Constructional engineering template settlement monitoring device

Through the clamped-connected support pipe and support rod structure and alarm mechanism, the problem of the steel pipe being forced to bend cannot be replaced separately, and low-cost maintenance and maintenance are achieved, which facilitates the replacement of stressed bend components separately, reducing the need for overall replacement.

CN223295427UActive Publication Date: 2025-09-02ANHUI WATER CONSERVANCY DEV CO LTD

Patent Information

Application Number
CN202422853292.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-22
Publication Date
2025-09-02
Estimated Expiration
2034-11-22

AI Technical Summary

Technical Problem

In the existing construction project formwork settlement monitoring device, when the steel pipe is under too much force, it cannot be replaced separately, resulting in high cost of replacing the overall equipment.

Method used

The support tube and support rod structure with a clamped connection design is combined with the alarm mechanism, and the alarm is emitted through conductive contact control alarms, which facilitates the replacement of the stressed bent parts separately to avoid overall replacement.

Benefits of technology

It reduces maintenance and monitoring costs, improves the convenience of the equipment's maintenance and maintenance, reduces resource waste, is simple and low-cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223295427U_ABST
    Figure CN223295427U_ABST
Patent Text Reader

Abstract

The utility model discloses a construction engineering template settlement monitoring device, and relates to the technical field of construction engineering. The construction engineering formwork settlement monitoring device comprises a base, an alarm mechanism and a bearing mechanism, the alarm mechanism comprises a supporting frame arranged on the base and a power supply device arranged in the supporting frame, and the power supply device is fixedly connected to the bottom of the inner side of the supporting frame; the bearing mechanism comprises a connecting assembly arranged on the alarm mechanism and a placing assembly arranged on the connecting assembly, and the placing assembly can move up and down relative to the connecting assembly. According to the device, clamping design is adopted for the supporting pipe and the supporting rod which are prone to bending, when the supporting pipe and the supporting rod are bent due to huge pressure, workers can conveniently and independently replace the supporting pipe and the supporting rod, the situation that the whole device needs to be replaced is avoided, and the device is simple in structure, convenient to assemble, beneficial to maintenance and overhaul and high in practicability. The waste of unnecessary resources can be reduced, and the maintenance and monitoring cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a construction engineering template settlement monitoring device. Background Art

[0002] Chinese patent document CN215868107U discloses a construction formwork settlement and deformation monitoring and alarm device. The device comprises a fixed base consisting of a support screw and an adjusting nut. A lower steel plate is welded to the top of the support screw, perpendicularly intersecting the support screw. Through holes are drilled on each wing of the lower steel plate. An upper steel plate is positioned above the lower steel plate, also with through holes drilled on each wing of the upper steel plate. Two sets of compression assemblies are connected between the lower and upper steel plates from the wing sides. A lower steel pipe is welded to the middle of the lower steel plate, an upper steel pipe is positioned in the middle of the upper steel plate, and conductive plates are positioned at the top and bottom of the lower steel pipe. A power supply is positioned at one end of the lower steel plate, with the positive and negative poles of the power supply connected to the lower steel plate and the corresponding upper steel plate, respectively. The power supply is connected to an electric bell and a light bulb via wires. The device is simple to manufacture, low in cost, and simple and effective in preventing safety accidents in formwork projects. It can be widely used by formwork workers on construction sites.

[0003] When the above device is in use, if the steel pipe is subjected to excessive force and bends, it cannot be replaced individually and the entire equipment needs to be replaced. The detection cost is high. Corrections are made to the above problems. Utility Model Content

[0004] The purpose of the utility model is to provide a construction engineering formwork settlement monitoring device, which can solve the problem that when the above device is in use, if the steel pipe is subjected to excessive force and bends, it cannot be replaced individually and the entire equipment needs to be replaced, resulting in high detection costs.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a construction engineering formwork settlement monitoring device, comprising a base, an alarm mechanism and a load-bearing mechanism, the alarm mechanism comprising a support frame arranged on the base and a power supply arranged in the support frame, the power supply is fixedly connected to the inner bottom of the support frame, the load-bearing mechanism comprises a connecting component arranged on the alarm mechanism and a placing component arranged on the connecting component, the placing component can move up and down relative to the connecting component, and the connecting component is snap-connected to the placing component.

[0006] Preferably, the alarm mechanism also includes an alarm, a conductive wire and a threaded shaft. The top of the power supply is fixedly connected to the alarm, the fixed end of the power supply is fixedly connected to the conductive wire, and the top of the support frame is fixedly connected to the threaded shaft. The device ultimately controls the alarm to sound an alarm through contact conduction, which makes it convenient for staff to respond in a short time. At the same time, the device is simple to manufacture, low in cost, and conducive to production and sales.

[0007] Preferably, the connecting assembly includes a placement plate, a fixing ring, a clamping ring, a support tube, a resistor and a conductive block. A placement plate is provided on the alarm mechanism, the bottom of the placement plate is fixedly connected to the fixing ring, the top of the placement plate is fixedly connected to the clamping ring, the support tube is clamped in the clamping ring, the inner bottom of the support tube is fixedly connected to the resistor, and the top of the placement plate is fixedly connected to the conductive block. The placement assembly includes a connecting plate, a limiting ring, an extrusion shaft and a support rod. A connecting plate is provided on the connecting assembly, the top of the connecting plate is fixedly connected to the limiting ring, the extrusion shaft is fixedly connected in the limiting ring, and the bottom of the connecting plate is clamped to the support rod through a connecting ring. The device adopts a clamping design for the support tube and support rod that are prone to bending. When both are bent under great pressure, it is convenient for the staff to replace them separately, avoiding the need to replace the entire device. The device has a simple structure, is easy to assemble, is conducive to maintenance and overhaul, can reduce unnecessary waste of resources, and reduce maintenance and monitoring costs.

[0008] Preferably, a hole is provided on the placement plate, and the other side of the conductive wire passes through the hole and is connected to the connecting end of the conductive block.

[0009] Preferably, the bottom of the support rod is overlapped with the top of the resistor, an internal thread groove is provided in the fixing ring, and the fixing ring is threadedly connected to the threaded shaft.

[0010] Preferably, the center points of the clamping ring, the support tube, the resistor and the support rod are all on the same straight line.

[0011] Compared with the prior art, the beneficial effects of the present invention are:

[0012] (1) The construction engineering template settlement monitoring device is used in conjunction with a base, an alarm mechanism, a load-bearing mechanism, a connecting assembly, a placement plate, a fixing ring, a clamping ring, a support pipe, a resistor, a conductive block, a placement assembly, a connection plate, a limit ring, an extrusion shaft and a support rod. When the above device is in use, if the steel pipe is subjected to excessive force and bends, it cannot be replaced individually and the entire device needs to be replaced, which is a defect with high detection cost. The device adopts a clamping design for the support pipe and support rod that are prone to bending. When both are bent under great pressure, it is convenient for the staff to replace them individually, avoiding the need to replace the entire device. The device has a simple structure, is easy to assemble, is conducive to maintenance and overhaul, can reduce unnecessary waste of resources, and reduce maintenance and monitoring costs.

[0013] (2) The construction engineering formwork settlement monitoring device is used in conjunction with a base, an alarm mechanism, a support frame, a power supply, an alarm, a conductive wire, a threaded shaft and a load-bearing mechanism. The device controls the alarm to sound an alarm through contact conduction, which makes it easy for workers to respond in a short time. At the same time, the device is simple to manufacture and low in cost, which is conducive to production and sales. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The present invention will be further described below with reference to the accompanying drawings and embodiments:

[0015] Figure 1 It is a three-dimensional diagram of the utility model;

[0016] Figure 2 This is a three-dimensional diagram of the alarm mechanism of the present utility model;

[0017] Figure 3 This is an analysis diagram of the load-bearing mechanism of the utility model.

[0018] Figure numerals: 1. base; 2. alarm mechanism; 201. support frame; 202. power supply; 203. alarm; 204. conductive wire; 205. threaded shaft; 3. load-bearing mechanism; 31. connecting assembly; 311. placement plate; 312. fixing ring; 313. snap ring; 314. support tube; 315. resistor; 316. conductive block; 32. placement assembly; 321. connecting plate; 322. limiting ring; 323. extrusion shaft; 324. support rod. DETAILED DESCRIPTION

[0019] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.

[0020] See also Figure 1-3 The utility model provides a technical solution: a construction engineering formwork settlement monitoring device, including a base 1, an alarm mechanism 2 and a load-bearing mechanism 3, the alarm mechanism 2 includes a support frame 201 arranged on the base 1 and a power supply 202 arranged in the support frame 201, the power supply 202 is fixedly connected to the inner bottom of the support frame 201, the load-bearing mechanism 3 includes a connecting component 31 arranged on the alarm mechanism 2 and a placing component 32 arranged on the connecting component 31, the placing component 32 can move up and down relative to the connecting component 31, and the connecting component 31 is connected to the placing component 32 by a snap connection.

[0021] Furthermore, the alarm mechanism 2 also includes an alarm 203, a conductive wire 204 and a threaded shaft 205. The top of the power supply 202 is fixedly connected to the alarm 203, the fixed end of the power supply 202 is fixedly connected to the conductive wire 204, and the top of the support frame 201 is fixedly connected to the threaded shaft 205. The device ultimately controls the alarm 203 to sound an alarm through contact conduction, which makes it convenient for staff to respond in a short time. At the same time, the device is simple to manufacture, low in cost, and is conducive to production and sales.

[0022] Furthermore, the connecting component 31 includes a placement plate 311, a fixing ring 312, a snap ring 313, a support tube 314, a resistor 315 and a conductive block 316. The alarm mechanism 2 is provided with a placement plate 311, the bottom of the placement plate 311 is fixedly connected to the fixing ring 312, the top of the placement plate 311 is fixedly connected to the snap ring 313, the inner snap connection of the snap ring 313 is connected to the support tube 314, the inner bottom of the support tube 314 is fixedly connected to the resistor 315, the top of the placement plate 311 is fixedly connected to the conductive block 316, the placement component 32 includes a connecting plate 321, a limiting ring 322, an extrusion shaft 323 and a support rod 324, the connecting component 31 is provided with a connecting plate 321, the top of the connecting plate 321 is fixedly connected to the limiting ring 322, the limiting ring 322 is fixedly connected The extrusion shaft 323 and the bottom of the connecting plate 321 are connected to the support rod 324 through a connecting ring. When in use, the building pile is placed on the extrusion shaft 323. When the building pile sinks, the building pile squeezes the extrusion shaft 323, and the extrusion shaft 323 drives the connecting plate 321 to move downward. The connecting plate 321 drives the support rod 324 to move downward. The bottom end of the extrusion shaft 323 contacts the conductive block 316, and the conductive block 316 circuit is circulated. The device adopts a clamping design for the support tube 314 and the support rod 324 that are prone to bending. When both are bent under great pressure, it is convenient for the staff to replace them separately, avoiding the need to replace the entire device. The device has a simple structure, is easy to assemble, is conducive to maintenance and overhaul, can reduce unnecessary waste of resources, and reduce maintenance and monitoring costs.

[0023] Secondly, a hole is provided on the placement plate 311, and the other side of the conductive wire 204 passes through the hole and is snap-connected to the connecting end of the conductive block 316. The bottom of the support rod 324 is overlapped with the top of the resistor 315. An internal thread groove is provided in the fixing ring 312, and the fixing ring 312 is threadedly connected to the threaded shaft 205. The center points of the snap ring 313, the support tube 314, the resistor 315 and the support rod 324 are all on the same straight line. The conductive block 316 transmits current to the power supply 202 through the conductive wire 204, and the current supplies the alarm 203 to sound an alarm.

[0024] Working principle: When in use, place the construction pile on the extrusion shaft 323. When the construction pile sinks, the construction pile squeezes the extrusion shaft 323, and the extrusion shaft 323 drives the connecting plate 321 to move downward. The connecting plate 321 drives the support rod 324 to move downward. The bottom end of the extrusion shaft 323 contacts the conductive block 316, and the conductive block 316 circuit is circulated. The conductive block 316 transmits current to the power supply 202 through the conductive wire 204, and the current supplies the alarm 203 to sound an alarm.

[0025] The embodiments of the present invention are described in detail above with reference to the accompanying drawings. However, the present invention is not limited to the above embodiments. Various changes can be made within the scope of knowledge possessed by ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A construction engineering template settlement monitoring device, characterized in that: include: Base (1); The alarm mechanism (2) comprises a support frame (201) provided on the base (1) and a power supply (202) provided in the support frame (201), wherein the power supply (202) is fixedly connected to the inner bottom of the support frame (201); The load-bearing mechanism (3) comprises a connecting component (31) arranged on the alarm mechanism (2) and a placement component (32) arranged on the connecting component (31). The placement component (32) can move up and down relative to the connecting component (31). The connecting component (31) and the placement component (32) are connected by snapping.

2. A construction engineering formwork settlement monitoring device according to claim 1, characterized in that: The alarm mechanism (2) further comprises an alarm (203), a conductive wire (204) and a threaded shaft (205); the top of the power supply (202) is fixedly connected to the alarm (203); the fixed end of the power supply (202) is fixedly connected to the conductive wire (204); and the top of the support frame (201) is fixedly connected to the threaded shaft (205).

3. A construction engineering formwork settlement monitoring device according to claim 2, characterized in that: The connecting assembly (31) comprises a placement plate (311), a fixing ring (312), a snap ring (313), a support tube (314), a resistor (315) and a conductive block (316); the alarm mechanism (2) is provided with a placement plate (311); the bottom of the placement plate (311) is fixedly connected to the fixing ring (312); the top of the placement plate (311) is fixedly connected to the snap ring (313); the inside of the snap ring (313) is snap-connected to the support tube (314); the inner bottom of the support tube (314) is fixedly connected to the resistor (315); and the top of the placement plate (311) is fixedly connected to the conductive block (316); The placement assembly (32) comprises a connecting plate (321), a limiting ring (322), an extrusion shaft (323) and a support rod (324). The connecting assembly (31) is provided with a connecting plate (321). The top of the connecting plate (321) is fixedly connected to the limiting ring (322). The extrusion shaft (323) is fixedly connected inside the limiting ring (322). The bottom of the connecting plate (321) is connected to the support rod (324) via a connecting ring.

4. A construction engineering formwork settlement monitoring device according to claim 3, characterized in that: The placement plate (311) is provided with a hole, and the other side of the conductive wire (204) passes through the hole and is connected to the connecting end of the conductive block (316) by snapping.

5. A construction engineering formwork settlement monitoring device according to claim 4, characterized in that: The bottom of the support rod (324) is overlapped with the top of the resistor (315), and an internal thread groove is provided in the fixing ring (312), and the fixing ring (312) is threadedly connected to the threaded shaft (205).

6. A construction engineering formwork settlement monitoring device according to claim 5, characterized in that: The center points of the clamping ring (313), the support tube (314), the resistor (315) and the support rod (324) are all on the same straight line.

Citation Information

Patent Citations

  • Constructional engineering template settlement deformation monitoring and alarming device

    CN215868107U

Cited By

  • Constructional engineering template settlement monitoring device

    CN223636851U

  • Construction engineering quality monitoring device

    CN224695266U