Trash holding fence laying device
By setting up winches and pulley assemblies on both sides of the river, and using traction ropes and tensioning mechanisms to automatically deploy the debris barrier, the problem of laborious manual dragging was solved, and the deployment of the debris barrier was achieved quickly and at low cost.
Patent Information
- Application Number
- CN202422984631.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-04
- Publication Date
- 2025-11-25
- Estimated Expiration
- 2034-12-04
AI Technical Summary
In the South-to-North Water Diversion Project channels, manually dragging the debris barriers is laborious and makes it difficult to respond quickly to emergencies, resulting in high labor costs. Existing technologies are not capable of rapid deployment.
By installing winches and pulley assemblies on both sides of the river, and using traction ropes and tensioning mechanisms, the winches drive the movement of the traction ropes to achieve automatic deployment of the debris barrier, reducing manpower input.
It enables rapid deployment of debris barriers, reduces manpower input, improves emergency response speed, and reduces operational difficulty and cost.
Smart Images

Figure CN223593326U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the equipment technical field that water surface cleaning used, specifically relates to a fence of intercepting trash layout device. BACKGROUND
[0002] Water surface intercepting fence such as oil containment boom, oil intercepting belt, trash intercepting belt etc. can float on water surface to form a barrier for intercepting water surface trash. Among them, the oil containment boom is an intercepting fence facility that can form an oil intercepting barrier on water surface to prevent oil pollution from spreading and guide it to a suitable area for recovery and treatment. The oil containment boom has various forms, and common ones include solid float type, inflatable type, beach type, fireproof type etc. The oil containment boom is usually connected by many sections, and its basic structure can be seen in the solid float type oil containment boom disclosed in the Chinese utility model patent with the authorization announcement number CN202595713U. At present, the application of the oil containment boom in blocking marine and port oil spill accidents is relatively mature, and the oil containment boom is dragged by a ship for rapid arrangement.
[0003] However, for the South-to-North Water Diversion Project channel, there are sometimes problems of water surface oil pollution and other trash, for example, if an oil transport vehicle has a traffic accident near a channel, oil pollution may flow into the channel, and the oil containment boom needs to be used for interception and treatment. However, the South-to-North Water Diversion Project channel has a wide cross section and fast flow rate, and does not have the condition to drag the oil containment boom by a ship. Therefore, when an emergency event of water quality occurs in an open channel project, a solid float type oil containment boom is usually arranged by manpower dragging, a bridge is found nearby, the tail end of the oil containment boom is fixed on the bank of one side of the river, the head end of the oil containment boom is dragged by manpower and sent to the bank of the other side of the river by the bridge, and the head end of the oil containment boom is fixed, so that the oil containment boom is arranged across the river to form a barrier. However, this way of arranging the oil containment boom by manpower dragging has the problems of large volume, long length and heavy weight of the oil containment boom, high manpower cost, high labor cost, and difficult rapid response to emergency events. UTILITY MODEL CONTENTS
[0004] The utility model aims to provide a fence of intercepting trash layout device to solve the problem of occupying more manpower in arranging the fence of intercepting trash on the river by manpower dragging at present.
[0005] The technical scheme of the fence of intercepting trash layout device of the utility model is as follows:
[0006] The application discloses a device for arranging a trash barrier fence on a river, which is powered by a traction device.
[0007] The device for arranging a trash barrier fence on a river is powered by a traction device, and the device comprises two fixing piles arranged on the two banks of the river respectively, wherein one of the fixing piles is provided with a winch, and the other fixing pile is provided with a pulley assembly; a traction rope is wound around the winch and the pulley assembly, and the two ends of the traction rope are connected to form a closed loop; the winch can drive the traction rope to reciprocate when the winch is working; when the trash barrier fence is arranged, the tail end of the trash barrier fence is connected to the fixing pile on one bank of the river, and the head end of the trash barrier fence is connected to the traction rope; the winch drives the traction rope to move, so that the head end of the trash barrier fence is driven to move away from the tail end and to move from one bank of the river to the other bank, and the trash barrier fence is arranged; the device for arranging a trash barrier fence is preset on the river, and the trash barrier fence is sent from one bank of the river to the other bank by the traction of the winch during use, so that the operation process is convenient, and the labor input can be reduced.
[0008] Further, the traction rope comprises a main rope and a tensioning mechanism; the main rope is wound around the winch and the redirecting pulley; the two ends of the main rope are connected to the two ends of the tensioning mechanism respectively, so that the traction rope is tensioned by the tensioning mechanism; one end of the main rope and the corresponding end of the tensioning mechanism form the two ends of the traction rope respectively.
[0009] Further, the two ends of the main rope are respectively provided with rope rings, and the two ends of the tensioning mechanism are respectively provided with connecting pieces for connecting the corresponding rope rings; the rope rings form the head end traction connecting structure.
[0010] Further, the pulley assembly comprises a mounting frame, the mounting frame comprises a fixing part for being fixed to the corresponding fixing pile and a cantilever part cantilevered based on the fixing part, and the redirecting pulley is installed at the end of the cantilever part.
[0011] Further, the fixing part of the mounting frame is a hoop, the hoop comprises two hoop pieces arranged oppositely, the end parts of the two hoop pieces are provided with connecting ears, and the cantilever part and the connecting ears at the end parts of the two hoop pieces are fixed and connected by bolts.
[0012] Further, the frame of the winch is provided with a hoop for being tightly fixed to the corresponding fixing pile.
[0013] Further, the two fixed piles for connecting the tail end of the trash barrier fence are a tail end fixed pile and a head end fixed pile, and the head end fixed pile is provided with a head end connecting structure for being connected to the head end fixed pile when the head end of the trash barrier fence is moved from one bank to the other bank of the river channel from the towing rope.
[0014] Further, the winch comprises a winding drum and an operation shaft in transmission connection with the winding drum, the towing rope is wound on the winding drum, and the operation shaft drives the winding drum to rotate when rotating, and the operation shaft is provided with an operation end for connecting a screwing tool.
[0015] Further, the operation shaft has two operation shafts, and the transmission ratios of the two operation shafts and the winding drum are different.
[0016] Further, the transmission structure between the operation shaft and the winding drum comprises a worm and gear mechanism. BRIEF DESCRIPTION OF DRAWINGS
[0017] Figure 1 it is the structural schematic diagram of the trash barrier fence layout device of the embodiment of the utility model;
[0018] Figure 2 it is the top view of the trash barrier fence layout device in Figure 1
[0019] Figure 3 it is the schematic diagram of the winch main part in Figure 1
[0020] Figure 4 it is the internal structure schematic diagram of the winch in Figure 1
[0021] Figure 5 it is the installation structure schematic diagram of the two operation shafts of the winch in Figure 4
[0022] In the drawing:
[0023] 10, tail end fixed pile; 20, head end fixed pile;
[0024] 30, winch; 31, frame clamp; 32, winding drum; 33, frame; 34, slow operation shaft; 35, fast operation shaft; 36, center shaft; 37, worm wheel; 38, worm;
[0025] 40, pulley assembly; 41, assembly clamp; 42, pulley mounting ear; 43, change direction pulley;
[0026] 50, towing rope; 51, main rope; 52, rope ring; 53, basket bolt; 54, rope shackle. DETAILED DESCRIPTION
[0027] The basic concept of the trash barrier fence laying device is to realize laying by using the fixed piles preset on the two banks of the river to cooperate with the winch and the pulley assembly to pull the rope to pull the trash barrier fence, so that the labor input is reduced.
[0028] The following will be specifically described in conjunction with the embodiments.
[0029] The embodiment of the trash barrier fence laying device of the utility model:
[0030] The trash barrier fence laying device comprises two fixed piles for being respectively fixed on the two banks of the river, one of the fixed piles is provided with a winch, the other fixed pile is provided with a pulley assembly, the pulley assembly comprises a reversing pulley, a traction rope is wound on the winch and the two ends of the traction rope are both extended out of the winch, one end of the traction rope is connected with the other end by being wound around the reversing pulley, the one fixed pile is provided with a tail end connecting structure for connecting the tail end of the trash barrier fence, and the traction rope is provided with a head end traction connecting structure for connecting the head end of the trash barrier fence so as to drive the head end of the trash barrier fence to move from one bank of the river to the other bank when the winch drives the traction rope to move.
[0031] Specifically, as shown in Figure 1 , Figure 2 The trash barrier fence laying device comprises a tail end fixed pile 10, a head end fixed pile 20 and a winch 30, a pulley assembly 40 and a traction rope 50, the tail end fixed pile 10 and the head end fixed pile 20 constitute the two fixed piles of the trash barrier fence laying device which are respectively fixed on the two banks of the river, wherein the tail end fixed pile 10 is fixed on the left bank of the river, the head end fixed pile 20 is fixed on the right bank of the river, the winch 30 is fixed on the tail end fixed pile 10, the pulley assembly 40 is fixed on the head end fixed pile 20, the pulley assembly 40 comprises a reversing pulley 43, the reversing pulley 43 is a fixed pulley, the traction rope 50 is wound on the winding drum 32 of the winch 30 and the two ends of the traction rope 50 are both extended out of the winch 30, one end of the traction rope 50 is connected with the other end by being wound around the reversing pulley 43 to form a closed loop of the traction rope 50, the tail end fixed pile 10 is provided with a tail end connecting structure for connecting the tail end of the trash barrier fence, and the traction rope 50 is provided with a head end traction connecting structure for connecting the head end of the trash barrier fence. The winch 30 can drive the traction rope 50 to reciprocate when working, and when the trash barrier fence is laid, the trash barrier fence is assembled on the left bank of the river, the tail end of the trash barrier fence is connected to the tail end fixed pile 10 on the left bank of the river, the head end of the trash barrier fence is connected to the traction rope 50, and the winch 30 drives the traction rope 50 to move to drive the head end of the trash barrier fence to move away from the tail end and move from the left bank of the river to the right bank, so that the trash barrier fence is laid.
[0032] The winch 30 and the pulley assembly 40 are arranged in the extension direction of the traction rope 50 to conform to the direction of the traction rope 50. The trash barrier arrangement device is preset on the river channel. When in use, the trash barrier is sent from one bank to the other bank of the river channel by the traction rope 50 in cooperation with the winch 30 and the pulley assembly 40 in a power traction manner. The operation process is convenient, and the labor input can be reduced. The first end and the tail end of the trash barrier are both provided with connectors. The tail end connecting structure for connecting the tail end of the trash barrier is not shown in the figure, and the form can be set as required. Generally, a steel wire rope can be used. The steel wire rope is looped around the tail end fixed pile 10, and the tail end is connected to the tail end of the trash barrier through a shackle. The tail end of the trash barrier is bolted to the tail end fixed pile 10. Of course, a lock can also be directly arranged on the fixed pile for connecting the tail end connector of the trash barrier. The first end of the trash barrier is connected to the traction rope 50 through a shackle by using the first end connector. In the embodiment, the fixed pile on the left bank of the river channel is provided with the tail end connecting structure for connecting the tail end of the trash barrier. The first end of the trash barrier is moved from the left bank to the right bank of the river channel. In other embodiments, the tail end connecting structure for connecting the tail end of the trash barrier can also be arranged on the fixed pile on the right bank of the river channel. The trash barrier is arranged from the right bank of the river channel. The first end of the trash barrier is moved from the right bank to the left bank of the river channel.
[0033] The traction rope 50 includes a main rope 51 and a tensioning mechanism. The main rope 51 is a steel wire rope. The main rope 51 is wound around the winding drum 32 of the winch 30 and the deflection pulley 43 of the pulley assembly 40. The tensioning mechanism is used to connect the two ends of the main rope 51 together. The tensioning mechanism includes a basket bolt 53 and a rope shackle 54 connected to the two ends of the basket bolt 53, respectively. The two ends of the main rope 51 are respectively provided with a rope ring 52. The rope shackle 54 constitutes a connecting piece for connecting the rope ring 52 of the main rope 51. The two ends of the main rope 51 are respectively connected to the rope shackles 54 at the two ends of the tensioning mechanism. One end of the main rope 51 and the corresponding end of the tensioning mechanism respectively constitute two ends of the traction rope 50. By twisting the basket bolt 53, the two ends of the main rope 51 can be tightened, and in turn the traction rope 50 is tensioned. This is convenient for adjusting the tensioning force and ensuring reliable installation of the steel wire rope. In other embodiments, the tensioning mechanism can not be provided. The two ends of the main rope 51 are directly connected through a shackle. The steel wire rope has a certain amount of sag, which does not affect the movement of the steel wire rope.
[0034] The rope ring 52 of the main pull rope 51 forms a head end traction connection structure for connecting the head end of the trash barrier, the joint of the head end of the trash barrier is provided with a connection hole, the joint of the head end of the trash barrier is connected at the rope ring 52 through a shackle, the size of the rope ring 52 can meet the connection of the rope shackle 54 of the tensioning mechanism and the shackle of the joint of the head end of the trash barrier, and the head end of the trash barrier is connected with one of the rope rings 52. It should be understood that before the trash barrier is laid, the rope ring 52 is moved to a position close to the river bank by the winch 30 to drive the traction rope 50, so as to facilitate the connection operation of the head end of the trash barrier. The trash barrier is connected by using the existing rope ring 52, which is simple in structure and convenient to connect. In other embodiments, a connecting ring can be separately fixed at other positions of the traction rope, and the connecting ring is used to form a head end traction connection structure for connecting the trash barrier, which can ensure that the traction rope drives the trash barrier to move.
[0035] The pulley assembly 40 includes a mounting frame, the mounting frame includes a fixed part for being fixed with the head end fixed pile 20 and a cantilever part cantilevered based on the fixed part, and the deflection pulley 43 is installed at the end of the cantilever part. The fixed part of the mounting frame is a component clamp 41, and the cantilever part of the mounting frame is a cantilever support. The component clamp 41 is tightly clamped and fixed on the head end fixed pile 20, the cantilever support is cantilevered to the horizontal side of the head end fixed pile 20, one end of the cantilever support is fixed with the component clamp 41, and the other end is provided with a pulley mounting lug 42, and the deflection pulley 43 is rotatably installed on the pulley mounting lug 42. The deflection pulley 43 is installed by using the cantilever part of the mounting frame, the mounting frame has a certain deformation ability, which can reduce the stress generated by the pulley assembly 40 under the pulling of the traction rope 50, and is beneficial to reliable use. The clamp is fixed with the head end fixed pile 20, which is convenient for disassembly and maintenance. In other embodiments, the cantilever support can not be provided, and the pulley mounting lug is directly fixed on the component clamp. In other embodiments, the mounting support can be directly welded and fixed on the head end fixed pile.
[0036] The component clamp 41 is a clamp of the pulley assembly 40, and the component clamp 41 includes two clamping pieces oppositely arranged. The two ends of the clamping pieces are respectively provided with connecting lugs, the two clamping pieces are fixed and connected by the connecting lugs at the ends through bolts and nuts, and are tightly clamped and fixed on the corresponding fixed piles. The cantilever support of the pulley assembly 40 shares the bolts and nuts with the connecting lugs at the ends of the two clamping pieces for fixing, which can simplify the connection structure. In other embodiments, a fixed connection structure for fixing the cantilever support can be separately provided on one side clamping piece of the component clamp.
[0037] The first end fixed pile 20 is provided with a first end connecting structure, which can adopt the same structure as the tail end connecting structure, not shown in the figure. When moving the trash barrier first end from one bank of the river to the other bank, the trash barrier first end can be detached from the traction rope 50 and connected to the first end connecting structure on the first end fixed pile 20. In this way, the first end connecting structure of the first end fixed pile 20 and the tail end connecting structure of the tail end fixed pile 10 are used to respectively fasten the first end and the tail end of the trash barrier to the fixed piles on the two banks of the river, and the fixed piles bear the force, avoiding that the traction rope 50 bears a large tension all the time, which is conducive to improving the use reliability. In other embodiments, if the traction rope 50 can ensure reliable force bearing, the first end connecting structure can also not be provided, and the position of the trash barrier is maintained by the traction rope in cooperation with the winch.
[0038] The rack 33 of the winch 30 is provided with a rack holding hoop 31 for holding the tail end fixed pile 10. The rack holding hoop 31 has the same structure as the assembly holding hoop 41. The rack 33 body is fixedly connected to the rack holding hoop 31 through a connecting plate. The tail end fixed pile 10 is held tightly by the rack holding hoop 31, which is convenient for on-site assembly and fixation. In other embodiments, a fixed seat can be welded on the fixed pile, and the winch is fixed on the fixed seat.
[0039] The part of the winch 30 after removing the rack holding hoop 31 and the connecting plate is the main body part thereof. Figure 3 、 Figure 4 、 Figure 5 The center shaft 36 is fixed on the rack 33 of the winch 30, and the winding drum 32 is rotatably installed on the center shaft 36. Two operation shafts are rotatably installed on the rack 33, which are a slow operation shaft 34 and a fast operation shaft 35. The operation shafts are in transmission connection with the winding drum 32. The traction rope 50 is wound on the winding drum 32. When the operation shafts rotate, the winding drum 32 is driven to rotate to drive the traction rope 50 to move. The operation shafts are provided with operation ends for connecting a screwing tool. The operation ends are exposed to facilitate connection with the screwing tool. The winding and unwinding actions of the winch 30 are driven by the additional screwing tool, which can simplify the structure of the winch 30. The winch 30 itself does not have a motor, which is conducive to long-term placement in an outdoor environment and facilitates manual operation without the need to carry a power source. In other embodiments, the winch can also be configured with a motor. When in use, a mobile power source is carried to drive the motor to work to realize the movement of the traction rope.
[0040] The slow operation shaft 34 and the fast operation shaft 35 are both in transmission connection with the winding drum 32, but the transmission ratios of the two shafts to the winding drum 32 are different. When the winch 30 is operated, the rotating speed of the winding drum 32 is lower than that of the operation shaft. The transmission ratio of the slow operation shaft 34 to the winding drum 32 is greater than that of the fast operation shaft 35 to the winding drum 32. When the slow operation shaft 34 is operated, the moving speed of the traction rope 50 is slow, and when the fast operation shaft 35 is operated, the moving speed of the traction rope 50 is fast. Different operation shafts can be selected according to the needs to facilitate the control of the moving speed of the trash barrier. In other embodiments, only one operation shaft can be provided.
[0041] The transmission structure between the operation shaft and the winding drum 32 includes a worm gear mechanism, and the mechanical locking function of the worm gear mechanism can avoid the reverse movement of the traction rope 50. In other embodiments, a conventional gear transmission structure can also be used according to the needs.
[0042] The slow operation shaft 34 is in transmission connection with the fast operation shaft 35 through a gear set. The worm gear mechanism includes a worm wheel 37 fixedly connected with the winding drum 32 and a worm 38 integrally formed on the fast operation shaft 35. When the fast operation shaft is operated by a screwing tool, the worm gear mechanism is used to reduce the speed and increase the torque. When the slow operation shaft is operated by a screwing tool, the gear set and the worm gear mechanism are used to reduce the speed and increase the torque. The screwing tool can be an electric wrench or a manual wrench.
[0043] The fixed pile is a steel pipe with a length of 3 m, and the buried depth is not less than 1.8 m. The steel pipe is filled with cement mortar. The steel wire rope part of the traction rope 50 is a steel wire rope with a diameter of Φ8 mm. The winch 30 is a friction type winch. In this embodiment, the trash barrier is an oil containment boom.
[0044] The use of the trash barrier arrangement will be described below in combination with the layout process of the oil containment boom.
[0045] After the oil containment boom is transported to the site, each section of the oil containment boom is unfolded and placed on the road in sequence to ensure that there is no obstacle to enter the water. Each section of the oil containment boom is provided with a thickened joint with holes at both ends. When connected, the joints of the adjacent two sections are overlapped and assembled together by connecting bolts and the through holes in the joints.
[0046] The first section of the oil containment boom is connected with the towing rope 50 by a U-shaped shackle at the end of the oil containment boom, and the last section of the oil containment boom is fixedly connected with the steel wire rope on the tail end fixing post 10 on the tail end of the oil containment boom on the left bank wave protection wall by a U-shaped shackle. After the oil containment boom is connected, the winch 30 is driven by a rotating tool, and the oil containment boom is slowly dragged into the water by the towing rope 50. Before being put into the water, the skirt body of the oil containment boom is arranged to avoid twisting and entanglement of the oil containment boom after being put into the water, and to ensure smooth deployment. In order to prevent damage to the oil containment boom, a mat or a sliding rack is laid at the water inlet of the oil containment boom to prevent sharp objects from damaging the oil containment boom. The oil containment boom is dragged by an operator holding an electric tool to drive the winch 30, and when the load is small, the fast operation shaft 35 can be used for traction, and when the load is large, the slow operation shaft 34 is switched.
[0047] When the oil containment boom approaches the opposite bank of the river, the operator detaches the oil containment boom from the towing rope 50 and connects it to the first end fixing post 20 on the right bank of the river through the steel wire rope and the shackle, thereby completing the anchor point switching of the oil containment boom. The recovery steps of the oil containment boom are opposite to the deployment steps.
[0048] The deployment device uses a portable handheld electric tool to drive the winch instead of manual dragging, so that 5 people can complete the rapid deployment of the oil containment boom within 30 minutes, greatly reducing the labor input, improving the deployment efficiency, and ensuring that the emergency event can be responded quickly. The deployment device basically does not involve dangerous operation during operation, and the risk of mechanical injury is low when the electric tool is used to drive the winch, which can reduce the risk of illegal operation of personnel and improve the safety performance of the equipment. The deployment device can be deployed multiple times, has high work efficiency, requires less resource input, runs stably and reliably, and has low equipment maintenance cost.
[0049] Finally, it should be noted that the above-described preferred embodiments of the present application are not intended to limit the present application, and although the present application has been described in detail with reference to the foregoing embodiments, those skilled in the art can modify the technical solutions described in the foregoing embodiments without creative labor, or make equivalent substitutions for some technical features. Any modification, equivalent substitution, improvement, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.
Claims
1. A boom deployment device, characterized in that, The device comprises two fixed piles for being fixed on the two banks of the river respectively, one of the fixed piles is provided with a winch, and the other fixed pile is provided with a pulley assembly, the pulley assembly comprises a change direction pulley, the winch is provided with a traction rope, and the two ends of the traction rope are extended out of the winch, one end of the traction rope is connected with the other end by winding around the change direction pulley, one of the fixed piles is provided with a tail end connecting structure for connecting the tail end of the trash barrier, and the traction rope is provided with a head end traction connecting structure for connecting the head end of the trash barrier so as to drive the head end of the trash barrier to move from one bank to the other bank of the river when the winch drives the traction rope to move.
2. The apparatus of claim 1, wherein, The traction rope comprises a main rope and a tensioning mechanism, the main rope is wound around the winch and the change direction pulley, and the two ends of the main rope are connected with the two ends of the tensioning mechanism respectively to tension the traction rope through the tensioning mechanism, and one end of the main rope and the corresponding end of the tensioning mechanism respectively form the two ends of the traction rope.
3. The apparatus of claim 2, wherein, The two ends of the main rope are respectively provided with rope rings, and the two ends of the tensioning mechanism are respectively provided with connecting pieces for connecting the corresponding rope rings, and the rope rings form the head end traction connecting structure.
4. A boom laying apparatus according to claim 1 or 2 or 3, characterised in that, The pulley assembly comprises a mounting frame, the mounting frame comprises a fixed part for being fixed with the corresponding fixed pile and a cantilever part cantilevered based on the fixed part, and the change direction pulley is installed at the end of the cantilever part.
5. The apparatus of claim 4, wherein, The fixed part of the mounting frame is a clamp hoop, the clamp hoop comprises two clamp hoop pieces arranged oppositely, the end parts of the two clamp hoop pieces are provided with connecting ears, and the cantilever part and the end part connecting ears of the two clamp hoop pieces are fixedly connected through bolts.
6. The apparatus of claim 1, 2 or 3, wherein, The frame of the winch is provided with a clamp hoop for clamping the corresponding fixed pile.
7. The apparatus of claim 1, 2 or 3, wherein, One of the two fixed piles for connecting the tail end of the trash barrier is a tail end fixed pile, and the other is a head end fixed pile, and the head end fixed pile is provided with a head end connecting structure for being connected to the head end fixed pile from the traction rope when the head end of the trash barrier moves from one bank to the other bank of the river.
8. The apparatus of claim 1, 2 or 3, wherein, The winch comprises a winding drum and an operation shaft in transmission connection with the winding drum, the traction rope is wound around the winding drum, the operation shaft drives the winding drum to rotate when the operation shaft rotates, and the operation shaft is provided with an operation end for connecting a screwing tool.
9. The apparatus of claim 8, wherein, The operation shaft has two operation shafts, and the transmission ratios of the two operation shafts and the winding drum are different.
10. The apparatus of claim 8, wherein, The transmission structure between the operation shaft and the winding drum comprises a worm gear mechanism.
Citation Information
Patent Citations
Solid floater oil fence
CN202595713U