Construction system of upper cross beam of tower column steel pipe truss
By using technical means such as mobile hydraulic combination frame, corbel support system, special-shaped groove rail sliding frame and mobile hanger construction platform in the construction of tower column steel pipe truss, the problems of poor positioning accuracy, low assembly accuracy, and difficult installation and dismantling of construction platforms during the construction process are solved, and efficient and safe construction progress and cost savings are achieved.
Patent Information
- Application Number
- CN202421874489.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2025-05-30
- Estimated Expiration
- 2034-08-05
AI Technical Summary
During the construction process of the cross beams on the tower column steel pipe truss, there are problems such as poor temporary positioning accuracy, low assembly accuracy, difficult installation and dismantling of the construction platform, high construction costs, and difficult temporary positioning at high altitudes, which affects the construction progress and safety.
Technical means such as mobile hydraulic combination frame, corrupt leg support system, special-shaped groove rail sliding frame and mobile hanger construction platform are adopted to improve the embedding accuracy and assembly accuracy of steel pipe trusses, reduce construction difficulty and cost, and improve construction safety and progress.
The installation accuracy of the beams on the tower column steel pipe truss is improved, the construction safety risks are reduced, the construction progress is accelerated, the construction cost is significantly saved, and the installation efficiency of steel anchor beams is improved.
Smart Images

Figure CN222923610U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of bridge engineering, and particularly relates to a construction system for the upper cross beam of a tower column steel pipe truss. Background Technique
[0002] In the construction of bridge engineering, it is necessary to continuously improve the bridge construction technology level in practice. Especially when facing complex structures such as long-span cable-stayed bridges, the steel anchor beam technology shows significant advantages in the construction of such bridges due to its high efficiency and adaptability. It not only improves the construction efficiency but also is particularly suitable for the construction of bridges in complex terrain areas, thereby ensuring the smoothness and safety of traffic.
[0003] The following problems will be encountered in the construction process of the upper cross beam of the tower column steel pipe truss:
[0004] (1) There is a problem of poor temporary positioning accuracy during the embedding construction of the embedded section of the upper cross beam of the steel pipe truss, which will directly affect the later construction of the steel pipe truss and increase the difficulty of the overall construction project;
[0005] (2) The steel pipe truss is assembled on the bridge deck on-site. Due to the poor flatness of the bridge deck, the assembly accuracy of the steel pipe truss is low;
[0006] (3) The construction platform for the upper cross beam of the tower column steel pipe truss adopts a floor support structure type such as a steel pipe support, which has problems of large construction installation and disassembly difficulty and high construction cost;
[0007] (4) The temporary positioning of the steel pipe truss at high altitude is also a thorny problem, which affects the construction progress and safety.
[0008] In view of this, in response to a series of problems that occur during the construction of the upper cross beam of the tower column steel pipe truss, it is urgent to invent a simple and effective construction system for the upper cross beam of the tower column steel pipe truss, reduce the construction difficulty of the high-altitude construction platform, improve the installation accuracy of the upper cross beam of the tower column steel pipe truss, reduce the construction safety risk, and speed up the construction progress. Summary of the Invention
[0009] The purpose of the utility model is to provide a construction system for the upper cross beam of a tower column steel pipe truss, which improves the installation accuracy of the upper cross beam of the tower column steel pipe truss, reduces the construction safety risk, speeds up the construction progress, and has the advantages of significantly saving construction costs and improving the installation efficiency of the steel anchor beam.
[0010] To achieve the above purpose, the present solution adopts a construction system for the upper cross beam of a tower column steel pipe truss, including:
[0011] A mobile hydraulic combined frame placed on the assembled bridge deck for assembling the steel pipe truss. The hydraulic combined frame includes multiple steel pipes perpendicular to the assembled bridge deck. A second I-beam is embedded in the concave-shaped support plate placed on the top of the steel pipe, and a steel pipe truss is arranged on the upper part of the second I-beam for assembly;
[0012] The bracket with a corbel is slidably arranged on the tower columns on both sides. Suspension ropes are arranged at both ends of the bracket with a corbel. A first support rod is slidably arranged on the bracket with a corbel. The first support rods are connected by a horizontal bracing. A first I-beam is arranged at the top of the first support rods. The steel pipe truss is temporarily placed on the first I-beam.
[0013] The tower wall suspension rod fixed at the top of the tower column. A stress positioning rod is arranged between the outer walls of the tower wall suspension rods. A special-shaped track member and a stress member are arranged on the stress positioning rod. A mobile hanging scaffold construction platform is arranged on the special-shaped track member. The hanging basket rod of the mobile hanging scaffold construction platform is embedded in the special-shaped track member. A driving device (44) is arranged on the hanging basket rod. And the bottom of the hanging basket rod is connected with a platform board and a guardrail.
[0014] The special-shaped groove rail is arranged at a position near the bottom inside the tower column. A sliding frame is arranged between the special-shaped groove rails on both sides. The sliding frame is slidably arranged along the height direction of the tower column along the special-shaped groove rail. The assembled steel pipe truss is placed and tied above the sliding frame.
[0015] Compared with the prior art, the technical solution has the following characteristics and beneficial effects:
[0016] 1. Developed a bracket with a corbel system for the embedded section of the steel pipe truss. The bracket with a corbel slides on the constructed tower column through structures such as special-shaped channel steels, improving the embedding accuracy of the embedded section of the steel pipe truss and reducing the construction difficulty.
[0017] 2. Developed a mobile hydraulic combined assembly system, a high-precision assembly platform for the steel pipe truss composed of a concave-shaped support plate, steel pipes, steering wheels, hydraulic bases, etc., improving the assembly accuracy of the steel pipe truss and reducing the construction difficulty.
[0018] 3. Developed a crossbeam installation construction platform system, a crossbeam installation construction platform composed of a platform board, hanging basket rods, hanging basket horizontal bracing rods, mobile wheels, etc., which can move freely between the tower columns, improving the safety of high-altitude construction.
[0019] 4. Developed a sliding frame, a mobile hydraulic sliding system composed of a moving device, a hydraulic telescopic rod, etc., realizing high-quality hoisting of the steel pipe truss and reducing the construction difficulty. Description of the Drawings
[0020] Figure 1 It is a schematic diagram of the bracket with a corbel;
[0021] Figure 2 It is a schematic diagram of the special-shaped channel steel;
[0022] Figure 3 It is a schematic diagram of the mobile hydraulic combined assembly system for the steel pipe truss;
[0023] Figure 4 It is a horizontal bracing diagram of the mobile hydraulic combined system;
[0024] Figure 5 It is a schematic diagram of the crossbeam installation construction platform system;
[0025] Figure 6 It is a schematic diagram of the connection between the tower wall suspension rod and the inner side of the tower wall;
[0026] Figure 7 It is a schematic sectional view of the construction platform;
[0027] Figure 8 It is a schematic diagram of the sliding frame construction;
[0028] Figure 9 It is a schematic diagram of the special-shaped groove rail;
[0029] Figure 10 It is a plan view of the sliding frame;
[0030] Figure 11 It is a side schematic diagram of the sliding frame.
[0031] Among them: 1 - corbel bracket, 2 - tower column, 3 - special-shaped channel steel, 4 - formwork, 5 - suspension rope, 6 - first I-beam, 7 - embedded steel plate, 8 - inclined steel pipe, 9 - stiffening plate, 10 - transverse steel pipe, 11 - sliding sleeve, 12 - track groove, 13 - diagonal brace, 14 - cross bar, 15 - first support rod, 16 - steel pipe truss, 17 - stiffening skeleton, 18 - assembled bridge deck, 19 - mobile hydraulic combined frame, 20 - parallel link telescopic rod, 21 - weld, 22 - second I-beam, 23 - hydraulic base, 24 - longitudinal diagonal link, 25 - steering wheel, 26 - flexible pad, 27 - hydraulic telescopic device, 28 - steel pipe, 29 - concave supporting plate, 30 - mobile hanging scaffold construction platform, 31 - platform board, 32 - guardrail, 33 - hanging basket rod, 34 - hanging basket parallel link, 35 - tower wall suspension rod, 36 - fixing piece, 37 - stress positioning rod, 38 - bolt, 39 - U-shaped fixing piece, 40 - special-shaped track piece, 41 - stress piece, 42 - first moving wheel, 43 - second moving wheel, 44 - driving device, 45 - sliding frame, 46 - special-shaped groove rail, 47 - moving device, 48 - sleeve, 49 - channel steel, 50 - moving wheel, 51 - hydraulic telescopic rod, 52 - strap, 53 - second support rod, 54 - vertical rod. Specific embodiments
[0032] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art belong to the scope of protection of the present invention.
[0033] Those skilled in the art should understand that in the disclosure of the present invention, the orientation or positional relationships indicated by the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. are based on the orientation or positional relationships shown in the drawings. These are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be construed as limiting the present invention.
[0034] It can be understood that the term "one" should be understood as "at least one" or "one or more". That is, in one embodiment, the number of one element can be one, while in other embodiments, the number of this element can be multiple. The term "one" should not be construed as a limitation on the quantity.
[0035] This solution provides a construction system for the upper cross beam of the tower column steel pipe truss, which is applicable to the construction of the upper cross beam of the steel pipe truss on the tower column, including:
[0036] The bracket with a bracket on both sides of the tower column 2 is slidably arranged, and sling ropes 5 are arranged at both ends of the bracket with a bracket 1. A first support rod 15 is slidably arranged on the bracket with a bracket 1. The first support rods 15 are connected by a horizontal bracing. A first I-beam 6 is arranged at the top of the first support rods 15, and the steel pipe truss 16 is temporarily placed on the first I-beam 6;
[0037] The mobile hydraulic combination frame 19 for assembling the steel pipe truss 16 is placed on the assembled bridge deck 18. The hydraulic combination frame 19 includes a plurality of steel pipes 28 perpendicular to the assembled bridge deck 18. A second I-beam 22 is embedded in the concave-shaped supporting plate 29 placed on the top of the steel pipe 28, and the steel pipe truss 16 is arranged on the upper part of the second I-beam 22 for assembly;
[0038] The tower wall suspension rod 35 fixed on the top of the tower column 2. A stress positioning rod 37 is arranged between the outer walls of the tower wall suspension rod 35. A special-shaped track member 40 and a stress member 41 are arranged on the stress positioning rod 37. A mobile hanging scaffold construction platform 30 is arranged on the special-shaped track member 40. The hanging basket rod 33 of the mobile hanging scaffold construction platform 30 is embedded in the special-shaped track member 40. A driving device 44 is arranged on the hanging basket rod 33, and the bottom of the hanging basket rod 33 is connected to the platform plate 31 and the guardrail 32;
[0039] The special-shaped groove track 46 is arranged at a position near the bottom inside the tower column 2. A sliding frame 45 is arranged between the two special-shaped groove tracks 46. The sliding frame 45 is slidably arranged along the height direction of the tower column 2 along the special-shaped groove track 46. The steel pipe truss 16 is placed and tied above the sliding frame 45.
[0040] In some embodiments, special-shaped steel channels 3 are fixedly arranged inside the tower column 2. The two ends of the bracket 1 are embedded into the special-shaped steel channels 3 to achieve sliding. The positions of two rows of special-shaped steel channels 3 are determined according to the positioning of the steel pipe truss and the size of the bracket on the already constructed tower column. After the special-shaped steel channels 3 are closely attached to the tower column, they are fixed to the tower column 2.
[0041] In some embodiments, the special-shaped steel channels 3 are arranged inside the tower column 2 and are arranged at a position close to the bottom of the tower column 2. As Figure 2 shown, the special-shaped steel channel 3 is a through-channel structure, and opposite track grooves 12 are arranged on the opposite two groove edges of the through-channel structure. The track grooves 12 are recessed relative to the groove edges. The two ends of the bracket 1 in this solution are embedded into the track grooves 12.
[0042] In some embodiments, the bracket 1 is composed of a diagonal brace 13 and a cross bar 14. One ends of the cross bar 14 and the diagonal brace 13 are respectively embedded into the special-shaped steel channel 3, and the other ends are connected to each other. Among them, the cross bar 14 is perpendicular to the tower column, and the diagonal brace 13 is inclined to the tower column. The assembled bracket needs to verify its bearing performance.
[0043] In some embodiments, a sliding sleeve 11 is arranged on the cross bar 14, and a first support rod 15 perpendicular to the cross bar 14 is arranged on the sliding sleeve 11. A first I-beam 6 is arranged at the top of the first support rod 15. Specifically, at least two first support rods 15 on the cross bars 14 on the same side are connected by a flat joint, and a first I-beam 6 is arranged on each first support rod 15.
[0044] In some embodiments, suspension ropes 5 are arranged at both ends of the bracket 1. By operating the suspension ropes 5 to lift, the steel pipe truss 16 located on the first I-beam 6 is lifted to the designed embedded position. The embedded steel plate 7 of the steel pipe truss 16 is welded to the stiffening skeleton 17 inside the tower column 2. Subsequently, the tower column pouring construction is carried out. When the tower column reaches the designed strength, the bracket 1 is lowered to the ground. In some embodiments, a formwork 4 is arranged outside the stiffening skeleton 17.
[0045] The steel pipe truss 16 in this solution is welded by stiffening plates 9, transverse steel pipes 10, etc. Four transverse steel pipes 10 are arranged in parallel at intervals to form a square truss space. Stiffening plates 9 are welded between adjacent two transverse steel pipes 10, and an embedded steel plate 7 is welded to the end of each transverse steel pipe 10.
[0046] In some embodiments, the steel pipe truss 16 is assembled and welded on site of the assembled bridge deck 18. Each steel pipe 28 is fixed on a hydraulic base 23. A steering wheel 25 and a hydraulic expander 27 are provided at the bottom of the hydraulic base 23, and a flexible pad 26 is provided at the bottom of the hydraulic expander 27. When the hydraulic expander 27 extends outwards relative to the steel pipe 28, the bottom of the hydraulic expander 27 is lower than the bottom of the steering wheel 25 to support each steel pipe 28. When the hydraulic expander 27 retracts inwards relative to the steel pipe 28, the bottom of the hydraulic expander 27 is higher than the bottom of the steering wheel 25, so that the steel pipe 28 can slide.
[0047] In some embodiments, two adjacent steel pipes 28 are connected by a longitudinal diagonal link 24, and two longitudinal diagonal links 24 cross each other in an "X" shape to connect the two steel pipes 28. A concave supporting plate 29 is provided at the top of each steel pipe 28, and a second I-beam 22 is placed in the concave supporting plate 29. The steel pipe truss 16 is erected on the second I-beam 22.
[0048] In addition, the mobile hydraulic combination frames 19 are spaced apart on the assembled bridge deck 18, and two adjacent mobile hydraulic combination frames 19 are connected by a horizontal link telescopic rod 20 transversely.
[0049] In some embodiments, the tower wall suspension rods 35 are provided at the top of the tower column 2, and the inner walls of the tower wall suspension rods 35 are connected by a fixing member 36. Specifically, as Figure 6 shown, the inner walls of multiple tower wall suspension rods 35 of this solution are connected by a fixing member 36, and U-shaped fixing members 39 with the same number as the tower wall suspension rods 25 are provided on the fixing member 36. Each U-shaped fixing member 39 is fixed on both sides of the corresponding tower wall suspension rod 25 by bolts 38.
[0050] As Figure 5 and Figure 7 shown, the tower wall suspension rod 35 is designed as a U-shaped structure, and the outer walls of the tower wall suspension rods 35 are connected by a horizontally arranged stress positioning rod 37. An abnormal track member 40 and a stress member 41 are provided between the stress positioning rods 37 of the two tower columns 2 on both sides. The abnormal track member 40 is fixed at a position close to both sides of the stress positioning rod 37, and the stress member 41 is fixed at a position close to the middle side of the stress positioning rod 37.
[0051] Moving wheels one 42 and moving wheels two 43 are provided on both sides of the hanging basket rod 33 of the moving hanging platform 30. The moving wheels one 42 and the moving wheels two 43 are embedded in the abnormal track member 40. The abnormal track member 40 is provided with grooves matching the moving wheels one 42 and the moving wheels two 43 on the side facing the hanging basket rod 33, and the moving wheels one 42 and the moving wheels two 43 are embedded in the grooves. In some embodiments, the hanging basket rod 33 straddles the abnormal track members 40 on both sides and is respectively fitted and embedded with the moving track members 30 on both sides.
[0052] The bottom of the hanging basket rod 33 is vertically connected with a platform plate 31, and guardrails 32 are vertically arranged in other directions of the platform plate 31 to jointly form a mobile hanging scaffold construction platform 30.
[0053] In some embodiments, such as Figure 9 As shown, the special-shaped groove rail 46 includes a channel steel 49 with a U-shaped cross-section, and sleeves 48 are arranged at intervals on both sides of the channel steel 49 relative to the outer side of the U-shaped cross-section.
[0054] Such as Figure 10 and Figure 11 As shown, the sliding frame 45 includes a support plate for supporting the steel pipe truss 16. Hydraulic telescopic rods 51 are respectively arranged obliquely at the four end sides of the support plate. The bottom of the hydraulic telescopic rod 51 bulges outward to be provided with moving wheels 50, and the moving wheels 50 are correspondingly arranged in the special-shaped groove rail 46. The hydraulic telescopic rods 51 between the tower columns 2 on the same side are connected by a horizontally arranged second support rod 53, and the second support rod 53 and the support plate are connected by a vertical rod 54. The sliding frame 45 is slowly slid by the lifting ropes 5 connected to the sliding frame 45. After the upper cross beam of the steel pipe truss 16 is slid to the designed position, the upper cross beam of the steel pipe truss is welded through the mobile hanging scaffold construction platform 30.
[0055] The construction method corresponding to the construction system of the upper cross beam of the tower column steel pipe truss includes the following steps: (1) Assembly of the bracket with corbel: First, determine the positions of two rows of special-shaped channel steels 3 on the already constructed tower column according to the positioning of the steel pipe truss and the dimensions of the bracket with corbel. The special-shaped channel steels 3 are fixed after being closely attached to the tower column. The first support rods 15 are connected by horizontal bracing, and the first I-beam 6 is arranged at the top of the first support rods 15. (2) Assembly of the upper cross beam section of the steel pipe truss: The embedded steel plate 7 is welded on one side of the embedded part of the upper cross beam section of the steel pipe truss. The steel pipe truss 16 is temporarily placed on the first I-beam 6, and the temporary fixation of the steel pipe truss 16 is done well. (3) Overall lifting of the bracket with corbel: By arranging the lifting ropes 5 at both ends of the bracket with corbel 1, the steel pipe truss 16 is lifted to the designed embedded position by operating the lifting ropes 5. The embedded steel plate 7 is welded to the stiffening skeleton 17 in the tower column 2, and then the tower column pouring construction is carried out. When the tower column reaches the designed strength, the bracket with corbel is lowered to the ground. (4) Assembly of the steel pipe truss: The assembly of the steel pipe truss is carried out in cooperation with a mobile hydraulic combined frame, and the sliding hydraulic combined frame realizes the assembly of the steel pipe truss, and finally the welding construction of the welds between the steel pipe trusses is carried out. (5) Installation of the construction platform for the cross beam installation. (7) Sliding installation of the upper cross beam of the steel pipe truss: The sliding frame 45 is slowly slid by the lifting ropes 5. After the upper cross beam of the steel pipe truss is slid to the designed position, the upper cross beam of the steel pipe truss is welded through the construction platform for the cross beam installation.
[0056] The present utility model is not limited to the above-mentioned optimal implementation mode. Any person can obtain other various forms of products under the inspiration of the present utility model. However, no matter what changes are made in its shape or structure, as long as it has a technical solution identical or similar to the present application, it falls within the protection scope of the present utility model.
Claims
1. A construction system for the upper cross beam of a tower steel tube truss, characterized in that: include: A movable hydraulic assembly frame (19) for assembling a steel tube truss (16) is placed on an assembled bridge deck (18), wherein the hydraulic assembly frame (19) includes a plurality of steel tubes (28) arranged perpendicular to the assembled bridge deck (18), a second I-beam (22) is embedded in a concave support plate (29) placed on top of the steel tube (28), and a steel tube truss (16) is arranged on top of the second I-beam (22) for assembly; A corbel bracket (1) is slidably arranged on the tower columns (2) on both sides, wherein suspension ropes (5) are arranged at both ends of the corbel bracket (1), a first support rod (15) is slidably arranged on the corbel bracket (1), the first support rods (15) are parallelly connected, a first I-beam (6) is arranged on the top of the first support rod (15), and a steel pipe truss (16) is temporarily placed on the first I-beam (6); A tower wall suspension rod (35) is fixed on the top of the tower column (2), a force-bearing positioning rod (37) is arranged between the outer walls of the tower wall suspension rod (35), a special-shaped track member (40) and a force-bearing member (41) are arranged on the force-bearing positioning rod (37), a mobile hanger construction platform (30) is arranged on the special-shaped track member (40), a hanging basket rod (33) of the mobile hanger construction platform (30) is embedded in the special-shaped track member (40), a driving device (44) is arranged on the hanging basket rod (33), and the bottom of the hanging basket rod (33) is connected to the platform plate (31) and the guardrail (32); A special-shaped groove rail (46) is arranged at a position near the bottom of the inner side of the tower column (2), and a sliding frame (45) is arranged between the special-shaped groove rails (46) on both sides. The sliding frame (45) is slidably arranged along the special-shaped groove rails (46) in the height direction of the tower column (2), and the assembled steel pipe trusses (16) are placed and bound above the sliding frame (45).
2. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: The bracket bracket (1) is composed of an oblique brace (13) and a cross bar (14), one end of the cross bar (14) and the oblique brace (13) are respectively embedded in the special-shaped channel steel (3), and the other ends are connected to each other, wherein the cross bar (14) is arranged perpendicular to the tower column, and the oblique brace (13) is arranged inclined to the tower column, and a sliding sleeve (11) is arranged on the cross bar (14), and a first support rod (15) arranged perpendicular to the cross bar (14) is arranged on the sliding sleeve (11).
3. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: The special-shaped channel steel (3) is a through-channel structure, and two opposite channel edges of the through-channel structure are provided with oppositely arranged track grooves (12), the track grooves (12) are recessed relative to the channel edges, and the two ends of the corbel bracket (1) are embedded in the track grooves (12).
4. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: Each steel pipe (28) is fixed on a hydraulic base (23). A steering wheel (25) and a hydraulic telescopic device (27) are provided at the bottom of the hydraulic base (23). A flexible pad (26) is provided at the bottom of the hydraulic telescopic device (27). When the hydraulic telescopic device (27) is extended outward relative to the steel pipe (28), the bottom of the hydraulic telescopic device (27) is lower than the bottom of the steering wheel (25) to support each steel pipe (28). When the hydraulic telescopic device (27) is retracted inward relative to the steel pipe (28), the bottom of the hydraulic telescopic device (27) is higher than the bottom of the steering wheel (25).
5. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: Two adjacent steel pipes (28) are connected via a longitudinal diagonal connecting rod (24), wherein the two longitudinal diagonal connecting rods (24) cross each other to form an "X" shape to connect the two steel pipes (28), and two adjacent mobile hydraulic assembly frames (19) are connected transversely via a parallel telescopic rod (20).
6. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: The inner walls of the plurality of tower wall hangers (35) are connected via a fixing member (36), wherein the fixing member (36) is provided with U-shaped fixing members (39) in the same number as the number of the tower wall hangers (35), and each U-shaped fixing member (39) is fixed to both sides of the corresponding tower wall hanger (35) via bolts (38).
7. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: A special-shaped track member (40) and a force-bearing member (41) are arranged between the force-bearing positioning rods (37) disposed on the tower columns (2) on both sides, wherein the special-shaped track member (40) is fixed on the force-bearing positioning rod (37) at positions close to both sides, and the force-bearing member (41) is fixed on the force-bearing positioning rod (37) at positions close to the middle side, and a moving wheel 1 (42) and a moving wheel 2 (43) are arranged on both sides of the hanging basket rod (33) of the mobile hanger construction platform (30), and the moving wheel 1 (42) and the moving wheel 2 (43) are embedded in the special-shaped track member (40).
8. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1 is characterized in that: The special-shaped groove rail (46) comprises a channel steel (49) with a U-shaped cross section, wherein sleeves (48) are arranged at intervals on both sides of the channel steel (49) relative to the outer side of the U-shaped cross section.
9. The construction system of the upper cross beam of the tower column steel tube truss according to claim 1, characterized in that: The sliding frame (45) comprises a supporting plate for supporting a steel pipe truss (16), wherein four end sides of the supporting plate are respectively inclinedly provided with hydraulic telescopic rods (51), and the bottom of the hydraulic telescopic rod (51) is protruding outward and provided with a moving wheel (50), and the moving wheel (50) is correspondingly arranged in the special-shaped groove rail (46).
10. The construction system of the upper cross beam of the tower column steel tube truss according to claim 9, characterized in that: The hydraulic telescopic rods (51) located on the same side tower column (2) are connected via a horizontal second support rod (53), and the second support rod (53) is connected to the support plate via a vertical rod (54).