AI Technical Summary
Traditional construction hanging baskets are not easy to adjust in height, and the lack of limiting components leads to swaying and safety issues, making them particularly difficult to operate when constructing bridges on slopes.
A construction basket including a suspension mechanism, a limiting mechanism, and a storage mechanism was designed. The position of the bracket is adjusted by bolts, and the guide wheel limiting mechanism stabilizes the basket. It is equipped with a storage box to store tools.
It achieves convenient and stable height adjustment of the hanging basket, improves construction safety and operational efficiency, and is especially more stable when constructing bridges on slopes.
Smart Images

Figure CN223522982U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to a construction hanging basket for building engineering, belong to the field of building construction technology. BACKGROUND
[0002] Building engineering is for new, reconstruction or extension house building and subsidiary construction facilities and carries out the planning, survey, design and construction, completion and so on technical work and the engineering entity of completion and the installation engineering of the line, pipeline, equipment of its matching, when carrying out bridge building construction, need to carry out construction to bridge side wall, need to use the hanging basket to carry out construction operation to the outside wall of bridge body in the construction process.
[0003] However, the traditional construction hanging basket is the whole structure, inconvenient to adjust the height of the hanging basket, cause when construction in different positions, the staff needs to crouch operation, it is very inconvenient, and the guide wheel on the hanging basket lacks the limiting component, easy to cause the hanging basket to shake, and when hanging on the bridge with certain slope, the hanging basket is easy to slide, and it is also very unsafe to operate. SUMMARY
[0004] The utility model discloses a construction hanging basket for building engineering can carry out the limiting protection to the hanging basket, and can carry out the preliminary regulation to the hanging basket according to the construction height, thereby facilitating construction operation.
[0005] The utility model discloses a construction hanging basket for building engineering, including the fixed frame, install the suspension mechanism on the fixed frame, the suspension mechanism includes the bracket, the fixed frame bottom slidingly connected with the bracket, the bracket top four corners are equipped with a plurality of equidistance distribution's fixed hole, the fixed frame bottom four corners side wall respectively threadedly connected with the bolt, the bolt extends to the fixed hole inside, the fixed frame top one side is welded with two hooks, the hook is " 7 " character shape structure, two the hook, fixed frame side wall and the bracket side wall are fixedly connected with a plurality of fixed blocks respectively, a plurality of the fixed block is respectively connected with the guide wheel of rotation, install the limiting mechanism on the fixed block, the limiting mechanism includes the pressing plate, the fixed block inside slidingly connected with the pressing plate, the fixed block top threadedly connected with the rotating rod, the rotating rod bottom and the pressing plate top rotatable connection, the pressing plate is located the guide wheel top side, install the storage mechanism on the fixed frame.
[0006] Preferably, the pressing plate is arc structure, and the rotating rod is cylindrical " T " shape structure.
[0007] Preferably, the pressing plate bottom is installed with antiskid pad, the antiskid pad bottom side is the dentate structure, and the antiskid pad is located the guide wheel top side.
[0008] Preferably, the bracket bottom is provided with a bottom plate, and a drain hole is arranged at the center of the bottom plate.
[0009] Preferably, the receiving mechanism comprises a receiving box, and the other side of the fixing frame is welded with the receiving box, and the receiving box is a trapezoidal structure with hollow interior and open on one side.
[0010] Preferably, the bottom of the receiving box is provided with a plurality of through holes which are equidistantly distributed and extend to the outside of the bottom of the receiving box.
[0011] Preferably, the bottom of the receiving box is provided with a plurality of through holes which are equidistantly distributed and extend to the outside of the bottom of the receiving box.
[0012] Preferably, the bracket is provided with a plurality of abutting mechanisms on one side, the abutting mechanism comprises a fixing sleeve, a plurality of fixing sleeves are transversely connected at the center line of one side of the bracket, a screw rod is threadedly connected to the fixing sleeve, and a pressing block is rotatably connected to one end of the screw rod.
[0013] Preferably, the screw rod is provided with a handle at one end, and the pressing block is a circular truncated cone structure.
[0014] Preferably, the pressing block is provided with a rubber pad on one side, and the rubber pad is of a corrugated structure on one side.
[0015] The utility model discloses a fixing frame, bracket and bridge body side wall hanging mechanism, and the utility model discloses a fixing frame, bracket and bridge body side wall hanging mechanism, and the utility model discloses a fixing frame, bracket and bridge body side wall hanging mechanism. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 It is the whole structure schematic diagram of the utility model;
[0017] Figure 2 It is the connecting structure schematic diagram of the bracket and the fixing frame of the utility model;
[0018] Figure 3 It is the connecting structure schematic diagram of the bottom plate and the bracket of the utility model;
[0019] Figure 4 It is the connecting structure schematic diagram of the screw bolt and the fixing frame of the utility model;
[0020] Figure 5 It is the connecting structure schematic diagram of the rotary rod and the fixing block of the utility model;
[0021] Figure 6 It is the connecting structure schematic view of the pressing plate and the rotating rod of the utility model;
[0022] Figure 7 It is the connecting structure schematic view of the screw rod and the fixed sleeve of the utility model;
[0023] Figure 8 It is the connecting structure schematic view of the through hole and the storage box of the utility model.
[0024] In the figure: 1, fixed frame;2, suspension mechanism;201, bracket;202, bolt;203, hook;204, fixed block;205, bottom plate;206, drain hole;207, fixed hole;208, guide wheel;3, storage mechanism;301, storage box;302, through hole;303, groove;4, abutting mechanism;401, rubber pad;402, pressing block;403, screw rod;404, fixed sleeve;405, rotating handle;5, limiting mechanism;501, rotating rod;502, pressing plate;503, antiskid pad. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the utility model.
[0026] Please refer to Figures 1-8 As shown in the figure, a construction basket for construction engineering, including fixed frame 1, be installed with suspension mechanism 2 on the fixed frame 1, the suspension mechanism 2 includes bracket 201, the bracket 201 is slidably connected on the bottom of the fixed frame 1, the top of the bracket 201 four corners is equipped with a plurality of equidistant distribution's fixed hole 207, the bottom of the fixed frame 1 four corners sidewall is respectively screw connected with bolt 202, the bolt 202 extends to the inside of fixed hole 207, the top of the fixed frame 1 one side is welded with two hooks 203, the hook 203 is "7" character-shaped structure, two the hook 203, fixed frame 1 sidewall and bracket 201 sidewall are respectively fixedly connected with a plurality of fixed blocks 204, a plurality of fixed blocks 204 are respectively rotatably connected with guide wheel 208, the fixed block 204 is installed with limiting mechanism 5, the limiting mechanism 5 includes pressing plate 502, the fixed block 204 is slidably connected with pressing plate 502, the top of the fixed block 204 is screw connected with rotating rod 501, the bottom of the rotating rod 501 is rotatably connected with the top of pressing plate 502, the pressing plate 502 is located on the top side of guide wheel 208, the fixed frame 1 is installed with storage mechanism 3.
[0027] As a technical optimization scheme of the utility model, the pressing plate 502 is arc structure, the rotating rod 501 is cylindrical "T" shape structure, benefit to the rotating rod 501 drive control, and make the pressing plate 502 with the guide wheel 208 outside close tightly, and the limiting effect is better.
[0028] As a technical optimization scheme of the utility model, the pressing plate 502 bottom is installed with antiskid pad 503, the antiskid pad 503 bottom side is the dentate structure, the antiskid pad 503 is located guide wheel 208 top side, through the installation of antiskid pad 503, play the role of increasing friction, through the design of dentate structure, make limiting effect better.
[0029] As a technical optimization scheme of the utility model, the bracket 201 bottom is installed with bottom plate 205, the bottom plate 205 center is equipped with drain hole 206, through the installation of bottom plate 205, the staff stands, through the design of drain hole 206 play the role of drainage.
[0030] As a technical optimization scheme of the utility model, the storage mechanism 3 includes storage box 301, the fixed frame 1 other side is welded with storage box 301, the storage box 301 is the trapezoidal structure of inside hollow and one side opening, through the installation of storage box 301, it is convenient to store the tool, and obtains convenient to take.
[0031] As a technical optimization scheme of the utility model, the storage box 301 bottom is equipped with multiple rows equidistant distribution through hole 302, the through hole 302 extends to the bottom outside of storage box 301, through the establishment of through hole 302, play the role of the sandstone debris discharge, prevent the sandstone debris on the tool to fall in the storage box 301 internal storage is not easy to clean.
[0032] As a technical optimization scheme of the utility model, the storage box 301 opening one side bottom is equipped with recess 303, the recess 303 is arc structure, through the design of recess 303, it is convenient to reduce the height of the opening of storage box 301, it is convenient to store the tool.
[0033] As a technical optimization scheme of the utility model, a plurality of abutting mechanisms 4 are installed on one side of the bracket 201, the abutting mechanism 4 comprises a fixed sleeve 404, a plurality of fixed sleeves 404 are transversely connected at the middle line of one side of the bracket 201, a screw rod 403 is threadedly connected on the fixed sleeve 404, a pressing block 402 is rotatably connected at one end of the screw rod 403, through the installation of the plurality of fixed sleeves 404, the screw rod 403 is facilitated to be threadedly connected, through the rotation of the screw rod 403, the screw rod 403 drives the pressing block 402 to move under the action of the thread, the pressing block 402 is abutted with the wall body, and the whole bracket 201 is not shaken.
[0034] As a technical optimization scheme of the utility model, a handle 405 is installed at one end of the screw rod 403, the pressing block 402 is in the shape of a circular truncated cone, through the installation of the handle 405, the screw rod 403 is facilitated to be driven and controlled, and through the design of the circular truncated cone structure of the pressing block 402, the contact area with the wall body is increased, and the abutting limiting effect is good.
[0035] As a technical optimization scheme of the utility model, a rubber pad 401 is installed on one side of the pressing block 402, one side of the rubber pad 401 is in the shape of a corrugated structure, through the installation of the rubber pad 401, the friction force is increased to prevent slipping, and the rubber pad 401 is elastic, and the shock absorption effect is achieved.
[0036] In use, first, the bracket 201 is inserted into the bottom of the fixing frame 1, the position is adjusted by sliding the bracket 201, the staff is facilitated to construct, then a plurality of bolts 202 are rotated, the bolts 202 are inserted into the fixed holes 207 in the bracket 201, the locking connection of the bracket 201 and the fixing frame 1 is realized, then the two hooks 203 on the fixing frame 1 are clamped with the side wall of the bridge body, and the plurality of guide wheels 208 are abutted with the side wall of the bridge body, the suspension of the fixing frame 1 and the bracket 201 is realized, then the staff is facilitated to maintain the outside of the bridge body in the bracket 201, the guide wheels 208 on the two hooks 203 are abutted and limited by the rotation of the two rotating rods 501, the fixing frame 1 is not easy to slide, the handles 405 are rotated again, the handles 405 drive the screw rods 403 and the fixed sleeves 404 to rotate in thread, the screw rods 403 drive the pressing blocks 402 and the rubber pads 401 to abut with the side wall of the bridge body, the bracket 201 is stably supported and abutted, the orderly construction of the staff is ensured, the storage box 301 is installed on the outside of the fixing frame 1, tools or parts needed to be installed are stored, and the construction is more convenient.
[0037] It is apparent for a person skilled in the art that the present application is not limited to the details of the above-described exemplary embodiments, but that it can be implemented in other concrete forms without departing from the spirit or the essential characteristics of the present application. Therefore, the embodiments should be considered as exemplary and non-limiting, the scope of the present application being defined by the claims appended hereto rather than by the above description, and all the changes which fall within the meaning and the scope of the equivalent elements of the claims are intended to be embraced therein. Any reference signs in the claims should not be construed as limiting the claims to the figures in which the reference signs are used.
[0038] Furthermore, it should be understood that although the present specification describes exemplary embodiments, not every embodiment contains only one independent technical solution, and the present specification is described in this way only for the sake of clarity, and a person skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that a person skilled in the art can understand.
Claims
1. A construction basket for use in construction work, comprising a fixed frame (1), characterised in that: The fixed frame (1) is provided with a hanging mechanism (2), the hanging mechanism (2) comprises a bracket (201), the fixed frame (1) is slidably connected with the bracket (201) at the bottom, the top of the bracket (201) is provided with a plurality of equidistantly distributed fixing holes (207) at the four corners, the bottom of the fixed frame (1) is threadedly connected with a bolt (202) at the four corners of the side wall respectively, the bolt (202) extends into the fixing hole (207), two hooks (203) are welded on one side of the top of the fixed frame (1), the hooks (203) are "7" shaped structures, a plurality of fixing blocks (204) are fixedly connected to the side walls of the hooks (203), the bracket (201) and the side wall of the bracket (201) respectively, a plurality of guide rollers (208) are rotatably connected to the fixing blocks (204) respectively, a limiting mechanism (5) is mounted on the fixing block (204), the limiting mechanism (5) comprises a pressing plate (502), the pressing plate (502) is slidably connected in the fixing block (204), a rotating rod (501) is threadedly connected to the top of the fixing block (204), the bottom of the rotating rod (501) is rotatably connected with the top of the pressing plate (502), the pressing plate (502) is located on the top side of the guide roller (208), and a storage mechanism (3) is mounted on the fixed frame (1).
2. The construction trolley for construction engineering according to claim 1, characterized in that: The pressing plate (502) is arc-shaped, and the rotating rod (501) is cylindrical "T"-shaped.
3. The construction trolley for construction engineering according to claim 2, characterized in that: The bottom of the pressing plate (502) is provided with a non-slip pad (503), the bottom side of the non-slip pad (503) is provided with a toothed structure, and the non-slip pad (503) is located on the top side of the guide roller (208).
4. The construction trolley for construction engineering according to claim 1, characterized in that: The bottom of the bracket (201) is provided with a bottom plate (205), and the center of the bottom plate (205) is provided with a drain hole (206).
5. The construction trolley for use in construction work as claimed in claim 1, wherein: The storage mechanism (3) comprises a storage box (301), the other side of the fixed frame (1) is welded with the storage box (301), and the storage box (301) is a trapezoidal structure with an open side in the hollow.
6. The construction trolley for use in construction work according to claim 5, wherein: The bottom of the storage box (301) is provided with a plurality of equidistantly distributed through holes (302), and the through holes (302) extend to the outside of the bottom of the storage box (301).
7. The construction trolley for use in construction work according to claim 6, wherein: The bottom of the open side of the storage box (301) is provided with a groove (303), and the groove (303) is arc-shaped.
8. The construction trolley for construction engineering according to claim 1, characterized in that: A plurality of abutting mechanisms (4) are mounted on one side of the bracket (201), the abutting mechanism (4) comprises a fixing sleeve (404), a plurality of fixing sleeves (404) are transversely connected to the side of the bracket (201) at the center line, a screw rod (403) is threadedly connected to the fixing sleeve (404), and a pressing block (402) is rotatably connected to one end of the screw rod (403).
9. The construction trolley for use in construction work according to claim 8, wherein: A handle (405) is mounted at one end of the screw rod (403), and the pressing block (402) is a circular truncated cone structure.
10. The construction trolley for use in construction work according to claim 9, wherein: A rubber pad (401) is mounted on one side of the pressing block (402), and one side of the rubber pad (401) is corrugated.