Anti-cracking structure of garbage pit of garbage power plant
By setting buttresses and pressure-bearing wall corners around the main body of the garbage pit wall, and using quick joints to connect multiple pipelines to form a modular structure, the problem of easy damage to the garbage pit structure and poor drainage is solved, and the stability and drainage of the garbage pit are improved.
Patent Information
- Application Number
- CN202422712624.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2025-09-05
- Estimated Expiration
- 2034-11-07
Smart Images

Figure CN223305510U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of garbage power plants, in particular to a crack-resistant structure for a garbage pit in a garbage power plant. Background Art
[0002] The crack-resistant structure of the garbage pit in a waste-to-energy plant is primarily a reinforced concrete structure. Specifically, the structure of the garbage pit is primarily a semi-underground cast-in-place reinforced concrete structure, which is a fully enclosed structure.
[0003] Conventional garbage pits have a relatively simple structure and therefore have limited pressure-bearing capacity. As the amount of garbage pile increases, it will affect the side walls of the pit, causing structural damage. Furthermore, the interior of the pit is generally a sealed structure, so as different amounts of garbage are added, sewage will accumulate, affecting the subsequent use and treatment of the garbage pile. Utility Model Content
[0004] The purpose of the utility model is to provide a crack-resistant structure for a garbage pit in a garbage power plant to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a crack-resistant structure of a garbage pit in a garbage power plant, comprising a garbage bin structure and an external pipe, wherein external pipes are horizontally arranged at the lower ends of the left and right sides of the garbage bin structure, and one end of the external pipe is connected to a four-way joint, and the end of the four-way joint away from the external pipe is connected to a connecting horizontal pipe, and the top of the four-way joint is connected to a connecting vertical pipe, and at the same time, the top of the connecting vertical pipe is connected to a three-way joint, and the side of the three-way joint close to the garbage bin structure is horizontally connected to a fiber cloth filter pipe, the garbage bin structure comprises a pit wall body, pressure-bearing wall corners, buttresses, and sealing sleeves, the bottom of the pit wall body is provided with pressure-bearing wall corners, and the side facades of the pit wall body are provided with buttresses, and sealing sleeves are arranged and installed on the surfaces of the left and right sides of the pit wall body.
[0006] Preferably, the pit wall body and the pressure-bearing wall corner are cast in an integrated structure, and the buttresses are equidistantly arranged on the four side facades of the pit wall body and staggered with the pressure-bearing wall corner.
[0007] Preferably, the lower end of the buttress is arranged in a trapezoidal structure, and the sealing sleeves are arranged in a horizontally equidistant array between two adjacent groups of buttresses and horizontally penetrate the surface of the pit wall body.
[0008] Preferably, the buttress and the pit wall body are cast in an integrated structure, and the sealing sleeve is cast in the interior of the pit wall body through a pre-embedded structure.
[0009] Preferably, the external pipe, four-way joint, connecting horizontal pipe, connecting vertical pipe, three-way joint, and fiber cloth filter pipe are all connected and installed with a quick joint structure, and the end of the external pipe away from the four-way joint is provided with a quick joint structure.
[0010] Preferably, the four-way joint and the connecting transverse pipe are arranged one by one in sequence in the horizontal direction, and a sewage valve structure is provided at the bottom of the four-way joint.
[0011] Preferably, the connecting vertical pipe and the three-way joint are arranged one by one in the vertical direction, and the ends of the four-way joint and the three-way joint close to the pit wall body are connected and installed with a fiber cloth filter tube, and the fiber cloth filter tube is horizontally inserted into the inside of the sealing sleeve.
[0012] Preferably, a one-way valve tube is vertically connected to the top of a group of three-way connectors located at the uppermost end, and the one-way valve tube and the three-way connector are connected and installed with each other using a quick connector structure.
[0013] Compared with the prior art, the beneficial effects of the present invention are as follows: the crack-resistant structure of the garbage pit in the garbage power plant is provided with buttresses equidistantly arranged on the side surfaces of the pit wall body, and the pressure-bearing wall corners arranged on the bottom of the pit wall body are combined to ensure that the entire garbage bin structure has sufficient structural support and structural pressure resistance, whether from the inside out or from the outside in, thereby ensuring the structural stability of the entire garbage bin structure when storing garbage. In addition, the external pipe, four-way joint, connecting horizontal pipe, connecting vertical pipe, three-way joint, fiber cloth filter pipe and one-way valve pipe are all connected to each other with a quick joint structure, which not only has good drainage and sewage discharge functions, but also is easy to disassemble and maintain, thereby improving the convenience of use of the structure.
[0014] The anti-cracking structure of the garbage pit of the waste-to-energy plant is characterized by equidistantly arranging a plurality of buttresses on the four side facades of the main body of the pit wall. At the same time, pressure-bearing wall corners connected to the structure are arranged on the outer bottom of the four sides of the main body of the pit wall. The lower half of the buttress adopts a trapezoidal structure. The use of the above structure can provide structural support for the main body of the pit wall to the greatest extent, so that the entire main body of the pit wall has pressure-bearing capacity from the inside out or from the outside in, avoiding pressure loss on the main body of the pit wall caused by garbage filled inside, reducing the load on the structure, optimizing the structural engineering quantity, and ensuring the service life of the main body of the pit wall. The sealing sleeves arranged on the left and right sides of the main body of the pit wall are convenient for the insertion of the fiber cloth filter tube and have good structural sealing performance to prevent unnecessary sewage leakage.
[0015] The anti-cracking structure of the garbage pit of the waste power plant adopts quick connectors to connect the external pipe, four-way joint, connecting horizontal pipe, connecting vertical pipe, three-way joint, fiber cloth filter pipe and one-way valve pipe. On the one hand, it can make the connection between each structure flexible, so as to facilitate the disassembly or installation combination between the structures, thereby making maintenance operations relatively convenient. On the other hand, the modular setting of each structure can effectively control the maintenance cost, so that any damaged part can be directly replaced. In addition, the fiber cloth filter pipe is used in combination with other pipeline structures to effectively solve the problem of drainage of garbage materials inside the garbage bin structure and reduce the moisture content of garbage power generation materials. The sewage valve structure is provided at the bottom of the four-way joint to effectively avoid siltation and blockage inside the pipeline structure, so as to facilitate better drainage. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the structure of the device of the utility model from the side of the main body axis;
[0017] Figure 2 This is a schematic cross-sectional view of the garbage bin structure of the device of the present utility model;
[0018] Figure 3 It is a schematic diagram of the three-dimensional structure of the main body of the device of the present invention.
[0019] In the figure: 1. Garbage bin structure; 101. Pit wall body; 102. Pressure-bearing wall corner; 103. Buttress; 104. Sealing sleeve; 2. External pipe; 3. Four-way joint; 4. Connecting horizontal pipe; 5. Connecting vertical pipe; 6. Tee joint; 7. Fiber cloth filter pipe; 8. One-way valve pipe. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0021] See also Figure 1-3The utility model provides a technical solution: a crack-resistant structure of a garbage pit in a garbage power plant, comprising a garbage bin structure 1 and an external pipe 2, external pipes 2 are horizontally arranged at the lower ends of the left and right sides of the garbage bin structure 1, and one end of the external pipe 2 is connected to a four-way joint 3, and the end of the four-way joint 3 away from the external pipe 2 is connected to a connecting horizontal pipe 4, and the top of the four-way joint 3 is connected to a connecting vertical pipe 5, and at the same time, the top of the connecting vertical pipe 5 is connected to a three-way joint 6, and the side of the three-way joint 6 close to the garbage bin structure 1 is horizontally connected to a fiber cloth filter pipe 7, the garbage bin structure 1 comprises a pit wall body 101, a pressure-bearing wall corner 102, a buttress 103, and a sealing sleeve 104, and the bottom of the pit wall body 101 is provided with a pressure-bearing wall corner 102, and Buttresses 103 are provided on the four side facades of the pit wall body 101, and sealing sleeves 104 are arranged and installed on the surfaces of the left and right sides of the pit wall body 101. The pit wall body 101 and the pressure-bearing wall corner 102 are cast in an integrated structure, and the buttresses 103 are equidistantly arranged on the four side facades of the pit wall body 101 and staggered with the pressure-bearing wall corner 102. The lower ends of the buttresses 103 are arranged in a trapezoidal structure, and the sealing sleeves 104 are horizontally equidistantly arranged between two adjacent groups of buttresses 103 and horizontally penetrate the surface of the pit wall body 101. The buttresses 103 and the pit wall body 101 are cast in an integrated structure, and the sealing sleeves 104 are cast into the interior of the pit wall body 101 through a pre-embedded structure.
[0022] When using the anti-cracking structure of the garbage pit of the waste power plant, if Figure 1 and Figure 3 As shown, by respectively setting pressure-bearing wall corners 102 and buttresses 103 cast integrally with the bottom of the pit wall body 101, the structural support of the pit wall body 101 can be effectively ensured, thereby ensuring that there is sufficient garbage stacking inside the garbage bin structure 1, which is convenient for the subsequent processing and use of the garbage power plant.
[0023] At the same time, the external pipe 2, the four-way joint 3, the connecting horizontal pipe 4, the connecting vertical pipe 5, the three-way joint 6, and the fiber cloth filter pipe 7 are all connected and installed with each other by using a quick joint structure, and the end of the external pipe 2 away from the four-way joint 3 is provided with a quick joint structure, the four-way joint 3 and the connecting horizontal pipe 4 are arranged and connected one by one in the horizontal direction, and the bottom of the four-way joint 3 is provided with a sewage valve structure, the connecting vertical pipe 5 and the three-way joint 6 are arranged and connected one by one in the vertical direction, and the ends of the four-way joint 3 and the three-way joint 6 close to the pit wall main body 101 are connected and installed with a fiber cloth filter pipe 7, and the fiber cloth filter pipe 7 is horizontally inserted into the inside of the sealing sleeve 104, and the top of the three-way joint 6 is located at the uppermost end. A one-way valve pipe 8 is vertically connected to the top, and the one-way valve pipe 8 and the three-way joint 6 are connected and installed with a quick joint structure.
[0024] When it is necessary to assemble the various structures such as the external connecting pipe 2, the four-way joint 3, the connecting horizontal pipe 4, the connecting vertical pipe 5, the three-way joint 6, the fiber cloth filter pipe 7 and the one-way valve pipe 8, the quick joint structure between the various structures is first used to sequentially combine and connect the four-way joint 3 and the connecting horizontal pipe 4 in the horizontal direction. After the assembly is completed, a group of external connecting pipes 2 are connected at both ends to connect them with the downstream sewage treatment equipment. Then, the connecting vertical pipe 5 and the three-way joint 6 are sequentially combined and connected in the vertical direction and installed on the top of the four-way joint 3. Then, the fiber cloth filter pipe 7 is connected and installed at one end of the four-way joint 3 and the three-way joint 6 close to the garbage bin structure 1, and the other end of the fiber cloth filter pipe 7 is horizontally inserted into the sealing sleeve 104 installed on the surface of the pit wall main body 101, so as to provide real-time drainage for the garbage material inside the garbage bin structure 1. This is the working principle of the anti-cracking structure of the garbage pit of the garbage power plant.
[0025] Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations may be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A garbage pit anti-cracking structure for a garbage power plant, comprising a garbage bin structure (1) and an external pipe (2), characterized in that: The lower ends of the left and right sides of the garbage bin structure (1) are horizontally provided with external pipes (2), and one end of the external pipe (2) is connected to a four-way joint (3), and the end of the four-way joint (3) away from the external pipe (2) is connected to a connecting horizontal pipe (4), and the top of the four-way joint (3) is connected to a connecting vertical pipe (5), and the top of the connecting vertical pipe (5) is connected to a three-way joint (6), and the three-way joint (6) is horizontally connected to a fiber cloth filter pipe (7) on the side close to the garbage bin structure (1). The garbage bin structure (1) comprises a pit wall body (101), a pressure-bearing wall corner (102), a buttress (103), and a sealing sleeve (104). The bottom of the pit wall body (101) is provided with a pressure-bearing wall corner (102), and the side elevations of the pit wall body (101) are provided with buttresses (103), and the surfaces of the left and right sides of the pit wall body (101) are arranged and installed with sealing sleeves (104).
2. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 1, characterized in that: The pit wall body (101) and the pressure-bearing wall corner (102) are cast in an integrated structure, and the buttresses (103) are equidistantly arranged on the four side elevations of the pit wall body (101) and interlaced with the pressure-bearing wall corner (102).
3. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 2, characterized in that: The lower ends of the buttresses (103) are arranged in a trapezoidal structure, and the sealing sleeves (104) are arranged in a horizontally equidistant array between two adjacent groups of buttresses (103) and horizontally penetrate the surface of the pit wall body (101).
4. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 2, characterized in that: The buttress (103) and the pit wall body (101) are cast in an integrated structure, and the sealing sleeve (104) is cast in the interior of the pit wall body (101) through a pre-embedded structure.
5. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 1, characterized in that: The external pipe (2), the four-way joint (3), the connecting horizontal pipe (4), the connecting vertical pipe (5), the three-way joint (6), and the fiber cloth filter pipe (7) are all connected and installed with each other using a quick joint structure, and the quick joint structure is provided at one end of the external pipe (2) away from the four-way joint (3).
6. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 1, characterized in that: The four-way joint (3) and the connecting transverse pipe (4) are arranged one by one in sequence in the horizontal direction, and a sewage valve structure is provided at the bottom of the four-way joint (3).
7. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 2, characterized in that: The connecting vertical pipe (5) and the three-way joint (6) are arranged one by one in a vertical direction, and the ends of the four-way joint (3) and the three-way joint (6) close to the pit wall body (101) are connected and installed with a fiber cloth filter tube (7), and the fiber cloth filter tube (7) is horizontally inserted into the interior of the sealing sleeve (104).
8. The anti-cracking structure of a garbage pit in a waste-to-energy plant according to claim 1, characterized in that: The top of the three-way connector (6) at the uppermost end is vertically connected to a one-way valve pipe (8), and the one-way valve pipe (8) and the three-way connector (6) are connected and installed with each other using a quick connector structure.