Hanging formwork plugging tool for indoor sewer pipe hole

By designing a hanging mold sealing tool for indoor sewer pipe renovation, the combination structure of semicircular plate and arc plate is used to solve the problems of large material consumption, lax sealing and inability to reuse during the sealing process of existing multi-layer board hanging molds, and an efficient and environmentally friendly sealing effect is achieved.

CN222909529UActive Publication Date: 2025-05-27CHINA XINXING CONSTR & DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420250868.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-01
Publication Date
2025-05-27
Estimated Expiration
2034-02-01

AI Technical Summary

Technical Problem

During the process of sealing holes for indoor sewer pipe renovation, existing multi-layer board hanging molds have problems such as high cost of artificial materials, lax sealing, inability to reuse, time-consuming and labor-intensive dismantling and pollution.

Method used

A mold sealing tool including a left mold and a right mold is designed. Through the combination of a semi-circular plate, a curved plate and a first rib plate, a through hole adapted to the outer diameter of the indoor sewer pipe, and fixed by a fastening bolt group, increasing sealing and reusability.

Benefits of technology

It has achieved multiple reuses, reduced the risk of slurry leakage, ensured the quality of hole sealing construction, avoided pollution to the ceiling of residents, and met the requirements of energy conservation and environmental protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222909529U_ABST
    Figure CN222909529U_ABST
Patent Text Reader

Abstract

The utility model discloses a suspended formwork plugging tool for an indoor sewer pipe reconstruction hole. The hanging mold plugging tool is arranged on the bottom surface of the hole and comprises a left mold and a right mold which are the same in structure, each of the left mold and the right mold comprises a semicircular plate, an arc-shaped plate extending downwards is arranged on an inner ring of the bottom surface of each semicircular plate, and first rib plates are connected to the upper end and the lower end of each arc-shaped plate; the first rib plates are fixed to the bottom faces of the semicircular plates, the two semicircular plates are in butt joint and jointly abut against the bottom face of the hole, a through hole matched with the outer diameter of an indoor sewer pipe is jointly formed in the two semicircular plates, the indoor sewer pipe is located in the hole and penetrates through the through hole downwards, and the two arc-shaped plates are attached to the outer surface of the indoor sewer pipe. The two first rib plates on the same side are jointly provided with fastening parts, and fastening bolt sets for connecting the two semicircular ring plates together are installed on the fastening parts. The defects of a multi-layer plate suspended formwork plugging mode are overcome, and repeated utilization is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of reconstruction and expansion construction, and particularly to a suspended formwork plugging tool for indoor sewer pipe renovation holes. Background Art

[0002] In the renovation project of old communities, the quality of renovation construction is the top priority for effectively improving the living quality of residents and enhancing the living environment; the indoor sewer pipes in bathrooms, kitchens, etc. need to be replaced urgently due to severe old-age corrosion, which is an essential construction content in the renovation project of old communities.

[0003] In the replacement construction of sewer pipes, it is necessary to re-chisel and drill the installation holes of the sewer pipes, install the new sewer pipes in the holes, and plug the holes. However, the commonly used plugging methods generally use multi-layer board suspended formwork, but there are the following disadvantages: 1. The formwork needs to be cut according to the size of the hole, consuming a large amount of labor and materials; 2. The gap between the formwork and the sewer pipe is large, resulting in poor sealing and a risk of slurry leakage; 3. The formwork cannot be reused, which does not meet the requirements of energy conservation and environmental protection; 4. The formwork removal work is not only time-consuming and laborious but also consumes a lot of labor; 5. It is easy to pollute the ceiling of the household and is inconvenient to clean.

[0004] Therefore, there is an urgent need for a suspended formwork plugging tool for indoor sewer pipe holes to solve the above defects. Summary of the Utility Model

[0005] The utility model aims to solve the above problems, thereby providing a suspended formwork plugging tool for indoor sewer pipe holes, solving the defects of the multi-layer board suspended formwork plugging method for holes, being able to be reused multiple times, meeting the requirements of energy conservation and environmental protection; reducing the risk of slurry leakage, ensuring the quality of the hole plugging construction, and being well applied in the actual construction process, and being recognized by all parties and residents.

[0006] The technical solution adopted by the utility model to solve the above problems is:

[0007] A formwork suspension and sealing tool for indoor sewer pipe holes. The formwork suspension and sealing tool is arranged on the bottom surface of the hole. The formwork suspension and sealing tool includes a left mold and a right mold with the same structure. Both the left mold and the right mold include a semi-circular ring plate. An arc-shaped plate extending downward is arranged on the inner ring of the bottom surface of the semi-circular ring plate. First rib plates are connected to the upper end and the lower end of the arc-shaped plate respectively, and the first rib plates are fixed on the bottom surface of the semi-circular ring plate. The two semi-circular ring plates are butted and jointly abutted against the bottom surface of the hole. A through hole adapted to the outer diameter of the indoor sewer pipe is formed by the two semi-circular ring plates. The indoor sewer pipe is located in the hole and passes downward through the through hole. Both arc-shaped plates are attached to the outer surface of the indoor sewer pipe. Fastening parts are jointly arranged on the two first rib plates on the same side, and fastening bolt groups for connecting and fixing the two semi-circular ring plates to the indoor sewer pipe are installed on the fastening parts.

[0008] Preferably, a further technical solution of the present utility model is as follows:

[0009] Furthermore, a circular ring sealing gasket is clamped between the two semi-circular ring plates and the bottom surface of the hole. The inner ring diameter of the circular ring sealing gasket is adapted to the outer diameter of the indoor sewer pipe, and the indoor sewer pipe is inserted into the inner ring of the circular ring sealing gasket.

[0010] Furthermore, the fastening part includes a left open slot and a right open slot. The left open slot is arranged on the left side of the first rib plate of the left mold, and the right open slot is arranged on the right side of the first rib plate of the right mold. A channel penetrating the two first rib plates is jointly arranged on the left open slot and the right open slot. The fastening bolt group includes a fastening bolt. One end of the fastening bolt is rotatably connected to the left open slot. The fastening bolt is placed in the channel and the other end extends out of the right open slot. A fastening nut is installed on the other end of the fastening bolt, and a steel gasket is clamped between the right open slot and the fastening nut.

[0011] Furthermore, a vertically penetrating vertical hole is jointly arranged on the left open slot and the end of the fastening bolt, and a hairpin pin is installed in the vertical hole.

[0012] Furthermore, a groove is arranged on the butting side of one of the semi-circular ring plates, and a boss adapted to the groove is arranged on the butting side of the other semi-circular ring plate.

[0013] Furthermore, a plurality of second rib plates are arranged in the middle of the outer arc surface of the arc-shaped plate. The plurality of second rib plates are fixed on the bottom surface of the semi-circular ring plate. The plurality of second rib plates are arranged between the two first rib plates, and adjacent second rib plates are spaced apart from each other.

[0014] The present utility model adopting the above technical solution, compared with the prior art, its prominent feature is:

[0015] The utility model comprises two parts, namely a left mold and a right mold. The left mold and the right mold jointly abut against the bottom surface of the hole. The left mold and the right mold are butted and surrounded and fixed on the indoor sewer pipe to realize the plugging of the hole, which solves the defects of the plugging method of the multi-layer board hanging mold for the hole. The left mold and the right mold are connected and fixed on the indoor sewer pipe through a fastening bolt group, which not only has a stable connection structure, but also is simple and convenient to install and disassemble. The hanging mold plugging tool can be reused multiple times, meeting the requirements of energy conservation and environmental protection. The left mold and the right mold have simple structures and low production costs. The hanging mold plugging tool not only reduces the risk of slurry leakage, but also avoids the defect of slurry leakage polluting the ceiling of the household, ensuring the quality of the hole plugging construction, and is well applied in the actual construction process and recognized by all parties and residents. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a schematic diagram of the front view structure of the utility model;

[0017] Figure 2 is a schematic diagram of the bottom view structure of the hanging mold plugging tool of the utility model;

[0018] In the figure: 1, hole; 2, semi-circular ring plate; 3, arc plate; 4, first rib plate; 5, through hole; 6, left mold; 7, right mold; 8, circular ring sealing gasket; 9, left open slot; 10, right open slot; 11, channel; 12, fastening bolt; 13, fastening nut; 14, steel gasket; 15, hairpin pin; 16, groove; 17, boss; 18, second rib plate; 19, indoor sewer pipe. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0019] Through the description of the embodiments below, it will be more helpful for the public to understand the utility model. However, the specific embodiments given by the applicant should not be regarded as a limitation to the technical solution of the utility model. Any change in the definition of components or technical features and / or any formal but not substantial transformation of the overall structure should be regarded as the protection scope defined by the technical solution of the utility model.

[0020] See Figures 1 to 2 as shown, the technical solution of the utility model is as follows:

[0021] A die suspension plugging tool for indoor sewer holes. The die suspension plugging tool is arranged on the bottom surface of the hole 1. The die suspension plugging tool includes a left mold 6 and a right mold 7 with the same structure. Both the left mold 6 and the right mold 7 are integrally formed of plastic material. Both the left mold 6 and the right mold 7 include a semi-circular ring plate 2. An arc plate 3 extending downward is arranged on the inner ring of the bottom surface of the semi-circular ring plate 2. The arc plate 3 is consistent with the radian of the inner ring of the semi-circular ring plate 2. First rib plates 4 are connected to both the upper end and the lower end of the arc plate 3. The two first rib plates 4, the arc plate 3 and the semi-circular ring plate 2 are integrally formed. The first rib plates 4 are all fixed on the bottom surface of the semi-circular ring plate 2. The two first rib plates 4 support the semi-circular ring plate 2 and reduce the risk of the semi-circular ring plate 2 breaking. The two semi-circular ring plates 2 are butted and jointly abutted against the bottom surface of the hole 1. A through hole 5 adapted to the outer diameter of the indoor sewer pipe 19 is formed by the two semi-circular ring plates 2. The inner diameter of the through hole 5 is consistent with the outer diameter of the indoor sewer pipe 19, avoiding the diameter of the through hole 5 being too large and the slurry leaking along the gap between the through hole 5 and the indoor sewer pipe 19. The indoor sewer pipe 19 is located in the hole 1 and passes downward through the through hole 5. The two arc plates 3 are both attached to the outer surface of the indoor sewer pipe 19. Fastening parts are jointly arranged on the two first rib plates 4 on the same side. Fastening bolt groups for connecting and fixing the two semi-circular ring plates 2 on the indoor sewer pipe 19 are installed on the fastening parts. The two semi-circular ring plates 2 are fixed on the indoor sewer pipe 19 relying on the indoor sewer pipe 19 to prevent the left mold 6 and the right mold 7 from sliding downward and causing slurry leakage.

[0022] A ring-shaped sealing gasket 8 is clamped between the two semi-circular ring plates 2 and the bottom surface of the hole 1. The ring-shaped sealing gasket 8 is integrally formed of rubber material. The inner diameter of the ring-shaped sealing gasket 8 is adapted to the outer diameter of the indoor sewer pipe 19. The indoor sewer pipe 19 is inserted into the inner ring of the ring-shaped sealing gasket 8. Through the above-mentioned ring-shaped sealing gasket 8, the gap between the bottom surface of the hole 1 and the two semi-circular ring plates 2 is plugged, improving the sealing performance, reducing the risk of slurry leakage, and at the same time facilitating the disassembly of the die suspension plugging tool after the plugging construction of the hole 1 is completed, avoiding the left mold 6 and the right mold 7 from adhering to the slurry.

[0023] The fastening part includes a left open slot 9 and a right open slot 10. Both the left open slot 9 and the right open slot 10 are integrally formed with the left mold 6 or the right mold 7. The left open slot 9 is fixed on the left side of the first rib plate 4 of the left mold 6, and the right open slot 10 is fixed on the right side of the first rib plate 4 of the right mold 7. A channel 11 penetrating through the two first rib plates 4 is commonly provided on the left open slot 9 and the right open slot 10. The channel 11 is in an open shape and the opening faces outward. The fastening bolt group includes a fastening bolt 12. One end of the fastening bolt 12 is rotatably connected to the left open slot 9. The fastening bolt 12 is placed in the channel 11 and the other end extends out of the right open slot 10. A fastening nut 13 is installed on the other end of the fastening bolt 12. A steel gasket 14 is clamped between the right open slot 10 and the fastening nut 13. Through the above structural arrangement, the fastening bolt group is connected to the fastening part. By screwing the fastening nut 13 on the fastening bolt group, the two semi-circular ring plates 2 are connected or separated, which is beneficial to the installation and disassembly of the semi-circular ring plates 2.

[0024] A vertically penetrating vertical hole is commonly provided on the end of the left open slot 9 and the fastening bolt 12. A hairpin pin 15 is installed in the vertical hole. The fastening bolt 12 is fixed on the left open slot 9 through the hairpin pin 15, and at the same time, it also ensures that the end of the fastening bolt 12 rotates around the hairpin pin 15.

[0025] A groove 16 is provided on the docking side of one of the semi-circular ring plates 2, and a boss 17 adapted to the groove 16 is provided on the docking side of the other semi-circular ring plate 2. The boss 17 is inserted into the groove 16. Through the cooperation of the boss 17 and the groove 16, the two semi-circular ring plates 2 are tightly connected together, which not only strengthens the firmness of the connection between the two semi-circular rings but also reduces the risk of slurry leakage along the docking seam of the two semi-circular ring plates 2.

[0026] A number of second rib plates 18 are fixed in the middle of the outer arc surface of the arc plate 3. The number of the second rib plates 18 is determined according to actual needs. The number of second rib plates 18 is fixed on the bottom surface of the semi-circular ring plate 2. The second rib plates 18 are integrally formed with the arc plate 3 and the semi-circular ring plate 2. The number of second rib plates 18 is provided between the two first rib plates 4, and adjacent second rib plates 18 are spaced apart from each other. Through the above second rib plates 18, the strength of the semi-circular ring plate 2 is strengthened, which plays a supporting role for the semi-circular ring plate 2 and reduces the risk of fracture of the semi-circular ring plate 2.

[0027] The utility model comprises two parts, namely a left mold 6 and a right mold 7. The left mold 6 and the right mold 7 jointly abut against the bottom surface of the hole 1. The left mold 6 and the right mold 7 are butted and surrounded and fixed on the indoor sewer pipe 19 to realize the plugging of the hole 1, solving the defect of the plugging method of the multi-layer board hanging mold for the hole 1. The left mold 6 and the right mold 7 are connected and fixed on the indoor sewer pipe 19 through a fastening bolt group. Not only is the connection structure stable, but also the installation and disassembly are simple and convenient. The hanging mold plugging tool can be reused multiple times, meeting the requirements of energy conservation and environmental protection. The left mold 6 and the right mold 7 have simple structures and low production costs. The hanging mold plugging tool not only reduces the risk of slurry leakage, but also avoids the defect of slurry leakage polluting the ceiling of the household, ensuring the quality of the plugging construction of the hole 1, and has been well applied in the actual construction process and recognized by all parties and residents.

[0028] The above are only the preferred and feasible embodiments of the present utility model, and do not limit the scope of rights of the present utility model accordingly. Any equivalent changes made by using the content of the specification and drawings of the present utility model are included in the scope of rights of the present utility model.

Claims

1. A hanging mold plugging tool for indoor sewer holes, the hanging mold plugging tool is arranged on the bottom surface of the hole, characterized in that: The hanging mold sealing tool includes a left mold and a right mold with the same structure. The left mold and the right mold both include a semicircular ring plate. A downwardly extending arc plate is arranged on the inner ring of the bottom surface of the semicircular ring plate. The upper and lower ends of the arc plate are connected with first ribs, and the first ribs are fixed on the bottom surface of the semicircular ring plate. The two semicircular ring plates are butted and abutted against the bottom surface of the hole together. A through hole adapted to the outer diameter of the indoor sewer pipe is formed in the two semicircular ring plates. The indoor sewer pipe is located in the hole and passes downward through the through hole. The two arc plates are both fitted on the outer surface of the indoor sewer pipe. A fastening portion is arranged on the two first ribs on the same side, and a fastening bolt group is installed on the fastening portion to connect and fix the two semicircular ring plates to the indoor sewer pipe.

2. The hanging mold plugging tool for indoor sewer holes according to claim 1 is characterized in that: A circular sealing gasket is sandwiched between the two semicircular ring plates and the bottom surface of the hole. The inner ring diameter of the circular sealing gasket is matched with the outer diameter of the indoor sewer pipe, and the indoor sewer pipe is inserted into the inner ring of the circular sealing gasket.

3. The hanging mold plugging tool for indoor sewer holes according to claim 1 is characterized in that: The fastening part includes a left open groove and a right open groove. The left open groove is arranged on the left side of the first rib of the left mold, and the right open groove is arranged on the right side of the first rib of the right mold. The left open groove and the right open groove are jointly provided with a channel penetrating the two first ribs. The fastening bolt group includes a fastening bolt, one end of which is rotatably connected to the left open groove, the fastening bolt is placed in the channel and the other section extends out of the right open groove, a fastening nut is installed on the other end of the fastening bolt, and a steel gasket is sandwiched between the right open groove and the fastening nut.

4. The hanging mold plugging tool for indoor sewer holes according to claim 3 is characterized in that: A vertical hole penetrating from top to bottom is commonly arranged on the left open groove and the end of the fastening bolt, and a hairpin pin is installed in the vertical hole.

5. The hanging mold plugging tool for indoor sewer holes according to claim 1 is characterized in that: A groove is arranged on the butt joint side of one of the semicircular ring plates, and a boss matched with the groove is arranged on the butt joint side of the other semicircular ring plate.

6. The hanging mold plugging tool for indoor sewer holes according to claim 1, characterized in that: A plurality of second ribs are arranged in the middle of the outer arc surface of the arc plate, the plurality of second ribs are fixed on the bottom surface of the semicircular ring plate, the plurality of second ribs are arranged between two first ribs, and two adjacent second ribs are arranged at intervals.