Metering and feeding device
By designing an automated metering and feeding device, using gravity sensors to detect and supplement plasticizers, the problem of error-prone manual operation is solved, and the production efficiency is improved and costs are reduced.
Patent Information
- Application Number
- CN202421810393.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2025-05-09
- Estimated Expiration
- 2034-07-30
AI Technical Summary
In the prior art, the metering and feeding devices of plasticizers are mostly manual operation, which are prone to errors, resulting in production interruptions and increased production costs.
Design a metering and feeding device, including a support platform, a support frame, a hopper, a collection bin and a gravity sensor, to automatically detect the weight of the material and realize automatic replenishment, avoiding errors in manual calculation and operation.
Accurate metering and automatic replenishment of plasticizers is achieved, production interruptions are avoided, production efficiency is improved, and production costs are reduced by recycling excess materials.
Smart Images

Figure CN222844515U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of mixers, in particular to a metering feeding device. Background Art
[0002] In the production process of plastics, rubber, chemical and other industries, plasticizers are commonly used additives to improve the plasticity and processing properties of materials. Accurate metering and addition of plasticizers are crucial to production quality and cost control.
[0003] In the prior art, the metering and feeding device of plasticizers is mostly operated manually, that is, the operator first calculates the required weight of plasticizer according to production needs, and then adds the plasticizer to the feeding device for standby use. Although this method is simple, manual calculation operations are prone to errors; in actual production, the amount of plasticizer material calculated is often different from the actual amount required for production. During the production process, if it is found that the plasticizer is insufficient, it is necessary to stop the machine and add it again, resulting in production interruption and reduced production efficiency; due to the lack of automated metering and adjustment mechanisms, the excess plasticizer in the production process cannot be effectively recycled, further increasing production costs.
[0004] Therefore, the prior art has defects and needs to be improved and developed. Summary of the invention
[0005] The embodiment of the utility model provides a metering feeding device, which is used to solve the problem that the metering feeding device of plasticizer in the prior art is mostly manually operated, that is, the operator first calculates the required weight of plasticizer according to production needs, and then adds the plasticizer to the feeding device for standby. Although this method is simple, manual calculation operation is prone to errors; in actual production, the amount of plasticizer material calculated is often different from the actual amount required for production. During the production process, if it is found that the plasticizer is insufficient, it is necessary to stop the machine and add it again, resulting in production interruption and reducing production efficiency; due to the lack of automated metering and adjustment mechanism, the excess plasticizer in the production process cannot be effectively recycled, further increasing the problem of production costs.
[0006] The utility model provides a metering feeding device, comprising a supporting platform, a supporting frame is mounted on the supporting platform, and a hopper is fixed on the supporting frame; the top of the hopper is air-tightly connected to a dust collecting bin, and the lowest point of the filter bag of the dust collecting bin is located in the hopper; the top of the dust collecting bin is air-tightly connected to an exhaust pipe, and the other end of the exhaust pipe is installed with an exhaust pump; a collecting bin with an opening at the top is mounted in the hopper, and a first gravity sensor is fixed at the bottom of the collecting bin, and when the material enters the collecting bin, the first gravity sensor is used to detect the weight of the material in the collecting bin; a second gravity sensor is installed on the outer wall of the hopper, and when the material enters the hopper, the second gravity sensor is used to detect the weight of the material in the hopper; the discharge port located at the bottom of the hopper is located below the bottom of the supporting frame, and a discharge valve is installed at the discharge port of the hopper; a feed pipe is air-tightly connected to the outer wall of the hopper, and the discharge port of the feed pipe is located below the filter bag of the dust collecting bin and above the collecting bin.
[0007] Furthermore, a vibration pump is installed on the outer wall of the hopper.
[0008] Furthermore, an air hole is provided on the outer wall of the hopper, and a one-way valve is installed on the air hole to allow gas to enter the hopper in one direction.
[0009] Furthermore, there are three air holes, one of which is located on the outer wall of the hopper below the vibration pump, and the other two are located above the discharge valve, and the central axes of the two air holes located above the discharge valve are collinear.
[0010] Furthermore, the volume of the collecting bin does not exceed 10% of the maximum volume of the material contained in the hopper.
[0011] Furthermore, there is at least one feed pipe. When the number of the feed pipes is greater than 1, the number of feed ports of the feed pipes is equal to the number of the feed pipes, and the number of outlet ports of the feed pipes is 1.
[0012] Furthermore, the outlet of the feed pipe is connected to a hose, and when the material enters the hopper from the feed pipe, the hose is used to absorb the material in all directions.
[0013] Furthermore, the discharge valve is a pneumatic butterfly valve.
[0014] Furthermore, the bottom of the support frame is bolted to the top of the support platform.
[0015] Furthermore, the top of the supporting platform is covered with a rubber layer.
[0016] Beneficial effects:
[0017] It can be seen from the above technical scheme that the utility model provides a metering feeding device. By designing a collecting bin, materials are stored in the collecting bin. During the production process, when it is found that the material is insufficient, there is no need to stop the machine for re-adding. The material stored in the collecting bin can be directly used for adding, which will not interrupt production and improve production efficiency. When there is excess plasticizer in the production process, the collecting bin can also recycle the material. The material stored in the collecting bin can be used for the next production, thereby reducing production costs.
[0018] It should be appreciated that all combinations of the foregoing concepts, as well as additional concepts described in greater detail below, may be considered to be part of the inventive subject matter of the present disclosure, provided such concepts are not mutually inconsistent.
[0019] The foregoing and other aspects, embodiments and features of the present invention can be more fully understood from the following description in conjunction with the accompanying drawings. Other additional aspects of the present invention, such as the features and / or beneficial effects of the exemplary embodiments, will be apparent from the following description or learned from the practice of the specific embodiments according to the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings are not drawn to scale according to actual reference objects. In the accompanying drawings, each identical or nearly identical component shown in various figures may be represented by the same reference numeral. For the sake of clarity, not every component is labeled in each figure. Now, embodiments of various aspects of the present invention will be described by way of example and with reference to the accompanying drawings, in which:
[0021] Figure 1 This is a schematic diagram of the structure of a metering feeding device in an embodiment of the present application.
[0022] Description of Figure Numbers:
[0023] Support platform 1; support frame 2; hopper 3; vibration pump 301; air hole 302; collection bin 303; second gravity sensor 304; dust collecting bin 4; air extraction pipeline 401; feed pipeline 5; pneumatic butterfly valve 6. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Unless otherwise defined, the technical terms or scientific terms used herein should be the common meaning understood by people with general skills in the field to which the present invention belongs.
[0025] The words "first", "second" and similar terms used in the patent specification and claims of the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, unless the context clearly indicates otherwise, the singular form "a" or "an" shall not be construed as "a" or "an";
[0026] The words “a”, “an”, “the” and the like do not denote a limitation of quantity, but rather denote the presence of at least one.
[0027] The words "include" or "comprises" and the like mean that the elements or objects appearing before "includes" or "comprises" include the features, wholes, steps, operations, elements and / or components listed after "includes" or "comprises", and do not exclude the existence or addition of one or more other features, wholes, steps, operations, elements, components and / or their collections. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0028] In the prior art, the metering and feeding device of the plasticizer is mostly operated manually, that is, the operator first calculates the required weight of the plasticizer according to the production needs, and then adds the plasticizer to the feeding device for standby use. Although this method is simple, the manual calculation operation is prone to errors; in actual production, the amount of plasticizer material calculated is often different from the actual amount required for production. During the production process, if it is found that the plasticizer is insufficient, it is necessary to stop the machine and add it again, resulting in production interruption and reducing production efficiency; due to the lack of automated metering and adjustment mechanisms, the excess plasticizer in the production process cannot be effectively recycled, further increasing production costs.
[0029] In view of this, the present invention provides a metering feeding device, referring to Figure 1, including a support platform 1, a support frame 2 is mounted on the support platform 1, and a hopper 3 is fixed on the support frame 2; the top of the hopper 3 is airtightly connected to a dust collecting bin 4, and the lowest point of the filter bag of the dust collecting bin 4 is located in the hopper 3; the top of the dust collecting bin 4 is airtightly connected to an exhaust pipe 401, and an exhaust pump is installed at the other end of the exhaust pipe 401; a collecting bin 303 with an opening at the top is mounted in the hopper 3, and a first gravity sensor is fixed at the bottom of the collecting bin 303. When the material enters the collecting bin 303, the first gravity sensor The sensor is used to detect the weight of the material in the collecting bin 303; a second gravity sensor 304 is installed on the outer wall of the hopper 3, and when the material enters the hopper 3, the second gravity sensor 304 is used to detect the weight of the material in the hopper 3; the discharge port at the bottom of the hopper 3 is located below the bottom of the support frame 2, and a discharge valve is installed at the discharge port of the hopper 3; a feed pipe 5 is airtightly connected to the outer wall of the hopper 3, and the discharge port of the feed pipe 5 is located below the filter bag of the dust collecting bin 4 and above the collecting bin 303.
[0030] In some embodiments, a vibration pump 301 is also installed on the outer wall of the hopper 3. The function of the vibration pump 301 is to work during the discharge, maintain continuous vibration, so that the material in the hopper 3 is vibrated and separated, and discharged smoothly through the discharge port.
[0031] In some embodiments, an air hole 302 is further provided on the outer wall of the hopper 3, and a one-way valve is installed on the air hole 302 to allow gas to enter the hopper 3 in one direction. The air hole 302 is provided, and the air hole 302 can be connected to a compressor, and the compressor is used to allow clean gas to enter the hopper 3 through the one-way valve. The material inside the hopper 3 cannot flow out of the hopper 3 under the control of the one-way valve. The clean gas flows in the hopper 3 to assist the vibration pump 301 to remove the material, and then it is smoothly discharged from the discharge port.
[0032] In some embodiments, there are three air holes 302, one of which is located on the outer wall of the hopper 3 below the vibration pump 301, and the other two air holes 302 are located above the discharge valve, and the central axes of the two air holes 302 located above the discharge valve are collinear. One air hole 302 is set on the outer wall of the hopper 3 at a height below the vibration pump 301, and the gas entering from the air hole 302 is used to blow the material inside the hopper 3 to make it fall off. Because the central axes of the two air holes 302 located above the discharge valve are collinear, when the compressor discharges the gas into the hopper 3, the gas forms a counter-attack, and the rebound force of the counter-attack circulates at the discharge port, blowing the material at the discharge port off.
[0033] In some embodiments, the volume of the collecting bin 303 does not exceed 10% of the maximum volume of the material contained in the hopper 3. The smaller the volume of the collecting bin 303, the easier it is to control the weight of the remaining material in the hopper 3.
[0034] In some embodiments, there is at least one feed pipe 5, and when the number of feed pipes 5 is greater than 1, the number of feed ports of the feed pipe 5 is equal to the number of feed pipes 5, and the number of discharge ports of the feed pipe 5 is 1. The more the number of feed pipes 5 is, the more uniform the feed is during feeding, and at this time, the diameter of the discharge port needs to be designed according to the power of the vacuum pump, and the diameter of the discharge port is positively correlated with the power of the vacuum pump.
[0035] In some embodiments, the outlet of the feed pipe 5 is connected with a hose, and the hose is used to absorb the material in all directions when the material enters the hopper 3 from the feed pipe 5. The material placed in the container is sucked in all directions and angles by the hose to prevent material waste or material weight not meeting the required standard weight.
[0036] In some embodiments, the discharge valve is a pneumatic butterfly valve 6 .
[0037] In some embodiments, the bottom of the support frame 2 is bolted to the top of the support platform 1 .
[0038] In some embodiments, a rubber layer is covered on the top of the support platform 1. The rubber layer is designed to cushion the support frame 2, reduce the friction between the support frame 2 and the support platform 1 when the vibration pump 301 is working, prevent the parts from loosening and being damaged, and increase the life of the equipment.
[0039] The working process of a metering feeding device provided by an embodiment of the utility model is as follows: placing the material at the feed port of the feed pipe 5, and burying the feed port in the material, turning on the vacuum pump connected to the exhaust pipe 401 at the top of the metering feeding device to exhaust air, and drawing negative pressure into the hopper 3. Since the hopper 3 is in a negative pressure state, the material will be sucked into the hopper 3 through the feed pipe 5. In some embodiments, a valve is also provided at the feed port of the feed pipe 5 to control the feed amount. During the material conveying process, the dust collecting bin 4 continues to operate, and the filter bag of the dust collecting bin 4 will remove dust from the gas drawn in by the exhaust pipe 401. The material first enters the collection bin 303 in the hopper 3, and the material exceeding the volume of the collection bin 303 is discharged and placed in the hopper 3. The weight of the material in the collection bin 303 is received by the first gravity sensor. The volume of the collecting bin 303 is selected according to actual needs to ensure that the volume of the collecting bin 303 does not exceed 10% of the volume of the material that the hopper 3 can accommodate, that is, 1.1 times the maximum volume of the material required in the hopper 3. The material that enters the hopper 3 and is not in the collecting bin 303 is detected by the second gravity sensor 304. If the volume of the collecting bin 303 is 10% of the volume of the material that the hopper 3 can accommodate, when the weight of the material required for production exceeds the theoretical demand for the material, the value detected by the second gravity sensor 304 needs to exceed 9 times the value detected by the first gravity sensor. When discharging, the vibration pump 301 is turned on to maintain continuous vibration to ensure that the material in the hopper 3 is discharged cleanly. In addition, the air hole 302 is connected to the compressor to inject clean gas into the hopper 3 to assist in the discharge of the material. The pneumatic butterfly valve 6 below the hopper 3 can control the speed of discharging when discharging, adapting to different production needs.
[0040] In summary, the utility model provides a metering feeding device, which designs a collection bin 303, uses the collection bin 303 to store materials, and uses the first gravity sensor to detect the weight of the materials in the collection bin 303. The gravity data can provide the second gravity sensor 304 with the help of material metering, thereby realizing automatic operation, reducing human errors, avoiding errors in manual calculation and operation, and improving the accuracy of the plasticizer when adding the material. The gravity sensor monitors the weight of the materials in the collection bin 303 in real time, and can timely detect the shortage of materials and automatically replenish them, avoiding production interruptions caused by insufficient materials. The replenishment mechanism ensures the continuous supply of plasticizers in the production process without stopping the machine for re-adding, which significantly improves production efficiency. The design adds a certain percentage of materials each time when adding materials, forming material redundancy, ensuring that there will be no shortage of materials even at peak demand. The material redundancy design improves the continuity and reliability of the production process, and reduces product quality problems caused by insufficient materials. Automatically metering and accurately controlling the amount of materials avoids the waste of materials caused by excessive addition, reduces production costs, reduces unnecessary waste, and realizes efficient use of resources. During the production process, when it is found that the material is insufficient, there is no need to stop the machine to add more materials. The materials stored in the collection bin 303 can be directly used for adding, which will not interrupt the production and improve the production efficiency. When there is excess plasticizer in the production process, the collection bin 303 can also recycle the materials. The materials stored in the collection bin 303 can be used for the next production, thereby reducing the production cost.
[0041] Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. A person with ordinary knowledge in the technical field to which the present invention belongs may make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, the protection scope of the present invention shall be determined by the definition of the claims.
Claims
1. A metering feeding device, characterized in that: It includes a supporting platform, a supporting frame is mounted on the supporting platform, and a hopper is fixed on the supporting frame; the top of the hopper is air-tightly connected to a dust collecting bin, and the lowest point of the filter bag of the dust collecting bin is located in the hopper; the top of the dust collecting bin is air-tightly connected to an exhaust pipe, and the other end of the exhaust pipe is installed with an exhaust pump; a collecting bin with an opening at the top is mounted in the hopper, and a first gravity sensor is fixed at the bottom of the collecting bin, and when the material enters the collecting bin, the first gravity sensor is used to detect the weight of the material in the collecting bin; a second gravity sensor is installed on the outer wall of the hopper, and when the material enters the hopper, the second gravity sensor is used to detect the weight of the material in the hopper; the discharge port located at the bottom of the hopper is located below the bottom of the supporting frame, and a discharge valve is installed at the discharge port of the hopper; a feed pipe is air-tightly connected to the outer wall of the hopper, and the discharge port of the feed pipe is located below the filter bag of the dust collecting bin and above the collecting bin.
2. A metering feeding device according to claim 1, characterized in that: A vibration pump is also installed on the outer wall of the hopper.
3. A metering feeding device according to claim 2, characterized in that: An air hole is also provided on the outer wall of the hopper, and a one-way valve is installed on the air hole to allow gas to enter the hopper in one direction.
4. A metering feeding device according to claim 3, characterized in that: There are three air holes, one of which is located on the outer wall of the hopper below the vibration pump, and the other two are located above the discharge valve. The central axes of the two air holes located above the discharge valve are collinear.
5. A metering feeding device according to claim 4, characterized in that: The volume of the collecting bin does not exceed 10% of the maximum volume of the material contained in the hopper.
6. A metering feeding device according to claim 5, characterized in that: There is at least one feed pipe. When the number of the feed pipes is greater than 1, the number of feed ports of the feed pipes is equal to the number of the feed pipes, and the number of outlet ports of the feed pipes is 1.
7. A metering feeding device according to claim 6, characterized in that: The outlet of the feed pipe is connected with a hose, and when the material enters the hopper from the feed pipe, the hose is used to absorb the material in all directions.
8. A metering feeding device according to claim 7, characterized in that: The discharge valve is a pneumatic butterfly valve.
9. A metering feeding device according to claim 8, characterized in that: The bottom of the support frame is bolted to the top of the support platform.
10. A metering feeding device according to claim 9, characterized in that: The top of the supporting platform is covered with a rubber layer.