Novel water shutoff and profile control device
By designing a new water blocking and dissection device, the combination of a shaker seat and a crushing box can achieve efficient crushing and uniform delivery of the blocking agent, which solves the problem of uneven distribution of the blocking agent in the oil field formation and improves the water flooding efficiency.
Patent Information
- Application Number
- CN202422046877.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2025-09-02
- Estimated Expiration
- 2034-08-22
AI Technical Summary
In the prior art, it is difficult to distribute the plugging agent evenly in the oil field formation, resulting in uneven water injection and rapid breakthroughs in some areas, resulting in oil well effluent and reduced production capacity.
A new type of water blocking and dissection adjustment device is designed, including a shaker seat, a rotating shaft, a crushing box, a suction pipe and a pressurization mechanism. The crushing box is driven by a motor to rotate and sway, and combined with solenoid valve control, it can achieve efficient crushing and uniform delivery of the plugging agent.
The efficient and uniform distribution of plugging agents in the oil field formation is achieved, which reduces the water-phase permeability, reduces the damage to the oil-phase permeability, and improves the water-flooding efficiency.
Smart Images

Figure CN223293691U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water plugging and profile control fillers, in particular to a novel water plugging and profile control device. Background Art
[0002] At present, in the middle and late stages of oil field development, the formation energy decreases and the recovery rate decreases. Most of my country's oil fields supplement the formation energy by injecting water to increase the recovery rate. However, since the reservoirs are usually heterogeneous, there will be "invasion" and "channeling" of water in the oil layer. As the amount of water injection increases, the unevenness of the water injection profile increases, resulting in a large amount of water output from the oil wells. At this time, it is necessary to plug the water and adjust the profile.
[0003] Among them, due to the multi-layer heterogeneity of the formation, the distribution of injected water is uneven. Some areas may quickly break through the high permeability layer, resulting in a large amount of water output from the oil wells and reducing production capacity. In order to solve this problem, chemical agents will be injected into the formation to block the water flow channel of the high permeability layer, forcing water to enter the low permeability layer or high oil-containing layer, thereby improving the efficiency of water-driven oil.
[0004] However, when adding plugging agents in the market, the pressure is often insufficient, which makes it difficult for the plugging agents to be evenly distributed inside the formation. Therefore, it is necessary to design a new technical solution to solve this problem, so that the plugging agents can be efficiently and evenly distributed in the formation. Utility Model Content
[0005] The purpose of the utility model is to provide a novel water plugging and profile control device, which solves the problems raised in the background technology.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a novel water plugging and profile control device, comprising a shaking seat, the shaking seat being a concave seat, a plugging agent being placed inside the shaking seat, rotating shafts being rotatably installed on both sides of the shaking seat, a crushing box being fixedly installed between two sets of the rotating shafts, a suction pipe being connected to one side of the bottom of the shaking seat, and a pressurizing mechanism being installed at the other end of the suction pipe;
[0007] The pressurizing mechanism includes a boosting box installed in communication with the other end of the suction pipe, a hydraulic push rod fixedly installed on the top of the boosting box, a sealing block fixedly installed at the other end of the hydraulic push rod, and a discharge pipe installed in communication with the bottom of the boosting box. The suction pipe is a hose.
[0008] As an optional solution of the technical solution of the present application, the sealing block is movably connected to the inner cavity of the booster box, and sealing rubber rings are fixedly installed on both sides of the outer wall of the sealing block.
[0009] As an optional solution to the technical solution of the present application, a first motor is fixedly installed on the side wall of the shaking seat, the driving output end of the first motor is connected to the transmission shaft, and the other end of the transmission shaft is fixedly installed on the side wall of the crushing box, which can drive the crushing box to rotate.
[0010] As an optional solution of the technical solution of the present application, a second motor is fixedly installed at the bottom of the crushing box, and the drive output end of the second motor is connected to the transmission shaft. A crushing blade is fixedly installed at the other end of the transmission shaft to crush the blockage agent.
[0011] As an optional solution of the technical solution of the present application, the other end of the discharge pipe is connected to the drill pipe, and electromagnetic valves are installed on the discharge pipe and the suction pipe to control the internal flow of the discharge pipe and the suction pipe.
[0012] As an optional solution to the technical solution of the present application, a mounting bracket is fixedly installed on the side wall of the shaking seat, and the other end of the mounting bracket is fixedly installed on the side wall of the booster box. A pressure relief port is opened on the top of the side wall of the booster box to support the booster box.
[0013] Compared with the prior art, the beneficial effects of the present invention are as follows:
[0014] 1. The technical solution of the present application closes the solenoid valve on the discharge pipe, opens the solenoid valve on the suction pipe, and drives the hydraulic push rod to push the sealing block, so that the sealing block slowly moves upward along the inner cavity of the booster box, so that a negative pressure is formed on the bottom side of the inside of the booster box and transported to the inside of the suction pipe, and the crushed internal plugging agent powder is continuously introduced into the inside of the booster box. Conversely, the solenoid valve on the suction pipe is closed, the solenoid valve on the discharge pipe is opened, and the hydraulic push rod is driven a second time to push the sealing block downward, so that the plugging agent powder inside the booster box can be squeezed into the inside of the drill pipe and efficiently introduced into the oil field, effectively reducing the water phase permeability with less damage to the oil phase permeability.
[0015] 2. The technical solution of the present application is to fix the first motor on the side wall of the shaking seat, and the other end of the motor shaft of the first motor is fixedly installed on the side wall of the crushing box. When the second motor is driven to drive the crushing blades to rotate and crush the plugging agent, the first motor on the shaking seat can be turned on synchronously to drive the crushing box to swing at a certain angle, which can ensure that the blockage agent inside the crushing box is in full contact with the crushing blades, achieve efficient crushing efficiency, and enable the blockage agent to be more efficiently introduced into the formation. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Other features, objects and advantages of the present invention will become more apparent from the detailed description of the non-limiting embodiments with reference to the following drawings:
[0017] Figure 1 This is a schematic diagram of the overall structure of a new type of water plugging and profile control device of the utility model;
[0018] Figure 2 This is a schematic diagram of the structure of a shaking seat of a new water plugging and profile control device of the utility model;
[0019] In the figure: 1. Shaking seat; 11. Rotating shaft; 12. Crushing box; 13. First motor; 2. Suction pipe; 21. Pressurizing box; 22. Hydraulic push rod; 23. Sealing block; 24. Discharge pipe; 3. Second motor; 31. Crushing blade; 32. Solenoid valve; 33. Mounting bracket; 34. Pressure relief port. DETAILED DESCRIPTION
[0020] See also Figure 1-2 The utility model provides a technical solution: a new water plugging and profile control device, including a shaking seat 1, the shaking seat 1 is a concave seat, a plugging agent is placed inside the shaking seat 1, both sides of the shaking seat 1 are rotatably installed with rotating shafts 11, a crushing box 12 is fixedly installed between the two sets of rotating shafts 11, one side of the bottom of the shaking seat 1 is connected to a suction pipe 2, and the other end of the suction pipe 2 is installed with a pressurizing mechanism;
[0021] The pressurizing mechanism includes a boosting box 21 installed in communication with the other end of the suction pipe 2, a hydraulic push rod 22 fixedly installed on the top of the boosting box 21, a sealing block 23 fixedly installed at the other end of the hydraulic push rod 22, and a discharge pipe 24 installed in communication with the bottom of the boosting box 21. The suction pipe 2 is a hose, the sealing block 23 is movably connected to the inner cavity of the boosting box 21, and sealing rubber rings are fixedly installed on both sides of the outer wall of the sealing block 23.
[0022] In this technical solution, by closing the solenoid valve 32 on the discharge pipe 24, opening the solenoid valve 32 on the suction pipe 2, and driving the hydraulic push rod 22 to push the sealing block 23, the sealing block 23 is slowly moved upward along the inner cavity of the boosting box 21, so that a negative pressure is formed on the bottom side of the inside of the boosting box 21 and transported to the inside of the suction pipe 2, and the crushed internal plugging agent powder is continuously introduced into the inside of the boosting box 21. Conversely, by closing the solenoid valve 32 on the suction pipe 2, opening the solenoid valve 32 on the discharge pipe 24, the hydraulic push rod 22 is driven a second time to push the sealing block 23 downward, and the plugging agent powder inside the boosting box 21 can be squeezed into the inside of the drill pipe and efficiently introduced into the oil field, effectively reducing the water phase permeability with less damage to the oil phase permeability.
[0023] In some technical solutions, a first motor 13 is fixedly installed on the side wall of the shaking seat 1, and the driving output end of the first motor 13 is connected to the transmission shaft, and the other end of the transmission shaft is fixedly installed on the side wall of the crushing box 12, which can drive the crushing box 12 to rotate.
[0024] In this technical solution, when the second motor 3 is driven to drive the crushing blades 31 to rotate and crush the blockage agent, the first motor 13 on the shaking seat 1 can be turned on synchronously to drive the crushing box 12 to swing at a certain angle, thereby ensuring that the blockage agent inside the crushing box 12 is in full contact with the crushing blades 31, achieving efficient crushing efficiency, and allowing the blockage agent to be more efficiently introduced into the formation.
[0025] In some technical solutions, a mounting bracket 33 is fixedly installed on the side wall of the shaking seat 1, and the other end of the mounting bracket 33 is fixedly installed on the side wall of the booster box 21. A pressure relief port 34 is opened on the top of the side wall of the booster box 21 to support the booster box 21.
[0026] In this technical solution, the boost box 21 can be firmly fixed to one side of the shaking seat 1 through the mounting frame 33, and cooperate with the pressure relief port 34 to allow the sealing block 23 to discharge the internal gas of the boost box 21 after rising.
[0027] In some technical solutions, the other end of the discharge pipe 24 is connected to the drill pipe, and electromagnetic valves 32 are installed on the discharge pipe 24 and the suction pipe 2 to control the internal flow of the discharge pipe 24 and the suction pipe 2.
[0028] In this technical solution, by installing electromagnetic valves 32 on the discharge pipe 24 and the suction pipe 2, the internal flows of the discharge pipe 24 and the suction pipe 2 can be controlled respectively, thereby controlling the introduction and discharge of the blocking agent powder.
[0029] In some technical solutions, a second motor 3 is fixedly installed at the bottom of the crushing box 12, and the driving output end of the second motor 3 is connected to the transmission shaft. A crushing blade 31 is fixedly installed at the other end of the transmission shaft to crush the blocking agent.
[0030] In this technical solution, a large amount of blocking agents can be crushed by placing them inside the crushing box 12 and driving the second motor 3 to rotate the crushing blades 31.
[0031] When a new type of water plugging and profile control device is used, it should be noted that the utility model is a new type of water plugging and profile control device, and each component is a universal standard part or a component known to technical personnel in this field. Its structure and principle can be known to technical personnel through technical manuals or through conventional experimental methods.
[0032] When in use, a large amount of blockage agent is first placed inside the crushing box 12, and the second motor 3 is driven to drive the crushing blade 31 to rotate, so that a large amount of blockage agent can be crushed. At the same time, the solenoid valve 32 on the discharge pipe 24 is closed, the solenoid valve 32 on the suction pipe 2 is opened, and the hydraulic push rod 22 is driven to push the sealing block 23, so that the sealing block 23 slowly moves up along the inner cavity of the boosting box 21, so that a negative pressure is formed on the bottom side of the inside of the boosting box 21 and transported to the inside of the suction pipe 2, and the crushed internal blockage agent powder is continuously introduced into the inside of the boosting box 21. Conversely, the solenoid valve 32 on the suction pipe 2 is closed, the solenoid valve 32 on the discharge pipe 24 is opened, and the hydraulic push rod 22 is driven for a second time to push the sealing block 23 down The plugging agent powder inside the booster box 21 can be squeezed and introduced into the drill pipe, and efficiently introduced into the oil field, effectively reducing the water phase permeability while having less damage to the oil phase permeability. At the same time, a first motor 13 is fixedly installed on the side wall of the shaking seat 1, and the other end of the motor shaft of the first motor 13 is fixedly installed on the side wall of the crushing box 12. When the second motor 3 is driven to drive the crushing blades 31 to rotate and crush the plugging agent, the first motor 13 on the shaking seat 1 can be turned on synchronously to drive the crushing box 12 to swing at a certain angle, which can ensure that the blockage agent inside the crushing box 12 is fully in contact with the crushing blades 31, thereby achieving efficient crushing efficiency and making the blockage agent more efficiently introduced into the formation.
Claims
1. A novel water plugging and profile control device, comprising a shaking seat (1), characterized in that: The shaking seat (1) is a concave seat, a blocking agent is placed inside the shaking seat (1), rotating shafts (11) are rotatably installed on both sides of the shaking seat (1), a crushing box (12) is fixedly installed between two groups of the rotating shafts (11), a suction pipe (2) is connected to one side of the bottom of the shaking seat (1), and a pressurizing mechanism is installed at the other end of the suction pipe (2); The pressurizing mechanism comprises a pressurizing box (21) connected to and installed at the other end of the suction pipe (2), a hydraulic push rod (22) fixedly installed on the top of the pressurizing box (21), a sealing block (23) fixedly installed at the other end of the hydraulic push rod (22), and a discharge pipe (24) connected to and installed at the bottom of the pressurizing box (21); the suction pipe (2) is in the form of a hose.
2. A novel water plugging and profile control device according to claim 1, characterized in that: The sealing block (23) is movably connected to the inner cavity of the boost box (21), and sealing rubber rings are fixedly installed on both sides of the outer wall of the sealing block (23).
3. The novel water plugging and profile control device according to claim 1 is characterized in that: A first motor (13) is fixedly mounted on the side wall of the shaking seat (1); a driving output end of the first motor (13) is connected to a transmission shaft, and the other end of the transmission shaft is fixedly mounted on the side wall of the crushing box (12).
4. The novel water plugging and profile control device according to claim 1 is characterized in that: A second motor (3) is fixedly mounted on the bottom of the crushing box (12); a driving output end of the second motor (3) is in transmission connection with a transmission shaft; a crushing blade (31) is fixedly mounted on the other end of the transmission shaft.
5. The novel water plugging and profile control device according to claim 1 is characterized in that: The other end of the discharge pipe (24) is connected to the drill pipe and installed, and the discharge pipe (24) and the suction pipe (2) are both installed with electromagnetic valves (32).
6. The novel water plugging and profile control device according to claim 1 is characterized in that: A mounting frame (33) is fixedly mounted on the side wall of the shaking seat (1), and the other end of the mounting frame (33) is fixedly mounted on the side wall of the boost box (21). A pressure relief port (34) is provided on the top of the side wall of the boost box (21).