Tower crane wall-attaching structure between towers

By designing the wall-attached structure between tower cranes and using temporary wall-attached disassembly and reuse of the first and second wall-attached components, the problem of frequent adjustment of the tower cranes and wall-attached components is solved, which improves construction efficiency and reduces costs, and at the same time, it realizes convenient switching of tower cranes between different towers.

CN223087479UActive Publication Date: 2025-07-11CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422243699.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2025-07-11
Estimated Expiration
2034-09-13

AI Technical Summary

Technical Problem

The existing tower crane wall-attached components are frequently adjusted, resulting in low construction efficiency and high cost, and it is difficult to switch between tower cranes at different heights.

Method used

A wall-attachment structure between tower cranes is designed, including the first and second wall-attachment components, and the disassembly and reuse of the first temporary wall-attachment and the second temporary wall-attachment is used to avoid lifting new components. Combined with the configuration of the first and second wall-attachment components, the flexible switching of the tower cranes between different towers is achieved.

Benefits of technology

It improves construction efficiency, reduces construction costs, and realizes convenient attachment switching of tower cranes between different towers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223087479U_ABST
    Figure CN223087479U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, and discloses a tower crane wall-attached structure between towers, which comprises a first wall-attached component and a second wall-attached component, the first wall attaching assembly comprises first wall attaching units which are arranged at intervals in the vertical direction, first temporary attaching walls are arranged between the adjacent first wall attaching units, one ends of the first wall attaching units and the first temporary attaching walls are connected with the outer wall of the first tower building, and the other ends of the first wall attaching units and the first temporary attaching walls are connected with one side wall of a tower body of the tower crane; the second wall attaching assembly comprises second wall attaching units arranged at intervals in the vertical direction, a second temporary attaching wall is arranged between every two adjacent second wall attaching units, one end of each second wall attaching unit and one end of each second temporary attaching wall are both connected with the outer wall of the second tower, and the other end of each second wall attaching unit and the other end of each second temporary attaching wall are both connected with the other side wall of the tower body. The utility model has the beneficial effects that two towers can be easily switched, the construction cost is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a tower crane attachment structure between towers. Background Art

[0002] When constructing a tower building, in order to facilitate the hoisting of building materials, a tower crane is usually installed near the tower building so that the tower building is within the hoisting range of the tower crane. In order to ensure the stability of the tower crane during hoisting, multiple attachment components are generally arranged in the height direction between the tower crane and the corresponding tower building under construction. In the prior art, in order to improve the utilization rate of the tower crane, one tower crane can correspond to the hoisting of building materials for two tower buildings. As the construction height of the tower building increases, it is necessary to synchronously adjust the distribution of the attachment components according to the construction height.

[0003] The adjustment method is as follows: hoist a new attachment component and set it above the original attachment component. After the newly hoisted attachment component is installed, remove the lowermost attachment component. By using this adjustment method, it is necessary to hoist the new attachment component each time, resulting in low construction efficiency and high overall construction cost. Moreover, when the construction heights between the two tower buildings are different and the tower crane is attached to the tower building with a lower construction height through the attachment component for construction, when it is necessary to construct the tower building with a higher construction height subsequently, it is not easy for the tower crane to switch the attachment between the two tower buildings. Summary of the Utility Model

[0004] The purpose of the utility model is to provide a tower crane attachment structure between towers, which is easy to switch between two tower buildings, reduces the construction cost and improves the construction efficiency.

[0005] In order to achieve the above purpose, the utility model provides a tower crane attachment structure between towers. The tower crane is arranged between a first tower building and a second tower building, and the height of the second tower building is greater than that of the first tower building. The structure includes a first attachment component and a second attachment component;

[0006] The first attachment component includes first attachment units arranged at intervals in the vertical direction. A first temporary attachment is arranged between adjacent first attachment units. One end of each of the first attachment unit and the first temporary attachment is connected to the outer wall of the first tower building, and the other end of each of them is connected to one side wall of the tower crane body;

[0007] The installation height of the second attachment component is greater than that of the first attachment component. The second attachment component includes second attachment units arranged at intervals in the vertical direction. A second temporary attachment is arranged between adjacent second attachment units. One end of each of the second attachment unit and the second temporary attachment is connected to the outer wall of the second tower building, and the other end of each of them is connected to the other side wall of the tower crane body.

[0008] Furthermore, the first wall-attached unit and the second wall-attached unit have the same structure. The first wall-attached unit includes a first wall-attached frame, a first wall-attached rod, and a support. The first wall-attached frame is sleeved on the tower body and fixed to the tower body. One end of the first wall-attached rod is hinged to the first wall-attached frame, and the other end is hinged to the support.

[0009] Furthermore, the first wall-attached rod includes a first rod body and an adjustment assembly. One end of the first rod body is provided with a first hinge hole for hinging to the first wall-attached frame or the support. The other end of the first rod body is provided with the adjustment assembly for adjusting the length of the first wall-attached rod. The adjustment assembly is provided with a second hinge hole for hinging to the first wall-attached frame or the support.

[0010] Furthermore, the adjustment assembly includes a screw rod and a connecting seat. One end of the screw rod is threadedly connected to the first rod body, and the other end is threadedly connected to the connecting seat. The other end of the connecting seat is provided with the second hinge hole.

[0011] Furthermore, first ribs are arranged on the outer wall of the first rod body along the length direction, and second ribs are arranged on the outer wall of the first rod body at intervals along the length direction. The first ribs and the second ribs are connected in sequence.

[0012] Furthermore, a through hole perpendicular to the axis of the screw rod is provided in the middle of the screw rod.

[0013] Furthermore, the support includes a base plate, a first support plate, and a second support plate. The first support plates are arranged on the base plate at intervals along the length direction. The side walls of adjacent support plates and the top surface of the base plate form an installation groove. One end of the first wall-attached rod is arranged in the installation groove, and the first support plate is provided with a through hole for passing through a pin shaft. The second support plates are arranged on the back side of the first support plate at intervals along the width direction of the base plate.

[0014] Furthermore, the base plate, the first support plate, and the second support plate are fixed by welding, and the base plate is provided with installation holes.

[0015] Compared with the prior art, the tower crane attachment structure between towers in an embodiment of the present utility model has the following beneficial effects: The first attachment assembly includes first attachment units arranged at intervals in the vertical direction. A first temporary attachment is provided between adjacent first attachment units. One end of each of the first attachment unit and the first temporary attachment is connected to the outer wall of the first tower, and the other end is connected to a side wall of the tower crane body. As the construction height of the first tower increases, when it is necessary to adjust the distribution of the first attachment units on the first tower, the first temporary attachment can be disassembled and used as the next first attachment unit, without hoisting new first attachment units, improving construction efficiency and reducing construction costs. Similarly, when it is necessary to adjust the distribution of the second attachment units on the second tower, the second temporary attachment can be disassembled and used as the next second attachment unit, without hoisting new second attachment units, improving construction efficiency and reducing construction costs. In addition, since the first attachment assembly is provided between the first tower and the tower crane, and the second attachment assembly is provided between the second tower and the tower crane, when constructing the floors of the second tower higher than the first tower, due to the existence of the first attachment assembly, there is no need to set an attachment structure at the bottom of the second tower and the tower crane, reducing the amount of attachment structure used and lowering construction costs. At the same time, the attachment switching of the tower crane between different towers can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a schematic structural diagram of the tower crane attachment structure between towers in an embodiment of the present utility model;

[0017] Figure 2 is a top view of the tower crane attachment structure between towers in an embodiment of the present utility model;

[0018] Figure 3 is a schematic structural diagram of the first attachment frame of the tower crane attachment structure between towers in an embodiment of the present utility model;

[0019] Figure 4 is a schematic structural diagram of the first attachment rod of the tower crane attachment structure between towers in an embodiment of the present utility model;

[0020] Figure 5 are the three views of the support of the tower crane attachment structure between towers in an embodiment of the present utility model.

[0021] In the figure, 1 is the first wall-attached component; 11 is the first wall-attached unit; 12 is the first temporary wall attachment; 111 is the first wall-attached frame; 112 is the first wall-attached rod; 113 is the support; 1131 is the base plate; 1132 is the first support plate; 1133 is the second support plate; 1134 is the installation groove; 11321 is the through hole; 1121 is the first rod body; 11211 is the first hinge hole; 11212 is the first rib; 11213 is the second rib; 1122 is the adjustment component; 11221 is the screw; 11222 is the connecting seat; 11223 is the second hinge hole; 2 is the second wall-attached component; 21 is the second wall-attached unit; 22 is the second temporary wall attachment; a is the first tower; b is the second tower; c is the tower crane. Detailed implementation manners

[0022] The following combines the drawings and embodiments to further describe in detail the specific implementation manners of the present utility model. The following embodiments are used to illustrate the present utility model, but are not used to limit the scope of the present utility model.

[0023] In the description of the present utility model, it should be understood that the orientation or positional relationship indicated by the terms "upper", "lower", "front", "rear", "inner", "outer", etc. in the present utility model is based on the positional relationship shown in the drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device and element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present utility model.

[0024] In the description of the present utility model, it should be understood that the terms "first", "second", etc. in the present utility model are used to describe various information, but these information should not be limited to these terms, and these terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present utility model, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.

[0025] As Figure 1 shown, in a tower crane wall attachment structure between towers in a preferred embodiment of the present utility model, the tower crane c is arranged between the first tower a and the second tower b, and the height of the second tower b is greater than the height of the first tower a. In order to facilitate the switching of the tower crane c between the two towers, meanwhile, reduce the wall attachment structure and lower the construction cost, the wall attachment structure of this embodiment includes a first wall-attached component 1 and a second wall-attached component 2; refer to Figure 1 、 Figure 2, the first attachment wall assembly 1 includes first attachment wall units 11 arranged at intervals in the vertical direction. A first temporary attachment wall 12 is provided between adjacent first attachment wall units 11. One end of each of the first attachment wall unit 11 and the first temporary attachment wall 12 is connected to the outer wall of the first tower a, and the other end is connected to one side wall of the tower body of the tower crane c. When it is necessary to adjust the distribution of the first attachment wall units 11 on the first tower a, the first temporary attachment wall 12 can be disassembled and used as the next first attachment wall unit 11, without hoisting new first attachment wall units 11, improving construction efficiency and reducing construction costs.

[0026] The installation height of the second attachment wall assembly 2 is greater than that of the first attachment wall assembly 1. The second attachment wall assembly 2 includes second attachment wall units 21 arranged at intervals in the vertical direction. A second temporary attachment wall 22 is provided between adjacent second attachment wall units 21. One end of each of the second attachment wall unit 21 and the second temporary attachment wall 22 is connected to the outer wall of the second tower b, and the other end is connected to the other side wall of the tower body. Similarly, when it is necessary to adjust the distribution of the second attachment wall units 21 on the second tower b, the second temporary attachment wall 22 can be disassembled and used as the next second attachment wall unit 21, without hoisting new second attachment wall units 21, improving construction efficiency and reducing construction costs.

[0027] Since the first attachment wall assembly 1 is provided between the first tower a and the tower crane c, and the second attachment wall assembly 2 is provided between the second tower b and the tower crane c, refer to Figure 1 , when constructing the floors of the second tower b higher than the first tower a, due to the existence of the first attachment wall assembly 1, there is no need to set up an attachment wall structure at the bottom of the second tower b and the tower crane c, reducing the amount of the attachment wall structure and lowering the construction cost. At the same time, the attachment of the tower crane c between different towers can be switched.

[0028] Furthermore, in order to simplify the attachment wall structure, in this embodiment, the structures of the first attachment wall unit 11, the second attachment wall unit 21, the first temporary attachment wall 12, and the second temporary attachment wall 22 are the same. For the sake of simplifying the description, only the structure of the first attachment wall unit 11 will be described.

[0029] Specifically, refer to Figure 2 , the first attachment wall unit 11 includes a first attachment wall frame 111, a first attachment wall rod 112, and a support 113. Among them, the first attachment wall frame 111 is sleeved on the tower body and fixed to the tower body. One end of the first attachment wall rod 112 is hinged to the first attachment wall frame 111, and the other end is hinged to the support 113. The first attachment wall frame 111 is a standard part, and its structure is as Figure 3 shown.

[0030] Furthermore, in order to facilitate fine-tuning of the overall length of the first attachment wall rod 112 and facilitate installation, in this embodiment, refer to Figure 4, the first wall-attached rod 112 includes a first rod body 1121 and an adjustment assembly 1122. One end of the first rod body 1121 is provided with a first hinge hole 11211 for hinging with the first wall-attached frame 111 or the support 113. The other end of the first rod body 1121 is provided with an adjustment assembly 1122 for adjusting the length of the first wall-attached rod 112. The adjustment assembly 1122 is provided with a second hinge hole 11223 for hinging with the first wall-attached frame 111 or the support 113.

[0031] Specifically, in order to facilitate the design of the adjustment assembly 1122, in this embodiment, the adjustment assembly 1122 includes a screw rod 11221 and a connecting seat 11222. One end of the screw rod 11221 is threadedly connected to the first rod body 1121, and the other end is threadedly connected to the connecting seat 11222. The other end of the connecting seat 11222 is provided with a second hinge hole 11223. In order to facilitate the rotation of the screw rod 11221 and thus adjust the overall length of the first wall-attached rod 112, a through hole perpendicular to the axis of the screw rod 11221 is provided in the middle of the screw rod 11221. An auxiliary instrument (such as a wrench, etc.) can be inserted into the through hole to adjust the insertion depth of the screw rod 11221 in the first rod body 1121 and the connecting seat 11222.

[0032] Further, in order to improve the structural strength of the first rod body 1121, refer to Figure 4 , a first rib 11212 is provided on the outer wall of the first rod body 1121 along the length direction, and a second rib 11213 is provided on the outer wall of the first rod body 1121 at intervals along the length direction. The first rib 11212 and the second rib 11213 are connected in sequence to ensure the overall structural strength of the first rod body 1121.

[0033] Even further, in order to facilitate the design of the support 113 and simplify the structure of the support 113, in this embodiment, the support 113 includes a base plate 1131, a first support plate 1132, and a second support plate 1133. Refer to Figure 5 , the base plate 1131 is provided with the first support plate 1132 at intervals along the length direction. The side walls of adjacent support plates and the top surface of the base plate 1131 form an installation groove 1134. One end of the first wall-attached rod 112 is arranged in the installation groove 1134, and the first support plate 1132 is provided with a through hole 11321 for passing through a pin shaft, that is, a pin shaft is passed through the first hinge hole 11211 and the through hole 11321 to realize the hinging of the support 113 and the first wall-attached rod 112. Similarly, the first wall-attached rod 112 and the first wall-attached frame 111 adopt the same fixing method, which will not be elaborated here. At the same time, in order to ensure that the first support plate 1132 has good structural strength, the second support plate 1133 is provided at intervals along the width direction of the base plate 1131 on the back side of the first support plate 1132.

[0034] Further, in order to facilitate the fixed connection between the substrate 1131, the first support plate 1132, and the second support plate 1133, in this embodiment, welding is used to fix them. In order to facilitate the fixation of the support 113 and the tower, mounting holes are provided in the substrate 1131, and wall-piercing screws 11221 can be arranged in the mounting holes.

[0035] In summary, the embodiment of the present utility model provides a tower crane attachment structure between towers. The first attachment assembly 1 includes first attachment units 11 arranged at intervals in the vertical direction. A first temporary attachment 12 is provided between adjacent first attachment units 11. One ends of the first attachment unit 11 and the first temporary attachment 12 are both connected to the outer wall of the first tower a, and the other ends are both connected to one side wall of the tower body of the tower crane c. As the construction height of the first tower a increases, when it is necessary to adjust the distribution of the first attachment units 11 on the first tower a, the first temporary attachment 12 can be disassembled and used as the next first attachment unit 11, without hoisting a new first attachment unit 11, improving the construction efficiency and reducing the construction cost. Similarly, when it is necessary to adjust the distribution of the second attachment units 21 on the second tower b, the second temporary attachment 22 can be disassembled and used as the next second attachment unit 21, without hoisting a new second attachment unit 21, improving the construction efficiency and reducing the construction cost. In addition, since the first attachment assembly 1 is provided between the first tower a and the tower crane c, and the second attachment assembly 2 is provided between the second tower b and the tower crane c, when constructing the floors of the second tower b higher than the first tower a, due to the existence of the first attachment assembly 1, there is no need to set an attachment structure at the bottom of the second tower b and the tower crane c, reducing the amount of the attachment structure used and lowering the construction cost. At the same time, the attachment switching of the tower crane c between different towers can be realized.

[0036] The above are only the preferred embodiments of the present utility model. It should be noted that for those of ordinary skill in the art in this technical field, without departing from the technical principle of the present utility model, several improvements and replacements can still be made, and these improvements and replacements should also be regarded as the protection scope of the present utility model.

Claims

1. A tower crane attachment structure between towers. The tower crane is located between a first tower and a second tower, and the height of the second tower is greater than that of the first tower. It is characterized in that: It includes a first wall-attaching component and a second wall-attaching component; The first wall-attaching component includes first wall-attaching units arranged at intervals in the vertical direction. A first temporary wall-attaching structure is provided between adjacent first wall-attaching units. One end of each of the first wall-attaching unit and the first temporary wall-attaching structure is connected to the outer wall of the first tower, and the other end of each is connected to one side wall of the tower crane body; The installation height of the second wall-attaching component is greater than that of the first wall-attaching component. The second wall-attaching component includes second wall-attaching units arranged at intervals in the vertical direction. A second temporary wall-attaching structure is provided between adjacent second wall-attaching units. One end of each of the second wall-attaching unit and the second temporary wall-attaching structure is connected to the outer wall of the second tower, and the other end of each is connected to the other side wall of the tower crane body.

2. The tower crane attachment structure between towers according to claim 1, characterized in that: The first wall-attaching unit and the second wall-attaching unit have the same structure. The first wall-attaching unit includes a first wall-attaching frame, a first wall-attaching rod, and a support. The first wall-attaching frame is sleeved on the tower crane body and fixed to the tower crane body. One end of the first wall-attaching rod is hinged to the first wall-attaching frame, and the other end is hinged to the support.

3. The tower crane attachment structure between towers according to claim 2, characterized in that: The first wall-attaching rod includes a first rod body and an adjustment component. One end of the first rod body is provided with a first hinge hole for hinging to the first wall-attaching frame or the support. The other end of the first rod body is provided with the adjustment component for adjusting the length of the first wall-attaching rod. A second hinge hole for hinging to the first wall-attaching frame or the support is provided on the adjustment component.

4. The tower crane attached wall structure between towers according to claim 3, wherein: The adjustment component includes a screw rod and a connection seat. One end of the screw rod is threadedly connected to the first rod body, and the other end is threadedly connected to the connection seat. The other end of the connection seat is provided with the second hinge hole.

5. The tower crane attachment structure between towers according to claim 4, characterized in that: First ribs are provided on the outer wall of the first rod body along the length direction, and second ribs are provided on the outer wall of the first rod body at intervals along the length direction. The first ribs and the second ribs are connected in sequence.

6. The tower crane attachment structure between towers according to claim 4, characterized in that: A through hole perpendicular to the axis of the screw rod is provided in the middle of the screw rod.

7. The tower crane attachment structure between towers according to claim 2, characterized in that: The support includes a base plate, a first support plate, and a second support plate. The first support plates are arranged at intervals along the length direction of the base plate. An installation groove is formed by the side walls of adjacent support plates and the top surface of the base plate. One end of the first wall-attaching rod is arranged in the installation groove, and a through hole for passing through a pin shaft is provided on the first support plate. The second support plates are arranged at intervals along the width direction of the base plate on the back side of the first support plate.

8. The tower crane attachment structure between towers according to claim 7, characterized in that: The base plate, the first support plate, and the second support plate are fixed by welding, and the base plate is provided with installation holes.