mode of the adjacent pipe gallery parts as described above, the overall stability of the pipe gallery system is further improved.
[0020] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 It is a schematic diagram of the external structure of the foundation pit of the utility model;
[0023] Figure 2 It is a side anatomical diagram of the internal structure of the foundation pit of the utility model;
[0024] Figure 3 It is a schematic diagram of the butt joint and splitting of the pipe gallery components of the utility model;
[0025] Figure 4 It is a schematic diagram of disassembling the metal frame of the utility model.
[0026] In the figure:
[0027] 1. Foundation pit;
[0028] 2. Pipe gallery parts; 21. Protruding end; 22. Embedded end;
[0029] 3. Metal sleeve;
[0030] 4. Cement support; 41. Support column; 42. Snap-in groove;
[0031] 5. Metal frame; 51. Steel bars; 52. Lower frame; 53. Upper frame; 54. Butt joints; 55. Connectors
[0032] 6. Core. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the embodiments of the utility model clearer, the technical solution of the utility model will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0034] Example:
[0035] like Figures 1 to 4As shown, a coastal assembled pipe gallery connection node comprises: a foundation pit 1 opened based on a preset line of the pipe gallery system and a single pipe gallery component 2 butt-jointed and built in the foundation pit 1, the pipe gallery system is formed in the foundation pit 1 through the pipe gallery component 2, adjacent pipe gallery components 2 are butt-jointed through metal sleeves 3, cement supports 4 are cast on both sides of the bottom of the pipe gallery component 2 near the adjacent pipe gallery components 2, a metal frame 5 is provided on the outer sleeve of the butt joint of adjacent pipe gallery components 2, the metal frame 5 is designed to be open toward the surface and the top of the pipe gallery component 2, and concrete is cast inside the metal frame 5 to form a core 6, and the metal frame 5 is connected to the butt joint of the adjacent pipe gallery component 2 through the core 6.
[0036] like Figure 2 and Figure 3 As shown, the two ends of the pipe gallery member 2 are respectively a protruding end 21 and an embedded end 22, the metal sleeve 3 is larger than the outer wall size of the protruding end 21 and smaller than the inner wall size of the embedded end 22, and is clamped around the outer wall of the protruding end 21 to ensure a tight connection.
[0037] The cement support 4 is cast in the foundation pit 1 through a mold, and during the casting process, several support columns 41 are inserted into the base surface below the foundation pit 1 through the cement support 4. The support columns 41 will provide additional supporting force to enhance the stability of the entire pipe gallery system.
[0038] A clamping groove 42 is formed at the top of the cement support 4 during the pouring process, and the length of the clamping groove 42 is matched with the bottom length of the pipe gallery member 2 .
[0039] like Figure 4 As shown, the metal frame 5 adopts an upper and lower split design, including a lower frame 52 and an upper frame 53. The lower frame 52 is located at the bottom of the joint between adjacent pipe gallery components 2, and the upper frame 53 is located on both sides and the top of the joint between adjacent pipe gallery components 2. The inner wall size of the metal frame 5 is compatible with the outer wall size of the pipe gallery component 2. The metal frame 5 adopts an upper and lower split design, which facilitates the installation during the joint process of the pipe gallery component 2, and the concrete is injected in sections to ensure the effective filling of the concrete.
[0040] A docking piece 54 and a plug-in piece 55 are welded on both sides of the lower frame 52 and the upper frame 53 respectively. The plug-in piece 55 is inserted into the docking piece 54 to complete the assembly of the metal frame 5. Through the combination of the plug-in piece 55 and the docking piece 54, the assembly of the metal frame 5 can be completed quickly, thereby improving the construction efficiency.
[0041] It should be added that the metal frame 5 is made of iron metal, and a reinforcement member 51 is provided inside the metal frame 5 . The strength of the core 6 is improved by the built-in reinforcement member 51 .
[0042] To sum up, the assembly process of the coastal prefabricated pipe gallery connection node is as follows: according to the preset route of the pipe gallery system, a foundation pit 1 is excavated in the coastal area to ensure that the size and depth of the foundation pit 1 meet the design requirements so as to accommodate the pipe gallery components 2 and subsequent construction operations; a cement support 4 is cast in the foundation pit 1 using a mold, and it is ensured that during the casting process, a number of support columns 41 are inserted through the cement support 4 to the base surface below the foundation pit 1; after the cement support 4 hardens, a single pipe gallery component 2 is hoisted into the foundation pit 1, and docked and constructed according to the preset route to ensure that the positions of adjacent pipe gallery components 2 are accurate, in preparation for subsequent connections, the metal sleeve 3 is clamped around the outer wall of the protruding end 21 of the adjacent pipe gallery component 2; at the same time, a clamping groove 42 matching the bottom length of the pipe gallery component 2 is formed during the casting process to support and clamp the bottom of the pipe gallery component 2.
[0043] At the same time, before the pipe gallery component 2 is hoisted into the foundation pit 1, the lower frame 52 of the metal frame 5 is placed at the bottom of the joint between the adjacent pipe gallery components 2. After the pipe gallery component 2 is hoisted into the foundation pit 1, the upper frame 53 is placed on both sides and the top of the joint between the adjacent pipe gallery components 2 to ensure that the inner wall size of the metal frame 5 is compatible with the outer wall size of the pipe gallery component 2 to achieve a close fit. The connector 55 is inserted into the docking component 54 to complete the assembly of the metal frame 5, and concrete is poured inside the metal frame 5 to form a core 6. The core 6 tightly connects the metal frame 5 with the joint between the adjacent pipe gallery components 2, thereby enhancing the stability and sealing of the entire connection node and completing the overall assembly of the prefabricated pipe gallery connection node.
[0044] The various devices selected in this application are all universal standard parts or parts known to those skilled in the art, and their structures and principles can be known to those skilled in the art through technical manuals or conventional experimental methods.
[0045] In the description of the embodiments of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0046] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0047] Based on the above ideal embodiments of the utility model, the relevant staff can make various changes and modifications without deviating from the technical concept of the utility model through the above description. The technical scope of the utility model is not limited to the content of the specification, and its technical scope must be determined according to the scope of the claims.
Claims
1. A coastal assembled pipe gallery connection node, comprising: A foundation pit (1) is opened based on a preset line of a pipe gallery system and a single pipe gallery component (2) is butt-jointed and built in the foundation pit (1). The pipe gallery system is formed in the foundation pit (1) through the pipe gallery components (2). The invention is characterized in that adjacent pipe gallery components (2) are butt-jointed through metal sleeves (3), cement supports (4) are cast on both sides of the bottom of the pipe gallery components (2) close to the adjacent pipe gallery components (2), and a metal frame (5) is sleeved on the outer periphery of the butt joint of adjacent pipe gallery components (2). The metal frame (5) is designed to be open on the surface and the top of the pipe gallery component (2), and concrete is cast inside the metal frame (5) to form a core (6), and the metal frame (5) is connected to the butt joint of the adjacent pipe gallery components (2) through the core (6).
2. A coastal assembled pipe gallery connection node as claimed in claim 1, characterized in that: The two ends of the pipe gallery member (2) are respectively a protruding end (21) and an embedded end (22); the metal sleeve (3) is larger than the outer wall size of the protruding end (21) and smaller than the inner wall size of the embedded end (22), and is clamped around the outer wall of the protruding end (21).
3. A coastal assembled pipe gallery connection node as claimed in claim 1, characterized in that: The cement support (4) is cast in the foundation pit (1) through a mold, and during the casting process, a plurality of supporting columns (41) are inserted into the base surface below the foundation pit (1) and penetrate the interior of the cement support (4).
4. A coastal assembled pipe gallery connection node as claimed in claim 3, characterized in that: A clamping groove (42) is formed at the top of the cement support (4) during the pouring process, and the length of the clamping groove (42) is matched with the bottom length of the pipe gallery component (2).
5. A coastal assembled pipe gallery connection node as claimed in claim 1, characterized in that: The metal frame (5) is made of iron metal, and a steel bar (51) is provided inside the metal frame (5).
6. A coastal assembled pipe gallery connection node as claimed in claim 1, characterized in that: The metal frame (5) adopts an upper and lower split design, comprising a lower frame (52) and an upper frame (53); the lower frame (52) is located at the bottom of the joint between the adjacent pipe gallery components (2); the upper frame (53) is located at both sides and the top of the joint between the adjacent pipe gallery components (2); the inner wall size of the metal frame (5) is compatible with the outer wall size of the pipe gallery component (2).
7. A coastal assembled pipe gallery connection node as claimed in claim 6, characterized in that: A butt joint (54) and a plug-in connector (55) are welded to the two sides of the lower frame (52) and the upper frame (53) respectively, and the plug-in connector (55) is inserted into the butt joint (54) to complete the assembly of the metal frame (5).