Hanging basket suspension type support suitable for curtain wall decoration construction
By designing a suspended scaffold with adjustable frame groups and steel wire rope connections, the problems of long construction period, poor stability and major safety hazards in existing technologies have been solved, achieving efficient and safe exterior curtain wall decoration construction.
Patent Information
- Application Number
- CN202422639872.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2025-10-24
- Estimated Expiration
- 2034-10-31
AI Technical Summary
Existing suspended scaffold structures have problems such as long construction period, inflexibility, poor stability and great safety hazards in curtain wall decoration construction, especially in high-rise buildings where it is impossible to carry out full decoration construction of the exterior curtain wall.
A suspended platform support system including an adjustable frame assembly is designed. It is connected to the building structure through upper and lower anchor plates. The height of the crossbeam is adjusted by sliding and locking the adjusting pipe and the support pipe. The diagonal connection of the steel wire rope enhances stability and ensures safe and convenient installation of the suspended platform device.
It enabled the comprehensive decoration construction of the exterior curtain wall without affecting the normal construction of the roof project, improving the overall safety performance and flexible installation capabilities, and eliminating safety hazards.
Smart Images

Figure CN223469021U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of high-altitude decoration construction of buildings, and particularly relates to a hanging basket suspension support suitable for curtain wall decoration construction. BACKGROUND
[0002] The curtain wall decoration of the outer wall of a building usually includes glass curtain wall, metal sheet curtain wall, stone plate curtain wall and the like, the curtain wall is usually 30cm to 48cm higher than the top frame beam of the building, the operation platform for curtain wall construction should avoid interfering with the decoration construction of the outer curtain wall and ensure the overall decoration construction of the outer curtain wall, so the scaffolding or attached lifting frame for the main structure construction of the building cannot be used, and the hanging basket is usually used to complete the decoration construction after the scaffolding is removed. The hanging basket system has the advantages of convenient disassembly and assembly, strong site adaptability, safety and reliability and the like, and is widely used in the high-altitude operation of curtain wall decoration of building engineering.
[0003] The suspension structure in the hanging basket system is a key component, in the prior art, the hanging basket suspension structure usually includes two structural forms of counterweight and no counterweight, and the following problems exist respectively: 1. In the suspension structure with counterweight, the counterweight is installed in the rear support, the rear support counterweight needs to occupy a large roof space, so that the roof construction and the curtain wall construction cannot be carried out at the same time, and the construction period is too long; and the installation of the front and rear supports is limited by the site, for example, it cannot be applied to the working conditions that the frame beam exceeds the parapet wall or the beam is more than 1.5m. 2. In the suspension support structure without counterweight, the suspension main beam is extended along the top of the frame beam in a nearly horizontal manner, the extended suspension main beam interferes with the decoration construction of the outer curtain wall, the overall decoration construction of the outer curtain wall cannot be carried out, and the suspension support cannot be flexibly adjusted according to different construction heights; the suspension support without counterweight usually uses a rubber support for support, and has the problems of poor stability, large safety hazard and the like; the installation plate for anchoring connection usually uses a flat plate, and has poor connection stability and stress performance. If the suspension main beam and the column are in a split type, the position of the suspension main beam and the installation plate and the position of the suspension main beam and the column need to be adjusted synchronously during the extension and adjustment of the suspension main beam, so as to ensure that the steel wire rope is stable, and then the construction complexity is increased, and it is difficult to meet the safety and convenience construction standard. CONTENT OF THE UTILITY MODEL
[0004] The present application provides a hanging basket suspension support suitable for curtain wall decoration construction, which is convenient to disassemble and assemble, has good firmness, can meet the flexible installation of various different heights on the frame beam, greatly improves the overall safety performance, realizes the avoidance of the outer curtain wall and the overall decoration construction of the outer curtain wall without affecting the normal construction of the roof engineering.
[0005] The application provides a hanging type support for curtain wall decoration construction, which comprises two adjusting frame groups anchored to a first building body and a second building body, each adjusting frame group is connected to the first building body through an upper anchor plate, and each adjusting frame group is connected to the second building body through a lower anchor plate.
[0006] Each adjusting frame group comprises a fixed sleeve connected to the upper anchor plate, a support frame group vertically sliding and lockably connected to the fixed sleeve, and a hanging frame group transversely sliding and lockably connected to the support frame group.
[0007] The lower part of the support frame group is provided with an adjusting pipe matched with the fixed sleeve, the top of the adjusting pipe is connected with a positioning pipe matched with the hanging frame group in a transverse manner, and the upper part of the positioning pipe is vertically connected with a support pipe.
[0008] The hanging frame group comprises a cross beam sliding and lockably sleeved in the positioning pipe, the first end of the cross beam is provided with a connecting pipe, and the second end of the cross beam is provided with a front lifting head.
[0009] Each adjusting frame group further comprises a first steel wire cable, a second steel wire cable and a working steel wire cable for connecting a hanging basket device.
[0010] The support pipe supports the middle bulge of the first steel wire cable, the first end of the first steel wire cable is connected to the connecting pipe in a slanting manner, and the second end of the first steel wire cable is connected to the front lifting head in a slanting manner.
[0011] The first end of the second steel wire cable is connected to the connecting pipe in a slanting manner, and the second end of the second steel wire cable is connected to the lower anchor plate in a slanting manner.
[0012] The working steel wire cable is connected to the front lifting head in an overlapping manner, and the end of the working steel wire cable away from the hanging basket device is positioned and connected to the lower anchor plate.
[0013] In the application, the upper anchor plate is anchored to the top frame beam, and the lower anchor plate is anchored to the parapet or beam, so that flexible installation can be realized for frame beams with different heights, and the overall stability is reliable.
[0014] When the adjusting pipe slides along the fixed sleeve and is locked, the height of the cross beam is adjusted, the outer curtain wall construction higher than the frame beam is avoided, and overall decoration construction of the outer curtain wall is realized.
[0015] The cross beam is slidingly and lockably positioned in the positioning pipe, the extension or contraction positioning mode of the cross beam is convenient, the position of the support pipe is stable, and the stability of the first steel wire cable is maintained.
[0016] The second steel wire cable is obliquely connected between the connecting pipe and the lower anchoring plate, so that the stability is enhanced, and the safety hazard is eliminated.
[0017] The hanging basket suspension support is convenient to disassemble and assemble, has good firmness, can meet flexible installation of various heights on the framework beam, improves overall safety performance, realizes avoidance of the outer curtain wall and overall decoration construction without affecting normal construction of the roof project.
[0018] In a specific implementation, two ends of the hanging basket device are connected with two working steel wire cables of the two adjusting frame groups. Each adjusting frame group is equipped with two working steel wire cables connected with the same end of the hanging basket device, or the two working steel wire cables are cross-connected at the two ends of the hanging basket device, so as to improve safety.
[0019] In a specific implementation, the upper anchoring plate is an L-shaped plate body buckled on the inner side corner of the first building body, and the plane and the vertical surface of the L-shaped plate body are provided with a plurality of first mounting holes.
[0020] The inner wall and the top plane of the first building body are anchored with a plurality of first expansion bolt assemblies, and the plurality of first expansion bolt assemblies are locked and fixed to the upper anchoring plate after penetrating through the corresponding first mounting holes. The L-shaped plate body is used as the upper anchoring plate, and the top and the inner wall of the framework beam are anchored and connected, so as to enhance the stability and the stress performance in multiple aspects.
[0021] In a specific implementation, the fixed sleeve is welded to the vertical surface of the L-shaped plate body, and the connection between the fixed sleeve and the L-shaped plate body is welded with a first reinforcing plate. The square tube is used as the fixed sleeve, the welding connection area is increased, and the overall firmness is reliable.
[0022] In a specific implementation, the fixed sleeve is provided with a plurality of first positioning holes in the height direction, and the adjusting pipe is provided with a plurality of first matching holes in the height direction.
[0023] When any at least two first matching holes and at least two first positioning holes one-to-one correspond and coincide, the fixed sleeve and the adjusting pipe are locked by a first bolt assembly penetrating through the corresponding coinciding first positioning hole and first matching hole. The first bolt assembly is used for convenient locking connection, the strength of the coinciding part is enhanced, the height of the cross beam is adjusted correspondingly, and after the height of the cross beam is higher than the top height of the outer curtain wall, the avoidance of the cross beam and the overall decoration construction of the outer curtain wall are realized.
[0024] In a specific implementation, the adjusting pipe and the supporting pipe are located in the same vertical direction, and the adjusting pipe and the supporting pipe are cross-distributed with the positioning pipe.
[0025] The second reinforcing plate is welded at the included angle between the adjusting pipe and the supporting pipe and the positioning pipe. The overall layout is reasonable, and the overall strength meets the construction requirements.
[0026] In a specific implementation, at least two second positioning holes are arranged on the positioning pipe in a transverse direction, and a plurality of second matching holes are arranged on the cross beam in a transverse direction at equal intervals;
[0027] When any at least two second matching holes and at least two second positioning holes are one-to-one corresponding and coinciding, the positioning pipe and the cross beam are locked by a second bolt assembly penetrating the corresponding second positioning hole and the second matching hole. The positioning pipe and the cross beam are both square tubes, and are conveniently locked by the second bolt assembly. The cross beam is conveniently adjusted by extension or contraction, and the supporting pipe is fixed to stably support the first steel wire cable.
[0028] In a specific implementation, the top end of the supporting pipe is provided with a fixed pulley for supporting the middle part of the first steel wire cable. The fixed pulley is always supported on the inner side of the framework beam, and reduces wear and tear while limiting the first steel wire cable, so that the first steel wire cable maintains better strength.
[0029] In a specific implementation, the connecting pipe is fixedly connected to the first end of the cross beam; or,
[0030] The connecting pipe is slidably sleeved and lockable at the first end of the cross beam;
[0031] The upper surface of the connecting pipe is provided with an upper connecting piece, and the upper connecting piece is connected to the first end of the first steel wire cable through an upper tensioner;
[0032] The lower surface of the connecting pipe is provided with a lower connecting piece, and the lower connecting piece is connected to the first end of the second steel wire cable through a lower tensioner. The upper tensioner is used to adjust the tensile strength of the first steel wire cable, and the lower tensioner is used to adjust the tensile strength of the second steel wire cable. Meanwhile, the second steel wire cable is connected between the connecting pipe and the lower anchor plate, so that the stability of the hanging basket suspension support can be improved without affecting the normal construction of the roof project.
[0033] In a specific implementation, a plurality of second mounting holes are arranged on the lower anchor plate, and a plurality of second expansion bolt assemblies are anchored to the inner wall of the second building body. The second expansion bolt assemblies are locked and fixed to the lower anchor plate after penetrating the corresponding second mounting holes.
[0034] The first positioning wheel is connected with the second steel cable through a wire rope buckle to realize fixed connection, and the two second positioning wheels are connected with the two working steel cables through wire rope buckles to realize fixed connection. BRIEF DESCRIPTION OF DRAWINGS
[0035] Figure 1 A structure schematic diagram of a hanging type support of a hanging basket for curtain wall decoration construction is provided for the embodiment of the present application.
[0036] Figure 2 An installation schematic diagram of an upper anchoring plate is provided for the embodiment of the present application.
[0037] Figure 3 An assembly schematic diagram of a fixed sleeve is provided for the embodiment of the present application.
[0038] Figure 4 A structure schematic diagram of an upper anchoring plate is provided for the embodiment of the present application.
[0039] Figure 5 A structure schematic diagram of a fixed sleeve is provided for the embodiment of the present application.
[0040] Figure 6 A structure schematic diagram of a support frame group is provided for the embodiment of the present application.
[0041] Figure 7 A structure schematic diagram of a hanging frame group is provided for the embodiment of the present application.
[0042] Figure 8 A structure schematic diagram of a lower anchoring plate is provided for the embodiment of the present application.
[0043] REFERENCE NUMERALS:
[0044] First building body-100, upper anchoring plate-110, first mounting hole-111, first reinforcing plate-112, first expansion bolt assembly-120;
[0045] Fixed sleeve-200, first bolt assembly-210, first positioning hole-220;
[0046] Support frame group-300, adjusting pipe-310, first matching hole-320, positioning pipe-330, second positioning hole-340, support pipe-350, second reinforcing plate-360, fixed pulley-370;
[0047] Cross beam-400, second matching hole-410, connecting pipe-420, upper connecting piece-421, upper tensioner-422, lower connecting piece-423, lower tensioner-424, front hanger-430;
[0048] Gondola device-500;
[0049] First steel wire cable-600;
[0050] Second steel wire cable-700;
[0051] Working steel wire cable-800;
[0052] Second building body-900, lower anchoring plate-910, second mounting hole-920, second expansion bolt assembly-930, first positioning wheel-940, second positioning wheel-950. DETAILED DESCRIPTION
[0053] In order to make the objects, technical solutions and advantages of the present disclosure clearer, the present disclosure will be further described in detail below with reference to specific embodiments and drawings.
[0054] It should be noted that, unless otherwise defined, the technical terms or scientific terms used in one or more embodiments of the present disclosure should be understood as the general meaning understood by those skilled in the art to which the present disclosure belongs. The terms "first", "second" and the like used in one or more embodiments of the present disclosure do not represent any order, number or importance, but are only used to distinguish different components. The terms "include", "contain" and the like mean that the elements or objects before the terms cover the elements or objects listed after the terms and their equivalents, and do not exclude other elements or objects. The terms "connect" or "connected" and the like are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. The terms "upper", "lower", "left", "right" and the like only represent relative positional relationships, and when the absolute positions of the described objects change, the relative positional relationships may also change accordingly.
[0055] In order to facilitate the understanding of the hanging basket suspension support for curtain wall decoration construction provided by the embodiments of the present application, the application scenario thereof is first described. In building engineering construction, the scaffold or attached lifting frame used by the main body cannot meet the needs of the external curtain wall decoration construction. Usually, after the main structure is completed, the external scaffold or attached lifting frame is removed, and the hanging basket is used for external curtain wall decoration construction. The hanging basket system has the advantages of convenient disassembly and assembly, strong site adaptability, safety and reliability, and has been widely used in high-altitude operation of building engineering. The traditional hanging basket rear support installs a counterweight, and the rear support counterweight occupies a large roof space, affecting the construction of the roof project. However, a higher framework beam (the framework beam is more than 1.5m above the parapet wall) cannot meet the installation requirements of the traditional hanging basket front and rear supports. At present, there are more buildings with one or more layers of framework beams in the design of public building roofs, and the height of the external curtain wall is higher than the top layer of framework beam by 30cm-48cm. The curtain wall decoration can be divided into glass curtain wall, metal sheet curtain wall, stone plate curtain wall and other types. In the process of decoration construction, when the existing suspension support without counterweight is selected, the suspension main beam of the suspension support is almost horizontally extended along the top of the framework beam. The extended suspension main beam of the suspension support interferes with the external curtain wall decoration construction, cannot carry out the overall construction of the external curtain wall decoration, and cannot be flexibly adjusted according to different heights. The stability of the rubber support used for support is poor, and there is a great safety hazard. At the same time, the installation plate for anchoring connection in the existing suspension support is a flat plate, and the connection stability and stress performance are poor. Moreover, the existing suspension support without counterweight adopts a split type suspension main beam and column. In the process of extending and adjusting the position of the suspension main beam, the positions of the suspension main beam and the installation plate and the positions of the suspension main beam and the column need to be adjusted synchronously to ensure the stable reinforcement of the steel wire rope, thereby increasing the construction complexity and not meeting the safety and convenience construction standard. In view of this, the present application provides a hanging basket suspension support for curtain wall decoration construction, which is convenient to disassemble and assemble, has good firmness, can meet the flexible installation of various different heights on the framework beam, and greatly improves the overall safety performance. Under the premise of not affecting the normal construction of the roof project, the external curtain wall is avoided and the overall decoration construction is realized.
[0056] Reference Figure 1 The hanging basket suspension support for curtain wall decoration construction provided by the embodiments of the present application comprises two adjustment frame groups anchored and connected to the first building body 100 and the second building body 900. In the process of external curtain wall decoration, multiple adjustment frame groups can be installed, and every two adjustment frame groups are connected to the hanging basket device 500 through four working steel wire ropes 800, so as to achieve stable safety performance.
[0057] The first building body 100 in the application refers to the frame beam located at the topmost layer, and the second building body 900 refers to the parapet or beam higher than the roof. The adjusting frame group is connected to the first building body 100 and the second building body 900 through anchoring, can be adapted to frame beams of different heights for positioning and installation, has strong adaptability and stability, meets the suspension installation requirement, does not occupy the roof space, thereby providing a stable and reliable hanging basket suspension support under the premise of not affecting the normal construction of the roof, thereby meeting the external curtain wall decoration construction requirement higher than the top end of the frame beam by 5cm-50cm. It needs to be specifically explained that in the rare case that the external curtain wall exceeds the frame beam by more than 50cm, the hanging basket suspension support of the application is not suitable for use, and the safety needs to be ensured by replacing the reinforcing fittings.
[0058] Continuing to refer to Figure 2 and Figure 3 shown, each adjusting frame group is connected to the first building body 100 through the upper anchoring plate 110, and the upper anchoring plate 110 is fixedly connected to the first building body 100, thereby ensuring the stability of the top. In the application, in order to ensure the stability and multi-aspect stress performance of the upper anchoring plate 110, in combination with Figure 4 shown, the upper anchoring plate 110 is an L-shaped plate body buckled to the inner side corner of the first building body 100, and the plane and vertical plane of the L-shaped plate body are provided with a plurality of first mounting holes 111; the inner wall and top plane of the first building body 100 are anchored with a plurality of first expansion bolt assemblies 120, and the plurality of first expansion bolt assemblies 120 are locked and fixed to the upper anchoring plate 110 after passing through the corresponding first mounting holes 111. The L-shaped plate body is used as the upper anchoring plate 110, and the top and inner wall of the frame beam are anchored and connected, thereby enhancing the stability and multi-aspect stress performance. The first expansion bolt assembly 120 adopts a chemical expansion bolt or a mechanical expansion bolt, which is subjected to pull-out detection by a detection unit after being anchored into the first building body 100, and the upper anchoring plate 110 is installed after the detection is qualified. The upper anchoring plate 110 of the L-shaped plate body is fixed on the building body 100 in a cladding mode through the plurality of first expansion bolt assemblies 120, realizes the stable connection and fixation of the whole hanging basket suspension support and the building body 100, avoids the occurrence of unilateral oblique pressure, improves the overall connection strength, makes the hanging basket suspension support have reliable fixation effect when subjected to multi-aspect force in construction and use, and meets the safety construction standard.
[0059] In addition, as Figure 5Each adjustment frame assembly shown in the figure includes a fixed sleeve 200 fixedly connected to the upper anchor plate 110; the fixed sleeve 200 is welded to the vertical surface of the L-shaped plate, and a first reinforcement plate 112 is welded to the connection between the fixed sleeve 200 and the L-shaped plate. The use of square tubes as the fixed sleeve 200 increases the welding connection area and ensures overall firmness and reliable performance. The lower half of the fixed sleeve 200 is welded to the upper anchor plate 110, and the upper half of the fixed sleeve 200 extends above the upper anchor plate 110 and is provided with a plurality of first positioning holes 220 at intervals. At the same time, the first reinforcement plate 112 is welded to enhance the connection strength between the fixed sleeve 200 and the upper anchor plate 110. The upper anchor plate 110 and the fixed sleeve 200 are prefabricated and welded together to form an integrated structure.
[0060] When specifically implementing the decoration construction of the exterior curtain wall at different heights above the first building body 100, each adjustment frame group also includes a support frame group 300 that slides vertically and can be locked to be connected to the fixed sleeve 200, and a suspension frame group that slides horizontally and can be locked to be connected to the support frame group 300; after the support frame group 300 adjusts the connection height with the fixed sleeve 200, the height of the suspension frame group is changed, thereby hanging the hanging basket device 500 across the top of the exterior curtain wall, without the need to synchronously adjust the position of the suspension main beam and the mounting plate, as well as the position of the suspension main beam and the column, thereby realizing flexible adjustment of the construction position and meeting the safety and convenience construction standards.
[0061] Specific, combined Figure 6 As shown in FIG, the lower portion of the support frame assembly 300 includes an adjustment tube 310 that mates with the fixed sleeve 200. A positioning tube 330 that mates laterally with the suspension frame assembly is connected to the top of the adjustment tube 310. A support tube 350 is vertically connected above the positioning tube 330. The fixed sleeve 200 is provided with a plurality of first positioning holes 220 along its height, and the adjustment tube 310 is provided with a plurality of first matching holes 320 along its height. When at least two of the first matching holes 320 align with at least two of the first positioning holes 220, the fixed sleeve 200 and the adjustment tube 310 are locked together by a first bolt assembly 210 that penetrates the corresponding first positioning holes 220 and first matching holes 320. The use of the first bolt assembly 210 facilitates a tightening connection, enhances the strength of the overlapping portion, and allows for corresponding adjustment of the height of the crossbeam 400. When the crossbeam 400 is higher than the top height of the exterior curtain wall, the crossbeam 400 can be avoided, allowing for comprehensive decorative construction of the exterior curtain wall.
[0062] The adjustment tube 310 and support tube 350 are located in the same vertical direction, and are arranged crosswise with the positioning tube 330. Second reinforcement plates 360 are welded to the adjustment tube 310 and the angles between the support tube 350 and the positioning tube 330. The overall layout is reasonable, and the overall strength meets construction requirements.
[0063] Reference is made to Figure 7 The suspension frame set comprises a cross beam 400 which is sleeved and lockable in the positioning pipe 330; the first end of the cross beam 400 is equipped with a connecting pipe 420, and the second end of the cross beam 400 is equipped with a front hanger head 430; at least two second positioning holes 340 are provided on the positioning pipe 330 in a transverse direction, and a plurality of second matching holes 410 are provided on the cross beam 400 in a transverse direction at equal intervals; when any at least two second matching holes 410 and at least two second positioning holes 340 correspond and coincide with each other, the positioning pipe 330 and the cross beam 400 are locked by a second bolt assembly penetrating the corresponding and coinciding second positioning hole 340 and the second matching hole 410. The positioning pipe 330 and the cross beam 400 are both square pipes, and are conveniently locked by the second bolt assembly. The cross beam 400 is extended or contracted to achieve convenient adjustment, and the support pipe 350 is fixed to stably support the first steel wire cable 600.
[0064] As can be seen from the above structure, when the top of the outer curtain wall is higher than the first building body 100 by 40 cm, the suspension main beam of the existing suspension support cannot be extended to span over, which interferes with the decoration construction of the outer curtain wall. In the present application, the height between the adjusting pipe 310 and the fixed sleeve pipe 200 can be adjusted and locked. The adjusting pipe 310 is a square pipe which is connected to the fixed sleeve pipe 200 by insertion. After the hole positions coincide, and when the height of the support cross beam 400 is higher than the first building body 100 by 41 cm, the first bolt assembly 210 is locked to achieve stable connection between the two, and the basket device 500 can be fully used to meet the decoration construction requirements.
[0065] Reference is made to Figure 1 、 Figure 7 and Figure 8 In order to enhance the stability and overall strength of the basket suspension support, each adjusting frame set is connected to the second building body 900 by a lower anchoring plate 910. The lower anchoring plate 910 is provided with a plurality of second mounting holes 920, and the inner wall of the second building body 900 is anchored with a plurality of second expansion bolt assemblies 930. The second expansion bolt assemblies 930 pass through the corresponding second mounting holes 920 to lock and fix the lower anchoring plate 910. The second expansion bolt assemblies 930 are chemical expansion bolts or mechanical expansion bolts, which are subjected to pull-out detection after being anchored in the second building body 900. After the detection is qualified, the lower anchoring plate 910 is installed.
[0066] In addition, each adjusting frame group further comprises a first steel wire cable 600, a second steel wire cable 700, and a working steel wire cable 800 for connecting the hanging basket device 500; the support pipe 350 supports the middle bulge of the first steel wire cable 600, the first end of the first steel wire cable 600 is connected to the connecting pipe 420 in a slanting manner, and the second end of the first steel wire cable 600 is connected to the front lifting head 430 in a slanting manner; the first end of the second steel wire cable 700 is connected to the connecting pipe 420 in a slanting manner, and the second end of the second steel wire cable 700 is connected to the lower anchoring plate 910 in a slanting manner; the working steel wire cable 800 is lapped on the front lifting head 430, and the end of the working steel wire cable 800 away from the hanging basket device 500 is positioned and connected to the lower anchoring plate 910. Each adjusting frame group is equipped with two working steel wire cables 800, one end of the working steel wire cable is fixedly connected to the two second positioning wheels 950 on the lower anchoring plate 910, and the two working steel wire cables 800 are connected to the same end of the hanging basket device 500; or, the two working steel wire cables 800 are cross-connected to the two ends of the hanging basket device 500, so as to improve the safety. The working steel wire cable 800 is extended to the wheel group of the front lifting head 430 after passing through the wheel group of the connecting pipe 420, and then is connected to the hanging basket device 500 vertically downward, and an anti-wear pad layer can be additionally installed at the contact position of the working steel wire cable 800 and the first end of the cross beam 400. Of course, in other embodiments of the present application, one end of the working steel wire cable is fixedly connected to the two second positioning wheels 950 on the lower anchoring plate 910, and a wheel group is additionally installed on the cross beam 400, so that the working steel wire cable extends to the wheel group of the front lifting head 430 after passing through the wheel group of the cross beam 400, thereby realizing stable connection.
[0067] Meanwhile, in order to enhance the stability of the suspension support, the upper surface of the connecting pipe 420 is equipped with an upper connecting piece 421, the upper connecting piece 421 is connected to the first end of the first steel wire cable 600 through an upper tensioner 422; the lower surface of the connecting pipe 420 is equipped with a lower connecting piece 423, the lower connecting piece 423 is connected to the first end of the second steel wire cable 700 through a lower tensioner 424. The upper tensioner 422 is used to adjust the tensile strength of the first steel wire cable 600, and the lower tensioner 424 is used to adjust the tensile strength of the second steel wire cable 700, and meanwhile, the second steel wire cable 700 is connected between the connecting pipe 420 and the lower anchoring plate 910, so that the stability of the hanging basket suspension support can be improved without affecting the normal construction of the roof project.
[0068] The connecting pipe 420 is fixedly connected to the first end of the cross beam 400; or, the connecting pipe 420 is slidably sleeved and lockable at the first end of the cross beam 400; the connecting pipe 420 is also a square pipe, which is sleeved at the first end of the cross beam 400 and is locked in position through the cooperation of bolts and corresponding second matching holes 410.
[0069] The top end of the support pipe 350 is equipped with a fixed pulley 370 for supporting the middle bulge of the first steel wire cable 600. The fixed pulley 370 is always guaranteed to support the inside of the framework beam, and the fixed pulley 370 reduces wear and tear while limiting the direction of the first steel wire cable 600, which maintains better strength.
[0070] The lower anchor plate 910 is fixedly equipped with a first positioning wheel 940 for positioning the second end of the second steel wire cable 700, and two second positioning wheels 950 for positioning the end of the working steel wire cable 800 away from the hanging basket device 500. The first positioning wheel 940 is connected to the second steel wire cable 700 through a wire rope buckle to achieve fixed connection; the two second positioning wheels 950 are connected to the two working steel wire cables 800 through wire rope buckles to achieve fixed connection.
[0071] In this application, the upper anchor plate 110 is anchored and connected to the top framework beam, and the lower anchor plate 910 is anchored and connected to the parapet wall or beam, so that flexible installation can be achieved for framework beams of different heights, and the overall stability is reliable; by adjusting the pipe 310 to slide along the fixed sleeve pipe 200 and lock, the height of the cross beam 400 is adjusted to avoid the outer curtain wall construction higher than the framework beam, and the overall decoration construction of the outer curtain wall is realized; by sliding and locking the cross beam 400 in the positioning pipe 330, the cross beam 400 is extended or retracted in a convenient adjustment mode, the support pipe 350 is stable in position, and the stability of the first steel wire cable 600 is maintained; the second steel wire cable 700 is connected between the connecting pipe fitting 420 and the lower anchor plate 910 in a diagonal manner, thereby enhancing the firmness and stability and eliminating safety hazards; the hanging basket suspension support is convenient to disassemble and assemble, has good firmness, can meet the flexible installation of various heights on the framework beam, and improves the overall safety performance. Under the premise of not affecting the normal construction of the roof project, the outer curtain wall is avoided and the overall decoration construction is realized.
[0072] Those skilled in the art will understand that the above discussion of any embodiment is only exemplary and is not intended to limit the scope of the disclosure (including claims) to these examples; under the idea of the present disclosure, the technical features of the above embodiments or different embodiments can also be combined, the steps can be implemented in any order, and there are many other changes of different aspects of one or more embodiments of the present disclosure as described above. In order to be brief, they are not provided in detail.
[0073] In addition, for simplicity and clarity of illustration, power / ground connections to some of the elements in the figures can or can not be shown. Further, as commonly has occurred in the art, where, for purposes of clarification, an illustrative block diagram has been utilized in this specification, the illustration has been simplified considerably. In actual implementations, there can be additional or fewer elements than shown in the figures, some of which can be combined with certain illustrated elements or eliminated from the described implementation. Further, the detailed description includes specific details for the purpose of providing an understanding of the described implementations. These specific details are not to be construed as limiting the scope of the described implementations. Rather, the described implementations include all modifications, equivalents, combinations, permutations, and the like of the principles and features described herein within the scope of the described implementations.
[0074] It is intended that all such additional, modified, equivalent, and alternative implementations also be included within the scope of the present disclosure. Moreover, it is intended that the disclosure be taken as including all such implementations and their equivalents.
Claims
1. A hanging type support for curtain wall decoration construction, comprising two adjusting frame groups anchored to a first building body and a second building body, each of the adjusting frame groups being connected to the first building body through an upper anchor plate and connected to the second building body through a lower anchor plate, characterized in that each of the adjusting frame groups comprises a fixed sleeve connected to the upper anchor plate, a support frame group vertically slidingly and lockably connected to the fixed sleeve, and a hanging frame group transversely slidingly and lockably connected to the support frame group, wherein the lower part of the support frame group is provided with an adjusting tube matched with the fixed sleeve, the top of the adjusting tube is connected with a positioning tube matched with the hanging frame group in transverse direction, and the upper part of the positioning tube is vertically connected with a support tube; the hanging frame group comprises a cross beam slidingly and lockably sleeved in the positioning tube, the first end of the cross beam is provided with a connecting pipe, and the second end of the cross beam is provided with a front lifting head; each of the adjusting frame groups further comprises a first steel wire cable, a second steel wire cable, and a working steel wire cable for connecting a hanging basket device; the support tube supports the middle bulge of the first steel wire cable, the first end of the first steel wire cable is connected to the connecting pipe in an oblique manner, and the second end of the first steel wire cable is connected to the front lifting head in an oblique manner; the first end of the second steel wire cable is connected to the connecting pipe in an oblique manner, and the second end of the second steel wire cable is connected to the lower anchor plate in an oblique manner; the working steel wire cable is connected to the front lifting head in an overlapping manner, and the end of the working steel wire cable away from the hanging basket device is connected to the lower anchor plate; the two ends of the hanging basket device are connected to the working steel wire cables of the two adjusting frame groups; the upper anchor plate is an L-shaped plate body buckled to the inner side corner of the first building body, the plane and the vertical plane of the L-shaped plate body are provided with a plurality of first mounting holes; the inner wall and the top plane of the first building body are anchored with a plurality of first expansion bolt assemblies, and the first expansion bolt assemblies are locked and fixed to the upper anchor plate after penetrating through the corresponding first mounting holes; the fixed sleeve is welded to the vertical plane of the L-shaped plate body, and the connection between the fixed sleeve and the L-shaped plate body is welded with a first reinforcing plate; the fixed sleeve is provided with a plurality of first positioning holes in the height direction, and the adjusting tube is provided with a plurality of first matching holes in the height direction; when any at least two first matching holes and at least two first positioning holes one-to-one correspond and coincide, the first bolt assembly is used to lock the fixed sleeve and the adjusting tube through the corresponding and coinciding first positioning holes and first matching holes; the adjusting tube and the support tube are located in the same vertical direction, and the adjusting tube and the support tube are cross-distributed with the positioning tube; the second reinforcing plate is welded at the included angle between the adjusting tube, the support tube and the positioning tube; the positioning tube is provided with at least two second positioning holes spaced apart in the transverse direction, and the cross beam is provided with a plurality of second matching holes spaced apart in the transverse direction. 2. The hanging type support for a curtain wall decoration work according to claim 1, wherein 3. The hanging type support for a curtain wall decoration work according to claim 1, wherein 4. The hanging type support for a curtain wall decoration work according to claim 3, wherein 5. The hanging type support for a curtain wall decoration work according to claim 4, wherein 6. The hanging type support for a curtain wall decoration work according to claim 5, wherein 7. The hanging type support for a curtain wall decoration work according to claim 6, wherein When any at least two second matching holes and at least two second positioning holes are one-to-one corresponding and coinciding, the positioning tube and the cross beam are locked by a second bolt assembly through the corresponding and coinciding second positioning holes and second matching holes.
8. The hanging type support for a curtain wall decoration work according to claim 1, wherein The top end of the support tube is equipped with a fixed pulley for supporting the middle part of the first steel cable.
9. The hanging type support for a curtain wall decoration work according to claim 1, wherein The connecting pipe is fixedly connected to the first end of the cross beam; or, The connecting pipe is slidingly sleeved and lockable at the first end of the cross beam; The upper surface of the connecting pipe is equipped with an upper connecting piece, and the upper connecting piece is connected to the first end of the first steel cable through an upper tensioner. The lower surface of the connecting pipe is equipped with a lower connecting piece, and the lower connecting piece is connected to the first end of the second steel cable through a lower tensioner.
10. The hanging type support for a curtain wall decoration work according to claim 9, wherein A plurality of second mounting holes are formed in the lower anchor plate, and a plurality of second expansion bolt assemblies are anchored to the inner wall of the second building body, and the plurality of second expansion bolt assemblies are locked and fixed to the lower anchor plate after penetrating through the corresponding second mounting holes. The lower anchor plate is fixedly equipped with a first positioning wheel for positioning the second end of the second steel cable, and a second positioning wheel for positioning the end of the working steel cable away from the hanging basket device.