Supporting structure for large-scale pipe joint pre-embedding construction

By using lower and upper support components in the pre-buried construction of large pipe segments, the problem of pipe segment displacement caused by deformation of the steel skeleton or formwork support is solved, the reliable fixation and position accuracy of the pipe segments are achieved, the construction safety hazards are reduced and material loss is reduced.

CN223460028UActive Publication Date: 2025-10-21CHINA METALLURGICAL CONSTR ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423215065.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-10-21
Estimated Expiration
2034-12-25

AI Technical Summary

Technical Problem

In the existing technology, during the pre-buried construction of large pipe sections, the steel frame or wall formwork support is easily deformed by load disturbance, causing the pipe sections to shift, posing installation quality and safety risks, especially during the pre-buried installation of large pipe sections.

Method used

The lower support assembly is used to support the large pipe segment below the embedded position, and the upper support assembly is used to support the large pipe segment in the inner circular hole. The lower support assembly consists of vertical support columns and transverse support beams, and the upper support assembly consists of trapezoidal support frames and connecting beams to ensure the initial positioning of the pipe segment and further support and bearing.

Benefits of technology

It achieves independent and reliable fixation of large pipe sections, avoids positional deviation caused by concrete pouring or self-load, reduces safety hazards during construction, and allows for the recycling of materials, reducing losses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223460028U_ABST
    Figure CN223460028U_ABST
Patent Text Reader

Abstract

The utility model discloses a supporting structure for large-scale pipe joint pre-burying construction, which comprises an upper supporting assembly and a lower supporting assembly, and the lower supporting assembly is arranged below the pre-burying position of a large-scale pipe joint and is used for supporting the bottom of a flange plate of the large-scale pipe joint. The upper supporting assembly is arranged in an inner circular hole of the large pipe joint and used for supporting the top of the inner circular hole. According to the supporting structure for pre-embedding construction of the large pipe joint, the lower supporting assemblies are arranged below the pre-embedding position of the large pipe joint, so that the large pipe joint is preliminarily supported and positioned when being hoisted to the pre-embedding position; the upper supporting assembly is arranged in the inner circular hole of the large pipe joint, so that the large pipe joint is further supported, borne and moved and limited; according to the supporting structure, independent and reliable fixing of the large pipe joint is achieved, the accuracy of the installation position of the embedded flange can be effectively guaranteed, and potential safety hazards in the construction process are greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of building construction, specifically relates to a support structure for large pipe joint pre -buried construction. BACKGROUND

[0002] In underground building construction, due to the complexity and diversity of the pipeline system, pipe joints are usually pre-buried on the concrete wall to facilitate easy connection of adjacent pipelines on both sides of the wall during subsequent construction, ensuring smooth pipeline systems.

[0003] In the prior art, pipe joints in underground buildings are pre-buried and installed by lifting equipment to the steel reinforcement framework in the concrete shear wall, and then connected to the steel reinforcement framework of the wall in a suspended state to form support for the pipe joints. Alternatively, the pipe joints are lifted to the wall formwork support using lifting equipment when the wall formwork is set up, and the pipe joints are supported by the wall formwork support. However, the above construction methods have the following defects: (1) During concrete pouring of the wall, the steel reinforcement framework or wall formwork support will be disturbed by the load and deformed, which will cause displacement of the pipe joints and potential installation quality problems; (2) When large pipe joints are pre-buried and installed, the steel reinforcement framework or wall formwork support in the wall cannot withstand the gravity load of the pipe joints, and forced fixation will not only cause quality problems, but also pose a significant safety hazard.

[0004] Therefore, it is necessary to improve the existing large pipe joint pre-buried construction method to effectively solve the problems existing in the prior art. INVENTION CONTENTS

[0005] Therefore, the purpose of the utility model is to provide a support structure for large pipe joint pre-buried construction, which realizes independent and reliable fixation of large pipe joints by setting a lower support assembly below the large pipe joint pre-buried position and an upper support assembly in the inner circular hole of the large pipe joint, avoiding the influence of concrete pouring or the influence of its own load, thereby improving the installation quality of large pipe joints and avoiding safety hazards.

[0006] The utility model provides a support structure for large pipe joint pre-buried construction, which comprises an upper support assembly and a lower support assembly, the lower support assembly is arranged below the large pipe joint pre-buried position and is used for supporting the bottom of the flange plate of the large pipe joint, and the upper support assembly is arranged in the inner circular hole of the large pipe joint and is used for supporting the top of the inner circular hole.

[0007] Further, the lower support assembly comprises lower support pieces symmetrically arranged on the left and right sides of the central axis of the large pipe joint, and the lower support pieces comprise vertical support columns pre-buried in the concrete beam plate and horizontal support beams arranged at the top of the vertical support columns.

[0008] Further, the upper support assembly comprises trapezoidal support frames symmetrically arranged on the front and back of the large pipe joint in the axial direction, and a connecting cross beam for supporting the top of the inner hole of the large pipe joint is arranged between the two trapezoidal support frames.

[0009] Further, the connecting cross beam is two and symmetrically arranged on the trapezoidal support frames on the left and right sides of the central axis of the large pipe joint.

[0010] Further, the top of the trapezoidal support frame is provided with a limiting piece for limiting the axial position of the large pipe joint.

[0011] Further, the bottom of the trapezoidal support frame is provided with a support embedded part for fixing the trapezoidal support frame on the concrete beam plate.

[0012] The support structure for large pipe joint pre-embedded construction has the advantages that: the lower support assembly arranged below the pre-embedded position of the large pipe joint realizes the preliminary support positioning of the large pipe joint hoisted to the pre-embedded position, and the upper support assembly arranged in the inner hole of the large pipe joint realizes the further support bearing and movement limiting of the large pipe joint; the support structure realizes the independent and reliable fixing of the large pipe joint, can effectively ensure the installation position accuracy of the large pipe joint, greatly reduces the safety hidden trouble in the construction process, and the upper support assembly can be recycled after the construction is completed, thereby reducing the material loss. BRIEF DESCRIPTION OF DRAWINGS

[0013] The utility model will be further described in connection with the drawings and embodiments:

[0014] Figure 1 It is the structure schematic diagram of the support structure in the utility model;

[0015] Figure 2 It is the structure schematic diagram of the support embedded part in the utility model;

[0016] Figure 3 It is the longitudinal section view of the support structure in the utility model;

[0017] Figure 4 It is Figure 3 the enlarged view of A of

[0018] Mark for explanation: 1-large pipe joint; 2-lower support piece; 3-vertical support column; 4-horizontal support beam; 5-trapezoidal support frame; 6-connecting cross beam; 7-limiting piece; 8-support embedded part; 9-concrete beam plate; 10-wall steel reinforcement cage; 11-lifting hook; 12-concrete shear wall. DETAILED DESCRIPTION

[0019] As shown in the figure, the utility model provides a kind of support structure for large pipe section pre-burying construction, including upper support assembly and lower support assembly, the lower support assembly is set to the large pipe section 1 pre-burying position below and is used to support the flange bottom of large pipe section 1, the upper support assembly is set to the inner circular hole of the large pipe section 1 and is used to support the top of inner circular hole;Wherein lower support assembly is mainly used for the preliminary support positioning of large pipe section 1 hoisting to pre-burying position, and upper support assembly is used to further provide support load for large pipe section 1, while limiting the front and back displacement of large pipe section 1 in the direction of central axis, to ensure the independent reliable fixation of large pipe section 1, without again relying on wall steel reinforcement framework 10 or formwork support frame to support positioning;And the cooperation of upper support assembly and lower installation component can effectively guarantee large pipe section 1 installation position accuracy, so that large pipe section 1 will not again be due to the flow of concrete pouring positional deviation, greatly reduce the security risk in construction process.

[0020] In the embodiment, the lower support assembly includes the lower support pieces 2 symmetrically arranged on the left and right sides of the central axis of the large pipe section 1, and the lower support pieces 2 include vertical support columns 3 pre-buried in the concrete beam plate 9 and horizontal support beams 4 arranged on the top of the vertical support columns 3. Figure 1 And Figure 3 As shown in the figure, the lower support assembly includes two groups of lower support pieces 2 symmetrically arranged on the left and right sides of the central axis of the large pipe section 1. Since the lower support assembly is mainly used to support the bottom of the flange of the large pipe section 1, and the flange profile is a circular structure, at least two groups of lower support pieces 2 need to be arranged to support the large pipe section 1. The lower support pieces 2 are formed by overlapping the vertical support columns 3 and the horizontal support beams 4. The vertical support columns 3 and the horizontal support beams 4 are both made of channel steel and are overlapped into the structure shown in the figure. In order to ensure that the lower support pieces 2 can meet the support requirements of the large pipe section 1, the vertical support columns 3 need to be pre-buried in the concrete beam plate 9 before pouring the concrete beam plate 9 to have sufficient load capacity. Then, the horizontal support beams 4 are arranged on the top of the vertical support columns 3, and the water stop pieces are arranged on the horizontal support beams 4. Figure 1

[0021] In the embodiment, the upper support assembly includes trapezoidal support frames 5 symmetrically arranged on the front and back sides of the large pipe section 1 in the axial direction. Two connecting cross beams 6 for supporting the top of the inner circular hole of the large pipe section 1 are arranged between the two trapezoidal support frames 5 arranged oppositely. The connecting cross beams 6 are both symmetrically arranged on the trapezoidal support frames 5 on the left and right sides of the central axis of the large pipe section 1. As shown in the figure, the trapezoidal support frames 5 are arranged on the inner circular hole of the large pipe section 1, and the connecting cross beams 6 are arranged on the top of the trapezoidal support frames 5. Figure 1 And Figure 3 ​The upper support assembly is mainly used for supporting the top of the inner circular hole of the large pipe section 1, wherein the trapezoidal support frames 5 are symmetrically arranged outside the flange surfaces on the front and rear sides of the large pipe section 1 in the axial direction, the connecting cross beams 6 are arranged between and fixedly connected with the two trapezoidal support frames 5, and the connecting cross beams 6 are two and symmetrically arranged on the trapezoidal support frames 5 in the present scheme to ensure the stability of the support when contacting the top of the inner circular hole of the large pipe section 1. Figure 4 As shown in Fig. 5, the connecting cross beams 6 and the trapezoidal support frames 5 are mainly fixed by bolt connection, and the several channel steels in the trapezoidal support frames 5 are also detachably connected by bolts, so as to facilitate subsequent recycling and reuse, and reduce material loss.

[0022] In the present embodiment, the top of the trapezoidal support frame 5 is provided with a limiting piece 7 for limiting the axial position of the large pipe section 1. Figure 1 Figure 3 As shown in Figs. 1 and 2, the limiting piece 7 is an angle steel arranged on the top of the trapezoidal support frame 5, and through cooperation of the limiting pieces 7 on the front and rear sides, the large pipe section 1 can be effectively limited from moving in the front and rear directions of the central axis, and the installation position accuracy of the large pipe section 1 is effectively ensured.

[0023] In the present embodiment, the bottom of the trapezoidal support frame 5 is provided with a support embedded part 8, and the support embedded part 8 is used for fixing the trapezoidal support frame 5 on the concrete beam plate 9. Figure 2 Figure 2 As shown in Fig. 3, the support embedded part 8 is a steel foot plate with a thickness of 10 mm and is fixed on the concrete beam plate 9 by chemical anchor bolts.

[0024] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the present application but not limit the present application. Although the present application has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present application can be modified or replaced by equivalents without departing from the spirit and scope of the present application, and all of them should be covered in the scope of the claims of the present application.​

Claims

1. A support structure for large pipe section pre-embedment construction, characterised in that: The upper support assembly is arranged in the inner hole of the large pipe section and is used for supporting the top of the inner hole.

2. The support structure for large pipe section pre-embedded construction according to claim 1, characterized in that: The lower support assembly comprises lower support members symmetrically arranged on the left and right sides of the central axis of the large pipe section, and the lower support member comprises a vertical support column embedded in the concrete beam plate and a transverse support beam arranged at the top of the vertical support column.

3. The support structure for large pipe section pre-embedded construction according to claim 1, characterized in that: The upper support assembly comprises trapezoidal support frames symmetrically arranged on the front and back sides of the large pipe section, and two connecting cross beams for supporting the top of the inner hole of the large pipe section are arranged between the two oppositely arranged trapezoidal support frames.

4. The support structure for large pipe section pre-embedded construction according to claim 3, characterized in that: The connecting cross beam is two and symmetrically arranged on the trapezoidal support frames on the left and right sides of the central axis of the large pipe section.

5. The support structure for large pipe section pre-embedded construction according to claim 3, characterized in that: The top of the trapezoidal support frame is provided with a limiting member for limiting the large pipe section in the axial direction.

6. The support structure for large pipe section pre-embedded construction according to claim 3, characterized in that: The bottom of the trapezoidal support frame is provided with a support embedded part for fixing the trapezoidal support frame on the concrete beam plate.