Waterproof board laying and hanging multifunctional trolley with reinforcing steel bar dragging and jacking functions
By designing a multifunctional trolley for laying waterproof sheets with the functions of dragging and pushing up steel bars, using a motor reducer to drive a traveling trolley with roller chains and ring chains, combined with steel bar positioning fixtures and jacking cylinders, the problem of low efficiency in the installation of waterproof sheets and steel bars in traditional tunnel lining construction is solved, efficient and precise automated construction is achieved, and construction quality and safety are improved.
Patent Information
- Application Number
- CN202422928079.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-29
- Publication Date
- 2025-10-10
- Estimated Expiration
- 2034-11-29
AI Technical Summary
In traditional tunnel lining construction, the laying of waterproof sheets and the installation of steel bars rely on manual operations, which are inefficient and prone to errors.
A multifunctional trolley for laying and hanging waterproof sheets with the functions of dragging and jacking steel bars has been designed. A motor reducer is used to drive the walking trolley on the roller chain and the ring chain. Combined with the steel bar positioning fixture and the jacking cylinder, the automatic laying of waterproof sheets and the automatic dragging and positioning of steel bars can be realized.
It realizes the automation or semi-automatic operation of tunnel lining construction, improves construction efficiency, reduces manual labor intensity and time cost, ensures the accuracy of steel bar installation and the quality of tunnel structure, improves the construction environment, and complies with the concept of green construction.
Smart Images

Figure CN223424028U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of trolleys, in particular to a multifunctional trolley for laying waterproof boards with the functions of dragging steel bars and pushing up steel bars. Background Art
[0002] Lining trolleys are essential, non-standard products for secondary lining during tunnel construction. Lifting and flipping formwork are also commonly used in hydraulic tunnels. For larger spans, full-circle trolleys are often employed. Side-arch trolleys are the most common, often used in highway and railway tunnels and underground caverns. A trolley typically consists of a formwork assembly, a top formwork frame, a translation mechanism assembly, a gantry assembly, a master-slave travel mechanism, a screw jack, a hydraulic system, and an electrical system.
[0003] In traditional tunnel lining construction, the laying of waterproof panels and the installation of steel bars mostly rely on manual operations, which are inefficient and prone to errors. Utility Model Content
[0004] The purpose of the utility model is to solve the shortcomings of the prior art in which the laying of waterproof boards and the installation of steel bars in traditional tunnel lining construction mostly rely on manual operation, which is inefficient and prone to errors. A multifunctional trolley for laying waterproof boards with the functions of dragging steel bars and pushing up steel bars is proposed.
[0005] In order to achieve the above purpose, the present invention adopts the following technical solutions:
[0006] A multifunctional trolley for laying waterproof boards with the function of dragging and pushing up steel bars comprises a trolley body, a working platform is provided inside the trolley body, a lining layer and a primary supporting layer are provided on the outside of the trolley body, the lining layer is located inside the primary supporting layer and is arranged in a ring shape on the outside of the trolley body, an inner layer of steel bars is provided on one side of the lining layer, an outer layer of steel bars is provided on one side of the primary supporting layer, a plurality of electric hoists for lifting waterproof boards are provided on the side of the trolley body, a pulling platform is provided on the bottom of one side of the trolley body, guide rollers are provided on the pulling platform, a center column is provided in the middle position of the bottom of the trolley body, and extended columns are provided on both sides of the bottom of the trolley body, and the bottoms of the extended columns and the center column are provided with the same longitudinal connecting beam.
[0007] In a possible design, two driving wheels are provided on one side of the bottom of the trolley body, and a plurality of driven wheels are provided on the bottom of a side of the trolley body away from the driving wheels.
[0008] In a possible design, a spring balancer is provided at the bottom of one side of the trolley body, and a waterproof coil is provided at the middle position of the top of the trolley body.
[0009] In one possible design, a driving chain is provided on the outer wall of the trolley body, a moving track at the bottom of the longitudinal beam of the climbing trolley is provided on the driving chain, a crawling trolley assembly is provided on the moving track at the bottom of the longitudinal beam of the climbing trolley, a through beam is provided inside the trolley body, a waterproof board mounting beam, a steel bar dragging fixture and a longitudinal steel bar placement frame are installed on the through beam, and a chain driving system is provided inside the trolley body.
[0010] In a possible design, a plurality of annular steel bar pushing mechanisms are provided on one side of the trolley body, an electric control box is provided at the middle position of the bottom of the trolley body, and a plurality of extended escalators are provided on one side of the trolley body.
[0011] In a possible design, a ventilation pipe is provided inside the trolley body.
[0012] In this application,
[0013] 1. There are arch rings at the front and rear of the trolley body. The arch rings are located just outside the door frame. Roller chains are installed on the arch rings. The chains are driven by a motor reducer placed above the beam.
[0014] 2. A walking trolley is provided on the ring chain, and the front and rear trolleys are provided with a through beam, on which a waterproof board installation beam and a steel bar positioning fixture are installed.
[0015] 3. A longitudinal steel bar storage rack is provided on the above-mentioned trolley beam.
[0016] 4. During tunnel construction, geotextile is laid first, and then waterproof board. The laying method is as follows: the circular trolley moves to the lower right corner of the figure, removes the waterproof board beam, manually installs the waterproof board on the beam, and then installs the beam on the beam connecting the front and rear trolleys. The circular trolley moves upward to the other side of the tunnel. During the moving process, the waterproof board is manually pulled out and laid while walking.
[0017] 5. After the geotextile and waterproof sheet are laid, start dragging the steel bars:
[0018] The picture shows 8 circumferential steel bars being dragged at a time, with the steel bars clamped with the extension bolts on the steel bar heads through the ring chain and the clamps.
[0019] After the reinforcement is installed, it is towed from the right side of the tunnel to the left side, initially pulling only the outer ring reinforcement of the secondary lining. During this process, seven rows of lifting cylinders mounted on the gantry extend to hold the ring reinforcement in place.
[0020] When the cart dragging the steel bars reaches the left side of the tunnel, it starts to tie the steel bars, and while walking, it takes out the longitudinal steel bars from the steel bar storage rack and ties them together with the circumferential steel bars.
[0021] Beneficial effects:
[0022] 1. Efficient and automated construction: The motor reducer drives the trolley on the roller chain and the ring chain, realizing automated or semi-automated operations during the tunnel lining construction process, including the laying of waterproof sheets and the dragging and positioning of steel bars. This significantly improves construction efficiency and reduces manual labor intensity and time costs.
[0023] 2. Precise positioning and installation: The combination of steel bar positioning fixtures and lifting cylinders can accurately lift the circumferential steel bars to the predetermined position, ensuring the accuracy and consistency of steel bar installation and improving the quality and safety of the tunnel lining structure.
[0024] 3. Flexibility and adaptability: The design allows the installation sequence and position of waterproof panels and steel bars to be adjusted as needed during the construction process. In particular, during the laying of waterproof panels, the flexible combination of the circular trolley and the through beam enables efficient laying of waterproof panels, while facilitating fine adjustments by on-site operators.
[0025] 4. Improve the working environment: The mechanized construction method reduces the time that construction workers are directly exposed to harsh construction environments, such as moisture and dust, which is beneficial to protecting the health of construction workers and also helps to keep the construction site clean and orderly.
[0026] 5. Improve construction quality: The automated rebar dragging and positioning system reduces human error and ensures the accuracy and stability of rebar installation. The continuity of waterproofing sheet laying helps to improve the overall performance of the tunnel waterproofing layer and extend the service life of the tunnel.
[0027] 6. Promote resource conservation and environmental protection: By improving construction efficiency and reducing material waste, this application helps to achieve resource conservation and utilization. At the same time, mechanized construction methods also help reduce construction noise and dust emissions, which is in line with the concept of green construction.
[0028] In summary, this application has significantly improved the efficiency, quality and safety of tunnel lining construction by introducing automated and mechanized construction technology, while improving the construction environment, promoting resource conservation and environmental protection, and has significant beneficial effects. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 This is a schematic diagram of the main structure of a multifunctional trolley for laying waterproof panels with the functions of dragging and pushing up steel bars proposed in the present invention;
[0030] Figure 2 This is an enlarged view of part A in the present utility model;
[0031] Figure 3 This is a side structural schematic diagram of a multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars proposed by the utility model.
[0032] In the figure: 1. Electric hoist for lifting waterproof board; 2. Drive chain; 3. Moving track at the bottom of longitudinal beam of climbing trolley; 4. Lining layer; 5. Inner steel bar; 6. Outer steel bar; 7. Primary support layer; 8. Steel bar pulling fixture; 9. Waterproof membrane; 10. Longitudinal steel bar placement frame; 11. Chain drive system; 12. Annular steel bar pushing mechanism; 13. Spring balancer; 14. Guide roller; 15. First-layer pulling platform; 16. Crawling trolley assembly; 17. Drive wheel; 18. Longitudinal connecting beam; 19. Center column; 20. Electric control box; 21. Driven wheel; 22. Extension column; 23. Extension ladder; 24. Trolley body; 25. Ventilation duct. DETAILED DESCRIPTION
[0033] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0034] Example 1
[0035] Reference Figure 1-3 , a waterproof board laying multifunctional trolley with the function of dragging steel bars and pushing steel bars, which is used in the trolley field,
[0036] 1. Trolley main structure:
[0037] The multifunctional trolley of this utility model primarily consists of a trolley body 24, with an internal work platform for easy access by construction personnel. A lining layer 4 and a primary support layer 7 are provided on the exterior of the trolley body. The lining layer is located within the primary support layer and annularly arranged outside the trolley body, forming the main framework of the tunnel structure. An inner layer of steel bars 5 are installed inside the lining layer, while an outer layer of steel bars 6 are installed outside the primary support layer to enhance the strength and stability of the structure.
[0038] 2. Waterproof board hoisting and pulling platform:
[0039] Multiple waterproof board hoisting electric hoists 1 are installed on the side of the trolley body 24 for lifting and moving waterproof boards. A pull-out platform 15 is installed on the bottom of one side of the trolley body, and guide rollers 14 are installed on the platform to facilitate the horizontal movement and positioning of waterproof boards or other materials.
[0040] 3. Traveling mechanism:
[0041] A central column 19 is provided at the bottom center of the trolley body, and an extended column 22 is provided on each side. The bottoms of these columns are connected by longitudinal connecting beams 18 to form a stable support structure. Two driving wheels 17 are provided on one side of the bottom of the trolley body, and multiple driven wheels 21 are provided on the other side to realize the movement and positioning of the trolley.
[0042] 4. Auxiliary device and control system:
[0043] The bottom of one side of the trolley body is also provided with a spring balancer 13 for balancing and adjusting the stability of the trolley during work. Waterproof coiled material 9 is laid in the middle of the top of the trolley to provide additional waterproof protection. In addition, a ring chain driving system 11 is arranged inside the trolley to drive the crawling trolley assembly 16 to move on the moving track 3 at the bottom of the climbing trolley longitudinal beam, so as to realize the automatic carrying and installation of waterproof plates, steel bars and other materials.
[0044] 5. Steel bar processing and ventilation system:
[0045] A through beam is arranged inside the trolley body, and waterproof plate installation beams, steel bar pulling jigs 8 and longitudinal steel bar placing frames 10 are installed on the through beam for storing and pulling steel bars. A plurality of ring-shaped steel bar jacking mechanisms 12 are arranged on one side of the trolley, which can provide jacking force during steel bar installation to ensure accurate positioning of the steel bars. At the same time, an electric control box 20 is arranged at the middle position of the bottom of the trolley for controlling the electrical system and automatic operation of the whole trolley. In addition, a ventilation pipe 25 is arranged inside the trolley to ensure the working comfort of construction personnel in a closed space.
[0046] 6. Safety and convenience facilities:
[0047] In order to facilitate the construction personnel to get on and off the trolley, a plurality of extended staircases 23 are arranged on one side of the trolley to ensure the safety of personnel entering and leaving.
[0048] However, as known to those skilled in the art, the working principles and wiring methods of the driving walking wheels 17, the driving ring chains 2, the ring chain driving systems 11, the electric control boxes 20 and the spring balancers 13 are common, which all belong to conventional means or common knowledge, and will not be described here. Those skilled in the art can make any selection or arrangement according to their needs or convenience.
[0049] The above is only the preferred specific implementation of the present application, but the protection scope of the present application is not limited to this. Any skilled person in the art can make equivalent replacement or change according to the technical scheme and the inventive concept of the present application within the technical range disclosed by the present application, which should be covered within the protection scope of the present application.
Claims
1. A multifunctional trolley for laying waterproof boards with the functions of dragging and pushing steel bars, characterized in that: include: A trolley body (24) is provided with a working platform inside the trolley body (24), a lining layer (4) and a primary support layer (7) are provided on the outside of the trolley body (24), the lining layer (4) is located inside the primary support layer (7) and is arranged in a ring shape outside the trolley body (24), an inner layer of steel bars (5) is provided on one side of the lining layer (4), and an outer layer of steel bars (6) is provided on one side of the primary support layer (7), a plurality of electric hoists (1) for lifting waterproof boards are provided on the side of the trolley body (24), a layer of pulling platform (15) is provided at the bottom of one side of the trolley body (24), a guide roller (14) is provided on the layer of pulling platform (15), a center column (19) is provided at the middle position of the bottom of the trolley body (24), and extended columns (22) are provided on both sides of the bottom of the trolley body (24), and the bottoms of the extended columns (22) and the center column (19) are provided with the same longitudinal connecting beam (18).
2. The multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars according to claim 1 is characterized in that: Two driving wheels (17) are provided on one side of the bottom of the trolley body (24), and a plurality of driven wheels (21) are provided on the bottom of a side of the trolley body (24) away from the driving wheels (17).
3. The multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars according to claim 1 is characterized in that: A spring balancer (13) is provided at the bottom of one side of the trolley body (24), and a waterproof coiled material (9) is provided at the middle position of the top of the trolley body (24).
4. The multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars according to claim 1 is characterized in that: The outer wall of the trolley body (24) is provided with a driving chain (2), a climbing trolley longitudinal beam bottom motion track (3) is provided on the driving chain (2), a crawling trolley assembly (16) is provided on the climbing trolley longitudinal beam bottom motion track (3), a through beam is provided inside the trolley body (24), a waterproof board installation beam, a steel bar dragging fixture (8) and a longitudinal steel bar placement frame (10) are installed on the through beam, and a chain driving system (11) is provided inside the trolley body (24).
5. The multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars according to claim 1 is characterized in that: A plurality of annular steel bar pushing mechanisms (12) are provided on one side of the trolley body (24), an electric control box (20) is provided at the middle position of the bottom of the trolley body (24), and a plurality of extended escalators (23) are provided on one side of the trolley body (24).
6. The multifunctional trolley for laying waterproof boards with the functions of dragging and pushing up steel bars according to claim 1 is characterized in that: A ventilation pipe (25) is provided inside the trolley body (24).