Operating platform for installing wind power split type tower drum

By designing an operating platform for installing wind turbine split-type towers, and utilizing electric telescopic wheels, folding rods, and a hydraulic system to achieve rapid deployment and adjustment, the project solved the problems of high construction difficulty and low safety in on-site installation of wind turbine towers, and improved work efficiency.

CN223724758UActive Publication Date: 2025-12-26TIANJIN KETONGLIDA HOISTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520606223.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-02
Publication Date
2025-12-26
Estimated Expiration
2035-04-02

AI Technical Summary

Technical Problem

The difficulties in on-site installation of wind turbine towers and uneven ground conditions lead to challenges in construction, low safety, and low work efficiency.

Method used

An operating platform for installing segmented wind turbine towers was designed, including a main beam frame, electric telescopic wheels, electric folding rods, hydraulic columns, and support beams. The platform can be quickly deployed and leveled by electric sliders and hydraulic jacks, supporting the assembly of segmented towers.

Benefits of technology

No site construction adjustments are required, simplifying the tower alignment process, improving installation safety and efficiency, and shortening the assembly time for each tower section from 1-2 days to 2 hours.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223724758U_ABST
    Figure CN223724758U_ABST
Patent Text Reader

Abstract

The utility model discloses an operating platform for installing a wind power sectioning type tower drum, which comprises a main beam frame, a plurality of electric telescopic wheels are arranged at the bottom of the main beam frame, a plurality of electric folding rods are arranged on both sides of the main beam frame, the outer ends of the electric folding rods are connected with auxiliary beams, and the auxiliary beams are parallel to the main beam frame and controlled by the electric folding rods to unfold laterally. A plurality of hydraulic columns are arranged at the bottom of the auxiliary beam, a plurality of supporting beams and first electric sliding blocks are arranged at the tops of the main beam frame and the auxiliary beam, the first electric sliding blocks slide along the main beam frame and the auxiliary beam, the two ends of the supporting beams are clamped on the first electric sliding blocks, second electric sliding blocks are arranged on the supporting beams, and hydraulic jacks are arranged at the tops of the second electric sliding blocks. The operation platform has the advantages that the operation platform is used for splicing the sectioned tower drum, the limitation that operation cannot be carried out due to the fact that an operation site is uneven in the past is eliminated, and the site does not need to be constructed and adjusted firstly; the problem that alignment is difficult when the sectioned tower drum is assembled in the prior art is solved, operation is easy, safety is high, the total assembling time of each section of tower drum is shortened to 2 h from original 1-2 days, operation time is greatly shortened, and operation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to wind power split section tower drum installation operation platform technical field, concretely refers to a kind of wind power split section tower drum installation operation platform. BACKGROUND

[0002] With market competition more and more intense, wind power tower drum is higher and higher, tower drum diameter is larger and larger;But transportation and installation condition is limited, so tower drum adopts split section, is transported to construction site and is assembled and installed, and it is the main way of current wind power field site construction. At present, the site installation of domestic split section tower drum is mostly first excavator excavates ground, then several pad blocks are placed on ground, after multiple leveling adjustment, split section tower drum is placed on pad block for assembly. Since wind power tower drum site installation is mostly in mountain plain, ground is uneven, not easy to level, and the construction method of currently used assembly on pad block is difficult to operate, has great construction difficulty, low safety and low operation efficiency. UTILITARY MODEL CONTENTS

[0003] The utility model aims at providing a kind of wind power split section tower drum installation operation platform to solve the problems raised in the above background technology.

[0004] To solve the above technical problems, the utility model provides the following technical scheme:

[0005] The utility model discloses a kind of wind power split section tower drum installation operation platform, including main beam frame, the main beam frame bottom is equipped with several electric telescopic wheels, the main beam frame both sides are equipped with several electric folding rods, the electric folding rod outer end is connected with auxiliary beam, the auxiliary beam is parallel with main beam frame and is controlled lateral unfolding by electric folding rod, the auxiliary beam bottom is equipped with several hydraulic columns, the main beam frame, auxiliary beam top is equipped with several support beams and electric sliding block one, the electric sliding block one slides along main beam frame, auxiliary beam, the support beam both ends are clamped on electric sliding block one, the support beam is equipped with electric sliding block two, the electric sliding block two top is equipped with hydraulic top.

[0006] As improvement, the support beam has twelve, six on each side, perpendicular to main beam frame, auxiliary beam, the electric folding rod has four, two on each side.

[0007] As improvement, the main beam frame top center is equipped with crane.

[0008] As improvement, the electric telescopic wheel is fixedly connected with main beam frame, the hydraulic column is fixedly connected with auxiliary beam, the electric folding rod both ends are fixedly connected with auxiliary beam, main beam frame.

[0009] The operation platform for the wind power split tower section installation has the advantages that the assembling of the split tower section is facilitated, the restriction that the previous operation site cannot be operated due to uneven site is removed, site construction adjustment is not necessary, the alignment difficulty during the assembling of the split tower section is solved, the operation is easy, the safety is high, the total time length of the assembling of each tower section is shortened from 1-2 days to 2 hours, the operation time is greatly shortened, and the operation efficiency is improved. BRIEF DESCRIPTION OF DRAWINGS

[0010] In order to more clearly illustrate the technical scheme in the embodiments of the present application or the prior art, the drawings needed to be used in the embodiments or the prior art description will be briefly introduced as follows. Obviously, the drawings listed below are only some structural schematic diagrams of the present application, but not all.

[0011] Figure 1 is a structural schematic diagram of the operation platform for the wind power split tower section installation of the present application Figure 1 .

[0012] Figure 2 is a structural schematic diagram of the operation platform for the wind power split tower section installation of the present application Figure 2 .

[0013] Figure 3 is a top view of the operation platform for the wind power split tower section installation of the present application.

[0014] Figure 4 is a side view of the operation platform for the wind power split tower section installation of the present application Figure 1 .

[0015] Figure 2 is a side view of the operation platform for the wind power split tower section installation of the present application Figure 6 .

[0016] Figure 7 is a structural schematic diagram of the electric sliding block one of the operation platform for the wind power split tower section installation of the present application.

[0017] Figures 1 to 7 is a structural schematic diagram of the electric sliding block two of the operation platform for the wind power split tower section installation of the present application.

[0018] Reference signs:

[0019] Main beam frame 1, electric telescopic wheel 2, electric folding rod 3, auxiliary beam 4, hydraulic column 5, supporting beam 6, electric sliding block one 7, electric sliding block two 8, hydraulic top 9, crane 10. DETAILED DESCRIPTION

[0020] With reference to the accompanying drawings, the technical solutions in the embodiments of the present application will be clearly and completely described below. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments of the present application. Based on the embodiments of the present application, all the other embodiments obtained by those skilled in the art without creative efforts belong to the scope of the present application.

[0021] In the description of the embodiments of the present application, it should be noted that if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and the like are used, the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship commonly used when the product of the present application is used, and is only for the convenience of describing the present application and simplifying the description, and therefore cannot be understood as indicating or implying that the indicated device or element must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as limiting the present application.

[0022] In addition, if the terms "first", "second", "third" and the like are used, they are only used for differentiation and cannot be understood as indicating or implying relative importance. If the terms "horizontal", "vertical", "overhanging" and the like are used, they do not mean that the component must be absolutely horizontal or overhanging, but can be slightly inclined. For example, "horizontal" only means that its direction is relatively more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly inclined.

[0023] In the description of the embodiments of the present application, if the terms "a plurality of", "several" are used, they represent at least two.

[0024] In the description of the embodiments of the present application, it should be further noted that unless otherwise explicitly specified and limited, if the terms "set", "install", "connect", "connect" are used, they should be understood in a broad sense, for example, they can be fixedly connected, or can be detachably connected, or integrally connected; can be mechanically connected, or can be electrically connected; can be directly connected, or can be indirectly connected through an intermediate medium; can be the communication between the two elements inside. For those skilled in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0025] The present embodiment is combined with the accompanying drawings Figure 3 A wind power split type tower cylinder installation operation platform is described in detail.

[0026] The embodiment of the application is a kind of operation platform for wind power split tower installation, comprising a main beam frame 1, the bottom of the main beam frame 1 is provided with a plurality of electric telescopic wheels 2, the both sides of the main beam frame 1 are provided with a plurality of electric folding rods 3, the outer end of the electric folding rod 3 is connected with a secondary beam 4, the secondary beam 4 is parallel to the main beam frame 1 and is controlled to expand laterally by the electric folding rod 3, the bottom of the secondary beam 4 is provided with a plurality of hydraulic columns 5, the top of the main beam frame 1 and the secondary beam 4 is provided with a plurality of support beams 6 and electric sliding blocks 7, the electric sliding blocks 7 slide along the main beam frame 1 and the secondary beam 4, the both ends of the support beam 6 are clamped on the electric sliding blocks 7, the support beam 6 is provided with electric sliding blocks 8, and the top of the electric sliding blocks 8 is provided with hydraulic jacks 9.

[0027] The support beam 6 has twelve, six on each side, perpendicular to the main beam frame 1 and the secondary beam 4, and the electric folding rod 3 has four, two on each side.

[0028] The top center of the main beam frame 1 is provided with a crane 10. The crane 10 is used to lift the support beam 6 to assist in disassembling the platform.

[0029] The electric telescopic wheel 2 is fixedly connected with the main beam frame 1, the hydraulic column 5 is fixedly connected with the secondary beam 4, and the both ends of the electric folding rod 3 are fixedly connected with the secondary beam 4 and the main beam frame 1.

[0030] In specific implementation, the main beam frame 1 is placed, each electric telescopic wheel 2 is started to land and make the main beam frame 1 horizontal, then the electric folding rod 3 is started to expand the secondary beam 4 on both sides, and then the hydraulic column 5 is started to make the secondary beam 4 horizontal, at this time the whole operation platform is stable on the ground and the upper surface is horizontal. The electric sliding block 7 is started to make each support beam 6 appropriately spaced, then each electric sliding block 8 is started to make each hydraulic jack 9 form a circular distribution, such as ​ Then the split tower is erected on the hydraulic jack 9 to form a circle, and then each hydraulic jack 9 is started to further adjust the level, so that each split tower is completely attached, and finally the adhesion and fastening work is carried out to complete the assembly of the split tower.

[0031] The above describes the application and its implementation, which is not restrictive, and the actual protection scope is not limited thereto, any person skilled in the art can easily think of changes or replacements within the technical range disclosed by the application, which should be covered within the protection scope of the application. Therefore, the protection scope of the application should be subject to the protection scope of the claims.

Claims

1. A wind power sectorized tower installation operation platform, characterized by, The utility model provides a kind of crane, including main beam frame (1), the bottom of the main beam frame (1) is equipped with several electric telescopic wheels (2), the both sides of the main beam frame (1) are equipped with several electric folding rods (3), the outer end of the electric folding rod (3) is connected with auxiliary beam (4), the auxiliary beam (4) is parallel with main beam frame (1) and is controlled lateral deployment by electric folding rod (3), the bottom of the auxiliary beam (4) is equipped with several hydraulic columns (5), the top of the main beam frame (1), auxiliary beam (4) is equipped with several support beams (6) and electric slider one (7), the electric slider one (7) slides along main beam frame (1), auxiliary beam (4), the both ends of the support beam (6) are clamped in electric slider one (7), the support beam (6) is equipped with electric slider two (8), the top of the electric slider two (8) is equipped with hydraulic jack (9).

2. The wind power sectorized tower installation operation platform according to claim 1, characterized in that, The support beam (6) has twelve, six on each side, perpendicular to main beam frame (1), auxiliary beam (4), the electric folding rod (3) has four, two on each side.

3. The wind power sectorized tower installation operation platform according to claim 1, characterized in that, The top center of the main beam frame (1) is equipped with crane (10).

4. The wind power sectorized tower installation operation platform according to claim 1, characterized in that, The electric telescopic wheel (2) is fixedly connected with main beam frame (1), the hydraulic column (5) is fixedly connected with auxiliary beam (4), the both ends of the electric folding rod (3) are fixedly connected with auxiliary beam (4), main beam frame (1).