Pipeline mounting bracket for pipeline gap bridge construction

By designing pipe installation supports with side and bottom brackets, the problem of inconvenient pipe replacement during pipe crossing construction was solved, achieving stable support and independent installation, improving the convenience of maintenance and replacement, and adapting to different layout requirements.

CN223754844UActive Publication Date: 2026-01-02SINOHYDRO FOUND ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520604197.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-02
Publication Date
2026-01-02
Estimated Expiration
2035-04-02

AI Technical Summary

Technical Problem

In existing technologies, pipeline replacement or maintenance is inconvenient and can easily interfere with other pipelines during pipeline bridge construction. The fixing devices are not flexible enough and cannot adapt to pipelines of different diameters and numbers.

Method used

Design a pipe installation bracket including side supports and bottom supports. The side supports and bottom supports are fixed to the bridge beam wall respectively. The side supports achieve stable support and independent installation of the pipe through multiple through holes and fixing structures via side mounting plates and bottom supports. The side mounting plates and bottom supports can install different numbers and diameters of pipe fixing structures according to requirements to adapt to different layout needs.

Benefits of technology

It achieves stable support and independent installation of pipelines, improves the convenience of maintenance and replacement, adapts to the needs of pipelines of different diameters and quantities, and avoids interference between pipelines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223754844U_ABST
    Figure CN223754844U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of bridge pipeline installation, in particular to a pipeline installation support for pipeline bridge construction, which comprises a side support and a bottom support which are fixedly connected with each other, and the sides of the side support and the bottom support are respectively fixed on a bridge wall. The side bracket comprises a side fixing plate and a side mounting plate, and the side fixing plate is used for being fixed on a bridge wall; the side mounting plates are used for mounting a plurality of groups of gap bridge pipelines which are arranged up and down; the bottom support is provided with a plurality of groups of gap bridge pipelines which are arranged left and right in the horizontal direction. According to the pipeline mounting bracket for pipeline gap bridge construction, a plurality of second fixing holes which are distributed up and down are formed in a vertical plate of a side mounting plate, and each group of gap bridge pipelines can be independently fixed through a second pipeline fixing structure. The bottom support is provided with a plurality of first through holes, a plurality of gap bridge pipelines can be arranged in parallel in the horizontal direction, each pipeline can be independently mounted and dismounted through the design, other pipelines do not need to be disturbed, and the convenience of later maintenance and replacement is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to the technical field of bridge crossing pipeline installation, more specifically, a kind of pipeline installation support for pipeline bridge construction is particularly related to. BACKGROUND

[0002] In pipeline bridge construction, pipeline support is usually used for construction to ensure the quality and safety of pipeline installation, so that the pipeline can operate normally after being put into use.

[0003] The patent with publication number CN208386075U discloses a power pipe bridge installation fixing device, which is installed and fixed on the bridge wall. First, a triangular steel support is fixed on the bridge wall. The light steel pipe is sleeved with a power pipe fixed by a pipe clamp. Then, the position of the upper triangular steel support is determined according to the position of the light steel pipe. The upper and lower triangular steel supports and the light steel pipe are connected and fixed by long fixing bolts to form a power pipe bridge installation fixing device. However, in the above-mentioned fixing device, the bridge crossing pipes are concentratedly fixed in the space formed by the upper and lower triangular steel supports and the light steel pipe. If one of the pipes needs to be replaced or maintained, the specific pipe needs to be found among the many pipes, which is inconvenient to operate and may interfere with other pipes. SUMMARY

[0004] The utility model aims to provide a pipeline installation support for pipeline bridge construction to overcome the above-mentioned shortcomings.

[0005] A pipeline installation support for pipeline bridge construction includes a side support and a bottom support connected fixedly. The side support and the bottom support are fixed to the bridge wall respectively.

[0006] The side support includes a side fixing plate and a side mounting plate. The side fixing plate is used to fix to the bridge wall. The side mounting plate is used to install several groups of bridge crossing pipes arranged vertically.

[0007] The bottom support is installed with several groups of bridge crossing pipes arranged horizontally.

[0008] Further, the bottom support includes a bottom plate and a first mounting plate perpendicular to the bottom plate. The first mounting plate is provided with a first connecting hole for fixing to the bridge wall.

[0009] Further, the bottom support further includes a diagonal brace. The top end of the diagonal brace is fixed to the lower end surface of the bottom plate. The bottom end of the diagonal brace is fixed to the side surface of the first mounting plate.

[0010] Further, the bottom plate is provided with several first through holes for fixing and installing the first pipe fixing structure.

[0011] Further, the first pipeline fixing structure is a U-shaped hoop, first fixing holes are formed in connecting ears at two ends of the U-shaped hoop, and the first fixing holes are matched with the first through holes.

[0012] Further, the side fixing plate is L-shaped and comprises a vertical fixing plate and a horizontal fixing plate, the vertical fixing plate is provided with a second connecting hole for being fixed to the bridge wall, and the horizontal fixing plate is provided with a plurality of second through holes which are vertically overlapped with the first through holes.

[0013] Further, the side fixing plate is L-shaped and comprises a vertical fixing plate and a horizontal fixing plate, the vertical fixing plate is provided with a second connecting hole for being fixed to the bridge wall, and the horizontal fixing plate is provided with a plurality of second through holes which are vertically overlapped with the first through holes.

[0014] Further, the second pipeline fixing structure comprises a clamping plate clamped between the vertical fixing plate and the vertical plate, the clamping plate is fixedly connected to the vertical plate, the clamping plate is fixedly connected with a lower hoop body and a limiting plate, the limiting plate is located above the lower hoop body, an upper hoop body is clamped between the lower hoop body and the limiting plate, and the upper hoop body and the lower hoop body are oppositely arranged and used for fixing the bridge-crossing pipeline.

[0015] Further, the clamping plate is provided with third fixing holes matched with the second fixing holes.

[0016] Further, the lower hoop body is provided with fourth fixing holes, the upper hoop body is provided with fifth fixing holes, and the lower hoop body and the upper hoop body are fixed by bolts.

[0017] Further, an auxiliary plate is arranged between the vertical fixing plate and the vertical plate and used for spacing the clamping plate.

[0018] Further, the auxiliary plate is provided with sixth fixing holes and is fixed to the vertical plate by bolts.

[0019] Compared with the prior art, the pipeline installation support has the following beneficial effects:

[0020] The pipeline installation support can stably support and fix the bridge-crossing pipeline through the cooperation of the side support and the bottom support, the side support and the bottom support are respectively used for separately erecting different bridge-crossing pipelines, and the bridge-crossing pipelines can be separately installed, thereby facilitating the maintenance or replacement of the bridge-crossing pipelines.

[0021] The pipeline installation support for pipeline bridge construction, the vertical plate of the side installation plate is provided with a plurality of second fixing holes arranged in up and down directions, and each group of bridge crossing pipelines can be fixed individually through the second pipeline fixing structure. The bottom support is provided with a plurality of first through holes, which can arrange a plurality of bridge crossing pipelines in parallel in the horizontal direction. This design enables each pipeline to be independently installed and disassembled without interfering with other pipelines, improving the convenience of later maintenance and replacement.

[0022] Further, the side installation plate and the bottom support can install different numbers of first pipeline fixing structures and second pipeline fixing structures according to actual needs, which can adapt to pipeline installation of different diameters and numbers.

[0023] Further, the second fixing holes on the vertical plate allow the pipeline to be flexibly arranged in the vertical direction, and the third through holes on the horizontal plate coincide with the first through holes on the bottom plate in up and down directions, allowing the pipeline to be flexibly arranged in the horizontal direction, improving the adaptability of the support. BRIEF DESCRIPTION OF DRAWINGS

[0024] The accompanying drawings are included to provide a further understanding of the present application, and constitute a part of the specification, which together with the embodiments of the present application serve to explain the present application, and do not constitute a limitation on the present application. In the drawings:

[0025] Figure 1 is a schematic diagram of the overall structure of the pipeline installation support for pipeline bridge construction in the embodiment.

[0026] Figure 2 is an exploded schematic diagram of the pipeline installation support for pipeline bridge construction in the embodiment.

[0027] Figure 3 is an exploded schematic diagram of the pipeline installation support for pipeline bridge construction in the embodiment.

[0028] Figure 4 is a schematic diagram of the bottom support in the embodiment.

[0029] Figure 5 is a schematic diagram of the side support and the bottom support in the embodiment.

[0030] Figure 6 is a schematic diagram of the side support and the bottom support in the embodiment.

[0031] Figure 7 is an exploded schematic diagram of the second pipeline fixing structure in the embodiment.

[0032] In the drawings: 1, bottom support; 11, bottom plate; 111, first through hole; 12, first installation plate; 121, first connecting hole; 13, inclined strut;

[0033] 2. Side fixing plate; 21. Vertical fixing plate; 211. Second connecting hole; 212. Third connecting hole; 22. Horizontal fixing plate; 221. Second through hole;

[0034] 3. Side mounting plate; 31. Vertical plate; 311. Second fixing hole; 32. Horizontal plate; 321. Third through hole;

[0035] 4. First pipe fixing structure; 41. First fixing hole;

[0036] 5. Second pipe fixing structure; 51. Clamping plate; 511. Third fixing hole; 52. Lower clamp; 521. Fourth fixing hole; 53. Limiting plate; 54. Upper clamp; 541. Fifth fixing hole;

[0037] 6. Auxiliary plate; 61. Sixth fixing hole. Detailed Implementation

[0038] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0039] like Figures 1-3 As shown, this embodiment provides a pipe installation bracket for pipe crossing bridge construction, including a side bracket and a bottom bracket 1 fixedly connected to each other. The sides of the side bracket and the bottom bracket 1 are respectively fixed to the bridge beam wall. The side bracket includes a side fixing plate 2 and a side mounting plate 3. The side fixing plate 2 is used to fix to the bridge beam wall, and the side mounting plate 3 is used to install several sets of crossing pipes arranged vertically. The bottom bracket 1 is equipped with several sets of crossing pipes arranged horizontally.

[0040] Specifically, such as Figure 4 As shown, the base support 1 includes a base plate 11 and a first mounting plate 12 perpendicular to the base plate 11. In this embodiment, two first mounting plates 12 are provided, which are respectively fixedly installed on the inner end of the base plate 11. The first mounting plate 12 has a first connecting hole 121 for fixing to the bridge beam wall.

[0041] Furthermore, the base support 1 also includes a diagonal brace 13, the top of which is fixed to the lower end face of the base plate 11, and the bottom end of which is fixed to the side of the first mounting plate 12. The base support 1, consisting of the base plate 11, the first mounting plate 12, and the diagonal brace 13, forms a triangular support structure, providing stable support and enabling the stable installation of the bridge pipeline.

[0042] The bottom plate 11 is provided with a plurality of first through holes 111 for fixing and mounting the first pipeline fixing structure 4. The first pipeline fixing structure 4 is a U-shaped hoop, and the connecting ears at both ends of the U-shaped hoop are provided with first fixing holes 41 which are matched with the first through holes 111. The U-shaped hoop is fixed on the bottom plate of the bottom support by bolts. By arranging a plurality of first through holes 111, the overpass pipelines can be arranged in parallel in the horizontal direction, so that the overpass pipelines can be installed separately, which is beneficial to the maintenance or replacement of the overpass pipelines in the later period.

[0043] In the side support of the embodiment, as shown in the figure, Figures 1-6 the side fixing plate 2 is L-shaped and includes a vertical fixing plate 21 and a horizontal fixing plate 22. The vertical fixing plate 21 is provided with four second connecting holes 211 for being fixed to the bridge wall. The horizontal fixing plate 22 is provided with a plurality of second through holes 221 which are vertically matched with the first through holes 111.

[0044] The side mounting plate 3 includes a vertical plate 31 and a horizontal plate 32 which are perpendicular to each other. The vertical plate 31 is arranged separately from the vertical fixing plate 21, i.e., there is a distance between the vertical plate 31 and the vertical fixing plate 21. The vertical plate 31 is provided with a plurality of second fixing holes 311 for fixing the second pipeline fixing structure 5, so as to install a plurality of groups of overpass pipelines which are arranged vertically. The horizontal plate 32 is fixed above the horizontal fixing plate 22, and the horizontal plate 32 is provided with a plurality of third through holes 321 which are vertically matched with the first through holes 111 and the second through holes 221. When the first through holes 111 are used to fix the first pipeline fixing structure 4, the bolts can penetrate the first through holes 111, the second through holes 221 and the third through holes 321 at the same time, so as to fix the bottom plate 11, the horizontal fixing plate 22 and the horizontal plate 32, i.e., to firmly fix the side support and the bottom support 1, thereby stably supporting and arranging the overpass pipelines.

[0045] As shown in the figure, Figures 1-3 and Figure 7 the second pipeline fixing structure 5 includes a clamping plate 51 which is clamped between the vertical fixing plate 21 and the vertical plate 31. The clamping plate 51 is fixedly connected to the vertical plate 31, and the clamping plate 51 is provided with third fixing holes 511 which are matched with the second fixing holes 311 of the vertical plate 31. The bolts penetrate the second fixing holes 311 of the vertical plate 31 and the third fixing holes 511 of the clamping plate 51, so as to fix the clamping plate 51 to the vertical plate 31, i.e., to fix the second pipeline fixing structure 5 to the side support. By arranging a plurality of second fixing holes 311, a plurality of overpass pipelines can be arranged in the vertical direction, so that the overpass pipelines can be installed separately, which is beneficial to the maintenance or replacement of the overpass pipelines in the later period.

[0046] The clamping plate 51 is fixed with a lower hoop body 52 and a limiting plate 53, the limiting plate 53 is located above the lower hoop body 52, a upper hoop body 54 is clamped between the lower hoop body 52 and the limiting plate 53, the upper hoop body 54 and the lower hoop body 54 are oppositely arranged and used for fixing the over-bridge pipeline. The lower hoop body 52 is provided with a fourth fixing hole 521, the upper hoop body 54 is provided with a fifth fixing hole 541, and the lower hoop body 54 and the upper hoop body 52 are fixed by bolts, so that the over-bridge pipeline can be erected. Since the second fixing hole 321 is arranged on the vertical fixed plate 31, the over-bridge pipeline can be individually erected upward and downward.

[0047] In the embodiment, an auxiliary plate 6 is arranged between the vertical fixed plate 21 and the vertical fixed plate 31, and is used for spacing the clamping plates 51. The sixth fixing hole 61 is arranged on the auxiliary plate 6 and is fixed to the vertical fixed plate 51 by bolts.

[0048] In order to more firmly fix the second pipeline fixing structure 5, the third connecting hole 212 is arranged on the vertical fixed plate 21, each third connecting hole 212 is matched with the second fixing hole 311 of the vertical fixed plate 31, and the bolts can be fixed to the bridge wall after passing through the vertical fixed plate 31, the clamping plate 51 and the vertical fixed plate 21, so that the firmness of the fixing is increased.

[0049] The pipeline installation support for pipeline over-bridge construction provided in the embodiment can realize stable support and fixing of the over-bridge pipeline through the cooperation of the side support and the bottom support 1. The side support and the bottom support 1 are respectively used for individually and separately erecting different over-bridge pipelines, so that the over-bridge pipelines can be separately installed, and the maintenance or replacement of the over-bridge pipelines in the later period is facilitated.

[0050] The bottom support 1 is fixed to the bridge wall through the first connecting hole 121 on the first mounting plate 12. The inclined support 13 connects the bottom plate 11 and the first mounting plate 12 to form a triangular support structure and provide stable support for the bottom support 1. The vertical fixed plate 21 of the side fixed plate 2 is fixed to the bridge wall through the second connecting hole 211. The first through hole 111 on the bottom plate 11 can be used as a through hole for fixing the first pipeline fixing structure and can be used in cooperation with the second through hole 221 of the horizontal fixed plate 22 in the side support to realize the connection between the side support and the bottom support 1. The side support and the bottom support 1 are respectively fixed to the bridge wall, and a stable support structure is formed through the connection between the horizontal fixed plate 22 and the bottom plate 11, which can bear the weight of the over-bridge pipeline and stably erect the over-bridge pipeline. The bottom support 1 forms a triangular support structure with the bottom plate 11, the first mounting plate 12 and the inclined support 13, which can effectively disperse external force and ensure the reliability of the bottom support 1 in long-term use, and stably erect the over-bridge pipeline.

[0051] The bottom plate 11 is provided with a plurality of first through holes 111 for mounting the first pipeline fixing structure 4, i.e., the U-shaped hoop member. The U-shaped hoop member is fixed to the bottom plate 11 at different first through holes by bolts and is used for fixing the bridge pipeline arranged horizontally and left and right.

[0052] The vertical plate 31 of the side mounting plate 3 is provided with a plurality of second fixing holes 311 for mounting the second pipeline fixing structure 5. The second pipeline fixing structure 5 is fixed to the side bracket by bolts passing through the second fixing holes 311 of the vertical plate 31 and the third fixing holes 511 of the clamping plate 51. The lower hoop body 52 and the upper hoop body 54 are fixed by bolts and are used for fixing the bridge pipeline arranged up and down. The vertical plate 31 of the side mounting plate 3 is provided with a plurality of second fixing holes 311, and each group of bridge pipelines can be fixed separately by the second pipeline fixing structure 5. This design enables each bridge pipeline to be independently installed and disassembled without interfering with other pipelines, thereby improving the convenience of maintenance and replacement. At the same time, the second fixing holes 311 arranged up and down can flexibly adjust the installation position of the pipeline according to actual needs, thereby improving the adaptability of the bracket.

[0053] An auxiliary plate 6 is arranged between the vertical fixing plate 21 and the vertical plate 31. The auxiliary plate 6 is fixed to the vertical plate 31 by the sixth fixing hole 61 and is used for spacing the clamping plates 51 to avoid interference between the pipelines. This design not only avoids interference between the pipelines, but also further enhances the structural stability of the bracket. The auxiliary plate 6 is fixed to the vertical plate 31 by bolts, and the installation and disassembly are convenient.

[0054] The first pipeline fixing structure 4 adopts a U-shaped hoop member, and the second pipeline fixing structure 5 adopts an upper and lower hoop body structure. Both pipeline fixing structures are convenient to install and disassemble and are beneficial to the construction of the bridge pipeline during erection.

[0055] The pipeline installation bracket for pipeline bridge construction provided in the embodiment is characterized in that the vertical plate 31 of the side mounting plate 3 is provided with a plurality of second fixing holes 311 arranged up and down, and each group of bridge pipelines can be fixed separately by the second pipeline fixing structure 5. The bottom bracket 1 is provided with a plurality of first through holes 11 and can arrange a plurality of bridge pipelines horizontally and in parallel. This design enables each pipeline to be independently installed and disassembled without interfering with other pipelines, thereby improving the convenience of later maintenance and replacement.

[0056] The side mounting plate 3 and the bottom bracket 1 can install different numbers of first pipeline fixing structures 4 and second pipeline fixing structures 5 according to actual needs and can adapt to pipeline installation of different diameters and numbers.

[0057] The second fixing holes 311 on the vertical plate 31 and the third through holes 321 on the horizontal plate 32 are vertically coincident with the first through holes 111 of the bottom plate 11, so that the pipeline can be flexibly arranged in the vertical direction and the horizontal direction, thereby improving the adaptability of the bracket.

[0058] It should be pointed out finally that: the above only for the preferred embodiments of the utility model have, and do not for limiting the utility model, although the utility model has been described in detail with reference to the foregoing embodiments, for the person skilled in the art, it still can modify the technical scheme recorded in the foregoing each embodiment, or equivalent replacement to part of technical features. Any modification, equivalent replacement, improvement etc. that is made within the spirit and principle of the utility model, should be included in the protection scope of the utility model.

Claims

1. A pipe installation bracket for pipe crossing bridge construction, characterized in that, The utility model provides a bridge pipe crossing support, which comprises a side support and a bottom support (1) fixedly connected, and the side and bottom supports (1) are fixed to the bridge wall respectively; The side support comprises a side fixing plate (2) for fixing to the bridge wall and a side mounting plate (3) for mounting a plurality of groups of over-bridge pipes arranged in an up-down manner; The bottom support (1) is provided with a plurality of groups of over-bridge pipes arranged in a left-right manner in a horizontal direction.

2. The pipe support for pipe crossing construction according to claim 1, wherein The bottom support (1) comprises a bottom flat plate (11) and a first mounting plate (12) perpendicular to the bottom flat plate (11), and the first mounting plate (12) is provided with a first connecting hole (121) for fixing to the bridge wall; The bottom support (1) further comprises a diagonal brace (13), the top end of the diagonal brace (13) is fixedly connected to the lower end surface of the bottom flat plate (11), and the bottom end of the diagonal brace (13) is fixedly connected to the side surface of the first mounting plate (12).

3. The pipe support for pipe crossing construction according to claim 2, wherein The bottom flat plate (11) is provided with a plurality of first through holes (111) for fixedly mounting first pipe fixing structures (4).

4. The pipe support for pipe crossing construction according to claim 3, wherein The first pipe fixing structure (4) is a U-shaped hoop, and the connecting ears at both ends of the U-shaped hoop are provided with first fixing holes (41) matched with the first through holes (111).

5. The pipe support for pipe crossing construction according to claim 4, wherein The side fixing plate (2) is L-shaped and comprises a vertical fixing plate (21) and a horizontal fixing plate (22), the vertical fixing plate (21) is provided with a second connecting hole (211) for fixedly connecting to the bridge wall, and the horizontal fixing plate (22) is provided with a plurality of second through holes (221) coinciding with the first through holes (111) in an up-down manner.

6. The pipe support for pipe crossing construction according to claim 5, wherein The side mounting plate (3) comprises a vertical plate (31) and a horizontal plate (32) perpendicular to each other, the vertical plate (31) is arranged separately from the vertical fixing plate (21), the vertical plate (31) is provided with a plurality of second fixing holes (311) for fixing second pipe fixing structures (5), the horizontal plate (32) is fixedly connected to the upper side of the horizontal fixing plate (22), and the horizontal plate (32) is provided with a plurality of third through holes (321) coinciding with the first through holes (111) and the second through holes (221) in an up-down manner.

7. The pipe support for pipe crossing construction according to claim 6, wherein The second pipe fixing structure (5) comprises a clamping plate (51) clamped between the vertical fixing plate (21) and the vertical plate (31), the clamping plate (51) is fixedly connected to the vertical plate (31), the clamping plate (51) is fixedly connected with a lower hoop body (52) and a limiting plate (53), the limiting plate (53) is located above the lower hoop body (52), an upper hoop body (54) is clamped between the lower hoop body (52) and the limiting plate (53), the upper hoop body (54) and the lower hoop body (52) are arranged oppositely and used for fixing over-bridge pipes.

8. The pipe support for pipe crossing construction according to claim 7, wherein The clamping plate (51) is provided with a third fixing hole (511) matched with the second fixing hole (311).

9. The pipe support for pipe crossing construction according to claim 8, wherein The lower hoop body (52) is provided with a fourth fixing hole (521), the upper hoop body (54) is provided with a fifth fixing hole (541), and the lower hoop body (52) and the upper hoop body (54) are fixed by bolts.

10. The pipe support for pipe crossing construction according to claim 9, wherein The vertical fixed plate (21) and the vertical plate (31) are further provided with an auxiliary plate (6) for spacing the clamping plate (51); the auxiliary plate (6) is provided with a sixth fixed hole (61) fixed with the vertical plate (31) through bolts.

Citation Information

Patent Citations

  • Electric power pipe is passed a bridge and is installed fixing device

    CN208386075U