Fabricated building laminated slab

By using assembled cardboard and suspended ring structures on the overlapping floor slabs, the construction hazards and resource waste caused by exposed steel bars are solved, and safe and efficient assembly and flexible pipeline layout are achieved.

CN223061846UActive Publication Date: 2025-07-04JIANGSU XUDE NEW CONSTRUCTION TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422234305.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2025-07-04
Estimated Expiration
2034-09-12

AI Technical Summary

Technical Problem

The exposed steel bars of existing building overlapping floor slabs are likely to injure workers during construction, and the fixed truss steel bars do not work after lifting, resulting in waste of resources and inflexible pipeline layout.

Method used

The assembly of the clamp plate and the lifting ring structure is adopted, and the stacking floor slab is assembled through the combination of the clamp plate and the pouring holes, and the lifting ring is installed on the side of the stacking floor slab for easy lifting and fixing. The assembly is made with built-in steel bars to avoid the use of exposed steel bars.

Benefits of technology

The safe and efficient assembly of overlapping floor slabs is achieved, which reduces construction risks, saves resources, simplifies pipeline layout, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223061846U_ABST
    Figure CN223061846U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type building laminated slab, and relates to the technical field of laminated floor slabs, the assembly type building laminated slab comprises a laminated floor slab, the outer wall of the front side of the laminated floor slab is fixedly provided with an assembly clamping plate I, the outer wall of the left side of the laminated floor slab is fixedly provided with an assembly clamping plate II, and the outer wall of the assembly clamping plate I is provided with a clamping plate I positioning hole. The assembly clamping plate I of one composite floor slab is clamped into the assembly clamping groove I of the other composite floor slab, the pouring hole I is aligned with the positioning hole of the clamping plate I, then the assembly clamping plate II is aligned with the assembly clamping groove II of the other composite floor slab, and the pouring hole II is aligned with the positioning hole of the clamping plate II; and then cement is poured into the first clamping plate positioning holes and the second clamping plate positioning holes through the first pouring holes and the second pouring holes correspondingly, so that the assembly of the laminated slabs is completed, and the effect that the assembly between the laminated slabs is safer and more efficient by using the built-in reinforcing steel bars is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of composite floor slabs, and particularly relates to a composite slab for prefabricated buildings. Background Art

[0002] A composite floor slab is an assembled integral floor slab formed by laminating a precast slab and a cast-in-place reinforced concrete layer. The composite floor slab has good integrity, and the upper and lower surfaces of the slab are flat, which is convenient for the decoration of the finishing layer, and is suitable for high-rise buildings and large-span buildings with high requirements for overall stiffness. The following problems exist in the prior art:

[0003] Because the existing building composite floor slabs are manufactured by the method of pouring cement mixed with steel bars, only the steel bars exposed around the composite slab can be used for assembly and combination, resulting in the problem that the exposed steel bars are very easy to injure workers during construction, and it is not conducive to assembly, with high danger. Moreover, in the existing composite slabs, the fixedly arranged truss steel bars are continuous. After the composite slab is hoisted, the truss steel bars no longer play any role, resulting in a great waste of resources, and the continuous truss steel bars will also affect the later pipeline installation, and it is not conducive to the flexible and effective layout of pipelines. Summary of the Utility Model

[0004] The utility model provides a composite slab for prefabricated buildings to solve the problems raised in the above background art.

[0005] To solve the above technical problems, the technical solution adopted by the utility model is:

[0006] A composite slab for prefabricated buildings includes a composite floor slab. An assembly clamping plate one is fixedly installed on the front outer wall of the composite floor slab, and an assembly clamping plate two is fixedly installed on the left outer wall of the composite floor slab. A clamping plate one positioning hole is opened on the outer wall of the assembly clamping plate one, and a clamping plate two positioning hole is opened on the outer wall of the assembly clamping plate two. An assembly slot two is opened on the right inner wall of the composite floor slab, and a pouring hole two is penetrated and opened on the top inner wall of the assembly slot two. An assembly slot one is opened on the rear inner wall of the composite floor slab, and a pouring hole one is penetrated and opened on the top inner wall of the assembly slot one.

[0007] The further improvement of the technical solution of the utility model lies in that: the size of the assembly clamping plate one is the same as the inner wall size of the assembly slot one, and the inner wall size of the clamping plate one positioning hole is the same as the inner wall size of the pouring hole one.

[0008] The further improvement of the technical solution of the utility model lies in that: the size of the assembly clamping plate two is the same as the inner wall size of the assembly slot two, and the inner wall size of the clamping plate two positioning hole is the same as the inner wall size of the pouring hole two.

[0009] By adopting the above technical solution, through the mutual cooperation among the positioning holes of the first clamping plate, the positioning holes of the second clamping plate, the first pouring hole, and the second pouring hole in this solution, the assembled composite floor slab can be directly poured with cement for fixation.

[0010] A further improvement of the technical solution of the present utility model lies in that: laminated floor slab steel bars are fixedly installed in the inner cavities on both the upper and lower sides of the laminated floor slab.

[0011] By adopting the above technical solution, through the laminated floor slab steel bars in this solution, the fixation of the first lifting ring and the second lifting ring is made more firm.

[0012] A further improvement of the technical solution of the present utility model lies in that: the first lifting rings are fixedly installed on both sides above the front side of the laminated floor slab, the outer wall of the bottom end of the first lifting ring is fixedly connected to the outer wall of one end of the front side of the laminated floor slab steel bars, and the first lifting ring slots are provided on the outer walls of the left and right ends above the rear side of the laminated floor slab.

[0013] A further improvement of the technical solution of the present utility model lies in that: the second lifting rings are fixedly installed on both sides below the rear side of the laminated floor slab, the outer wall of the bottom end of the second lifting ring is fixedly connected to the outer wall of one end of the right side of the laminated floor slab steel bars, and the second lifting ring slots are provided on the outer walls of the left and right ends below the front side of the laminated floor slab.

[0014] By adopting the above technical solution, through the mutual cooperation among the first lifting ring, the second lifting ring, the first lifting ring slot, and the second lifting ring slot in this solution, the laminated floor slab can be lifted by the double first lifting rings and the double second lifting rings on the front and rear sides, which is convenient for handling, and when assembling, the first lifting ring is snapped into the first lifting ring slot and the second lifting ring is snapped into the second lifting ring slot without affecting the assembly.

[0015] Due to the adoption of the above technical solution, the technical progress achieved by the present utility model compared with the prior art is:

[0016] 1. The utility model provides a composite slab for prefabricated buildings. By using the cooperation of assembly slot 1, pouring hole 1, assembly slot 2, pouring hole 2, assembly clamping plate 1, clamping plate 1 positioning hole, assembly clamping plate 2, and clamping plate 2 positioning hole, when assembling the composite floor slab, one assembly clamping plate 1 of one composite floor slab is clamped into the assembly slot 1 of another composite floor slab, and the pouring hole 1 is aligned with the clamping plate 1 positioning hole. Then, the assembly clamping plate 2 is aligned with the assembly slot 2 of another composite floor slab, and the pouring hole 2 is aligned with the clamping plate 2 positioning hole. Then, cement is poured into the clamping plate 1 positioning hole and the clamping plate 2 positioning hole through the pouring hole 1 and the pouring hole 2 respectively, so that the assembly of the composite slab is completed. This solves the problem that the existing building composite floor slabs are manufactured by pouring a mixture of cement and steel bars, and can only be assembled and combined by relying on the steel bars exposed around the composite slab, resulting in the exposed steel bars being very easy to injure workers during construction, and being not conducive to assembly, with a relatively high risk. It achieves the effect of making the assembly between the composite floor slabs safer and more efficient by using the method of internal steel bars.

[0017] 2. The utility model provides a composite slab for prefabricated buildings. By using the cooperation of lifting ring 1, lifting ring slot 1, lifting ring 2, lifting ring slot 2, and composite floor slab steel bars, when the composite floor slab needs to be lifted, only the lifting ropes need to pass through the inner walls of the two lifting rings 1 and the two lifting rings 2 respectively. Moreover, both the lifting ring 1 and the lifting ring 2 are fixedly connected to the composite floor slab steel bars built into the composite floor slab, so it is more firm. And when the composite floor slab is assembled, the lifting ring 1 will be clamped into the lifting ring slot 1, and the lifting ring 2 will be clamped into the lifting ring slot 2, which does not affect the assembly. This solves the problem that in the existing composite slabs, the fixedly arranged truss steel bars are continuous. After the composite slab is hoisted, the truss steel bars no longer play any role, resulting in a great waste of resources, and the continuous truss steel bars will also affect the later pipeline installation, being not conducive to the flexible and effective layout of pipelines. It achieves the effect of keeping both the upper and lower surfaces of the composite floor slab flat by installing four lifting rings on the side of the composite floor slab, saving costs and facilitating the later pipeline installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0019] Figure 2 It is a schematic side sectional view of the composite floor slab of the structure of the utility model;

[0020] Figure 3 It is a schematic front sectional view of the composite floor slab of the structure of the utility model;

[0021] Figure 4 It is a schematic side sectional view of the lifting ring slot of the structure of the utility model.

[0022] In the figure: 1, composite floor slab; 11, first assembly card slot; 111, first pouring hole; 12, second assembly card slot; 121, second pouring hole; 13, first lifting ring; 131, first lifting ring card slot; 14, second lifting ring; 141, second lifting ring card slot; 15, steel bars of composite floor slab; 2, first assembly card plate; 21, positioning hole of first card plate; 3, second assembly card plate; 31, positioning hole of second card plate. Specific implementation mode

[0023] The following further describes the present utility model in detail with reference to the embodiments: Embodiment

[0024] As Figures 1-4 shown, the present utility model provides a composite slab for prefabricated buildings, including a composite floor slab 1. A first assembly card plate 2 is fixedly installed on the front outer wall of the composite floor slab 1, and a second assembly card plate 3 is fixedly installed on the left outer wall of the composite floor slab 1. A positioning hole 21 of the first card plate is opened on the outer wall of the first assembly card plate 2, and a positioning hole 31 of the second card plate is opened on the outer wall of the second assembly card plate 3. A second assembly card slot 12 is opened on the right inner wall of the composite floor slab 1, and a second pouring hole 121 penetrates through the top inner wall of the second assembly card slot 12. A first assembly card slot 11 is opened on the rear inner wall of the composite floor slab 1, and a first pouring hole 111 penetrates through the top inner wall of the first assembly card slot 11.

[0025] In this embodiment, by inserting the first assembly card plate 2 of one composite floor slab 1 into the first assembly card slot 11 of another composite floor slab 1, aligning the first pouring hole 111 with the positioning hole 21 of the first card plate, then aligning the second assembly card plate 3 with the second assembly card slot 12 of another composite floor slab 1, and aligning the second pouring hole 121 with the positioning hole 31 of the second card plate, and so on, the composite floor slabs 1 to be assembled are completed for assembly. Embodiment

[0026] As Figures 1-4 shown, on the basis of Embodiment 1, the present utility model provides a technical solution: Preferably, the size of the first assembly card plate 2 is the same as the inner wall size of the first assembly card slot 11, the inner wall size of the positioning hole 21 of the first card plate is the same as the inner wall size of the first pouring hole 111, the size of the second assembly card plate 3 is the same as the inner wall size of the second assembly card slot 12, and the inner wall size of the positioning hole 31 of the second card plate is the same as the inner wall size of the second pouring hole 121.

[0027] In this embodiment, after the assembly is completed, cement is respectively poured into the positioning hole 21 of the first card plate and the positioning hole 31 of the second card plate through the first pouring hole 111 and the second pouring hole 121 until the surfaces of the first pouring hole 111 and the second pouring hole 121 are leveled, and then the pouring is stopped. After the cement solidifies, the assembly of all composite floor slabs 1 can be completed. Embodiment

[0028] AsFigures 1-4 As shown in the figure, on the basis of Embodiment 1, the present utility model provides a technical solution: Preferably, laminated floor slabs 1 are fixedly installed in the inner cavities on both the upper and lower sides of the laminated floor slab 1. On both sides above the front side of the laminated floor slab 1, lifting rings 13 are fixedly installed. The outer wall of the bottom end of the lifting ring 13 is fixedly connected to the outer wall of one end of the front side of the laminated floor slab reinforcement 15. On the outer walls of the upper left and right ends above the rear side of the laminated floor slab 1, lifting ring slots 131 are provided. On the outer walls of the lower left and right sides below the rear side of the laminated floor slab 1, lifting rings 14 are fixedly installed. The outer wall of the bottom end of the lifting ring 14 is fixedly connected to the outer wall of one end of the right side of the laminated floor slab reinforcement 15. On the outer walls of the lower left and right ends of the front side of the laminated floor slab 1, lifting ring slots 141 are provided.

[0029] In this embodiment, when the laminated floor slab 1 needs to be lifted and transported, only the lifting ropes need to pass through the inner walls of the two lifting rings 13 and the two lifting rings 14 respectively. Moreover, both the lifting ring 13 and the lifting ring 14 are fixedly connected to the laminated floor slab reinforcement 15 inside the laminated floor slab 1, so it is more firm. And when the laminated floor slab 1 is assembled, the lifting ring 13 will be stuck into the lifting ring slot 131, and the lifting ring 14 will be stuck into the lifting ring slot 141, which does not affect the assembly.

[0030] Next, the working principle of the laminated slab of the prefabricated building will be specifically described.

[0031] As Figures 1-4 shown, by inserting the assembly clamping plate 1 2 of one laminated floor slab 1 into the assembly slot 1 11 of another laminated floor slab 1, and aligning the pouring hole 1 111 with the clamping plate 1 positioning hole 21, then aligning the assembly clamping plate 2 3 with the assembly slot 2 12 of another laminated floor slab 1, and aligning the pouring hole 2 121 with the clamping plate 2 positioning hole 31, and then pouring cement into the clamping plate 1 positioning hole 21 and the clamping plate 2 positioning hole 31 through the pouring hole 1 111 and the pouring hole 2 121 respectively, so that the laminated floor slab 1 is assembled. When the laminated floor slab 1 needs to be lifted and transported, only the lifting ropes need to pass through the inner walls of the two lifting rings 13 and the two lifting rings 14 respectively. Moreover, both the lifting ring 13 and the lifting ring 14 are fixedly connected to the laminated floor slab reinforcement 15 inside the laminated floor slab 1, so it is more firm. And when the laminated floor slab 1 is assembled, the lifting ring 13 will be stuck into the lifting ring slot 131, and the lifting ring 14 will be stuck into the lifting ring slot 141, which does not affect the assembly.

[0032] The above has generally described the present utility model in detail. However, based on the present utility model, some modifications or improvements can be made, which are obvious to those of ordinary skill in the art. Therefore, the modifications or improvements made without departing from the spirit of the present utility model are within the protection scope of the present utility model.

Claims

1. A prefabricated building composite slab, comprising a composite floor slab (1), characterized in that: An assembly clamping plate one (2) is fixedly installed on the front outer wall of the composite floor slab (1), an assembly clamping plate two (3) is fixedly installed on the left outer wall of the composite floor slab (1), a clamping plate one positioning hole (21) is formed in the outer wall of the assembly clamping plate one (2), a clamping plate two positioning hole (31) is formed in the outer wall of the assembly clamping plate two (3), an assembly clamping groove two (12) is formed in the right inner wall of the composite floor slab (1), a pouring hole two (121) is formed through the top inner wall of the assembly clamping groove two (12), an assembly clamping groove one (11) is formed in the rear inner wall of the composite floor slab (1), and a pouring hole one (111) is formed through the top inner wall of the assembly clamping groove one (11).

2. The precast building composite slab according to claim 1, characterized in that: The size of the assembly clamping plate one (2) is the same as the inner wall size of the assembly clamping groove one (11), and the inner wall size of the clamping plate one positioning hole (21) is the same as the inner wall size of the pouring hole one (111).

3. The precast building composite slab according to claim 1, characterized in that: The size of the assembly clamping plate two (3) is the same as the inner wall size of the assembly clamping groove two (12), and the inner wall size of the clamping plate two positioning hole (31) is the same as the inner wall size of the pouring hole two (121).

4. A prefabricated building composite slab according to claim 1, characterized in that: Composite floor slab steel bars (15) are fixedly installed in the upper and lower inner cavities of the composite floor slab (1).

5. The precast building composite slab according to claim 4, wherein: Lifting rings one (13) are fixedly installed on both sides above the front side of the composite floor slab (1), the bottom outer wall of the lifting ring one (13) is fixedly connected to the front end outer wall of the composite floor slab steel bar (15), and lifting ring clamping grooves one (131) are formed in the outer walls at the left and right ends above the rear side of the composite floor slab (1).

6. The precast building composite slab according to claim 4, characterized in that: Lifting rings two (14) are fixedly installed on both sides of the lower left and right sides of the rear side of the composite floor slab (1), the bottom outer wall of the lifting ring two (14) is fixedly connected to the right end outer wall of the composite floor slab steel bar (15), and lifting ring clamping grooves two (141) are formed in the outer walls at the left and right ends of the lower front side of the composite floor slab (1).