Adjustable integrated pier body construction operation platform

By designing an adjustable integrated pier construction platform, the problems of low applicability and poor protection effect of the existing platform are solved, and adaptability and efficient protection of different pier cross-sectional sizes are achieved.

CN223226491UActive Publication Date: 2025-08-15CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202422498938.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-15
Publication Date
2025-08-15
Estimated Expiration
2034-10-15

AI Technical Summary

Technical Problem

The existing construction platform is less suitable and has poor protection effect on workers.

Method used

An adjustable integrated pier body construction work platform is designed, including the bottom platform frame, adjustable platform frame, the first platform box, the corridor bridge, the second platform box and the construction components. Through modular splicing, it is suitable for pier body construction of different cross-sectional sizes, and a protective net and personnel up and down passage are set up to improve the protection effect.

Benefits of technology

The applicability to pier bodies of different cross-sectional sizes is achieved, the risk of falling of workers is reduced, and the protection effect and traffic efficiency during construction is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223226491U_ABST
    Figure CN223226491U_ABST
Patent Text Reader

Abstract

The utility model provides an adjustable integrated pier body construction operation platform, belongs to the technical field of tower column construction, and mainly aims at solving the problem that an existing construction operation platform is poor in universality. According to the technical scheme, the platform comprises a bottom platform frame, an adjustable platform frame is arranged at the top of the bottom platform frame, multiple sets of first platform box bodies are arranged at the top of the adjustable platform frame, three sets of gallery bridges are arranged at the tops of the multiple sets of first platform box bodies correspondingly, and multiple sets of second platform box bodies are arranged at the tops of the multiple sets of first platform box bodies correspondingly; the same construction assembly is arranged on one sides of the multiple second platform box bodies. Through the arrangement of the construction assembly, the construction platform can be applied to construction of vase-shaped round end piers, cylindrical piers and the like, modular splicing can be adopted, a user can adjust the number of the first platform box bodies and the number of the second platform box bodies to be suitable for pier bodies with different section sizes, and universality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tower column construction, and more specifically relates to an adjustable integrated pier body construction operation platform. Background Art

[0002] During the daily construction of the pier body, a construction work platform is often required. The construction work platform is used for installing steel bars, formwork, and pouring concrete on the pier body. The traditional pier body formwork construction method uses a personnel up and down passage on the side of the pier to install steel bars and reinforce the formwork. However, the existing construction work platform has low applicability and poor protection effect for workers. Utility Model Content

[0003] In order to solve the above technical problems, the utility model provides an adjustable integrated pier body construction work platform to solve the technical problems in the existing technology that traditional construction work platforms have low applicability and poor protection effect for workers.

[0004] The purpose and function of the adjustable integrated pier construction work platform of the utility model are achieved by the following specific technical means:

[0005] An adjustable integrated pier body construction work platform includes a bottom platform frame, an adjustable platform frame is arranged on the top of the bottom platform frame, multiple groups of first platform boxes are arranged on the top of the adjustable platform frame, three groups of gallery bridges are respectively arranged on the top of the multiple groups of first platform boxes, multiple groups of second platform boxes are respectively arranged on the top of the multiple groups of first platform boxes, and the same group of construction components are arranged on one side of the multiple groups of second platform boxes.

[0006] According to a preferred embodiment, the construction component includes four groups of support plates and four groups of movable pedals, and the four groups of support plates are respectively provided on one side of the multiple groups of the first platform box, and the four groups of movable pedals are respectively provided on the top of the four groups of support plates. The construction component also includes four groups of circular arc flaps, and the four groups of circular arc flaps are respectively provided on one side of the multiple groups of the second platform box.

[0007] According to a preferred embodiment, four groups of flip platforms are respectively provided on the top of the four groups of support plates, flip rods are passed through the four groups of flip platforms, the four groups of movable pedals are connected to the flip rods, and the four groups of arc flip plates are detachably connected to the second platform box.

[0008] According to a preferred embodiment, two groups of safety protection doors are respectively provided at one end of the four groups of first platform boxes, and a protection door handle is provided at one end of the two groups of safety protection doors. Stairs are provided at one end of the two groups of safety protection doors, and both sides of the two groups of stairs are respectively connected to the four groups of first platform boxes, and multiple groups of handrails are provided at one end of the two groups of stairs. Two groups of rotating rods are respectively passed through the four groups of first platform boxes, and one side of the two groups of safety protection doors is connected to the rotating rods.

[0009] According to a preferred embodiment, multiple groups of protective nets are provided on the multiple groups of the first platform boxes and the multiple groups of the second platform boxes.

[0010] According to a preferred embodiment, one side of each two groups of the first platform boxes are connected by a group of connecting parts, one side of each two groups of the second platform boxes are connected by a group of the connecting parts, one side of each two groups of the first platform boxes are connected by two groups of first pull rods, and one side of each two groups of the second platform boxes are connected by two groups of the first pull rods.

[0011] According to a preferred embodiment, the tops of the multiple groups of second platform boxes are provided with the same group of top platform frames, the bottoms of the top platform frames are provided with column frames, and one end of the column frames is provided with multiple groups of second pull rods.

[0012] Compared with the prior art, the present invention has the following beneficial effects:

[0013] 1. By assembling different numbers of first platform boxes and second platform boxes, it can be applied to the construction of piers with different cross-sectional sizes. By adjusting the size and width of the movable pedal and the lateral sliding of the corridor bridge, it can be applied to piers with different cross-sectional sizes. By adding arc flaps at the four corners, it can be well used in the construction of vase-shaped round-end piers, cylindrical piers, etc.

[0014] 2. The movable pedal is used as a platform for workers to tie steel bars and install or remove formwork, effectively avoiding the risk of workers falling. There are personnel up and down passages on both sides of the construction platform, which has high personnel passage efficiency and prevents the safety risks caused by crowding caused by a single up and down passage. The protective net is set to prevent workers from falling, thereby improving the protection effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a structural diagram of an adjustable integrated pier body construction work platform of the utility model;

[0016] Figure 2 This is an exploded view of an adjustable integrated pier construction work platform of the utility model;

[0017] Figure 3This is a structural diagram of a construction component in an adjustable integrated pier body construction work platform of the utility model;

[0018] Figure 4 The utility model is a structural schematic diagram of the disassembled construction components of an adjustable integrated pier body construction work platform.

[0019] In the figure, the corresponding relationship between the component names and the drawing numbers is as follows:

[0020] 10. Bottom platform frame; 11. Adjustable platform frame; 12. First platform box; 13. Corridor bridge; 14. Second platform box; 15. Support plate; 16. Flip platform; 17. Flip rod; 18. Movable pedal; 19. Arc flap; 20. Safety protection door; 21. Stairs; 22. Handrail; 23. Protection net; 24. Connector; 25. First pull rod; 26. Second pull rod; 27. Top platform frame; 28. Column frame; 29. Protection door handle; 30. Rotating rod. DETAILED DESCRIPTION

[0021] The following embodiments of the present invention are described in further detail with reference to the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0022] Example:

[0023] As attached Figure 1 To the attached Figure 4 As shown:

[0024] The utility model provides an adjustable integrated pier body construction work platform, comprising a bottom platform frame 10, an adjustable platform frame 11 is provided on the top of the bottom platform frame 10, a plurality of first platform boxes 12 are provided on the top of the adjustable platform frame 11, three groups of corridors 13 are respectively provided on the top of the plurality of first platform boxes 12, users can perform construction or walk on the corridors 13, and a gap is provided between the corridors 13 and the second platform boxes 14, operators can slide the corridors 13 laterally so that the operators maintain an appropriate distance from the pier body for construction to adapt to pier bodies with different cross-sectional sizes, a plurality of second platform boxes 14 are respectively provided on the top of the plurality of first platform boxes 12, and different numbers of first platform boxes 12 and second platform boxes 14 are assembled to be suitable for pier body construction with different cross-sectional sizes, and the first platform boxes 12 and the second platform boxes 14 can also be spliced upward to form a multi-layer platform to increase the construction height.

[0025] The same set of construction components are set on one side of multiple groups of second platform boxes 14. The construction components include four groups of support plates 15 and four groups of movable pedals 18. Four groups of support plates 15 are respectively set on one side of multiple groups of first platform boxes 12. Four groups of movable pedals 18 are respectively set on the top of the four groups of support plates 15. The support plates 15 support the movable pedals 18. Users can stand on the movable pedals 18 to construct the pier body. Users can adapt to different pier body sizes through the size and width of the movable pedals 18 to avoid the gap between the movable pedals 18 and the pier body, effectively avoiding the risk of workers falling. The construction components also include four groups of arc flaps 19. Multiple groups of first platform boxes 12 are respectively provided with four groups of support plates 15. Four groups of movable pedals 18 are respectively set on the top of the four groups of support plates 15. The support plates 15 support the movable pedals 18. Four groups of arc flaps 19 are respectively provided on one side of the second platform box 14, and the four groups of arc flaps 19 are detachably connected to the second platform box 14. By adding arc flaps 19 at the four corners, it can be well used in the construction of vase-shaped round-end piers, cylindrical piers, etc. Four groups of flip platforms 16 are respectively provided on the top of the four groups of support plates 15. Flip rods 17 are passed through the four groups of flip platforms 16, and four groups of movable pedals 18 are connected to the flip rods 17. When the steel bars of the pier body are installed, the movable pedals 18 can be turned over, the arc flaps 19 can be removed, and the pier body template can be installed after the corridor 13 slides sideways. After the template is installed, it can be reset.

[0026] Among them, see Figure 2 、 Figure 3 and Figure 4 As shown, two groups of safety protection doors 20 are respectively provided at one end of the four groups of first platform boxes 12. Users can open the safety protection doors 20 to enter the passage of the construction work platform. One end of the two groups of safety protection doors 20 is provided with a protection door handle 29. One end of the two groups of safety protection doors 20 is provided with stairs 21. Users can climb the stairs 21 and walk onto the corridor bridge 13 to carry out construction. The two groups of stairs 21 are respectively connected to the four groups of first platform boxes 12 on both sides. One end of the two groups of stairs 21 is provided with multiple groups of handrails 22. Two groups of rotating rods 30 are respectively passed through the four groups of first platform boxes 12. The rotating rods 30 enable the safety protection doors 20 to be rotated and opened normally. One side of the two groups of safety protection doors 20 is connected to the rotating rod 30. Personnel up and down passages are provided on both sides of the construction work platform, and the personnel passage efficiency is high, preventing the safety risks caused by crowding of people due to a single up and down passage.

[0027] Multiple sets of protection nets 23 are provided on the multiple sets of first platform boxes 12 and the multiple sets of second platform boxes 14. These protection nets 23 can prevent workers from falling, thereby improving the protection effect.

[0028] One side of each two groups of first platform boxes 12 is connected by a group of connecting parts 24, one side of each two groups of second platform boxes 14 is connected by a group of connecting parts 24, one side of each two groups of first platform boxes 12 is connected by two groups of first pull rods 25, and one side of each two groups of second platform boxes 14 is connected by two groups of first pull rods 25. The first pull rods 25 can increase the stability of the splicing of the first platform box 12 and the second platform box 14. The construction work platform adopts modular splicing, and the operators can master the assembly and disassembly methods after simple training.

[0029] The top of multiple groups of second platform boxes 14 are provided with the same group of top platform frames 27, the bottom of the top platform frames 27 are provided with column frames 28, and one end of the column frames 28 is provided with multiple groups of second pull rods 26. The second pull rods 26, column frames 28 and top platform frames 27 can improve the stability of the splicing of the first platform box 12 and the second platform box 14, and can also improve the stability of the construction work platform. During the reusing process, the construction work platform can be transferred as a whole to the next work point for use by using lifting equipment.

[0030] The embodiments of the present invention are provided for purposes of illustration and description and are not intended to be exhaustive or to limit the present invention to the disclosed forms. Many modifications and variations will be apparent to those skilled in the art. The embodiments are selected and described to better illustrate the principles and practical applications of the present invention and to enable those skilled in the art to understand the present invention and design various embodiments with various modifications suitable for specific applications.

Claims

1. An adjustable integrated pier construction work platform, characterized by: The invention comprises a bottom platform frame (10), an adjustable platform frame (11) is arranged on the top of the bottom platform frame (10), a plurality of first platform boxes (12) are arranged on the top of the adjustable platform frame (11), three groups of corridor bridges (13) are respectively arranged on the tops of the plurality of first platform boxes (12), a plurality of second platform boxes (14) are respectively arranged on the tops of the plurality of first platform boxes (12), and the same group of construction components are arranged on one side of the plurality of second platform boxes (14).

2. The adjustable integrated pier construction work platform according to claim 1, characterized in that: The construction assembly includes four groups of support plates (15) and four groups of movable pedals (18), and the four groups of support plates (15) are respectively provided on one side of the plurality of first platform boxes (12). The four groups of movable pedals (18) are respectively provided on the top of the four groups of support plates (15). The construction assembly also includes four groups of circular arc flip plates (19), and the four groups of circular arc flip plates (19) are respectively provided on one side of the plurality of second platform boxes (14).

3. The adjustable integrated pier construction work platform according to claim 2, characterized in that: Four groups of flip platforms (16) are respectively provided on the top of the four groups of support plates (15), and flip rods (17) are inserted into the four groups of flip platforms (16). The four groups of movable pedals (18) are connected to the flip rods (17), and the four groups of circular arc flip plates (19) are detachably connected to the second platform box (14).

4. The adjustable integrated pier construction work platform according to claim 1, characterized in that: One end of each of the four groups of the first platform boxes (12) is provided with two groups of safety protection doors (20), one end of each of the two groups of the safety protection doors (20) is provided with a protection door handle (29), one end of each of the two groups of the safety protection doors (20) is provided with a staircase (21), both sides of the two groups of the staircase (21) are connected to the four groups of the first platform boxes (12), one end of each of the two groups of the staircase (21) is provided with multiple groups of handrails (22), and two groups of rotating rods (30) are respectively passed through the four groups of the first platform boxes (12), and one side of each of the two groups of the safety protection doors (20) is connected to the rotating rod (30).

5. The adjustable integrated pier construction work platform according to claim 1, characterized in that: Multiple groups of protective nets (23) are provided on multiple groups of the first platform boxes (12) and multiple groups of the second platform boxes (14).

6. The adjustable integrated pier construction work platform according to claim 1, characterized in that: One side of each two groups of the first platform boxes (12) is connected by a group of connecting parts (24), one side of each two groups of the second platform boxes (14) is connected by a group of connecting parts (24), one side of each two groups of the first platform boxes (12) is connected by two groups of first pull rods (25), and one side of each two groups of the second platform boxes (14) is connected by two groups of first pull rods (25).

7. The adjustable integrated pier construction work platform according to claim 1, characterized in that: The tops of the plurality of second platform boxes (14) are provided with the same group of top platform frames (27), the bottoms of the top platform frames (27) are provided with column frames (28), and one end of the column frames (28) is provided with a plurality of second pull rods (26).

Citation Information

Cited By

  • Storage box test tower unfolding platform

    CN121475539A