Garbage bin control room observation window mounting structure

The combination structure of cement filling layer, U-shaped fiberglass mesh and grout layer solves the sealing problem during the installation of the observation window of the garbage bin, ensuring that garbage odor does not leak out, and improving installation efficiency and sealing effect.

CN223508927UActive Publication Date: 2025-11-04THE FIRST CONSTR ENG COMPANY LTD OF CHINA CONSTR SECOND ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423099509.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-16
Publication Date
2025-11-04
Estimated Expiration
2034-12-16

AI Technical Summary

Technical Problem

In existing technologies, the observation window of the waste storage control room is difficult to seal effectively during installation, causing the odor of waste to escape and affecting environmental quality.

Method used

The observation window is sealed by a combination of a cement filling layer, a U-shaped fiberglass mesh, and a grouting layer, and is installed through pre-embedded connectors and low-pressure injection of grouting material.

Benefits of technology

It achieves effective sealing of the observation window, prevents garbage odor from leaking out, maintains the airtightness of the garbage compartment, and improves installation efficiency and sealing performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223508927U_ABST
    Figure CN223508927U_ABST
Patent Text Reader

Abstract

The utility model provides a garbage bin control room observation window mounting structure, and relates to the technical field of garbage bin assembly. An installation groove is formed in the observation room wall, a connecting piece is pre-embedded in the installation groove, an observation window is installed in the installation groove, an operation opening is reserved in one end of the observation window, the position between the observation window and the connecting piece is filled with a cement filling layer, and the outer side of the cement filling layer is filled with a U-shaped glass fiber net. The operation opening is filled with a grouting material layer for sealing. Through cooperation of the cement filling layer, the U-shaped glass fiber net and the grouting material layer, the observation window is installed on the wall of the observation room in a sealed mode, odor in the garbage bin is prevented from leaking out, the external environment cannot be affected, the experience of visitors in the visiting process cannot be affected, and the observation window is simple in installation structure, good in installation efficiency and good in sealing performance.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of waste bin assembly, in particular to a waste bin control room observation window mounting structure. BACKGROUND

[0002] With the progress of society, more and more garbage is produced. In order to reasonably dispose of various types of garbage and prepare for the next step of processing, it is usually necessary to establish a waste bin to store garbage. The waste bin in the related art has a bin body and a ceiling, and the ceiling is supported above the bin body by columns. The bin body is used to store garbage.

[0003] The waste bin control room observation window is an important part of odor control, which is related to the environmental observation window of the visiting corridor. When installing the observation window, it needs to be effectively sealed to prevent the odor of the garbage inside the body from spreading outside, so as to ensure the airtightness and integrity of the waste bin to prevent the odor of the garbage from polluting the environment outside the waste bin. SUMMARY

[0004] In order to overcome the existing deficiencies, the present application provides a waste bin control room observation window mounting structure, which can solve the problem that the observation window needs to be effectively sealed when installing the observation window to prevent the odor of the garbage inside the body from spreading outside, so as to ensure the airtightness and integrity of the waste bin to prevent the odor of the garbage from polluting the environment outside the waste bin.

[0005] The technical solution adopted by the embodiment of the present application to solve the technical problem is: a waste bin control room observation window mounting structure, comprising an observation room wall.

[0006] An installation slot is formed in the observation room wall, a connecting piece is pre-buried in the installation slot, an observation window is installed in the installation slot, one end of the observation window is reserved as an operation port, a cement filling layer is filled between the observation window and the connecting piece, a U-shaped glass fiber mesh is filled outside the cement filling layer, and a grouting material layer is filled in the operation port for sealing.

[0007] In a specific embodiment, a grouting port is formed in the operation port, and a grouting nail is detachably inserted in the grouting port.

[0008] In a specific embodiment, the operation port is filled with weather-resistant curtain wall glue at the grouting port for sealing.

[0009] In a specific embodiment, the cement filling layer between the observation window and the connecting piece is reserved with a reserved closing opening on one side of the operation port, and both ends of the U-shaped glass fiber mesh are pressed into the inside of the two reserved closing openings.

[0010] In a specific embodiment, the length of the two reserved closing openings is 80 mm.

[0011] In a specific embodiment, the thickness of the cement filling layer is 5mm.

[0012] In a specific embodiment, the grout layer is self-leveling mortar.

[0013] In a specific embodiment, the cement filling layer is cement mortar.

[0014] The advantages of the embodiments of the present application are:

[0015] By the cooperation of the cement filling layer, the U-shaped glass fiber mesh and the grout layer, the observation window is sealed and installed on the wall of the observation room, the stench inside the garbage bin is prevented from leaking out, the environment outside is not affected, the experience of the visitors during the visit is not affected, and the installation structure of the present application is simple, the installation efficiency is good, and the sealing performance is good. BRIEF DESCRIPTION OF DRAWINGS

[0016] Figure 1 The structure schematic diagram of the garbage bin control room observation window installation structure provided for the embodiments of the present application is shown in the figure.

[0017] Figure 2 The structure schematic diagram of the completed observation window installation structure provided for the embodiments of the present application is shown in the figure.

[0018] Figure 3 The structure schematic diagram of the garbage bin control room observation window operation port grouting provided for the embodiments of the present application is shown in the figure.

[0019] Figure 4 The structure schematic diagram of the observation window operation port grouting provided for the embodiments of the present application is shown in the figure.

[0020] In the figure: 1-observation window; 2-cement filling layer; 3-U-shaped glass fiber mesh; 4-operation port; 5-annular grouting nail; 6-grout layer; 7-weatherable curtain wall glue. DETAILED DESCRIPTION

[0021] The technical solution in the embodiments of the present application is to solve the problem that the observation window 1 needs to be effectively sealed during installation to prevent the stench of the garbage inside from spreading out, so as to ensure the airtightness and integrity of the garbage bin and prevent the stench of the garbage from polluting the environment outside the garbage bin. The general idea is as follows:

[0022] Please refer to Figures 1-4 A garbage bin control room observation window installation structure, comprising an observation room wall.

[0023] Please refer to Figure 1 , Figure 2 , Figure 3 and Figure 4The installation groove is formed in the wall of the observation room in advance during construction, and the connecting piece is pre-buried in the installation groove; then the observation window 1 is fixed with the connecting piece, the surface of the wall of the observation room on both sides is sealed with the cement filling layer 2, the U-shaped glass fiber mesh 3 is pressed on the outside of the cement filling layer 2, and the grouting material layer 6 is filled in the operation port 4 to be sealed. Through the cooperation of the cement filling layer 2, the U-shaped glass fiber mesh 3 and the grouting material layer 6, the observation window 1 is sealed and installed on the wall of the observation room, the stench in the garbage bin is prevented from leaking out, the environment outside is not affected, the experience of visitors during the visit is not affected, and the installation structure of the application is simple, the installation efficiency is good, and the sealing performance is good.

[0024] The grouting port is formed in the operation port 4, and the grouting nail 5 is detachably inserted in the grouting port. The weatherable curtain wall glue 7 is filled in the operation port 4 at the grouting port to be sealed. Among them, the grouting nail 5 is inserted into the grouting port, then the grouting material layer 6 is injected by low pressure, the operation port 4 is filled, then the grouting nail 5 is pulled out, the operation port 4 is sealed by sealing the grouting port with the weatherable curtain wall glue 7, and finally the observation window 1 is installed and sealed.

[0025] The cement filling layer 2 between the observation window 1 and the connecting piece is reserved on one side of the operation port 4, and the two ends of the U-shaped glass fiber mesh 3 are pressed in the two reserved notches. The length of the two reserved notches is 80mm. The thickness of the filled cement filling layer 2 is 5mm. Among them, the two ends of the U-shaped glass fiber mesh 3 are inserted into the two reserved notches, and the sealing performance of the cement filling layer 2 is improved.

[0026] The grouting material layer 6 is self-leveling mortar. Among them, the self-leveling mortar has excellent fluidity, automatic accurate leveling of ground, good adhesion, flatness and no hollow, so as to ensure the sealing integrity of the operation port 4.

[0027] The cement filling layer 2 is 1:3 cement mortar. Among them, 1:3 cement mortar is made of 1 weight of cement and 3 weight of sand, and the water component is actually ignored, generally in the proportion of about 0.65, that is, it should be called 1:3:0.65, and the density of the cement mortar is 2000Kg / m3.

[0028] When the application is used:

[0029] During the installation of the observation window 1 in the waste storage control room, installation grooves are pre-cut in the wall of the observation room during construction, and connectors are pre-embedded inside the grooves. The observation window 1 is then fixed to the connectors. Next, the two side walls of the observation room are sealed with a cement filling layer 2. Then, a U-shaped fiberglass mesh 3 is pressed onto the outside of the cement filling layer 2. Finally, a grouting layer 6 is filled into the operating opening 4 for sealing. Through the cooperation of the cement filling layer 2, the U-shaped fiberglass mesh 3, and the grouting layer 6, the observation window 1 is sealed and installed on the wall of the observation room, preventing the leakage of odors from inside the waste storage room. This will not affect the external environment or the visitor experience. Furthermore, this application features a simple installation structure, high installation efficiency, and excellent sealing performance.

[0030] In summary, this application achieves a sealed installation of the observation window 1 on the wall of the observation room by combining the cement filling layer 2, the U-shaped fiberglass mesh 3, and the grouting layer 6, preventing the odor inside the garbage bin from leaking out, without affecting the external environment or the visitor's experience. Furthermore, this application has a simple installation structure, good installation efficiency, and good sealing performance.

[0031] Finally, it should be noted that the above embodiments are merely examples for clearly illustrating the present invention and are not intended to limit the implementation. Those skilled in the art will recognize that other variations or modifications can be made based on the above description. It is neither necessary nor possible to exhaustively list all possible implementations. However, obvious variations or modifications derived therefrom are still within the scope of protection of this invention.

Claims

1. A structure for installing an observation window in a waste storage control room, characterized in that, The utility model relates to a kind of observation room wall, observation room wall is equipped with installation slot, installation slot is pre-embedded with connecting piece inside, and installation slot is equipped with observation window (1) inside, and one end of the observation window (1) is reserved with operating port (4), and the observation window (1) is filled with cement filling layer (2) between connecting piece, and the outside of the cement filling layer (2) is filled with U-shaped glass fiber net (3), and the operating port (4) is filled with grouting material layer (6) inside and sealed. Grouting port is arranged on the operating port (4), and grouting nail (5) is detachably inserted on the grouting port.

2. The trash enclosure control room viewing window mounting structure of claim 1, wherein, Weatherable curtain wall adhesive (7) is filled in the operating port (4) at grouting port and sealed.

3. The trash enclosure control room viewing window mounting structure of claim 2, wherein, The cement filling layer (2) between the observation window (1) and connecting piece is reserved with reserved closing mouth on one side of the operating port (4), and both ends of the U-shaped glass fiber net (3) are pressed in the inside of two reserved closing mouths.

4. The trash enclosure control room viewing window mounting structure of claim 1, wherein, The length of two reserved closing mouths is 80mm.

5. The trash enclosure control room viewing window mounting structure of claim 4, wherein, The thickness of the filled cement filling layer (2) is 5mm.

6. The trash enclosure control room viewing window mounting structure of claim 1, wherein, The grouting material layer (6) is self-leveling mortar.

7. The trash enclosure control room viewing window mounting structure of claim 1, wherein, The cement filling layer (2) is 1:3 cement mortar.

8. The trash enclosure control room viewing window mounting structure of claim 1, wherein, ​