Roof-out air shaft waterproof structure

By setting multiple layers of waterproof sealant and waterproof membrane between the upper and lower parts of the air shaft pipe and the roof anti-slope, the problem of leakage of the roof air shaft pipe is solved, and efficient waterproofing effect and simple construction process are achieved.

CN223358576UActive Publication Date: 2025-09-19CHINA CONSTR EIGHTH ENG BUREAU TECH CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422307524.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2025-09-19
Estimated Expiration
2034-09-20

AI Technical Summary

Technical Problem

During construction, the gap between the roof ventilation pipe and the structure causes roof leakage, and the existing sealing method cannot guarantee the construction quality, resulting in leakage and repair every year, and maintenance is difficult.

Method used

The top and bottom waterproof structures are adopted, including the top waterproof structure and the bottom waterproof structure, and multiple layers of waterproof sealant, waterproof membrane layer, metal plate, etc. are respectively arranged between the upper and lower parts of the air shaft pipe and the roof anti-ridge to form a multi-layer waterproof protection.

Benefits of technology

Without significantly increasing the construction cost, it can significantly reduce leakage problems, has a clever design, and is easy to construct, making it suitable for large-scale promotion and application.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223358576U_ABST
    Figure CN223358576U_ABST
Patent Text Reader

Abstract

The utility model provides a waterproof structure of an out-of-roof air shaft, which is characterized in that a top waterproof structure is arranged between the upper part of an air shaft pipeline and the position on the right side surface of a roof reverse ridge and above the upper part of an air shaft pipeline mounting hole; the top waterproof structure comprises a top heat preservation layer, a top cement mortar layer, a top metal plate, a top waterproof roll layer, a top first waterproof sealant, a top second waterproof sealant and a top third waterproof sealant. The bottom waterproof structure comprises an additional waterproof layer, a waterproof coating layer, a bottom waterproof roll layer, a bottom heat preservation layer, a bottom metal plate, a first leveling layer, a slope making layer, a second leveling layer, an integral pouring layer, a bottom first waterproof sealant, a bottom second waterproof sealant and a bottom third waterproof sealant. According to the utility model, under the condition that the construction cost is not obviously increased, the problem of leakage caused by untight plugging of the structure at the air shaft pipeline out of the roof can be obviously reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to the technical field of roof ventilation shaft construction, and specifically refers to a waterproof structure of a roof ventilation shaft. Background Art

[0002] Building construction refers to the production activities during the implementation phase of a project. It is the process of constructing various buildings. It can also be said to be the process of transforming the various lines on the design drawings into physical objects at the designated location. It includes foundation construction, main structure construction, roof construction, and decorative construction.

[0003] During construction, roof ventilation shafts are often involved. Since the 1980s, roof leakage has become a prominent issue in my country's construction projects, directly impacting the functionality and safety of buildings. The gaps between the roof ventilation shaft pipes and the structure are common leak points on roofs. During construction, they are often sealed with masonry mortar, making construction quality difficult to guarantee and leaving hidden dangers for roof leakage. Furthermore, ventilation shaft pipes run through the entire building. Once a leak occurs, the more complex the building structure, the more difficult it is to identify the leak. During maintenance, this often results in leaks year after year, followed by repairs year after year, and leaks year after year.

[0004] Therefore, in order to reduce the problem of roof water leakage caused by the gap between the roof ventilation shaft pipe and the structure, it is necessary to provide a roof ventilation shaft waterproof structure, which can significantly reduce the leakage problem caused by the loose sealing of the roof ventilation shaft pipe structure without significantly increasing the construction cost. Utility Model Content

[0005] In order to overcome the shortcomings of the above-mentioned prior art, one purpose of the present invention is to provide a waterproof structure for roof ventilation shafts, which can significantly reduce the leakage problem caused by lax structural sealing of roof ventilation shaft pipes without significantly increasing construction costs, and is suitable for large-scale promotion and application.

[0006] Another object of the present invention is to provide a roof ventilation shaft waterproof structure, which has an ingenious design, a simple structure, simple construction, low construction cost, and is suitable for large-scale promotion and application.

[0007] To achieve the above objectives, the present invention provides a roof ventilation shaft waterproof structure, comprising a roof top plate, a roof inverted ridge, and a ventilation shaft pipe, wherein the roof top plate is arranged horizontally and along the front-to-back direction, the roof inverted ridge is arranged vertically and along the front-to-back direction on the left side of the roof top plate, the roof inverted ridge is provided with ventilation shaft pipe mounting holes along the left-right direction, the ventilation shaft pipe is arranged horizontally and along the left-right direction and inserted into the ventilation shaft pipe mounting holes along the left-right direction, and the characteristic of the present invention is that the roof ventilation shaft waterproof structure further comprises a top waterproof structure and a bottom waterproof structure, wherein:

[0008] The top waterproof structure includes a top insulation layer, a top cement mortar layer, a top metal plate, a top waterproof membrane layer, a top first waterproof sealant, a top second waterproof sealant and a top third waterproof sealant. The top insulation layer is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe. The top insulation layer is located on the right side of the roof anti-slope and is connected to the roof anti-slope. The top cement mortar layer is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe. The top cement mortar layer is located on the right side of the top insulation layer and is connected to the top insulation layer. The bottom of the top cement mortar layer is located on the top insulation layer. The bottom of the thermal insulation layer is under the bottom and connected to the bottom of the top thermal insulation layer. The bottom of the top cement mortar layer is located on the right side of the roof anti-slope and connected to the roof anti-slope. The top first waterproof sealing paste is arranged between the bottom of the top cement mortar layer and the upper part of the air shaft pipe. The top metal plate includes a top first plate and a top second plate. The top first plate is arranged vertically and along the front-back direction. The top first plate is clamped and rests on the upper part of the air shaft pipe. The top first plate is located on the right side of the top cement mortar layer and the top first waterproof sealing paste and respectively connects the top cement mortar layer and the top first waterproof sealing paste. Water-sealing paste, the top second plate is arranged along the left and right directions and is arranged in an arc shape along the front and back directions, the middle part of the top second plate protrudes upward in an arc shape, the top second plate is clamped and abuts against the upper part of the air shaft pipe, the left side of the top second plate is connected to the lower side of the top first plate, the top waterproof roll layer includes a top first roll layer and a top second roll layer, the top first roll layer is arranged vertically and along the front and back directions, the top first roll layer is clamped and abuts against the top second plate, the top first roll layer is located on the right side of the top first plate and connected to the top first plate, the top second roll layer The second roll material layer is arranged along the left-right direction and in an arc shape along the front-back direction, the middle part of the second roll material layer is convex in an arc shape upward, the second roll material layer is laid on the second top plate, the left side of the second roll material layer is connected to the lower side of the first top roll material layer, the second top waterproof sealing paste is arranged on the first top plate and the first top roll material layer and is located on the right side of the top cement mortar layer and is connected to the top cement mortar layer, the third top waterproof sealing paste is arranged on the upper part of the air shaft pipe and is located on the right side of the second top plate and the second top roll material layer and is respectively connected to the second top plate and the second top roll material layer;

[0009] The bottom waterproof structure includes an additional waterproof layer, a waterproof coating layer, a bottom waterproof coiled material layer, a bottom insulation layer, a bottom metal plate, a first leveling layer, a slope layer, a second leveling layer, a pouring layer, a bottom first waterproof sealant, a bottom second waterproof sealant and a bottom third waterproof sealant. The additional waterproof layer includes an upper waterproof layer, a lower waterproof layer and an intermediate waterproof layer. The upper waterproof layer is arranged along the left and right directions and in an arc shape along the front and back directions. The middle part of the upper waterproof layer protrudes in an arc shape downward. The upper waterproof layer is arranged on the lower hole wall of the air shaft pipe installation hole. The lower waterproof layer is arranged horizontally and on the roof top plate along the front and back directions. The intermediate waterproof layer is arranged vertically and along the front and back directions. The intermediate waterproof layer is located at The right side of the upper waterproof layer and the left side of the lower waterproof layer are respectively connected to the right side of the upper waterproof layer and the left side of the lower waterproof layer. The middle waterproof layer is located on the right side of the roof anti-slope and connected to the roof anti-slope. The waterproof coating layer includes a vertical coating layer and a horizontal coating layer. The vertical coating layer is arranged along the front-to-back direction and is located on the right side of the lower part of the middle waterproof layer and connected to the lower part of the middle waterproof layer. The horizontal coating layer is arranged on the lower waterproof layer and the roof top plate along the front-to-back direction. The left side of the horizontal coating layer is connected to the lower side of the vertical coating layer. The bottom waterproof coiled material layer includes an upper coiled material layer, a lower coiled material layer and an intermediate coiled material layer. The upper coiled material layer is arranged along the left-right direction and is arc-shaped along the front-to-back direction. The middle part of the upper coiled material layer is arc-shaped and protrudes downward, the upper coiled material layer is arranged on the upper waterproof layer, the lower coiled material layer is horizontally arranged and arranged on the horizontal coating layer along the front-to-back direction, the middle coiled material layer is vertically arranged and arranged along the front-to-back direction, the middle coiled material layer is located between the right side of the upper coiled material layer and the left side of the lower coiled material layer and is respectively connected to the right side of the upper coiled material layer and the left side of the lower coiled material layer, the middle coiled material layer is located on the upper part of the middle waterproof layer and on the right side of the vertical coating layer and is respectively connected to the upper part of the middle waterproof layer and the vertical coating layer, the first leveling layer is horizontally arranged and arranged on the lower coiled material layer along the front-to-back direction, the first leveling layer is located on the right side of the middle coiled layer And connected to the middle coiled material layer, the bottom insulation layer includes a vertical insulation layer and a horizontal insulation layer, the vertical insulation layer is arranged on the left side of the first leveling layer along the front-to-back direction and is located on the right side of the middle coiled material layer and is connected to the middle coiled material layer, the horizontal insulation layer is arranged on the first leveling layer along the front-to-back direction and is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer, the slope layer is arranged horizontally and arranged on the horizontal insulation layer along the front-to-back direction, the slope layer is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer, the second leveling layer is arranged horizontally and arranged on the slope layer along the front-to-back direction, the second leveling layer is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer,The bottom metal plate includes a first bottom plate and a second bottom plate, the second bottom plate is arranged along the left and right directions and arranged in an arc shape along the front and back directions, the middle portion of the second bottom plate protrudes in an arc shape downward, the second bottom plate is arranged on the upper coiled material layer and is located above the vertical insulation layer, the lower portion of the air shaft pipe is embedded in the second bottom plate, the first bottom plate is arranged vertically and along the front and back directions, the lower side of the first bottom plate abuts on the left side of the second leveling layer and is located on the right side of the vertical insulation layer and abuts against the vertical insulation layer, the right side of the second bottom plate is connected to the first bottom plate On the upper side of the plate, the first bottom waterproof sealant is arranged between the lower part of the air shaft pipe and the right side of the second bottom plate. The whole pouring layer is arranged horizontally and along the front-to-back direction on the second leveling layer and is located on the right side of the lower side of the first bottom plate. The second bottom waterproof sealant is arranged on the lower hole wall of the air shaft pipe installation hole and is located on the left side of the upper waterproof layer, the upper coiled material layer and the second bottom plate, and respectively connects the upper waterproof layer, the upper coiled material layer and the second bottom plate. The third bottom waterproof sealant is arranged between the lower side of the first bottom plate and the left side of the whole pouring layer.

[0010] Preferably, the top metal plate is galvanized iron sheet.

[0011] Preferably, the thickness of the top metal plate is 1 mm.

[0012] Preferably, the upper surface of the second top plate slopes toward the right.

[0013] Preferably, the top waterproof structure also includes a top fixing nail, which is arranged along the left-right direction and inserted into the top first plate, the bottom of the top cement mortar layer and the roof anti-ridge along the left-right direction, and the head of the top fixing nail is located on the right side of the top first plate and abuts against the top first plate.

[0014] Preferably, the dimension of the lower waterproof layer in the left-right direction is ≥250 mm.

[0015] Preferably, the height of the vertical coating layer is ≥250 mm.

[0016] Preferably, the upper surface of the second bottom plate slopes toward the right.

[0017] Preferably, the thickness of the bottom metal plate is 4 mm.

[0018] Preferably, the top waterproof structure also includes a bottom fixing nail, which is vertically arranged and vertically inserted into the lower hole wall of the bottom second plate, the upper coiled material layer, the upper waterproof layer and the air shaft pipe installation hole, and the head of the bottom fixing nail rests on the bottom second plate.

[0019] The beneficial effects of the present invention are mainly:

[0020] 1. The roof air shaft waterproof structure of the present invention is achieved by arranging a top waterproof structure between the upper part of the air shaft pipe and the right side of the roof inverted ridge, which is located above the upper part of the air shaft pipe installation hole. The top waterproof structure includes a top insulation layer, a top cement mortar layer, a top metal plate, a top waterproof membrane layer, a top first waterproof sealing paste, a top second waterproof sealing paste and a top third waterproof sealing paste. A bottom waterproof structure is achieved by arranging a bottom waterproof structure between the lower part of the air shaft pipe and the right side of the roof inverted ridge, which is located below the lower part of the air shaft pipe installation hole. The bottom waterproof structure includes an additional waterproof layer, a waterproof coating layer, a bottom waterproof membrane layer, a bottom insulation layer, a bottom metal plate, a first leveling layer, a slope layer, a second leveling layer, a whole pouring layer, a bottom first waterproof sealing paste, a bottom second waterproof sealing paste and a bottom third waterproof sealing paste. Therefore, it can significantly reduce the leakage problem caused by the loose sealing of the roof air shaft pipe structure without significantly increasing the construction cost, and is suitable for large-scale promotion and application.

[0021] 2. The roof air shaft waterproof structure of the present invention is achieved by setting a top waterproof structure between the upper part of the air shaft pipe and the right side of the roof inverted ridge, which is located above the upper part of the air shaft pipe installation hole. The top waterproof structure includes a top insulation layer, a top cement mortar layer, a top metal plate, a top waterproof membrane layer, a top first waterproof sealing paste, a top second waterproof sealing paste and a top third waterproof sealing paste. The bottom waterproof structure is achieved by setting a bottom waterproof structure between the lower part of the air shaft pipe and the right side of the roof inverted ridge, which is located below the lower part of the air shaft pipe installation hole. The bottom waterproof structure includes an additional waterproof layer, a waterproof coating layer, a bottom waterproof membrane layer, a bottom insulation layer, a bottom metal plate, a first leveling layer, a slope layer, a second leveling layer, a whole pouring layer, a bottom first waterproof sealing paste, a bottom second waterproof sealing paste and a bottom third waterproof sealing paste. Therefore, it has an ingenious design, a simple structure, simple construction, low construction cost and is suitable for large-scale promotion and application.

[0022] These and other objects, features and advantages of the present invention are fully reflected in the following detailed description and drawings, and can be achieved by the means, devices and their combinations specifically pointed out in the content of the utility model. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1It is a partial schematic diagram of a main cross-section of a specific embodiment of the roof ventilation shaft waterproof structure of the present invention.

[0024] Figure 2 yes Figure 1 A partial enlarged schematic diagram of the structure shown Figure 1 .

[0025] Figure 3 yes Figure 1 A partial enlarged schematic diagram of the structure shown Figure 2 .

[0026] Figure 4 yes Figure 1 A partial enlarged schematic diagram of the structure shown Figure 3 .

[0027] (Explanation of Symbols)

[0028] 1. Roof top plate; 2. Roof anti-slope; 3. Air shaft pipe;

[0029] 4 Top waterproof structure; 41 Top insulation layer; 42 Top cement mortar layer; 43 Top metal plate; 44 Top waterproof membrane layer; 45 Top first waterproof sealant; 46 Top second waterproof sealant; 47 Top third waterproof sealant; 48 Top fixing nails; 401 Top first plate; 402 Top second plate; 403 Top first membrane layer; 404 Top second membrane layer;

[0030] 5 Bottom waterproof structure; 51 Additional waterproof layer; 52 Waterproof coating layer; 53 Bottom waterproof membrane layer; 54 Bottom thermal insulation layer; 55 Bottom metal plate; 56 First leveling layer; 57 Slope layer; 58 Second leveling layer; 59 Casting layer; 60 Bottom first waterproof sealant; 61 Bottom second waterproof sealant; 62 Bottom third waterproof sealant; 63 Bottom fixing nails; 501 Upper waterproof layer; 502 Lower waterproof layer; 503 Middle waterproof layer; 504 Vertical coating layer; 505 Horizontal coating layer; 506 Upper membrane layer; 507 Lower membrane layer; 508 Middle membrane layer; 509 Vertical thermal insulation layer; 510 Horizontal thermal insulation layer; 511 Bottom first plate; 512 Bottom second plate;

[0031] 6. Air shaft pipe installation holes. DETAILED DESCRIPTION

[0032] In order to more clearly understand the technical content of the present invention, the following embodiments are given to explain in detail.

[0033] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention.

[0034] See Figures 1 to 4 As shown, in a specific embodiment of the present invention, the roof ventilation shaft waterproof structure of the present invention includes a roof top plate 1, a roof anti-ridge 2, a ventilation shaft pipe 3, a top waterproof structure 4 and a bottom waterproof structure 5, wherein:

[0035] The roof top plate 1 is arranged horizontally and along the front-to-back direction, the roof counter-ridge 2 is arranged vertically and along the front-to-back direction on the left side of the roof top plate 1, the roof counter-ridge 2 is provided with an air shaft pipe installation hole 6 along the left-right direction, and the air shaft pipe 3 is arranged horizontally and along the left-right direction and inserted into the air shaft pipe installation hole 6 along the left-right direction;

[0036] The top waterproof structure 4 includes a top insulation layer 41, a top cement mortar layer 42, a top metal plate 43, a top waterproof roll material layer 44, a top first waterproof sealant 45, a top second waterproof sealant 46 and a top third waterproof sealant 47. The top insulation layer 41 is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe 3. The top insulation layer 41 is located on the right side of the roof anti-slope 2 and is connected to the roof anti-slope 2. The top cement mortar layer 42 is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe 3. The top cement mortar layer 42 is located on the right side of the top insulation layer 41 and is connected to the top insulation layer 41. The top cement The bottom of the mortar layer 42 is located under the bottom of the top insulation layer 41 and is connected to the bottom of the top insulation layer 41. The bottom of the top cement mortar layer 42 is located on the right side of the roof anti-slope 2 and is connected to the roof anti-slope 2. The top first waterproof sealant 45 is arranged between the bottom of the top cement mortar layer 42 and the upper part of the air shaft pipe 3. The top metal plate 43 includes a top first plate 401 and a top second plate 402. The top first plate 401 is arranged vertically and along the front-to-back direction. The top first plate 401 is clamped and abuts against the upper part of the air shaft pipe 3. The top first plate 401 is located between the top cement mortar layer 42 and the top first The right side of the waterproof sealing paste 45 is respectively connected to the top cement mortar layer 42 and the top first waterproof sealing paste 45, the top second plate 402 is arranged along the left and right directions and arranged in an arc shape along the front and back directions, the middle part of the top second plate 402 protrudes upward in an arc shape, the top second plate 402 is clamped and abuts against the upper part of the wind shaft pipe 3, the left side of the top second plate 402 is connected to the lower side of the top first plate 401, the top waterproof roll layer 44 includes a top first roll layer 403 and a top second roll layer 404, the top first roll layer 403 is arranged vertically and along the front and back directions, the top first roll layer 403 is clamped and abuts against the top second roll layer 404. On the second plate 402, the top first coiled material layer 403 is located on the right side of the top first plate 401 and is connected to the top first plate 401. The top second coiled material layer 404 is arranged along the left-right direction and is arranged in an arc shape along the front-back direction. The middle part of the top second coiled material layer 404 protrudes upward in an arc shape. The top second coiled material layer 404 is laid on the top second plate 402. The left side of the top second coiled material layer 404 is connected to the lower side of the top first coiled material layer 403. The top second waterproof sealing paste 46 is arranged on the top first plate 401 and the top first coiled material layer 403 and is located on the right side of the top cement mortar layer 42 and is connected to the top cement mortar layer 42.The top third waterproof sealant 47 is arranged on the upper part of the air shaft pipe 3 and is located to the right of the top second plate 402 and the top second coiled material layer 404 and is respectively connected to the top second plate 402 and the top second coiled material layer 404;

[0037] The bottom waterproof structure 5 includes an additional waterproof layer 51, a waterproof coating layer 52, a bottom waterproof coiled material layer 53, a bottom thermal insulation layer 54, a bottom metal plate 55, a first leveling layer 56, a slope layer 57, a second leveling layer 58, a pouring layer 59, a bottom first waterproof sealant 60, a bottom second waterproof sealant 61 and a bottom third waterproof sealant 62. The additional waterproof layer 51 includes an upper waterproof layer 501, a lower waterproof layer 502 and an intermediate waterproof layer 503. The upper waterproof layer 501 is arranged along the left and right directions and is arranged in an arc shape along the front and back directions. The middle part of the upper waterproof layer 501 protrudes in an arc shape downward. The upper waterproof layer 501 is arranged on the lower hole wall of the air shaft pipe installation hole 6. The lower waterproof layer 50 2 is horizontally arranged and arranged on the roof top plate 1 along the front-to-back direction, the intermediate waterproof layer 503 is vertically arranged and arranged along the front-to-back direction, the intermediate waterproof layer 503 is located between the right side of the upper waterproof layer 501 and the left side of the lower waterproof layer 502 and is respectively connected to the right side of the upper waterproof layer 501 and the left side of the lower waterproof layer 502, the intermediate waterproof layer 503 is located on the right side of the roof anti-slope 2 and is connected to the roof anti-slope 2, the waterproof coating layer 52 includes a vertical coating layer 504 and a horizontal coating layer 505, the vertical coating layer 504 is arranged along the front-to-back direction and is located on the right side of the lower part of the intermediate waterproof layer 503 and is connected to the lower part of the intermediate waterproof layer 503, The horizontal coating layer 505 is arranged on the lower waterproof layer 502 and the roof top plate 1 along the front-to-back direction. The left side of the horizontal coating layer 505 is connected to the lower side of the vertical coating layer 504. The bottom waterproof coiled material layer 53 includes an upper coiled material layer 506, a lower coiled material layer 507 and an intermediate coiled material layer 508. The upper coiled material layer 506 is arranged along the left-right direction and is arranged in an arc shape along the front-to-back direction. The middle part of the upper coiled material layer 506 protrudes in an arc shape downward. The upper coiled material layer 506 is arranged on the upper waterproof layer 501. The lower coiled material layer 507 is arranged horizontally and is arranged on the horizontal coating layer 505 along the front-to-back direction. The intermediate coiled material layer 508 is arranged vertically and arranged in the front-to-back direction. The intermediate coiled material layer 508 is located between the right side of the upper coiled material layer 506 and the left side of the lower coiled material layer 507 and is respectively connected to the right side of the upper coiled material layer 506 and the left side of the lower coiled material layer 507. The intermediate coiled material layer 508 is located on the upper part of the intermediate waterproof layer 503 and on the right side of the vertical coating layer 504 and is respectively connected to the upper part of the intermediate waterproof layer 503 and the vertical coating layer 504. The first leveling layer 56 is horizontally arranged and arranged on the lower coiled material layer 507 along the front-to-back direction. The first leveling layer 56 is located on the right side of the intermediate coiled material layer 508 and is connected to the intermediate coiled material layer 508. The bottom thermal insulation layer 54 includes a vertical thermal insulation layer 509 and a horizontal thermal insulation layer 510.The vertical thermal insulation layer 509 is arranged on the left side of the first leveling layer 56 along the front-to-back direction and is located on the right side of the middle coiled material layer 508 and is connected to the middle coiled material layer 508. The horizontal thermal insulation layer 510 is arranged on the first leveling layer 56 along the front-to-back direction and is located on the right side of the vertical thermal insulation layer 509 and is connected to the vertical thermal insulation layer 509. The slope layer 57 is arranged horizontally and arranged on the horizontal thermal insulation layer 510 along the front-to-back direction. The slope layer 57 is located on the right side of the vertical thermal insulation layer 509 and is connected to the vertical thermal insulation layer 509. The second leveling layer 58 is arranged horizontally and on the slope layer 57 along the front-to-back direction. The second leveling layer 58 is located on the right side of the vertical thermal insulation layer 509 and is connected to the vertical thermal insulation layer 509. The bottom metal plate 55 includes a bottom first plate 511 and a bottom second plate 512. The bottom second plate 512 is arranged along the left-right direction and in an arc shape along the front-to-back direction. The middle part of the bottom second plate 512 protrudes in an arc shape downward. The bottom second plate 512 is arranged on the upper coiled material layer 506 and is located above the vertical thermal insulation layer 509. The lower part of the air shaft pipe 3 is embedded in the second bottom plate 512, the first bottom plate 511 is arranged vertically and along the front-to-back direction, the lower side of the first bottom plate 511 abuts on the left side of the second leveling layer 58 and is located on the right side of the vertical thermal insulation layer 509 and abuts on the vertical thermal insulation layer 509, the right side of the second bottom plate 512 is connected to the upper side of the first bottom plate 511, the first bottom waterproof sealant 60 is arranged between the lower part of the air shaft pipe 3 and the right side of the second bottom plate 512, and the whole pouring layer 59 is horizontal The second leveling layer 58 is provided along the front-to-back direction and is located on the right side of the lower side of the first bottom plate 511. The second bottom waterproof sealant 61 is provided on the lower hole wall of the air shaft pipe installation hole 6 and is located to the left of the upper waterproof layer 501, the upper coiled material layer 506 and the second bottom plate 512, and respectively connects the upper waterproof layer 501, the upper coiled material layer 506 and the second bottom plate 512. The third bottom waterproof sealant 62 is provided between the lower side of the first bottom plate 511 and the left side of the cast-in-place layer 59.

[0038] The top metal plate 43 can be a metal plate made of any suitable material. In a specific embodiment of the present invention, the top metal plate 43 is galvanized iron sheet.

[0039] The thickness of the top metal plate 43 can be determined as needed. In a specific embodiment of the present invention, the thickness of the top metal plate 43 is 1 mm.

[0040] The upper surface of the second top plate 402 can be set horizontally or tilted along the left-right direction. Figures 1 and 2 As shown, in a specific embodiment of the present invention, the upper surface of the second top plate 402 is sloped toward the right. That is, the upper surface of the second top plate 402 is higher on the left and lower on the right.

[0041] The rightward slope of the upper surface of the second top plate 402 can be determined as needed. Figures 1 and 2 As shown, in a specific embodiment of the present invention, the upper surface of the second top plate 402 is sloped 1% toward the right.

[0042] The top waterproof roll layer 44 can be a waterproof roll layer made of any suitable material. In a specific embodiment of the present invention, the top waterproof roll layer 44 is a thermoplastic polyolefin waterproof roll layer, namely, a TPO waterproof roll layer.

[0043] The top first plate 401 is located on the right side of the top cement mortar layer 42 and is connected to the top cement mortar layer 42. Any suitable structure can be used. Figures 1 and 2 As shown, in a specific embodiment of the present utility model, the top waterproof structure 4 also includes a top fixing nail 48, which is arranged along the left-right direction and inserted into the top first plate 401, the bottom of the top cement mortar layer 42 and the roof anti-ridge 2 along the left-right direction, and the head of the top fixing nail 48 is located on the right side of the top first plate 401 and abuts against the top first plate 401.

[0044] The top fixing nail 48 can be any suitable fixing nail. In a specific embodiment of the present invention, the top fixing nail 48 is a cement nail.

[0045] The distance between the bottom of the top cement mortar layer 42 and the upper part of the air shaft pipe 3, or the thickness of the top first waterproof sealant 45, can be determined as needed. In a specific embodiment of the present invention, the distance between the bottom of the top cement mortar layer 42 and the upper part of the air shaft pipe 3 is 20 mm.

[0046] The size of the top second plate 402 in the left-right direction, that is, the width of the top second plate 402, can be determined as needed. In a specific embodiment of the present invention, the size of the top second plate 402 in the left-right direction is 100 mm.

[0047] The dimension of the lower waterproof layer 502 in the left-right direction, i.e., the width of the lower waterproof layer 502, can be determined as needed. Preferably, the dimension of the lower waterproof layer 502 in the left-right direction is ≥ 250 mm. In a specific embodiment of the present invention, the dimension of the lower waterproof layer 502 in the left-right direction is 300 mm.

[0048] The height of the vertical coating layer 504 can be determined as needed. Preferably, the height of the vertical coating layer 504 is ≥ 250 mm. In a specific embodiment of the present invention, the height of the vertical coating layer 504 is 300 mm.

[0049] The upper surface of the second bottom plate 512 can be set horizontally or tilted along the left-right direction. Figure 1 and Figure 3 As shown, in a specific embodiment of the present invention, the upper surface of the second bottom plate 512 is sloped toward the right. That is, the upper surface of the second bottom plate 512 is higher on the left and lower on the right.

[0050] The rightward slope of the upper surface of the second bottom plate 512 can be determined as needed. Figure 1 and Figure 3 As shown, in a specific embodiment of the present invention, the upper surface of the bottom second plate 512 is sloped 1% toward the right.

[0051] The thickness of the bottom metal plate 55 can be determined as needed. In a specific embodiment of the present invention, the thickness of the bottom metal plate 55 is 4 mm.

[0052] The bottom second plate 512 is disposed on the upper coil layer 506 and may be of any suitable structure. Figure 1 and Figure 3 As shown, in a specific embodiment of the present utility model, the top waterproof structure 4 also includes a bottom fixing nail 63, which is vertically arranged and vertically inserted into the bottom second plate 512, the upper coiled material layer 506, the upper waterproof layer 501 and the lower hole wall of the air shaft pipe installation hole 6, and the head of the bottom fixing nail 63 rests on the bottom second plate 512.

[0053] The bottom fixing nail 63 can be any suitable fixing nail. In a specific embodiment of the present invention, the bottom fixing nail 63 is a cement nail.

[0054] The distance between the lower part of the air shaft pipe 3 and the second bottom plate 512, or the thickness of the bottom first waterproof sealant 60, can be determined as needed. In a specific embodiment of the present invention, the distance between the lower part of the air shaft pipe 3 and the second bottom plate 512 is 20 mm.

[0055] The first leveling layer 56 can be a leveling layer made of any suitable material. In a specific embodiment of the present invention, the first leveling layer 56 is a cement mortar leveling layer, such as a 1:3 cement mortar leveling layer.

[0056] The slope layer 57 can be a slope layer made of any suitable material. In a specific embodiment of the present invention, the slope layer 57 is a lightweight aggregate concrete slope layer, such as an LC7.5 lightweight aggregate concrete slope layer.

[0057] The second leveling layer 58 can be a leveling layer made of any suitable material. In a specific embodiment of the present invention, the second leveling layer 58 is a cement mortar leveling layer, such as a 1:3 cement mortar leveling layer.

[0058] The cast-in-place layer 59 can be a cast-in-place layer of any suitable material. In a specific embodiment of the present invention, the cast-in-place layer 59 is a fine stone concrete cast-in-place layer, such as a C30 fine stone concrete cast-in-place layer, with φ6@200 bidirectional steel bars.

[0059] During construction, the following structure is available: the roof top plate 1 is arranged horizontally and in the front-to-back direction, the roof anti-ridge 2 is arranged vertically and in the front-to-back direction on the left side of the roof top plate 1, the roof anti-ridge 2 is provided with a ventilation shaft pipe installation hole 6 in the left-right direction, and the ventilation shaft pipe 3 is arranged horizontally and in the left-right direction. The ventilation shaft pipe 3 needs to be installed in the ventilation shaft pipe installation hole 6 in the left-right direction. The construction process of the utility model is briefly described as follows:

[0060] 1. Cleaning up the grassroots

[0061] Remove protrusions, dust, concrete residues and other foreign matter on the concrete surface around the ventilation shaft pipe installation hole 6 on the right side of the roof anti-ridge 2, and thoroughly clean the dust and debris on the roof top plate 1 to ensure that the base layer is flat and clean;

[0062] 2. Roof anti-ridge 2 waterproof construction:

[0063] (1) Arc angle construction at the corners

[0064] The right side of the root of the roof anti-ridge 2 is made into an arc. The radius of the inner and outer corners of the arc meets the requirements of the specifications. The mortar surface is compacted and smoothed.

[0065] (2) Construction of additional waterproof layer at corners

[0066] The waterproof membrane is laid on the lower wall of the ventilation shaft pipe installation hole 6, the right side of the roof anti-ridge 2 below the lower part of the ventilation shaft pipe installation hole 6, and the roof top plate 1, thereby forming an upper waterproof layer 501, a middle waterproof layer 503, and a lower waterproof layer 502 respectively;

[0067] (3) Construction of waterproof coating layer 52

[0068] A rubber scraper is used to apply the waterproof material to the right side of the lower portion of the middle waterproof layer 503, the lower waterproof layer 502 and the roof top plate 1, thereby forming a vertical coating layer 504 and a horizontal coating layer 505 respectively;

[0069] (4) Construction of bottom waterproof membrane layer 53

[0070] Lay waterproofing membranes on the upper waterproof layer 501, the right side of the upper portion of the middle waterproof layer 503, the right side of the vertical coating layer 504, and the horizontal coating layer 505, thereby forming an upper membrane layer 506, a middle membrane layer 508, and a lower membrane layer 507, respectively.

[0071] 3. Insulation layer construction

[0072] (1) Lay the insulation board on the right side of the roof anti-ridge 2 at a position above the upper part of the air shaft pipe installation hole 6, thereby forming a top insulation layer 41;

[0073] (2) a first leveling layer 56 is provided on the lower coiled material layer 507 and to the right of the middle coiled material layer 508, and an insulation board is laid on the right side of the middle coiled material layer 508 and on the first leveling layer 56, thereby forming a vertical insulation layer 509 and a horizontal insulation layer 510, respectively;

[0074] 4. Installation of bottom metal plate 55

[0075] A slope layer 57 is provided on the horizontal insulation layer 510 and on the right side of the vertical insulation layer 509. A second leveling layer 58 is provided on the slope layer 57 and on the right side of the vertical insulation layer 509. The lower side of the first bottom plate 511 of the bottom metal plate 55 is pressed against the left side of the second leveling layer 58 and is placed on the right side of the vertical insulation layer 509 and against the vertical insulation layer 509. The second bottom plate 512 of the bottom metal plate 55 is placed above the vertical insulation layer 509 and is provided on the bottom side of the second leveling layer 58. On the upper coiled material layer 506, on the lower hole wall of the air shaft pipe installation hole 6 and between the upper waterproof layer 501, the upper coiled material layer 506 and the left side of the second bottom plate 512, a waterproof sealant is embedded to form a bottom second waterproof sealant 61. On the second leveling layer 58 and to the right of the lower side of the first bottom plate 511, a cast layer 59 is provided. Between the lower side of the first bottom plate 511 and the left side of the cast layer 59, a waterproof sealant is embedded to form a bottom third waterproof sealant 62.

[0076] 5. Installation of ventilation shaft pipe 3

[0077] Insert the air shaft pipe 3 into the air shaft pipe installation hole 6 in the left-right direction, so that the top insulation layer 41 is fixed on the upper part of the air shaft pipe 3, and the lower part of the air shaft pipe 3 is embedded in the bottom second plate 512. A waterproof sealant is embedded between the lower part of the air shaft pipe 3 and the right side of the bottom second plate 512 to form a bottom first waterproof sealant 60;

[0078] 6. Construction of top cement mortar layer 42

[0079] Cement mortar is applied to the right side of the roof anti-slope 2, above the upper portion of the air shaft pipe installation hole 6, under the bottom of the top insulation layer 41, and to the right of the top insulation layer 41, thereby forming a top cement mortar layer 42.

[0080] 7. Installation of top metal plate 43

[0081] The second top plate 402 and the first top plate 401 of the top metal plate 43 are clamped and placed against the upper portion of the air shaft pipe 3. The first top plate 401 is placed to the right of the top cement mortar layer 42 and the top first waterproof sealant 45 and connected to the top cement mortar layer 42 and the top first waterproof sealant 45 respectively.

[0082] 8. Construction of top waterproof membrane layer 44

[0083] The waterproof roll materials are laid on the right side of the top first plate 401 and the top second plate 402 respectively, thereby forming the top first roll material layer 403 and the top second roll material layer 404 respectively; waterproof sealing paste is used to embed on the top first plate 401 and the top first roll material layer 403 and on the right side of the top cement mortar layer 42 to form the top second waterproof sealing paste 46; waterproof sealing paste is used to embed on the upper part of the air shaft pipe 3 and on the right side of the top second plate 402 and the top second roll material layer 404 to form the top third waterproof sealing paste 47.

[0084] Therefore, the utility model provides a new waterproof structure for the roof ventilation shaft, which significantly reduces the leakage problem caused by the loose sealing of the roof ventilation shaft pipe structure without significantly increasing the construction cost, improves the technical level of roof leakage control, and improves the living and working environment.

[0085] In summary, the waterproof structure of the roof air shaft of the utility model can significantly reduce the leakage problem caused by the loose sealing of the roof air shaft pipe without significantly increasing the construction cost. It has a clever design, a simple structure, simple construction, and low construction cost, and is suitable for large-scale promotion and application.

[0086] It can be seen that the purpose of this utility model has been fully and effectively achieved. The functional and structural principles of this utility model have been demonstrated and explained in the embodiments. Without departing from the principles described, the embodiments may be modified in any way. Therefore, this utility model includes all modified embodiments based on the spirit and scope of the claims.

Claims

1. A roof ventilation shaft waterproof structure, comprising a roof top plate, a roof ridge and a ventilation shaft pipe, wherein the roof top plate is arranged horizontally and along the front-to-back direction, the roof ridge is arranged vertically and along the front-to-back direction on the left side of the roof top plate, the roof ridge is provided with ventilation shaft pipe mounting holes along the left-right direction, the ventilation shaft pipe is arranged horizontally and along the left-right direction and inserted into the ventilation shaft pipe mounting holes along the left-right direction, and is characterized in that: The roof ventilation shaft waterproof structure also includes a top waterproof structure and a bottom waterproof structure, wherein: The top waterproof structure includes a top insulation layer, a top cement mortar layer, a top metal plate, a top waterproof membrane layer, a top first waterproof sealant, a top second waterproof sealant and a top third waterproof sealant. The top insulation layer is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe. The top insulation layer is located on the right side of the roof anti-slope and is connected to the roof anti-slope. The top cement mortar layer is vertically arranged and arranged along the front-to-back direction and is clamped on the upper part of the air shaft pipe. The top cement mortar layer is located on the right side of the top insulation layer and is connected to the top insulation layer. The bottom of the top cement mortar layer is located on the top insulation layer. The bottom of the thermal insulation layer is under the bottom and connected to the bottom of the top thermal insulation layer. The bottom of the top cement mortar layer is located on the right side of the roof anti-slope and connected to the roof anti-slope. The top first waterproof sealing paste is arranged between the bottom of the top cement mortar layer and the upper part of the air shaft pipe. The top metal plate includes a top first plate and a top second plate. The top first plate is arranged vertically and along the front-back direction. The top first plate is clamped and rests on the upper part of the air shaft pipe. The top first plate is located on the right side of the top cement mortar layer and the top first waterproof sealing paste and respectively connects the top cement mortar layer and the top first waterproof sealing paste. Water-sealing paste, the top second plate is arranged along the left and right directions and is arranged in an arc shape along the front and back directions, the middle part of the top second plate protrudes upward in an arc shape, the top second plate is clamped and abuts against the upper part of the air shaft pipe, the left side of the top second plate is connected to the lower side of the top first plate, the top waterproof roll layer includes a top first roll layer and a top second roll layer, the top first roll layer is arranged vertically and along the front and back directions, the top first roll layer is clamped and abuts against the top second plate, the top first roll layer is located on the right side of the top first plate and connected to the top first plate, the top second roll layer The second roll material layer is arranged along the left-right direction and in an arc shape along the front-back direction, the middle part of the second roll material layer is convex in an arc shape upward, the second roll material layer is laid on the second top plate, the left side of the second roll material layer is connected to the lower side of the first top roll material layer, the second top waterproof sealing paste is arranged on the first top plate and the first top roll material layer and is located on the right side of the top cement mortar layer and is connected to the top cement mortar layer, the third top waterproof sealing paste is arranged on the upper part of the air shaft pipe and is located on the right side of the second top plate and the second top roll material layer and is respectively connected to the second top plate and the second top roll material layer; The bottom waterproof structure includes an additional waterproof layer, a waterproof coating layer, a bottom waterproof coiled material layer, a bottom insulation layer, a bottom metal plate, a first leveling layer, a slope layer, a second leveling layer, a pouring layer, a bottom first waterproof sealant, a bottom second waterproof sealant and a bottom third waterproof sealant. The additional waterproof layer includes an upper waterproof layer, a lower waterproof layer and an intermediate waterproof layer. The upper waterproof layer is arranged along the left and right directions and in an arc shape along the front and back directions. The middle part of the upper waterproof layer protrudes in an arc shape downward. The upper waterproof layer is arranged on the lower hole wall of the air shaft pipe installation hole. The lower waterproof layer is arranged horizontally and on the roof top plate along the front and back directions. The intermediate waterproof layer is arranged vertically and along the front and back directions. The intermediate waterproof layer is located at The right side of the upper waterproof layer and the left side of the lower waterproof layer are respectively connected to the right side of the upper waterproof layer and the left side of the lower waterproof layer. The middle waterproof layer is located on the right side of the roof anti-slope and connected to the roof anti-slope. The waterproof coating layer includes a vertical coating layer and a horizontal coating layer. The vertical coating layer is arranged along the front-to-back direction and is located on the right side of the lower part of the middle waterproof layer and connected to the lower part of the middle waterproof layer. The horizontal coating layer is arranged on the lower waterproof layer and the roof top plate along the front-to-back direction. The left side of the horizontal coating layer is connected to the lower side of the vertical coating layer. The bottom waterproof coiled material layer includes an upper coiled material layer, a lower coiled material layer and an intermediate coiled material layer. The upper coiled material layer is arranged along the left-right direction and is arc-shaped along the front-to-back direction. The middle part of the upper coiled material layer is arc-shaped and protrudes downward, the upper coiled material layer is arranged on the upper waterproof layer, the lower coiled material layer is horizontally arranged and arranged on the horizontal coating layer along the front-to-back direction, the middle coiled material layer is vertically arranged and arranged along the front-to-back direction, the middle coiled material layer is located between the right side of the upper coiled material layer and the left side of the lower coiled material layer and is respectively connected to the right side of the upper coiled material layer and the left side of the lower coiled material layer, the middle coiled material layer is located on the upper part of the middle waterproof layer and on the right side of the vertical coating layer and is respectively connected to the upper part of the middle waterproof layer and the vertical coating layer, the first leveling layer is horizontally arranged and arranged on the lower coiled material layer along the front-to-back direction, the first leveling layer is located on the right side of the middle coiled layer And connected to the middle coiled material layer, the bottom insulation layer includes a vertical insulation layer and a horizontal insulation layer, the vertical insulation layer is arranged on the left side of the first leveling layer along the front-to-back direction and is located on the right side of the middle coiled material layer and is connected to the middle coiled material layer, the horizontal insulation layer is arranged on the first leveling layer along the front-to-back direction and is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer, the slope layer is arranged horizontally and arranged on the horizontal insulation layer along the front-to-back direction, the slope layer is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer, the second leveling layer is arranged horizontally and arranged on the slope layer along the front-to-back direction, the second leveling layer is located on the right side of the vertical insulation layer and is connected to the vertical insulation layer,The bottom metal plate includes a first bottom plate and a second bottom plate, the second bottom plate is arranged along the left and right directions and arranged in an arc shape along the front and back directions, the middle portion of the second bottom plate protrudes in an arc shape downward, the second bottom plate is arranged on the upper coiled material layer and is located above the vertical insulation layer, the lower portion of the air shaft pipe is embedded in the second bottom plate, the first bottom plate is arranged vertically and along the front and back directions, the lower side of the first bottom plate abuts on the left side of the second leveling layer and is located on the right side of the vertical insulation layer and abuts against the vertical insulation layer, the right side of the second bottom plate is connected to the first bottom plate On the upper side of the plate, the first bottom waterproof sealant is arranged between the lower part of the air shaft pipe and the right side of the second bottom plate. The whole pouring layer is arranged horizontally and along the front-to-back direction on the second leveling layer and is located on the right side of the lower side of the first bottom plate. The second bottom waterproof sealant is arranged on the lower hole wall of the air shaft pipe installation hole and is located on the left side of the upper waterproof layer, the upper coiled material layer and the second bottom plate, and respectively connects the upper waterproof layer, the upper coiled material layer and the second bottom plate. The third bottom waterproof sealant is arranged between the lower side of the first bottom plate and the left side of the whole pouring layer.

2. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The top metal sheet is galvanized iron.

3. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The thickness of the top metal plate is 1 mm.

4. The waterproof structure for roof ventilation shaft according to claim 1, characterized in that: The upper surface of the second top plate is sloped toward the right.

5. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The top waterproof structure also includes a top fixing nail, which is arranged along the left-right direction and inserted into the top first plate, the bottom of the top cement mortar layer and the roof anti-slope along the left-right direction, and the head of the top fixing nail is located on the right side of the top first plate and abuts against the top first plate.

6. The waterproof structure for roof ventilation shaft according to claim 1, characterized in that: The dimension of the lower waterproof layer in the left-right direction is ≥250 mm.

7. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The height of the vertical coating layer is ≥250 mm.

8. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The upper surface of the second bottom plate is sloped toward the right.

9. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The thickness of the bottom metal plate is 4 mm.

10. The roof ventilation shaft waterproof structure according to claim 1, characterized in that: The top waterproof structure also includes a bottom fixing nail, which is vertically arranged and vertically inserted into the lower hole wall of the bottom second plate, the upper coiled material layer, the upper waterproof layer and the air shaft pipe installation hole, and the head of the bottom fixing nail rests on the bottom second plate.