Trestle limb stand column positioner
By designing a locator for the edge columns of the trestle and using a clamping assembly and a hanging hammer assembly to ensure the installation position and verticality of the columns, the problems of low construction efficiency and manual influence in the existing technology are solved, and efficient and accurate column installation is achieved.
Patent Information
- Application Number
- CN202423094701.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-16
- Publication Date
- 2025-10-24
- Estimated Expiration
- 2034-12-16
AI Technical Summary
In the prior art, it is difficult to simultaneously determine the installation position and verticality of the pier edge columns during installation, resulting in low construction efficiency and a significant impact on the effect of manual labor.
A trestle edge column locator is designed, which includes a base assembly, a positioning assembly, a clamping assembly, a hanging hammer assembly and a height adjustment assembly. The accuracy and verticality of the column installation position are ensured by the cooperation of the positioning assembly and the hanging hammer assembly. Multiple adjustment components are used to adapt to different trestles and column sizes.
The high efficiency and positioning accuracy of guardrail installation are achieved, the consistency of edge protection line shape is ensured, and the construction efficiency and construction effect are improved.
Smart Images

Figure CN223470659U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to the technical field of guardrail construction auxiliary tool, specifically relates to a trestle edge column positioner. BACKGROUND
[0002] Trestle is very widely used in the engineering construction process, and is a temporary bridge facility built for transporting materials, equipment and personnel. The trestle is usually built by steel or prefabricated concrete components, and has strong bearing capacity and stability. Because steel has good strength, toughness and recyclability, the trestle deck is usually made of steel. In order to protect the safety of personnel and equipment, a series of protective columns are usually set at the edge of the steel trestle.
[0003] In the installation of the traditional trestle edge protective column, the construction personnel first need to determine the installation position of the column by relying on construction experience or through the method of pulling a line, then vertically erect the column on the bridge deck, and then weld the column and the bridge deck. On the one hand, during the process of determining the installation position of the column, even if the distance of the column from the edge of the trestle is determined by the method of pulling a line, errors are likely to occur due to manual reasons, resulting in distortion of the overall line shape of the edge protection and poor appearance of the bridge deck. On the other hand, during the welding period, other workers need to maintain the vertical state of the column, which is easily affected by manual or construction environment, resulting in poor verticality of the column installation, and phenomena such as non-uniform height of the edge protection top surface and height not meeting the requirements, and low efficiency.
[0004] In order to standardize the installation of the trestle edge column, a straight-buried guardrail column welding auxiliary positioning device is disclosed in patent 202223339383.4, which is provided with a horizontal base and a vertical positioning rod in the middle of the horizontal base. When in use, the guardrail column is only needed to be fitted with the positioning rod and fixed, so that the vertical state between the guardrail column and the concrete foundation can be maintained. However, the implementation of the technical scheme of the patent is premised on that the horizontal base is completely fitted with the concrete foundation. If the device is applied in the installation of the trestle edge column, the undulations of different areas of the trestle plane will make the positioning rod not vertical to the ground. During the long-distance installation of the guardrail, due to the lack of reference for the verticality, the verticality of the installed guardrail will have a large deviation. Moreover, if the device is applied in the installation of the trestle edge column, the distance between the column and the edge of the trestle cannot be directly determined, and the construction efficiency is low. UTILITY MODEL CONTENTS
[0005] The utility model is to overcome the defects in the prior art that it is difficult to determine the installation position of the column and whether the column is vertical at the same time through the existing device during the installation of the trestle edge column, the construction efficiency is low, and the construction effect is greatly affected by manual work, and provides a trestle edge column positioner to overcome the above defects.
[0006] To achieve the above object, the utility model discloses the following technical scheme realizes:
[0007] A bridge edge column positioner, comprising:
[0008] Including base assembly, one side extends the clamping assembly for clamping the trestle, the clamping assembly is reserved the installation space of placing the edge column, and the main body column is arranged on the base assembly and is perpendicular to the base assembly;
[0009] The main body column is provided with two or more than two clamping assemblies for clamping the edge column on one side of the installation space, and is provided with a plumb line assembly on the side away from the installation space.
[0010] Because the trestle is used for the construction of water building, such as bridge, wharf, because there is no obstacle around the shelter, is easily influenced by environmental factors, thus the construction on the trestle wants to improve the construction efficiency under the premise of guaranteeing the construction effect.After the trestle is installed by large-scale machinery, in order to guarantee the safety of workers and equipment on the trestle, manual installation of the edge column is usually carried out on the edge of the bridge, first needs to determine the distance of the column distance from the edge of the bridge through the guy line, then every interval distance column is placed vertically on the bridge and is welded.This period, because of the influence of the wind on the bridge, the guy line is easy to produce deviation, and when the column is vertically installed, it is also difficult to guarantee the construction effect by manual determination.
[0011] Therefore, the utility model sets up a base assembly as the basis of the stable placement of the positioner on the bridge, and in practice, four square steels can be welded to form a rectangular structure as the base assembly. The clamping assembly for clamping the trestle is extended on one side of the base assembly, and the distance between the positioner and the edge of the trestle is maintained by clamping the edge of the trestle. The utility model vertically sets the main body column on the base assembly, which is used as the support of the clamping assembly and the plumb line assembly. The main body column is provided with two or more than two clamping assemblies on one side of the clamping assembly for fixing the column, and when the two or more than two clamping assemblies extend the same distance, the parallelism of the edge column and the main body column can be realized. The plumb line assembly is arranged on the main body column opposite to the clamping assembly. Because the overall quality of the plumb line assembly is large, it is arranged above the base assembly to ensure the stability of the positioner. The verticality of the main body column can be ensured through the plumb line assembly, and the installed edge column is also vertical through the multiple clamping assemblies.
[0012] As a preferred, the base assembly is provided with a height adjusting assembly. When the body column is found not vertical by the plumb bob assembly, it is inconvenient to adjust the height of the base assembly by means of a gasket or the like, so the height adjusting assembly is arranged on the side of the base assembly in contact with the trestle, facilitating the adjustment of the positioner. In practice, the height adjusting assembly can be arranged only on the side away from the body column, so as to adjust the inclination of the whole device by adjusting the single height adjusting assembly.
[0013] As a further preferred, the height adjusting assembly comprises an adjusting screw bolted to the base assembly, and an adjusting seat fixedly connected to the adjusting screw bolt. In order to facilitate the installation of the device, the height of the base assembly is adjusted by means of the adjusting screw bolt, and the adjusting seat is arranged at the bottom of the adjusting screw bolt, so that the overall structure is more stable after the height is adjusted.
[0014] As a preferred, the clamping assembly comprises two or more extension rods fixed to the base assembly, and the extension rods are provided with hooks at the ends away from the base assembly, for clamping the edges of the trestle.
[0015] As a preferred, the clamping assembly comprises a gripper for clamping the edge column.
[0016] As a further preferred, the clamping assembly comprises a positioning tube fixed to the body column, and the positioning tube is sleeved with the gripper.
[0017] As a further preferred, the positioning tube is provided with a positioning screw bolt capable of penetrating the wall of the positioning tube and contacting the gripper. When the positioning screw bolt is screwed in, the positioning screw bolt presses the gripper in the positioning tube, so as to fix the distance of the gripper.
[0018] As a further preferred, the gripper is further provided with an adjusting device for adjusting the clamping range. In order to adapt to different types of edge columns, an adjusting device is arranged on the gripper, and in practice, the structure of a clamp can be adopted, and two clamp arms are connected in series by a bolt, so that the two clamp arms can adjust the clamping range by rotating.
[0019] As a preferred, the bottom of the base assembly is provided with an anti-skid pad.
[0020] As a preferred, the plumb bob assembly comprises a connecting rod fixed to the body column, and a bob head connected to the connecting rod by a plumb bob line.
[0021] Therefore, the utility model has the following beneficial effects:
[0022] (1) The utility model discloses the cooperation of the clamping assembly and the plumb bob assembly, which facilitates the positioning of the installation position of the edge column, provides a reference for whether the edge column is vertical, and realizes the efficiency, position accuracy and overall edge protection line consistency of the guardrail installation in practice.
[0023] (2) The utility model discloses through the optimization scheme multiple adjusting assembly, make the positioner of the utility model can adapt to multiple stack bridge deck and the installation of multiple size stand column.
[0024] (3) The utility model discloses simple structure, and the operation is quick, and the device main part can be welded by square steel, and the cost is lower, is favorable in the production practice promotes the application. BRIEF DESCRIPTION OF DRAWINGS
[0025] Figure 1 It is the positioner structure schematic view of the utility model embodiment 1.
[0026] Figure 2 It is the positioner side view of the utility model embodiment 2.
[0027] Figure 3 It is the grab and clamp of the utility model embodiment 2.
[0028] Figure 4 It is the grab and clamp installation schematic view of the utility model embodiment 2.
[0029] In the drawing: base assembly 1;Installation space 2;Main column 3;Antiskid pad 4;Clamping component 10;Extension rod 11;Hook 12;Clamping assembly 20;Grab and clamp 21;Positioning tube 22;Positioning bolt 23;Adjusting device 24;Plummet assembly 30;Connecting rod 31;Plummet line 32;Hammer head 33;Height adjusting assembly 40;Adjusting screw rod 41;Adjusting seat 42. DETAILED DESCRIPTION
[0030] The utility model will be further described below in conjunction with the drawings of specification and specific embodiment. The person skilled in the art will be able to realize the utility model based on these instructions. In addition, the embodiment of the utility model involved in the following description is generally only a part of the embodiment of the utility model, not all embodiments. Therefore, based on the embodiment in the utility model, all other embodiments obtained by the person skilled in the art without making creative work should belong to the scope of the utility model protection.
[0031] Embodiment 1
[0032] As Figure 1As shown, the edge column positioner of the present embodiment includes a rectangular base assembly 1 welded by four square steels, two extension rods 11 welded on one side of the base assembly 1, the base assembly 1 and the extension rods 11 are in contact with the bridge deck to stabilize the positioner when in use, the extension rods 11 are bent 90° downward at the end away from the base assembly 1 to form hooks 12 for lapping on the edge of the bridge deck, and the installation space 2 for installing the edge column is formed between the two extension rods 11. A main column 3 is welded on the square steel of the base assembly 1 away from the extension rods 11, perpendicular to the base assembly. Two positioning tubes 22 are pre-installed on one side of the main column 3 in the installation space 2, the size of the clamping assembly 20 is determined according to the installed edge column, and a part of the clamping assembly 20 is sleeved in the positioning tube 22 and fixed with the positioning tube 22 through the pre-installed positioning bolt 23 on the positioning tube 22. A connecting rod 31 is pre-installed on the upper end of the main column 3 on one side of the base assembly 1, and a conical hammer head 33 is connected through a plumb line 32, so that the hammer head 33 is opposite to the center of the base assembly 1. A height adjustment assembly 40 is arranged on the square steel of the base assembly 1 away from the extension rods 11, including an adjustment screw 41 capable of penetrating through the base assembly 1, and an adjustment seat 42 welded on the side of the adjustment screw 41 in contact with the bridge deck.
[0033] The implementation of the embodiment is as follows:
[0034] When installing the edge column, the distance between the edge column and the edge of the bridge deck is determined in advance, the clamping assembly 20 is inserted into the positioning tube 22 at different distances and fixed by tightening the positioning bolt 23, and the distance inserted by the two clamping assemblies 21 is required to be consistent, and no adjustment is required for subsequent installation. First, the two hooks 12 are clamped on the edge of the bridge deck, at this time the extension rods 11 and the base assembly 1 are stably placed on the bridge deck, the hammer head 33 is pulled tight under the action of gravity, and whether the plumb line 32 is parallel to the main column 3 is observed, if not, the adjustment screw 41 is adjusted until parallel. Then the edge column is placed in the clamping assembly 21, and the column is tightly attached to the two clamping assemblies 21. Finally, the joint between the edge column and the bridge deck is welded, the installation of the column is completed, and the other columns are installed by repeating the above steps.
[0035] Embodiment 2
[0036] As Figures 2-4The stack edge column positioner of the embodiment comprises a rectangular base assembly 1 welded by four square steels, two extension rods 11 welded on one side of the base assembly 1, and anti-skid pads 4 attached to the bottom of the base assembly 1. The anti-skid pads 4 and the extension rods 11 are in contact with the stack bridge surface to stabilize the positioner. The extension rods 11 are bent 90° at the end away from the base assembly 1 to form hooks 12 for lapping on the edge of the stack bridge. The installation space 2 for the edge column is formed between the two extension rods 11. A main column 3 is welded on the square steel of the base assembly 1 away from the extension rods 11. Two positioning tubes 22 are arranged on one side of the main column 3 in the installation space 2. Two clamping assemblies 20 are arranged in the positioning tubes 22. One part of the clamping assembly 20 is sleeved in the positioning tube 22 and is fixed with the positioning tube 22 through the positioning bolt 23 pre-installed on the positioning tube 22. The clamping assembly 20 is provided with an adjusting device 24. A connecting rod 31 is arranged on the upper end of the main column 3 away from the base assembly 1. A conical hammer head 33 is connected to the connecting rod 31 through a lifting line 32, so that the hammer head 33 is opposite to the center of the base assembly 1. An adjusting screw 41 is arranged on the square steel of the base assembly 1 away from the extension rods 11. The adjusting screw 41 is welded with an adjusting seat 42 on the side in contact with the stack bridge surface. Figure 3 The clamping assembly 20 is sleeved in the positioning tube 22. Figure 4 The clamping assembly 20 is sleeved in the positioning tube 22.
[0037] The use process of the embodiment is as follows:
[0038] When the edge column is installed, the distance between the edge column and the edge of the stack bridge is determined in advance. The clamping assembly 20 is inserted into the positioning tube 22 at different distances and is fixed through the tightening of the positioning bolt 23. The distance inserted by the two clamping assemblies 20 should be consistent. According to the different sizes of the edge column, the clamping range of the clamping assembly 20 is adjusted and the adjusting device 24 is tightened. The subsequent installation does not need to adjust the above device. First, the two hooks 12 are clamped on the edge of the stack bridge. Since the anti-skid pad 4 is thin, the extension rod 11 and the anti-skid pad 4 are stably placed on the stack bridge surface. The hammer head 33 is pulled tight under the action of gravity. Whether the lifting line 32 is parallel to the main column 3 is observed. If not, the adjusting screw 41 is adjusted until it is parallel. Then the edge column is placed in the clamping assembly 20, and the column is tightly attached to the two clamping assemblies 20. Finally, the joint between the edge column and the stack bridge surface is welded, the installation of the column is completed, and the other columns are installed by repeating the above steps.
[0039] The above embodiment only describes the preferred mode of the utility model, and does not limit the scope of the utility model. Without departing from the design spirit of the utility model, various modifications and improvements to the technical solution of the utility model made by those skilled in the art shall fall within the protection scope determined by the claims of the utility model.
Claims
1. A trestle edge post positioner characterized by: Including base assembly (1), one side of base assembly (1) extends out for clamping wharf clamping position assembly (10), the clamping position assembly (10) reserves the installation space (2) for placing the edge column; The base assembly (1) is provided with a main column (3) perpendicular to the base assembly (1) on the base assembly (1); The main column (3) is provided with two or more clamping assemblies (20) for clamping the edge column on one side of the installation space (2); The main column (3) is provided with a weight assembly (30) away from the installation space (2) on one side.
2. A wharf edge post locator according to claim 1, wherein: The base assembly (1) is provided with a height adjusting assembly (40) at the bottom.
3. A wharf edge post locator according to claim 2, wherein: The height adjusting assembly (40) comprises an adjusting screw (41) bolted with the base assembly (1), and an adjusting seat (42) fixedly connected with the adjusting screw (41).
4. A pier edge post positioner according to claim 1, wherein: The clamping position assembly (10) comprises two or more extension rods (11) fixed with the base assembly (1), and the extension rod (11) is provided with a hook (12) for clamping the edge of the wharf away from the base assembly (1).
5. A pier edge post positioner according to claim 1, wherein: The clamping assembly (20) comprises a grab (21) for clamping the edge column.
6. A wharf edge post locator according to claim 5 wherein: The clamping assembly (20) comprises a positioning tube (22) fixed on the main column (3), and the positioning tube (22) is sleeved with the grab (21).
7. A wharf edge post locator according to claim 6 wherein: The positioning tube (22) is provided with a positioning bolt (23) capable of penetrating the wall of the positioning tube (22) and contacting the grab (21).
8. A pier edge column positioner according to any one of claims 5-7, wherein: The grab (21) is also provided with an adjusting device (24) for adjusting the clamping range.
9. A pier edge post positioner according to claim 1, wherein: The base assembly (1) is provided with a non-slip pad (4) at the bottom.
10. A pier edge post positioner according to claim 1, wherein: The weight assembly (30) comprises a connecting rod (31) fixed on the main column (3), and a hammer head (33) connected with the connecting rod (31) through a weight line (32).
Citation Information
Patent Citations
Auxiliary positioning device for welding of direct-buried guardrail stand column
CN218757173U